Preface
These Standard Bidding Documents for Procurement of Works (SBD (Works)) have been
prepared by Japan International Cooperation Agency (JICA).
These SBD (Works) are consistent with the Guidelines for Procurement under Japanese ODA
Loans, April 2012 and their use is required for civil works contracts to be financed, in whole
or in part, by JICA under the aforesaid Guidelines. The use of these SBD (Works) is also
encouraged for contracts under the Guidelines for Procurement published in October 1999 or
March 2009, as these SBD (Works) reflect recent best practices of public procurement and
JICA’s policy.
These SBD (Works) are to be used for the procurement of admeasurement (unit price or rate)
type of works through International Competitive Bidding (ICB). These SBD (Works) are not
suitable for lump sum contracts without substantial changes to the method of payment and
price adjustment, and to the Bill of Quantities, Schedules of Activities, and so forth.
The structure and the provisions of these SBD (Works) are harmonized with the Standard
Bidding Documents for Procurement of Works of the Multilateral Development Banks,
except where specific considerations within JICA have required a change.
If the user has questions regarding the use of these SBD (Works), the appropriate JICA’s
official should be consulted.
ii
Summary Description
These Standard Bidding Documents for Procurement of Works (SBD (Works)) include both
One-Envelope (Option A) and Two-Envelope (Option B) bidding procedures to be chosen by
the Employer as appropriate to each circumstance. These SBD (Works) apply either when a
prequalification process has taken place before bidding or when a prequalification process
has not taken place before bidding (provided alternative documents should be selected as
applicable). A brief description of these documents is given below.
for
Procurement of
[insert identification of the Works]
_______________________________
_______________________________
Ideally, the Invitation for Bids is sent to the qualified Bidders at the time that the
prequalification results are announced.
The Invitation for Bids should be consistent with the information contained in Section II -
Bid Data Sheet.
IFB-1
1. The [insert name of Borrower] has received1 a loan from Japan International
Cooperation Agency (JICA) towards the cost of [insert name of Project]. It is intended that
part of the proceeds of this loan will be applied to eligible payments under the contract2 for
[insert title of contract].
2. The [insert name of the Employer] now invites sealed Bids from prequalified eligible
Bidders for the construction and completion of [insert name of the works] (“the Works”).
4. Prequalified eligible Bidders may obtain further information from and inspect the
Bidding Documents at the office of [insert name of appropriate purchasing unit] 3 [insert
mailing address of appropriate office for inquiry and issuance of Bidding Documents and
cable, telex, and/or facsimile numbers].
6. Bids must be delivered to the address above5 on or before [insert time] on [insert date] 6
and must be accompanied by a security of [insert fixed sum].
7. Bids will be opened in the presence of Bidders’ representatives who choose to attend at
[insert time and date] at the offices of [insert address of appropriate office].
Notes
1. Substitute “has applied for,” if appropriate.
2. Substitute “contracts” where Bids are called concurrently for multiple contracts. Add a new para. 4 and
renumber paras 4 - 7 as follows: “Bidders may bid for one or several contracts, as further defined in the
IFB-2
Bidding Document. Bidders wishing to offer discounts in case they are awarded more than one contract
will be allowed to do so, provided those discounts are included in the Letter of Bid.”
3. The office for inquiry and issuance of Bidding Documents and that for Bid submission may or may not
be the same.
4. The fee, to defray printing and mailing/shipping costs, should be nominal.
5. Substitute the Employer’s address for Bid submission if different from its address for inquiry and
issuance of Bidding Documents.
6. The time allowed for preparation of the Bid submission should be sufficient for Bidders to gather all the
information required - preferably sixty (60) days, but in any case not less than forty-five (45) days after
the date when the documents are available for distribution or the date of the advertisement, whichever is
later. This period may be longer for very large projects, where time should be allowed for the formation
of joint ventures and assembly of the necessary resources, and/or scrutiny of the Bidding Documents.
Invitation for Bids: Without Prequalification
The Invitation for Bids provides information that enables potential Bidders to decide whether to
participate. Apart from a summary description of the works, the Invitation for Bids should also
indicate any important Bid evaluation criteria (for example, technical alternatives) or
qualification requirement (for example, a requirement for a minimum level of experience in
similar works for which the Invitation for Bids is issued).
The Invitation for Bids should be consistent with the information contained in Section II -
Bid Data Sheet.
IFB-1
1. The [insert name of Borrower] has received1 a loan from Japan International
Cooperation Agency (JICA) towards the cost of [insert name of Project]. It is intended that
part of the proceeds of this loan will be applied to eligible payments under the contract2 for
[insert title of contract].
2. The [insert name of the Employer] now invites sealed Bids from eligible Bidders for the
construction and completion of [insert brief description of the works] 3 (“the Works”).
4. Interested eligible Bidders may obtain further information from and inspect the Bidding
Documents at the office of [insert name of appropriate purchasing unit] 4 [insert mailing
address of appropriate office for inquiry and issuance of Bidding Documents and cable, telex,
and/or facsimile numbers].
6. The provisions in the Instructions to Bidders and in the General Conditions of Contract
are the provisions of the Standard Bidding Documents under Japanese ODA Loans for the
Procurement of Works.
7. Bids must be delivered to the address above6 on or before [insert time] on [insert date] 7
and must be accompanied by a security of [insert fixed sum].
8. Bids will be opened in the presence of Bidders’ representatives who choose to attend at
[insert time and date] at the offices of [insert address of appropriate office].
Notes
1. Substitute “has applied for,” if appropriate.
2. Substitute “contracts” where Bids are called concurrently for multiple contracts. Add a new para. 4 and
renumber paras 4 - 8 as follows: “Bidders may bid for one or several contracts, as further defined in the
Bidding Documents. Bidders wishing to offer discounts in case they are awarded more than one
contract will be allowed to do so, provided those discounts are included in the Letter of Bid.”
3. A brief description of the Works or Goods should be provided, including quantities, location of project, and
other information necessary to enable potential Bidders to decide whether or not to respond to the invitation.
Bidding Documents may require Bidders to have specialized experience or capabilities; such requirements
should also be included in this paragraph.
4. The office for inquiry and issuance of Bidding Documents and that for Bid submission may or may not
be the same.
5. The fee, to defray printing and mailing/shipping costs, should be nominal.
6. Substitute the Employer’s address for Bid submission if different from its address for inquiry and
issuance of Bidding Documents.
7. The time allowed for preparation of the Bid submission should be sufficient for Bidders to gather all the
information required - preferably sixty (60) days, but in any case not less than forty-five (45) days after
the date when the documents are available for distribution or the date of the advertisement, whichever is
later. This period may be longer for very large projects, where time should be allowed for the formation
of joint ventures and assembly of the necessary resources, and/or scrutiny of the Bidding Documents.
PART 1 – BIDDING PROCEDURES
OPTION A: One-Envelope Bidding
Option A: Section I. Instructions to Bidders
The use of the Standard Instructions to Bidders set forth in Section I of these Standard
Bidding Documents for the Procurement of Works (version 1.1) published by JICA in
October, 2012 (hereafter referred to as “Standard ITB”), in all Bidding Documents for
construction works financed by Japanese ODA Loans is required, and they shall be used
without modification. Any necessary changes, acceptable to JICA, to address specific
country and project issues, shall be introduced only through the Bid Data Sheet.
A copy of the Standard Instructions to Bidders may be attached to the Bidding Documents
prepared by the Employer for reference purposes only. If the Instructions to Bidders in the
Bidding Documents prepared by the Employer contain modifications from the Standard
Instructions to Bidders, JICA will not consider them valid and the Standard Instructions to
Bidders, as defined above, shall apply.
Instead of attaching a copy of the Standard Instructions to Bidders, the Employer may use
the following introductory text.]
The Instructions to Bidders governing this bidding process are the “Instructions to Bidders”
included in Option A: One-Envelope Bidding, Section I, of the Standard Bidding Documents
for Procurement of Works (version 1.1), published by JICA in October, 2012. Those
Instructions to Bidders are available on the JICA’s web site shown below:
http://www.jica.go.jp/english/our_work/types_of_assistance/oda_loans/oda_op_info/guide/tender/index.html
Table of Clauses
A. General ................................................................................................................................3
1. Scope of Bid ..............................................................................................................3
2. Source of Funds.........................................................................................................3
3. Corrupt and Fraudulent Practices ..............................................................................3
4. Eligible Bidders .........................................................................................................5
5. Eligible Materials, Equipment, and Services ...........................................................6
A. General
1. Scope of Bid 1.1 In connection with the Invitation for Bids specified in
Section II, Bid Data Sheet (BDS), the Employer, as
specified in the BDS, issues these Bidding Documents
(hereinafter referred to as “Bidding Documents”) for the
procurement of Works as specified in Section VI, Works
Requirements. The name, identification, and number of the
lot(s) (contract(s)) comprising this International Competitive
Bidding (ICB) process are specified in the BDS.
1.2 Throughout these Bidding Documents:
(a) the term “in writing” means communicated in written
form and delivered against receipt;
(b) except where the context requires otherwise, words
indicating the singular also include the plural and words
indicating the plural also include the singular; and
(c) “day” means calendar day.
2. Source of Funds 2.1 The Borrower specified in the BDS has received or has
applied for a Japanese ODA Loan from Japan International
Cooperation Agency (hereinafter referred to as “JICA”),
with the number, in the amount and on the signed date of the
Loan Agreement specified in the BDS, towards the cost of
the project specified in the BDS. The Borrower intends to
apply a portion of the proceeds of the loan to payments
under the contract(s) for which these Bidding Documents are
issued.
2.2 Disbursement of a Japanese ODA Loan by JICA will be
subject, in all respects, to the terms and conditions of the
Loan Agreement, including the disbursement procedures and
the applicable Guidelines for Procurement under Japanese
ODA Loans specified in the BDS. No party other than the
Borrower shall derive any rights from the Loan Agreement
or have any claim to the loan proceeds.
2.3 The above Loan Agreement will cover only a part of the
project cost. As for the remaining portion, the Borrower will
take appropriate measures for finance.
3. Corrupt and 3.1 It is JICA’s policy to require that Bidders and Contractors,
Fraudulent as well as Borrowers, under contracts funded with Japanese
Practices ODA Loans and other Japanese ODA, observe the highest
standard of ethics during the procurement and execution of
ITB-4 Option A: Section I. Instructions to Bidders
5.2 For purposes of ITB 5.1 above, “origin” means the place
where the materials and equipment are mined, grown,
produced or manufactured, and from which the services are
provided. Materials and equipment are produced when,
through manufacturing, processing, or substantial or major
assembling of components, a commercially recognized
product results that differs substantially in its basic
characteristics or in purpose or utility from its components.
meeting.
7.6 Minutes of the pre-bid meeting, if applicable, including the
text of the questions asked by Bidders, without identifying
the source, and the responses given, together with any
responses prepared after the meeting, will be transmitted
promptly to all Bidders who have acquired the Bidding
Documents in accordance with ITB 6.3. Any modification
to the Bidding Documents that may become necessary as a
result of the pre-bid meeting shall be made by the Employer
exclusively through the issue of an addendum pursuant to
ITB 8 and not through the minutes of the pre-bid meeting.
Nonattendance at the pre-bid meeting will not be a cause for
disqualification of a Bidder.
8. Amendment of 8.1 At any time prior to the deadline for submission of Bids, the
Bidding Documents Employer may amend the Bidding Documents by issuing
addenda.
8.2 Any addendum issued shall be part of the Bidding
Documents and shall be communicated in writing to all who
have obtained the Bidding Documents from the Employer in
accordance with ITB 6.3. If so specified in the BDS, the
Employer shall also promptly publish the addendum on the
Employer’s web page in accordance with ITB 7.1.
8.3 To give Bidders reasonable time in which to take an
addendum into account in preparing their Bids, the
Employer may extend the deadline for the submission of
Bids, pursuant to ITB 22.2.
C. Preparation of Bids
9. Cost of Bidding 9.1 The Bidder shall bear all costs associated with the
preparation and submission of its Bid, and the Employer
shall not be responsible or liable for those costs, regardless
of the conduct or outcome of the bidding process.
10. Language of Bid 10.1 The Bid, as well as all correspondence and documents
relating to the Bid exchanged by the Bidder and the
Employer, shall be written in the language specified in the
BDS. Supporting documents and printed literature that are
part of the Bid may be in another language provided they are
accompanied by an accurate translation of the relevant
passages in the language of Bid, in which case, for purposes
of interpretation of the Bid, such translation shall govern.
11. Documents 11.1 The Bid shall comprise the following:
ITB-10 Option A: Section I. Instructions to Bidders
13. Alternative Bids 13.1 Unless otherwise specified in the BDS, alternative Bids
shall not be considered.
14. Bid Prices and 14.1 The prices and discounts (including any price reduction)
Discounts quoted by the Bidder in the Letter of Bid and in the Bill of
Quantities shall conform to the requirements specified
below.
14.2 The Bidder shall fill in rates and prices for all items of the
Works described in the Bill of Quantities. Items against
which no rate or price is entered by the Bidder shall be
deemed covered by the rates for other items in the Bill of
Quantities and will not be paid for separately by the
Employer. An item not listed in the priced Bill of Quantities
shall be assumed to be not included in the Bid, and provided
that the Bid is determined substantially responsive
notwithstanding this omission, the average price of the item
quoted by substantially responsive Bidders will be added to
the Bid Price and the equivalent total cost of the Bid so
determined will be used for price comparison.
14.4 The Bidder shall quote any discounts and the methodology
for their application in the Letter of Bid, in accordance with
ITB 12.1.
15. Currencies of Bid 15.1 The currency(ies) of the Bid shall be as specified in the
and Payment BDS. Payment of the contract price shall be made in the
currency or currencies in which the Bid Price is expressed in
the Bid of the successful Bidder.
15.2 Bidders may be required by the Employer to justify, to the
Employer’s satisfaction, their local and foreign currency
requirements, and to substantiate that the amounts included
in the unit rates and prices and shown in the Schedule of
Adjustment Data are reasonable, in which case a detailed
breakdown of the foreign currency requirements shall be
provided by Bidders.
15.3 The foreign currency requirements generally include the
following:
(a) expatriate staff and labour employed directly on the
Works;
(b) social, insurance, medical and other charges relating to
such expatriate staff and labour, and foreign travel -
expenses;
(c) imported materials, both temporary and permanent,
including fuels, oil and lubricants required for the
Works;
(d) depreciation and usage of imported Plant and
Contractor’s Equipment, including spare parts, required
Option A: Section I. Instructions to Bidders ITB-13
18. Period of Validity 18.1 Bids shall remain valid for the period specified in the BDS
of Bids after the Bid submission deadline date prescribed by the
Employer in accordance with ITB 22.1. A Bid valid for a
shorter period shall be rejected by the Employer as non-
responsive.
18.2 In exceptional circumstances, prior to the expiration of the
Bid validity period, the Employer may request Bidders to
extend the period of validity of their Bids. The request and
the responses shall be made in writing. The Bid Security
shall also be extended for twenty-eight (28) days beyond the
deadline of the extended validity period. A Bidder may
refuse the request without forfeiting its Bid Security. A
Bidder granting the request shall not be required or
permitted to modify its Bid, except as provided in ITB 18.3.
18.3 If the award is delayed by a period exceeding fifty-six (56)
days beyond the expiry of the initial Bid validity, the
Contract price shall be determined as follows:
(a) In the case of fixed price contracts, the Contract price
shall be the Bid Price adjusted by the factor specified in
the BDS.
(b) In the case of adjustable price contracts, to determine the
Contract price, the fixed portion of the Bid Price shall be
adjusted by the factor specified in the BDS.
(c) In any case, Bid evaluation shall be based on the Bid
Price without taking into consideration the applicable
correction from those indicated above.
19. Bid Security 19.1 The Bidder shall furnish as part of its Bid, a Bid Security in
the amount and currency specified in the BDS.
19.2 The Bid Security shall be a demand guarantee in any of the
following forms at the Bidder’s option:
(a) an unconditional guarantee issued by a bank or financial
institution (such as an insurance, bonding or surety
company);
(b) an irrevocable letter of credit;
(c) a cashier’s or certified check; or
(d) another security specified in the BDS,
from a reputable source from an eligible source country. If
the unconditional guarantee is issued by a financial
Option A: Section I. Instructions to Bidders ITB-15
22.2 The Employer may, at its discretion, extend the deadline for
the submission of Bids by amending the Bidding Documents
in accordance with ITB 8, in which case all rights and
obligations of the Employer and Bidders previously subject
to the deadline shall thereafter be subject to the deadline as
extended.
23. Late Bids 23.1 The Employer shall not consider any Bid that arrives after
the deadline for submission of Bids, in accordance with ITB
22. Any Bid received by the Employer after the deadline for
submission of Bids shall be declared late, rejected, and
returned unopened to the Bidder.
24. Withdrawal, 24.1 A Bidder may withdraw, substitute, or modify its Bid after it
Substitution, and has been submitted by sending a written notice, duly signed by
Modification of an authorized representative, and shall include a copy of the
Bids authorization in accordance with ITB 20.2, (except that
withdrawal notices do not require copies). The corresponding
substitution or modification of the Bid must accompany the
respective written notice. All notices must be:
(a) prepared and submitted in accordance with ITB 20 and
ITB 21 (except that withdrawals notices do not require
copies), and in addition, the respective envelopes shall
be clearly marked “WITHDRAWAL,” “SUBSTITUTION,”
“MODIFICATION;” and
(b) received by the Employer prior to the deadline
prescribed for submission of Bids, in accordance with
ITB 22.
24.2 Bids requested to be withdrawn in accordance with ITB 24.1
shall be returned unopened to the Bidders.
24.3 No Bid may be withdrawn, substituted, or modified in the
interval between the deadline for submission of Bids and the
expiration of the period of Bid validity specified by the
Bidder on the Letter of Bid or any extension thereof.
25. Bid Opening 25.1 Except in the cases specified in ITB 23 and ITB 24, the
Employer shall publicly open and read out in accordance
with ITB 25.3 all Bids received by the deadline, at the date,
time and place specified in the BDS, in the presence of
ITB-18 Option A: Section I. Instructions to Bidders
30. Qualification of the 30.1 The Employer shall determine to its satisfaction whether
Bidder Bidders meet the qualifying criteria specified in Section III,
Evaluation and Qualification Criteria, during the evaluation
of Bids. However, if prequalification was carried out prior to
the bidding process, the Employer may carry out the
assessment of the qualification criteria specified in Section
III, Evaluation and Qualification Criteria, for the Bidder who
submitted the lowest evaluated and substantially responsive
Bid only.
30.2 The determination shall be based upon an examination of the
documentary evidence of the Bidder’s qualifications
submitted by the Bidder, pursuant ITB 17.
30.3 An affirmative determination shall be a prerequisite for
award of the Contract to the Bidder. A negative
determination shall result in disqualification of the Bid, in
which event if the assessment of the Bidder’s qualification
was conducted for the lowest evaluated Bidder only, in
accordance with ITB 30.1, the Employer shall proceed to the
next lowest evaluated Bid to make a similar determination.
31. Determination of 31.1 The Employer’s determination of a Bid’s responsiveness is
Responsiveness to be based on the contents of the Bid itself, as defined in
Option A: Section I. Instructions to Bidders ITB-21
ITB 11.
31.2 A substantially responsive Bid is one that meets the
requirements of the Bidding Documents without material
deviation, reservation, or omission. A material deviation,
reservation, or omission is one that,
(a) if accepted, would
(i) affect in any substantial way the scope, quality, or
performance of the Works specified in the
Contract; or
(ii) limit in any substantial way, inconsistent with the
Bidding Documents, the Employer’s rights or the
Bidder’s obligations under the proposed Contract; or
(b) if rectified, would unfairly affect the competitive
position of other Bidders presenting substantially
responsive Bids.
31.3 The Employer shall examine the technical aspects of the Bid
submitted in accordance with ITB 16, Technical Proposal, in
particular, to confirm that all requirements of Section VI,
Works Requirements have been met without any material
deviation, reservation or omission.
31.4 If a Bid is not substantially responsive to the requirements of
the Bidding Documents, it shall be rejected by the Employer
and may not subsequently be made responsive by correction
of the material deviation, reservation, or omission.
32. Nonmaterial 32.1 Provided that a Bid is substantially responsive, the Employer
Nonconformities may waive any nonconformities in the Bid that do not
constitute a material deviation, reservation, or omission.
32.2 Provided that a Bid is substantially responsive, the Employer
may request that the Bidder submit the necessary
information or documentation, within a reasonable period of
time, to rectify nonmaterial nonconformities in the Bid
related to documentation requirements. Requesting
information or documentation on such nonconformities shall
not be related to any aspect of the price of the Bid. Failure
of the Bidder to comply with the request may result in the
rejection of its Bid.
32.3 Provided that a Bid is substantially responsive, the Employer
shall rectify quantifiable nonmaterial nonconformities
related to the Bid Price. To this effect, the Bid Price shall be
ITB-22 Option A: Section I. Instructions to Bidders
34. Conversion to 34.1 For evaluation and comparison purposes, the currency(ies)
Single Currency of the Bid shall be converted into a single currency as
specified in the BDS.
35. Subcontractors 35.1 Unless otherwise stated in the BDS, the Employer does not
intend to execute any specific elements of the Works by
subcontractors selected in advance by the Employer
(nominated subcontractors).
36. Evaluation of Bids 36.1 The Employer shall use the criteria and methodologies listed
in this Clause. No other evaluation criteria or methodologies
shall be permitted.
Qualification Criteria.
36.5 If the Bid, which results in the lowest Evaluated Bid Price, is
seriously unbalanced or front loaded in the opinion of the
Employer, the Employer may require the Bidder to produce
detailed price analyses for any or all items of the Bill of
Quantities, to demonstrate the internal consistency of those
prices with the construction methods and schedule proposed.
After evaluation of the price analyses, taking into
consideration the schedule of estimated Contract payments,
the Employer may require that the amount of the
Performance Security be increased at the expense of the
Bidder to a level sufficient to protect the Employer against
financial loss in the event of default of the successful Bidder
under the Contract.
37. Comparison of Bids 37.1 The Employer shall compare the evaluated prices of all
substantially responsive Bids established in accordance with
ITB 36.2 to determine the lowest evaluated Bid.
38. Employer’s Right 38.1 The Employer reserves the right to accept or reject any Bid,
to Accept Any Bid, and to annul the bidding process and reject all Bids at any
and to Reject Any time prior to contract award, without thereby incurring any
or All Bids liability to Bidders. In case of annulment, all Bids submitted
and specifically, Bid securities, shall be promptly returned to
the Bidders.
F. Award of Contract
39. Award Criteria 39.1 Subject to ITB 38.1, the Employer shall award the Contract
to the Bidder whose offer has been determined to be the
lowest evaluated Bid and is substantially responsive to the
Bidding Documents, provided further that the Bidder is
determined to be qualified to perform the Contract
satisfactorily.
40. Notification of 40.1 Prior to the expiration of the period of Bid validity, the
Award Employer shall notify the successful Bidder, in writing, that
its Bid has been accepted. The notification letter
(hereinafter and in the Conditions of Contract and Contract
Forms called the “Letter of Acceptance”) shall specify the
sum that the Employer will pay the Contractor in
consideration of the execution and completion of the Works
(hereinafter and in the Conditions of Contract and Contract
Forms called “the Accepted Contract Amount”). At the
same time, the Employer shall also notify all other Bidders
Option A: Section I. Instructions to Bidders ITB-25
42. Performance 42.1 Within twenty-eight (28) days of the receipt of the Letter of
Security Acceptance from the Employer, the successful Bidder shall
furnish the Performance Security in accordance with the
General Conditions of Contract, subject to ITB 36.5, using
for that purpose the Performance Security Form included in
Section IX, Annex to the Particular Conditions - Contract
Forms, or another form acceptable to the Employer. If the
Performance Security furnished by the successful Bidder is
in the form of a bond, it shall be issued by a bonding or
insurance company that has been determined by the
successful Bidder to be acceptable to the Employer. A
foreign institution providing a bond shall have a
correspondent financial institution located in the Employer’s
Country.
ITB-26 Option A: Section I. Instructions to Bidders
Section II, Bid Data Sheet, shall be filled in by the Employer before issuance of the Bidding
Documents.
The Bid Data Sheet (BDS) contains information and provisions that are specific to a
particular bidding process. The Employer must specify in the BDS only the information that
the ITB request be specified in the BDS. All information shall be provided; no clause shall
be left blank.
To facilitate the preparation of the BDS, its clauses are numbered with the same numbers as
the corresponding ITB clause.
Option A: Section II. Bid Data Sheet BDS-1
ITB 7.4 A Pre-bid meeting [insert “will” or “will not”, as appropriate] take place
at the following date, time and place:
[If a pre-bid meeting will take place, insert the date, time and place
information in the spaces provided below. Otherwise insert “Not
Applicable” in the spaces provided below for the date, time and place]
Date:
Time:
Place:
A site visit conducted by the Employer [insert “will be” or “will not be”,
as appropriate] organized.
ITB 8.2 Addenda, if any, [select “will” or “will not”, as appropriate] be published
on the Employer’s web page.
C. Preparation of Bids
ITB 10.1 The language of the Bid is: [insert one of the following: Japanese, English,
Spanish or French.]
ITB 11.1 (i) The Bidder shall submit with its Bid the following additional documents:
[List any additional document not already listed in ITB 11.1 that must be
submitted with the Bid.]
ITB 13.1 [The following provision should be included and the required
corresponding information inserted only if alternative Bids will be
considered. Otherwise delete this BDS 13.1.]
The prices quoted by the Bidder shall be: [insert “fixed; consequently, the
Bidder is not required to furnish the indices and weightings for the price
Option A: Section II. Bid Data Sheet BDS-3
ITB 19.1 The amount and currency of the Bid Security shall be [Insert amount and
currency of the Bid Security. The amount should be approximately 2% of
the estimated cost of the contract.]
ITB 19.2 (d) Other types of acceptable securities: [Insert names of other acceptable
securities. Insert “None” if no other forms of bid securities besides those
listed in ITB 19.2 (a) through (c) are acceptable.]
ITB 20.1 In addition to the original of the Bid, the number of copies is: [Insert
number of copies.]
ITB 20.2 The written confirmation of authorization to sign on behalf of the Bidder
shall consist of: [Insert the name and description of the documentation
required to demonstrate the authority of the signatory to sign the Bid.]
D. Submission and Opening of Bids
ITB 22.1 For Bid submission purposes only, the Employer’s address is :
Attention: [insert full name of person, if applicable]
Street Address: [insert street address and number]
Floor/Room number: [insert floor and room number, if applicable]
City: [insert name of city or town]
ZIP Code: [insert postal (ZIP) code, if applicable]
Country: [insert name of country]
The date for the exchange rate shall be: [Insert day, month and year, e.g.
15 June, 2008, the date not earlier than 30 days prior to, nor later than,
the date of Bid opening specified in ITB 25.1.]
The Employer will convert the amounts in various currencies in which the
Bid Price, corrected pursuant to ITB 33, is payable (excluding Provisional
Sums but including Daywork where priced competitively) to the single
currency identified above at the selling rates established for similar
transactions by the authority specified and on the date stipulated above.
ITB 35.1 [Insert the following only if the Employer intends to execute any specific
elements of the Works by subcontractors selected in advance (nominated
subcontractors). Otherwise delete this BDS 35.1.]
At this time the Employer intends to execute certain specific parts of the
Works by subcontractors selected in advance. [List the specific parts of the
Works and the respective nominated subcontractors.]
OPTION B: Two-Envelope Bidding
Option B: Section I. Instructions to Bidders
The use of the Standard Instructions to Bidders set forth in Section I of these Standard
Bidding Documents for the Procurement of Works (version 1.1) published by JICA in
October, 2012 (hereafter referred to as “Standard ITB”), in all Bidding Documents for
construction works financed by Japanese ODA Loans is required, and they shall be used
without modification. Any necessary changes, acceptable to JICA, to address specific
country and project issues, shall be introduced only through the Bid Data Sheet.
A copy of the Standard Instructions to Bidders may be attached to the Bidding Documents
prepared by the Employer for reference purposes only. If the Instructions to Bidders in the
Bidding Documents prepared by the Employer contain modifications from the Standard
Instructions to Bidders, JICA will not consider them valid and the Standard Instructions to
Bidders, as defined above, shall apply.
Instead of attaching a copy of the Standard Instructions to Bidders, the Employer may use
the following introductory text.]
The Instructions to Bidders governing this bidding process are the “Instructions to Bidders”
included in Option B: Two-Envelope Bidding, Section I, of the Standard Bidding
Documents for Procurement of Works (version 1.1), published by JICA in October, 2012.
Those Instructions to Bidders are available on the JICA’s web site shown below:
http://www.jica.go.jp/english/our_work/types_of_assistance/oda_loans/oda_op_info/guide/tender/index.html
Table of Clauses
A. General ................................................................................................................................3
1. Scope of Bid ..............................................................................................................3
2. Source of Funds.........................................................................................................3
3. Corrupt and Fraudulent Practices ..............................................................................3
4. Eligible Bidders .........................................................................................................5
5. Eligible Materials, Equipment, and Services ...........................................................6
A. General
1. Scope of Bid 1.1 In connection with the Invitation for Bids specified in
Section II, Bid Data Sheet (BDS), the Employer, as
specified in the BDS, issues these Bidding Documents
(hereinafter referred to as “Bidding Documents”) for the
procurement of Works as specified in Section VI, Works
Requirements. The name, identification, and number of the
lot(s) (contract(s)) comprising this International Competitive
Bidding (ICB) process are specified in the BDS.
1.2 Throughout these Bidding Documents:
(a) the term “in writing” means communicated in written
form and delivered against receipt;
(b) except where the context requires otherwise, words
indicating the singular also include the plural and words
indicating the plural also include the singular; and
(c) “day” means calendar day.
2. Source of Funds 2.1 The Borrower specified in the BDS has received or has
applied for a Japanese ODA Loan from Japan International
Cooperation Agency (hereinafter referred to as “JICA”),
with the number, in the amount and on the signed date of the
Loan Agreement specified in the BDS, towards the cost of
the project specified in the BDS. The Borrower intends to
apply a portion of the proceeds of the loan to payments
under the contract(s) for which these Bidding Documents are
issued.
2.2 Disbursement of a Japanese ODA Loan by JICA will be
subject, in all respects, to the terms and conditions of the
Loan Agreement, including the disbursement procedures and
the applicable Guidelines for Procurement under Japanese
ODA Loans specified in the BDS. No party other than the
Borrower shall derive any rights from the Loan Agreement
or have any claim to the loan proceeds.
2.3 The above Loan Agreement will cover only a part of the
project cost. As for the remaining portion, the Borrower will
take appropriate measures for finance.
3. Corrupt and 3.1 It is JICA’s policy to require that Bidders and Contractors,
Fraudulent as well as Borrowers, under contracts funded with Japanese
Practices ODA Loans and other Japanese ODA, observe the highest
standard of ethics during the procurement and execution of
ITB-4 Option B: Section I. Instructions to Bidders
5.2 For purposes of ITB 5.1 above, “origin” means the place
where the materials and equipment are mined, grown,
produced or manufactured, and from which the services are
provided. Materials and equipment are produced when,
through manufacturing, processing, or substantial or major
assembling of components, a commercially recognized
product results that differs substantially in its basic
characteristics or in purpose or utility from its components.
meeting.
7.6 Minutes of the pre-bid meeting, if applicable, including the
text of the questions asked by Bidders, without identifying
the source, and the responses given, together with any
responses prepared after the meeting, will be transmitted
promptly to all Bidders who have acquired the Bidding
Documents in accordance with ITB 6.3. Any modification
to the Bidding Documents that may become necessary as a
result of the pre-bid meeting shall be made by the Employer
exclusively through the issue of an addendum pursuant to
ITB 8 and not through the minutes of the pre-bid meeting.
Nonattendance at the pre-bid meeting will not be a cause for
disqualification of a Bidder.
8. Amendment of 8.1 At any time prior to the deadline for submission of Bids, the
Bidding Documents Employer may amend the Bidding Documents by issuing
addenda.
8.2 Any addendum issued shall be part of the Bidding
Documents and shall be communicated in writing to all who
have obtained the Bidding Documents from the Employer in
accordance with ITB 6.3. If so specified in the BDS, the
Employer shall also promptly publish the addendum on the
Employer’s web page in accordance with ITB 7.1.
8.3 To give Bidders reasonable time in which to take an
addendum into account in preparing their Bids, the
Employer may extend the deadline for the submission of
Bids, pursuant to ITB 22.2.
C. Preparation of Bids
9. Cost of Bidding 9.1 The Bidder shall bear all costs associated with the
preparation and submission of its Bid, and the Employer
shall not be responsible or liable for those costs, regardless
of the conduct or outcome of the bidding process.
10. Language of Bid 10.1 The Bid, as well as all correspondence and documents
relating to the Bid exchanged by the Bidder and the
Employer, shall be written in the language specified in the
BDS. Supporting documents and printed literature that are
part of the Bid may be in another language provided they are
accompanied by an accurate translation of the relevant
passages in the language of Bid, in which case, for purposes
of interpretation of the Bid, such translation shall govern.
11. Documents 11.1 The Bid shall comprise two envelopes submitted
ITB-10 Option B: Section I. Instructions to Bidders
Comprising the Bid simultaneously, one called the Technical Bid containing the
documents listed in ITB 11.2 and the other the Price Bid
containing the documents listed in ITB 11.3, both envelopes
enclosed together in an outer single envelope.
11.2 The Technical Bid shall comprise the following:
(a) Letter of Technical Bid;
(b) Bid Security, in accordance with ITB 19;
(c) alternative bids, if permissible, in accordance with ITB
13;
(d) written confirmation authorizing the signatory of the Bid
to commit the Bidder, in accordance with ITB 20.2;
(e) documentary evidence in accordance with ITB 17
establishing the Bidder’s qualifications to perform the
contract if its Bid is accepted;
(f) Technical Proposal in accordance with ITB 16;
(g) Acknowledgement of Compliance with Guidelines for
Procurement under Japanese ODA Loans (Form ACK),
which shall be signed and dated by the Bidder’s
authorized representative.
(h) Any other document required in the BDS.
11.3 The Price Bid shall comprise the following:
(a) Letter of Price Bid;
(b) completed Price Schedules, in accordance with ITB 12
and 14;
(c) alternative price bids, at Bidder’s option and if
permissible, in accordance with ITB 13;
(d) Any other document required in the BDS.
11.4 In addition to the requirements under ITB 11.2, Bids
submitted by a JV shall include a copy of the Joint Venture
Agreement entered into by all members. Alternatively, a
letter of intent to execute a Joint Venture Agreement in the
event of a successful Bid shall be signed by all members and
submitted with the Bid, together with a copy of the proposed
Agreement.
12. Letters of Bid and 12.1 The Letters of Technical Bid and Price Bid and the
Schedules Schedules, including the Bill of Quantities, shall be prepared
using the relevant forms furnished in Section IV, Bidding
Forms. The forms must be completed without any alterations
to the text, and no substitutes shall be accepted except as
Option B: Section I. Instructions to Bidders ITB-11
13. Alternative Bids 13.1 Unless otherwise specified in the BDS, alternative Bids
shall not be considered.
14. Bid Prices and 14.1 The prices and discounts (including any price reduction)
Discounts quoted by the Bidder in the Letter of Price Bid and in the
Bill of Quantities shall conform to the requirements
specified below.
14.2 The Bidder shall fill in rates and prices for all items of the
Works described in the Bill of Quantities. Items against
which no rate or price is entered by the Bidder shall be
deemed covered by the rates for other items in the Bill of
Quantities and will not be paid for separately by the
Employer. An item not listed in the priced Bill of Quantities
shall be assumed to be not included in the Bid, and provided
that the Bid is determined substantially responsive
notwithstanding this omission, the average price of the item
quoted by substantially responsive Bidders will be added to
the Bid Price and the equivalent total cost of the Bid so
determined will be used for price comparison.
accordance with ITB 12.1, shall be the total price of the Bid,
excluding any discounts offered.
14.4 The Bidder shall quote any discounts and the methodology
for their application in the Letter of Price Bid, in accordance
with ITB 12.1.
15. Currencies of Bid 15.1 The currency(ies) of the Bid shall be as specified in the
and Payment BDS. Payment of the contract price shall be made in the
currency or currencies in which the Bid Price is expressed in
the Bid of the successful Bidder.
15.2 Bidders may be required by the Employer to justify, to the
Employer’s satisfaction, their local and foreign currency
requirements, and to substantiate that the amounts included
in the unit rates and prices and shown in the Schedule of
Adjustment Data are reasonable, in which case a detailed
breakdown of the foreign currency requirements shall be
provided by Bidders.
15.3 The foreign currency requirements generally include the
Option B: Section I. Instructions to Bidders ITB-13
following:
(a) expatriate staff and labour employed directly on the
Works;
(b) social, insurance, medical and other charges relating to
such expatriate staff and labour, and foreign travel -
expenses;
(c) imported materials, both temporary and permanent,
including fuels, oil and lubricants required for the
Works;
(d) depreciation and usage of imported Plant and
Contractor’s Equipment, including spare parts, required
for the Works;
(e) foreign insurance and freight charges for imported
materials, Plant and Contractor’s Equipment, including
spare parts; and
(f) overhead expenses, fees, profit, and financial charges
arising outside the Employer’s country in connection
with the Works.
16. Documents 16.1 The Bidder shall furnish as part of the Technical Bid, a
Comprising the Technical Proposal including a statement of work methods,
Technical Proposal equipment, personnel, schedule, safety plan and any other
information as stipulated in Section IV, Bidding Forms, in
sufficient detail to demonstrate the adequacy of the Bidder’s
proposal to meet the work requirements and the completion
time.
17. Documents 17.1 In accordance with Section III, Evaluation and Qualification
Establishing the Criteria, if the prequalification process was conducted prior
Qualifications of to the bidding process, the Bidder shall provide in the
the Bidder corresponding information sheets included in Section IV,
Bidding Forms, (i) updated information on any assessed
aspect that changed from that time to establish that the
Bidder continues to meet the criteria used at the time of
prequalification and (ii) the requested information on the
additional qualification criteria stated in Section III,
Evaluation and Qualification Criteria, or if the assessment of
qualification criteria was not conducted prior to the bidding
process, the Bidder shall provide the information requested
in the corresponding information sheets included in Section
IV, Bidding Forms.
23. Late Bids 23.1 The Employer shall not consider any Bid that arrives after
the deadline for submission of Bids, in accordance with ITB
22. Any Bid received by the Employer after the deadline for
submission of Bids shall be declared late, rejected, and
returned unopened to the Bidder.
24. Withdrawal, 24.1 A Bidder may withdraw, substitute, or modify its Bid –
Substitution, and Technical or Price – after it has been submitted by sending a
Modification of written notice, duly signed by an authorized representative, and
Bids shall include a copy of the authorization in accordance with
ITB-18 Option B: Section I. Instructions to Bidders
29. Preliminary 29.1 The Employer shall examine the Technical Bid to confirm
Examination of that all documents and technical documentation requested in
Technical Bids ITB 11.2 have been provided, and to determine the
completeness of each document submitted.
29.2 The Employer shall confirm that the following documents
ITB-22 Option B: Section I. Instructions to Bidders
30. Qualification of the 30.1 The Employer shall determine to its satisfaction whether
Bidder Bidders meet the qualifying criteria specified in Section III,
Evaluation and Qualification Criteria, during the evaluation
of Technical Bids. However, if prequalification was carried
out prior to the bidding process, the Employer may carry out
the assessment of the qualification criteria specified in
Section III, Evaluation and Qualification Criteria, for the
Bidder who submitted the lowest evaluated and substantially
responsive Bid only.
30.2 The determination shall be based upon an examination of the
documentary evidence of the Bidder’s qualifications
submitted by the Bidder, pursuant ITB 17.
30.3 An affirmative determination shall be a prerequisite for
award of the Contract to the Bidder. A negative
determination shall result in disqualification of the Bid, in
which event if the assessment of the Bidder’s qualification
was conducted for the lowest evaluated Bidder only, in
accordance with ITB 30.1, the Employer shall proceed to the
next lowest evaluated Bid to make a similar determination.
31. Determination of 31.1 The Employer’s determination of a Technical Bid’s
Responsiveness of responsiveness is to be based on the contents of the Bid
Technical Bid itself, as defined in ITB 11.2.
31.2 A substantially responsive Technical Bid is one that meets
the requirements of the Bidding Documents without material
deviation, reservation, or omission. A material deviation,
reservation, or omission is one that,
(a) if accepted, would
(i) affect in any substantial way the scope, quality, or
performance of the Works specified in the
Contract; or
Option B: Section I. Instructions to Bidders ITB-23
and quantity, the unit price shall prevail and the total
price shall be corrected, unless in the opinion of the
Employer there is an obvious misplacement of the
decimal point in the unit price, in which case the total
price as quoted shall govern and the unit price shall be
corrected;
(b) if there is an error in a total corresponding to the
addition or subtraction of subtotals, the subtotals shall
prevail and the total shall be corrected; and
(c) if there is a discrepancy between words and figures, the
amount in words shall prevail, unless the amount
expressed in words is related to an arithmetic error, in
which case the amount in figures shall prevail subject to
(a) and (b) above.
33.2 Bidders shall be requested to accept correction of
arithmetical errors. Failure to accept the correction in
accordance with ITB 33.1, shall result in the rejection of the
Bid.
34. Conversion to 34.1 For evaluation and comparison purposes, the currency(ies)
Single Currency of the Bid shall be converted into a single currency as
specified in the BDS.
35. Subcontractors 35.1 Unless otherwise stated in the BDS, the Employer does not
intend to execute any specific elements of the Works by
subcontractors selected in advance by the Employer
(nominated subcontractors).
36. Evaluation of Price 36.1 The Employer shall use the criteria and methodologies listed
Bids in this Clause. No other evaluation criteria or methodologies
shall be permitted.
38. Employer’s Right 38.1 The Employer reserves the right to accept or reject any Bid,
to Accept Any Bid, and to annul the bidding process and reject all Bids at any
and to Reject Any time prior to contract award, without thereby incurring any
or All Bids liability to Bidders. In case of annulment, all Bids submitted
and specifically, Bid securities, shall be promptly returned to
the Bidders.
F. Award of Contract
39. Award Criteria 39.1 Subject to ITB 38.1, the Employer shall award the Contract
to the Bidder whose offer has been determined to be the
lowest evaluated Bid and is substantially responsive to the
Bidding Documents, provided further that the Bidder is
determined to be qualified to perform the Contract
satisfactorily.
40. Notification of 40.1 Prior to the expiration of the period of Bid validity, the
Award Employer shall notify the successful Bidder, in writing, that
its Bid has been accepted. The notification letter
(hereinafter and in the Conditions of Contract and Contract
Forms called the “Letter of Acceptance”) shall specify the
sum that the Employer will pay the Contractor in
consideration of the execution and completion of the Works
(hereinafter and in the Conditions of Contract and Contract
Forms called “the Accepted Contract Amount”). At the
same time, the Employer shall also notify all other Bidders
of the results of the bidding.
Section II, Bid Data Sheet, shall be filled in by the Employer before issuance of the Bidding
Documents.
The Bid Data Sheet (BDS) contains information and provisions that are specific to a
particular bidding process. The Employer must specify in the BDS only the information that
the ITB request be specified in the BDS. All information shall be provided; no clause shall
be left blank.
To facilitate the preparation of the BDS, its clauses are numbered with the same numbers as
the corresponding ITB clause.
Option B: Section II. Bid Data Sheet BDS-1
ITB 7.4 A Pre-bid meeting [insert “will” or “will not”, as appropriate] take place
at the following date, time and place:
[If a pre-bid meeting will take place, insert the date, time and place
information in the spaces provided below. Otherwise insert “Not
Applicable” in the spaces provided below for the date, time and place]
Date:
Time:
Place:
A site visit conducted by the Employer [insert “will be” or “will not be”,
as appropriate] organized.
ITB 8.2 Addenda, if any, [select “will” or “will not”, as appropriate] be published
on the Employer’s web page.
C. Preparation of Bids
ITB 10.1 The language of the Bid is: [Insert one of the following: Japanese, English,
Spanish or French.]
ITB 11.2 (h) The Bidder shall submit with its Technical Bid the following additional
documents:
[List any additional document not already listed in ITB 11.2 that must be
submitted with the Technical Bid.]
ITB 11.3 (d) The Bidder shall submit with its Price Bid the following additional
documents:
[List any additional document not already listed in ITB 11.3 that must be
submitted with the Price Bid.]
ITB 13.1 [The following provision should be included and the required
corresponding information inserted only if alternative Bids will be
considered. Otherwise delete this BDS 13.1.]
information inserted only if the prices quoted by the Bidder are not subject
to price adjustment. Otherwise delete this BDS 14.5.]
The prices quoted by the Bidder shall be: [insert “fixed; consequently, the
Bidder is not required to furnish the indices and weightings for the price
adjustment formulae in the Schedule of Adjustment Data”]
ITB 14.7 [The following provision should be included and the corresponding
information inserted only if duties, taxes and other levies will be exempted,
reimbursed, or paid by the Employer on behalf of the Contractor.
Otherwise delete this BDS 14.7.]
Duties, taxes and other levies indicated below shall be [choose one of the
following: “exempted”, reimbursed, “paid by the Employer on behalf of
the Contractor”, as appropriate.]:
[List duties, taxes and other levies.]
ITB 15.1 The currency(ies) of the Bid shall be as described below:
The unit rates and prices shall be quoted by the Bidder in the Bill of
Quantities separately in the following currencies:
(i) for those inputs to the Works that the Bidder expects to supply from
within the Employer’s country, in [insert the name of the currency of
the Employer’s country], the name of the currency of the Employer’s
country, and further referred to as “the local currency”; and
(ii) for those inputs to the Works that the Bidder expects to supply from
outside the Employer’s country (referred to as “the foreign currency
requirements”), in [insert Japanese Yen and/or other international
trading currency or currencies].
ITB 18.1 The Bid validity period shall be [insert a number of days] days.
[This period should be realistic, allowing sufficient time to evaluate the
Bids, bearing in mind the complexity of the Works and the time required
for obtaining references, clarifications, clearances, and approvals
(including JICA’s concurrence) and for notification of the award.
Normally the validity period should not exceed 120 days.]
ITB 18.3 (a) The Bid Price shall be adjusted by the following factor: [insert factor for
adjustment]
[The local currency portion of the Contract price shall be adjusted by a
factor reflecting local inflation during the period of extension, and the
foreign currency portion of the Contract price shall be adjusted by a factor
reflecting the international inflation (in the country of the foreign
currency) during the period of extension.]
ITB 18.3 (b) The fixed portion of the Bid Price shall be adjusted by the following factor:
[insert factor for adjustment]
[The local currency portion of the fixed portion of the Contract price shall
be adjusted by a factor reflecting local inflation during the period of
BDS-4 Option B: Section II. Bid Data Sheet
extension, and the foreign currency portion of the fixed portion of the
Contract price shall be adjusted by a factor reflecting the international
inflation (in the country of the foreign currency) during the period of
extension.]
ITB 19.1 The amount and currency of the Bid Security shall be [Insert amount and
currency of the Bid Security. The amount should be approximately 2% of
the estimated cost of the contract.]
ITB 19.2 (d) Other types of acceptable securities: [Insert names of other acceptable
securities. Insert “None” if no other forms of bid securities besides those
listed in ITB 19.2 (a) through (c) are acceptable.]
ITB 20.1 In addition to the original of the Bid, the number of copies is: [Insert
number of copies.]
ITB 20.2 The written confirmation of authorization to sign on behalf of the Bidder
shall consist of: [Insert the name and description of the documentation
required to demonstrate the authority of the signatory to sign the Bid.]
D. Submission and Opening of Bids
ITB 22.1 For Bid submission purposes only, the Employer’s address is :
Attention: [insert full name of person, if applicable]
Street Address: [insert street address and number]
Floor/Room number: [insert floor and room number, if applicable]
City: [insert name of city or town]
ZIP Code: [insert postal (ZIP) code, if applicable]
Country: [insert name of country]
ITB 25.1 The opening of the Technical Bid shall take place at:
Street Address: [insert street address and number]
Floor/Room number: [insert floor and room number, if applicable]
City : [insert name of city or town]
Country: [insert name of country]
Date: [insert day, month, and year]
Time: [insert time, and identify if a.m. or p.m., e.g. 10:30 a.m.]
1. Evaluation
1.1.2 Personnel
The Bidder must demonstrate that it has the personnel for the key positions that meet
the following requirements:
Total Work Experience in
No. Position Experience Similar Works
(years) (years)
1 Project Manager
2 e.g. Chief Engineer(s)1
3 e.g. Health & Safety (Accident Prevention)2
Officer
4
5
Notes for the Employer:
1 Chief Engineer(s) or Section Manager(s) who is(are) responsible for the major activities
should be evaluated.
2 The personnel for the key position include an accident prevention officer, as appropriate.
The Bidder shall provide details of the proposed personnel and their experience
records in Form PER-1 and Form PER-2 in Section IV, Bidding Forms.
1.1.3 Equipment
The Bidder must demonstrate that it has the key equipment listed hereafter:
Minimum Number
No. Equipment Type and Characteristics
required
1
2
3
EQC-2 Section III. Evaluation and Qualification Criteria (following prequalification)
4
5
The Bidder shall provide further details of proposed items of equipment using Form
EQU in Section IV, Bidding Forms.
1.4 Alternative Technical Solutions for Specified Parts, if permitted under ITB 13.4, will
be evaluated as follows:
…………………………………………………………………………………………
………………………………………………………………………............................
Section III. Evaluation and Qualification Criteria (following prequalification) EQC-3
2. Qualification
(ii) Qualification Criteria for Multiple Contracts: [Insert the following text in case of Multiple Contracts. Otherwise delete
this EQC clause.
“The criteria for qualification is the aggregate minimum requirement, or any other reasonable requirements set forth by the
Employer, for respective lots as specified under Sub-Factors 2.2 (i) and (ii) below.”]
2. Usually not less than 25% of the requirement for each member of a JV.
3. Usually not less than 40% of the requirement for one member of a JV.
Section III. Evaluation and Qualification Criteria (without prequalification)
This Section contains all the criteria that the Employer shall use to evaluate Bids and qualify
Bidders. In accordance with ITB 30 and ITB 36, no other factors, methods or criteria shall be
used. The Bidder shall provide all the information requested in the forms included in Section IV,
Bidding Forms.
The Notes for the Bidders contained in this Section III should be included in the actual Bidding
Documents issued by the Employer.
Section III. Evaluation and Qualification Criteria (without prequalification) EQC-1
1. Evaluation
1.1.2 Personnel
The Bidder must demonstrate that it has the personnel for the key positions that meet
the following requirements:
Total Work Experience in
No. Position Experience Similar Works
(years) (years)
1 Project Manager
2 e.g. Chief Engineer(s)1
3 e.g. Health & Safety (Accident Prevention)2
Officer
4
5
Notes for the Employer:
1 Chief Engineer(s) or Section Manager(s) who is(are) responsible for the major activities
should be evaluated.
2 The personnel for the key position include an accident prevention officer, as appropriate.
The Bidder shall provide details of the proposed personnel and their experience
records in Form PER-1 and Form PER-2 in Section IV, Bidding Forms.
1.1.3 Equipment
The Bidder must demonstrate that it has the key equipment listed hereafter:
Minimum Number
No. Equipment Type and Characteristics
required
1
2
3
EQC-2 Section III. Evaluation and Qualification Criteria (without prequalification)
4
5
The Bidder shall provide further details of proposed items of equipment using Form
EQU in Section IV, Bidding Forms.
1.3 Alternative Completion Times, if permitted under ITB 13.2, will be evaluated as
follows:
…………………………………………………………………………………………
………………………………………………………………………............................
1.4 Alternative Technical Solutions for Specified Parts, if permitted under ITB 13.4, will
be evaluated as follows:
…………………………………………………………………………………………
………………………………………………………………………............................
Section III. Evaluation and Qualification Criteria (without prequalification) EQC-3
2. Qualification
(ii) Qualification Criteria for Multiple Contracts: [Insert the following text in case of Multiple Contracts. Otherwise delete
this EQC clause.
“The criteria for qualification is the aggregate minimum requirement, or any other reasonable requirements set forth by
the Employer, for respective lots as specified under Sub-Factors 2.3.2, 2.4.2(a), 2.4.2(b), 2.5.1(i), 2.5.1(ii) below.”]
2.1. Eligibility
2.1.1 Nationality Nationality in accordance with ITB Must meet N/A Must meet N/A Forms ELI – 1
4.3 requirement requirement and 2, with
attachments
2.1.2 Conflict of No conflicts of interest in ITB 4.2 Must meet N/A Must meet N/A Letter of Bid
Interest requirement requirement
2.1.3 JICA Ineligibility Not having been declared ineligible Must meet N/A Must meet N/A Letter of Bid
by JICA, as described in ITB 4.4 requirement requirement Form ACK
EQC-4 Section III. Evaluation and Qualification Criteria (without prequalification)
2.3.2 Average Annual Minimum average annual Must meet Must meet Must meet Must meet Form FIN – 2
Construction construction turnover of USD requirement requirement [insert [insert
Turnover 3 6 7
[insert amount in USD] , number] % of number] %
calculated as total certified the of the
payments received for contracts in requirement requirement
progress and/ or completed, within
4
the last [insert number] years,
5
divided by [insert number] years.
2. The financial information provided by a Bidder should be reviewed in its entirety to allow a truly informed judgment, and the pass-fail decision on the
financial position of the Bidder should be given on this basis. Any abnormal features which may lead to financial problems should alert the Employer to
seek expert professional advice for further review and interpretation.
3. The amount stated should normally not be less than twice the estimated annual turnover in the proposed Works contract (based on a straight-line
projection of the Employer’s estimated cost, including contingencies, over the contract duration). The multiplier of 2 may be reduced for very large
contracts but should not be less than 1.5.
4. The time period is normally five (5) years or more, but may be reduced to not less than three (3) years (in agreement with JICA) under special country
circumstances, such as to provide opportunities for a newly privatized construction industry with only a short record of experience, etc.
6. Usually not less than 25% of the requirement for each member of a JV.
7. Usually not less than 40% of the requirement for one member of a JV.
EQC-8 Section III. Evaluation and Qualification Criteria (without prequalification)
2.4. Experience
2.4.1 General Experience under construction Must meet N/A Must meet N/A Form EXP – 1
Construction contracts in the role of prime requirement requirement
Experience contractor (single entity or JV
member), subcontractor, or
(i)
management contractor for at
least the last [insert number]
1 st
years , starting 1 January [insert
year].
2.4.2 Specific A minimum number of [insert Must meet Must meet N/A N/A Form EXP – 2 (a)
(a) Construction 2 (ii) requirement (v)
number of contracts] similar requirement
Experience contracts that have been
(iii)
satisfactorily and substantially
completed as a prime contractor
(iv)
(single entity or JV member)
3
between 1st January [insert year]
and Bid submission deadline.
2.4.2 For the above or other contracts Must meet Must meet N/A N/A Form EXP – 2 (b)
(b) completed and under requirement requirement
implementation as prime contractor (can be a (can be a
(single entity or JV member), specialist specialist
management contractor or subcontractor) subcontractor)
(vi) st
subcontractor between 1
4
January [insert year] and Bid
submission deadline, a minimum
Section III. Evaluation and Qualification Criteria (without prequalification) EQC-9
of the Employer to risk of contractor default, country conditions and history of similar works constructed in the past.
3. The time range is normally five (5) years, and may be extended up to a period of ten (10) years for large-scale projects.
4. Same as that stipulated in Sub-Factor 2.4.2 (a) above.
3
5. List the monthly or annual production rate for the key construction activity (or activities) in the proposed contract or works, e.g., “one million m of rock
3
placed in rockfill dams in one year; X tons of asphalt concrete per month place in road paving; Y m of concrete place in … etc.” The rates should be a
percentage (say about 80 percent) of the estimated production rate of the key activity (or activities) in the contract or Works as needed to meet the
expected construction schedule with due allowance for adverse climatic condition.
Section III. Evaluation and Qualification Criteria (without prequalification) EQC-11
1. Indicate the construction cash flow requirement for a number of months, determined as the total time needed by the Employer to pay a contractor’s
invoice, allowing for (a) the actual time consumed for construction, from the beginning of the month invoiced, (b) the time needed by the Engineer to issue
the monthly payment certificate, (c) the time needed by the Employer to pay the amount certified, and (d) a contingency period of one month to allow for
EQC-12 Section III. Evaluation and Qualification Criteria (without prequalification)
unforeseen delays. The total period should not exceed six (6) months. The assessment of the monthly amount should be based on a straight-line
projection of the estimated cash flow requirement over the particular contract period, neglecting the effect of any advance payment and retention monies,
but including contingency allowances in the estimated contract cost.
2. Usually not less than 25% of the requirement for each member of a JV.
3. Usually not less than 40% of the requirement for one member of a JV.
Section IV. Bidding Forms
Table of Forms
Letter of Bid............................................................................................................................. 3
Letter of Bid
(a) We have examined and have no reservations to the Bidding Documents, including
addenda issued in accordance with Instructions to Bidders (ITB 8). [Insert the number
and issuing date of each addendum];
(b) We, including subcontractors meet the eligibility requirements in accordance with ITB 4
and ITB 5.
(c) We, including subcontractors have no conflict of interest in accordance with ITB 4;
(d) We offer to execute in conformity with the Bidding Documents the following Works:
[insert a brief description of the Works];
(e) The total price of our Bid, excluding any discounts offered in item (f) below is:
In case of only one lot, total price of the Bid [insert the total price of the Bid in words
and figures, indicating the various amounts and the respective currencies]
[In case of multiple lots, insert the total price of each lot]
[In case of multiple lots, insert the total price of all lots (sum of all lots)];
(f) The discounts offered and the methodology for their application are:
The exact method of calculations to determine the net price after application of discounts
is shown below: [specify in detail the method that shall be used to apply the discounts.] ;
(g) Our Bid shall be valid for a period of [specify the number of calendar days] days from
the date fixed for the Bid submission deadline in accordance with the Bidding
Documents, and it shall remain binding upon us and may be accepted at any time before
the expiration of that period;
BF-4 Section IV. Bidding Forms
(h) If our Bid is accepted, we commit to obtain a Performance Security in accordance with
the Bidding Documents;
(i) We are not participating, as a Bidder or as a subcontractor, in more than one Bid in this
bidding process in accordance with ITB 4.2(c), other than alternative Bids submitted in
accordance with ITB 13;
(j) We understand that this Bid, together with your written acceptance thereof included in
your Letter of Acceptance, shall constitute a binding contract between us, until a formal
contract is prepared and executed;
(k) We understand that you are not bound to accept the lowest evaluated Bid or any other
bid that you may receive; and
(l) We hereby certify that we have taken steps to ensure that no person acting for us or on
our behalf will engage in any type of fraud and corruption.
Title of the person signing the Bid [insert complete title of the person signing the Bid]
Signature of the person named above [insert signature of person whose name and capacity
are shown above]
Date signed [insert date of signing] day of [insert month], [insert year]
*: In the case of the Bid submitted by joint venture specify the name of the Joint Venture as
Bidder
**: Person signing the Bid shall have the power of attorney given by the Bidder to be
attached with the Bid.
Section IV. Bidding Forms BF-5
(a) We have examined and have no reservations to the Bidding Documents, including
addenda issued in accordance with Instructions to Bidders (ITB 8). [Insert the number
and issuing date of each addendum];
(b) We, including subcontractors meet the eligibility requirements in accordance with ITB 4
and ITB 5;
(c) We, including subcontractors have no conflict of interest in accordance with ITB 4;
(d) We offer to execute in conformity with the Bidding Documents the following Works:
[insert a brief description of the Works];
(e) Our Bid shall be valid for a period of [specify the number of calendar days] days from
the date fixed for the Bid submission deadline in accordance with the Bidding
Documents, and it shall remain binding upon us and may be accepted at any time before
the expiration of that period;
(f) We are not participating, as a Bidder or as a subcontractor, in more than one Bid in this
bidding process in accordance with ITB 4.2(c), other than alternative Bids submitted in
accordance with ITB 13; and
(g) We hereby certify that we have taken steps to ensure that no person acting for us or on
our behalf will engage in any type of fraud and corruption.
Title of the person signing the Bid [insert complete title of the person signing the Bid]
BF-6 Section IV. Bidding Forms
Signature of the person named above [insert signature of person whose name and capacity
are shown above]
Date signed [insert date of signing] day of [insert month], [insert year]
*: In the case of the Bid submitted by joint venture specify the name of the Joint Venture as
Bidder
**: Person signing the Bid shall have the power of attorney given by the Bidder to be
attached with the Bid.
Section IV. Bidding Forms BF-7
(a) We have examined and have no reservations to the Bidding Documents, including
addenda issued in accordance with Instructions to Bidders (ITB 8). [Insert the number
and issuing date of each addendum];
(b) We offer to execute in conformity with the Bidding Documents and Technical Bid the
following Works: [insert a brief description of the Works];
(c) The total price of our Bid, excluding any discounts offered in item (d) below is:
In case of only one lot, total price of the Bid [insert the total price of the Bid in words
and figures, indicating the various amounts and the respective currencies]
[In case of multiple lots, insert the total price of each lot]
[In case of multiple lots, insert the total price of all lots (sum of all lots)];
(d) The discounts offered and the methodology for their application are:
The exact method of calculations to determine the net price after application of discounts
is shown below: [specify in detail the method that shall be used to apply the discounts.] ;
(e) Our Bid shall be valid for a period of [specify the number of calendar days] days from
the date fixed for the Bid submission deadline in accordance with the Bidding
Documents, and it shall remain binding upon us and may be accepted at any time before
the expiration of that period;
(f) If our Bid is accepted, we commit to obtain a Performance Security in accordance with
the Bidding Documents;
BF-8 Section IV. Bidding Forms
(g) We understand that this Bid, together with your written acceptance thereof included in
your Letter of Acceptance, shall constitute a binding contract between us, until a formal
contract is prepared and executed; and
(h) We understand that you are not bound to accept the lowest evaluated Bid or any other
Bid that you may receive.
Title of the person signing the Bid [insert complete title of the person signing the Bid]
Signature of the person named above [insert signature of person whose name and capacity
are shown above]
Date signed [insert date of signing] day of [insert month], [insert year]
*: In the case of the Bid submitted by joint venture specify the name of the Joint Venture as
Bidder
**: Person signing the Bid shall have the power of attorney given by the Bidder to be
attached with the Bid.
Section IV. Bidding Forms BF-9
[In this Table A, the Employer shall indicate the necessary information in columns (a), (b),
(c) and (d), and shall also provide a fixed value in A and a range of values in B, C, D and E
of column (f). For very large and/or complex works contracts, it may be necessary to specify
several families of price adjustment formulae for the different works involved and to prepare
the corresponding adjustment tables.]
The Bidder shall fill in column (e) and specify a value within the ranges given by the
Employer in B, C, D and E of column (f), so that the total weighting equals 1.00.
BF-10 Section IV. Bidding Forms
Currency: __________[Insert name of currency; if the Bidder wishes to quote in more than
one foreign currency then this table should be repeated for each foreign currency.]
The Bidder shall indicate the type of currency and columns (c), (d), (e) and (f), and specify a
value within the ranges given by the Employer in B, C, D and E of column (g), so that the
total weighting equals 1.00.
Section IV. Bidding Forms BF-11
Bill of Quantities
Content
The Bill of Quantities should be divided generally into the following sections:
(a) Preamble;
(b) Work Items (grouped into parts);
(c) Daywork Schedule; and
(d) Summary.
Preamble
The Preamble should indicate the inclusiveness of the unit prices, and should state the
methods of measurement that have been adopted in the preparation of the Bill of Quantities
and that are to be used for the measurement of any part of the Works.
Rock
Where excavation, boring, or driving is included in the Works, a comprehensive definition of
rock (always a contentious topic in contract administration), if not given in the Technical
Specification, should be given in the Preamble, and this definition should be used for the
purposes of measurement and payment.
Work Items
The items in the Bill of Quantities should be grouped into sections to distinguish between
those parts of the Works that by nature, location, access, timing, or any other special
characteristics may give rise to different methods of construction, phasing of the Works, or
considerations of cost. General items common to all parts of the Works may be grouped as a
separate section in the Bill of Quantities. When a family of Price Adjustment Formulae is
used, they should relate to appropriate sections in the Bill of Quantities.
BF-12 Section IV. Bidding Forms
Quantities
Quantities should be computed net from the Drawings, unless directed otherwise in the
Contract, and no allowance should be made for bulking, shrinkage, or waste. Quantities
should be rounded up or down where appropriate and spurious accuracy should be avoided.
Units of Measurement
The following units of measurement and abbreviations are recommended for use (unless
other national units are mandatory in the country of the Employer).
Unit Abbreviation Unit Abbreviation
cubic meter m3 or cu m millimeter mm
hectare ha month mon
hour h number nr
kilogram kg square meter m2 or sq m
lump sum sum square millimeter mm2 or sq mm
meter m week wk
metric ton t
(1,000 kg)
Daywork Schedule
A Daywork Schedule should be included if the probability of unforeseen work, outside the
items included in the Bill of Quantities, is relatively high. To facilitate checking by the
Employer of the realism of rates quoted by the Bidders, the Daywork Schedule should
normally comprise:
(a) a list of the various classes of labour, materials, and Contractor’s Equipment for which
basic Daywork rates or prices are to be inserted by the Bidder, together with a statement
of the conditions under which the Contractor will be paid for work executed on a
Daywork basis; and
(b) a percentage to be entered by the Bidder against each basic Daywork Subtotal amount
for labour, materials, and Plant representing the Contractor’s profit, overheads,
supervision, and other charges.
Summary
The Summary should contain a tabulation of the separate parts of the Bill of Quantities
carried forward, with provisional sums for Daywork, for physical (quantity) contingencies,
and for price contingencies (upward price adjustment) where applicable.
These Notes for Preparing a Bill of Quantities are intended only as information for the
Employer or the person drafting the Bidding Documents. They should not be included in the
final documents.
BF-14 Section IV. Bidding Forms
2. The quantities given in the Bill of Quantities are estimated and provisional, and are
given to provide a common basis for bidding. The basis of payment will be the actual
quantities of work ordered and carried out, as measured by the Engineer (accepted by the
Contractor) and valued at the rates and prices bid in the priced Bill of Quantities, where
applicable, and otherwise at such rates and prices as the Engineer may fix within the terms of
the Contract.
3. The rates and prices bid in the priced Bill of Quantities shall, except insofar as it is
otherwise provided under the Contract, include all Constructional Plant, labour, supervision,
materials, erection, maintenance, insurance, profit, taxes, and duties, together with all general
risks, liabilities, and obligations set out or implied in the Contract.
4. A rate or price shall be entered against each item in the priced Bill of Quantities,
whether quantities are stated or not. The cost of Items against which the Contractor has
failed to enter a rate or price shall be deemed to be covered by other rates and prices entered
in the Bill of Quantities.
5. The whole cost of complying with the provisions of the Contract shall be included in
the Items provided in the priced Bill of Quantities, and where no Items are provided, the cost
shall be deemed to be distributed among the rates and prices entered for the related Items of
Work.
6. General directions and descriptions of work and materials are not necessarily repeated
nor summarized in the Bill of Quantities. References to the relevant sections of the Contract
documentation shall be made before entering prices against each item in the priced Bill of
Quantities.
7. The Employer shall indicate in the Summary of Provisional Sums an amount equivalent
to one-half of the Employer’s estimate of the cost of the Dispute Board (DB) for payments to
the Contractor of the Employer’s share of the payments to the DB member(s).
Contractor’s overhead, profit, etc., shall not be included in the provisional sums for the cost
of the DB.
11. Rock is defined as all materials that, in the opinion of the Engineer, require blasting, or
the use of metal wedges and sledgehammers, or the use of compressed air drilling for their
removal, and that cannot be extracted by ripping with a tractor of at least 150 brake hp with a
single, rear-mounted, heavy-duty ripper.
B. Work Items
1. The Bill of Quantities usually contains the following part Bills, which have been
grouped according to the nature or timing of the work:
2. Bidders shall price the Bill of Quantities in the currency or currencies specified in the
Instructions to Bidders.
1
The method of measurement should be spelled out precisely in the Preamble to the Bill of Quantities,
describing for example the allowances (if any) for timbering in excavation, etc. Many national standard
reference guides have been prepared on the subject, and one such guide is the Standard Method of
Measurement of the U.K. Institution of Civil Engineers.
BF-16 Section IV. Bidding Forms
—etc.—
C. Daywork Schedule 2
General
1. Reference should be made to Sub-Clause 13.6 of the General Conditions. Work shall
not be executed on a daywork basis except by written order of the Engineer. Bidders shall
enter basic rates for daywork items in the Schedules, which rates shall apply to any quantity
of daywork ordered by the Engineer. Nominal quantities have been indicated against each
item of daywork, and the extended total for Daywork shall be carried forward as a
Provisional Sum to the Summary Total Bid Amount. Unless otherwise adjusted, payments
for daywork shall be subject to price adjustment in accordance with the provisions in the
Conditions of Contract. The basic rates applied to daywork items will be stated and payable
in local currency only.
Daywork Labour
2. In calculating payments due to the Contractor for the execution of daywork, the hours
for labour will be reckoned from the time of arrival of the labour at the job site to execute the
particular item of daywork to the time of return to the original place of departure, but
excluding meal breaks and rest periods. Only the time of classes of labour directly doing
work ordered by the Engineer and for which they are competent to perform will be
measured. The time of gangers (charge hands) actually doing work with the gangs will also
be measured but not the time of foremen or other supervisory personnel.
3. The Contractor shall be entitled to payment in respect of the total time that labour is
employed on daywork, calculated at the basic rates entered by him in the Schedule of
Daywork Rates: 1. Labour, together with an additional percentage payment on basic rates
representing the Contractor’s profit, overheads, etc.,3 as described below:
2
(i) A “Daywork Schedule” is commonly found in contracts where the likely incidence of unforeseen work
cannot be covered by definitive descriptions and approximate quantities in the Bill of Quantities. The
preferred alternative is to value the additional work in accordance with Sub-Clauses 13.1 and 13.2 of the
Conditions of Contract. A Daywork Schedule normally has the disadvantage of not being competitive
among Bidders, who may therefore load the rates assigned to some or all the items. If a Daywork
Schedule is to be included at all in the Bidding Documents, it is preferable to include nominal quantities
against the items most likely to be used, and to carry the sum of the extended amounts forward into the
Bid Summary in order to make the basic Schedule of Daywork Rates competitive.
(ii) The total amount assigned to such competitive daywork is normally 3–5 percent of the estimated base
Contract Price and is regarded as a Provisional Sum for contingencies to be expended under the direction
and at the discretion of the Engineer. A limitation on quantity should not apply, and the unit rate quoted
should be invariable whatever quantities of work are ordered.
3
This method of indicating profit and overheads separately facilitates the addition of further items of daywork,
if needed, the basic costs of which can then be checked more easily. An alternative is to make Daywork rates
all-inclusive of the Contractor’s overhead and profit, etc., in which case this paragraph and the relevant
Daywork Schedule should be modified accordingly.
BF-20 Section IV. Bidding Forms
(a) The basic rates for labour shall cover all direct costs to the Contractor, including
(but not limited to) the amount of wages paid to such labour, transportation time,
overtime, subsistence allowances, and any sums paid to or on behalf of such
labour for social benefits in accordance with [country of Borrower] law.
(b) The additional percentage payment to be quoted by the Bidder and applied to
costs incurred under (a) above shall be deemed to cover the Contractor’s profit,
overheads, superintendence, liabilities, and insurances and allowances to labour,
timekeeping, and clerical and office work, the use of consumable stores, water,
lighting, and power; the use and repair of stagings, scaffolding, workshops, and
stores, portable power tools, manual plant, and tools; supervision by the
Contractor’s staff, foremen, and other supervisory personnel; and charges
incidental to the foregoing.
Daywork Materials
4. The Contractor shall be entitled to payment in respect of materials used for daywork
(except for materials for which the cost is included in the percentage addition to labour costs
as detailed heretofore), at the basic rates entered by him in the Schedule of Daywork Rates:
2. Materials, together with an additional percentage payment on the basic rates to cover
overhead charges and profit, as follows:
(a) the basic rates for materials shall be calculated on the basis of the invoiced price,
freight, insurance, handling expenses, damage, losses, etc., and shall provide for
delivery to store for stockpiling at the Site.
(b) the additional percentage payment shall be quoted by the Bidder and applied to
the equivalent local currency payments made under (a) above. The basic rates
will be payable in local currency only.
(c) the cost of hauling materials for use on work ordered to be carried out as daywork
from the store or stockpile on the Site to the place where it is to be used will be
paid in accordance with the terms for Labour and Construction in this schedule.
4
This is an example of wording to include overhead and profit, etc., in the daywork rates. A separate
percentage addition could be used as for labour and materials.
Section IV. Bidding Forms BF-21
operators, and assistants will be paid for separately as described under the section on
Daywork Labour.5
6. In calculating the payment due to the Contractor for Contractor’s Equipment employed
on daywork, only the actual number of working hours will be eligible for payment, except
that where applicable and agreed with the Engineer, the travelling time from the part of the
Site where the Contractor’s Equipment was located when ordered by the Engineer to be
employed on daywork and the time for return journey thereto shall be included for payment.
5
An alternative, sometimes adopted for administrative convenience, is to include the cost of drivers, operators,
and assistants in the basic rates for Contractor’s Equipment. The last sentence of paragraph 5 should then be
modified accordingly.
BF-22 Section IV. Bidding Forms
Subtotal
a
D122 Allow percent of Subtotal for Contractor’s
overhead, profit, etc., in accordance with
paragraph 3 (b) above.
Subtotal
D122 Allow percenta of Subtotal for Contractor’s
overhead, profit, etc., in accordance with
paragraph 3 (b) above.
Daywork Summary
Amount
Description
Local
1. Total for Daywork: Labour
2. Total for Daywork: Materials
3. Total for Daywork: Contractor’s Equipment
Total for Daywork (Provisional Sum)
(carried forward to Bid Summary, p. ) ---------
BF-26 Section IV. Bidding Forms
etc.
Cost of DB*
[*One-half of the Employer’s cost estimate of the Disputes Board shall be included in the Provisional Sums.
Contractor’s overheads and profits shall not be included in this amount.]
Section IV. Bidding Forms BF-27
Grand Summary
Contract Name:
Contract No.:
Technical Proposal
- Site Organization
- Method Statement
- Mobilization Schedule
- Construction Schedule
- Safety Plan
- Personnel
- Equipment
- [Others]
Section IV. Bidding Forms BF-29
Site Organization
Method Statement
Mobilization Schedule
Construction Schedule
Safety Plan
[The Bidder shall provide the names of suitably qualified personnel to meet the specified
requirements stated in Section III, Evaluation and Qualification Criteria, Clause 1.1.2. ]
1. Title of position*
Name
2. Title of position*
Name
3. Title of position*
Name
4. Title of position*
Name
[The Bidder shall provide the data on the experience of the personnel indicated in Form
PER-1, in the form below:]
Name of Bidder
Position
Professional qualifications
Address of employer
Fax E-mail
[Summarize professional experience over the last 20 years, in reverse chronological order.
Indicate particular technical and managerial experience relevant to the project.]
[The Bidder shall provide adequate information to demonstrate clearly that it has the
capability to meet the requirements for the key equipment listed in Section III, Evaluation and
Qualification Criteria, Clause 1.1.3. A separate Form shall be prepared for each item of
equipment listed, or for alternative equipment proposed by the Bidder.]
Item of equipment
Bidders Qualification
[The Employer must choose Option I below if prequalification was carried out prior to the
bidding process, or Option II if Bidder’s qualification will be assessed at the bidding stage.]
1. In accordance with Section III, Evaluation and Qualification Criteria, Clause 2.1, the Bidder
shall update the information given during the corresponding prequalification exercise to
demonstrate that he continues to meet the criteria used at the time of prequalification using
the following forms:
To establish its qualifications to perform the contract in accordance with Section III, Evaluation
and Qualification Criteria, the Bidder shall provide the information requested in the
corresponding Forms included hereunder:
[The following form is additional to Form ELI-1, and shall be completed to provide
information relating to each JV member (in case the Bidder is a JV) as well as any
specialist subcontractor proposed to be used by the Bidder for any part of the Contract
resulting from this process.]
[The following table shall be filled in for the Bidder and for each member of a JV]
Non-Performing Contracts
Contract non-performance did not occur since 1st January [insert year], in accordance with the
Prequalification criteria or Section III, Evaluation and Qualification Criteria, Sub-Factor 2.2.1, as
appropriate.
Contract(s) not performed since 1st January [insert year], in accordance with the
Prequalification criteria or Section III, Evaluation and Qualification Criteria, Sub-Factor 2.2.1,
as appropriate, is(are) indicated below:
Year Non- performed portion Contract Identification Total Contract
of contract Amount (current
value, currency,
exchange rate
and USD
equivalent)
[insert [insert amount and Contract Identification: [insert complete [insert amount]
year] percentage] contract name, number, and any other
identification]
Name of Employer: [insert full name]
Address of Employer: [insert
street/city/country]
Reason(s) for non performance: [indicate
main reason(s)]
BF-42 Section IV. Bidding Forms
2. Pending Litigation
Pending Litigation
No pending litigation in accordance with the Prequalification criteria or Section III, Evaluation
and Qualification Criteria, Sub-Factor 2.2.2, as appropriate.
Pending litigation in accordance with the Prequalification criteria or Section III, Evaluation and
Qualification Criteria, Sub-Factor 2.2.2, as appropriate, is indicated below:
Year of Amount in dispute Outcome Contract Identification Total Contract
dispute (currency) as Amount (current
Percentage value, currency,
of Net exchange rate and
Worth USD equivalent)
[insert [insert amount] [insert Contract Identification: [insert amount]
year] percentage] [indicate complete contract
name, number, and any other
identification]
Name of Employer: [insert
full name]
Address of Employer: [insert
street/ city/ country]
Matter in dispute: [indicate
main issues in dispute]
Status of dispute: [Indicate if
it is being treated by the
Adjudicator, under
Arbitration or being dealt
with by the Judiciary]
Section IV. Bidding Forms BF-43
3. Litigation History
Litigation History
No court/arbitral award decisions against the Bidder since 1st January [insert year], in
accordance with the Prequalification criteria or Section III, Evaluation and Qualification Criteria, Sub-
Factor 2.2.3, as appropriate.
Court/ arbitral award decisions against the Bidder since 1st January [insert year], in accordance
with the Prequalification criteria or Section III, Evaluation and Qualification Criteria, Sub-Factor 2.2.3,
as appropriate, are indicated below:
Year of Contract Identification Total Contract
award Amount (current
value, currency,
exchange rate and
USD equivalent)
[insert year] Contract Identification: [indicate complete contract name, [insert amount]
number, and any other identification]
Name of Employer: [insert full name]
Address of Employer: [insert street/city/country]
Matter in dispute: [indicate main issues in dispute]
Party who initiated the dispute: [indicate “Employer” or
“Contractor”]
Status of dispute: [Indicate if it is being treated by the
Adjudicator, under Arbitration or being dealt with by the
Judiciary]
BF-44 Section IV. Bidding Forms
1. Financial data
Type of Financial information Historic information for previous [insert number] years
in (amount in currency, currency, exchange rate, USD
(currency) equivalent)
2. Financial documents
The Bidder and its parties shall provide copies of the financial statements for [number of years]
years pursuant the Prequalification criteria or Section III, Evaluation and Qualification Criteria
Sub-Factor 2.3.1, as appropriate. The financial statements shall:
(a) reflect the financial situation of the Bidder or in case of JV, of each member, and not of
an affiliated entity (such as parent company or group member).
Attached are copies of financial statements* for the [number of years] years required above;
and complying with the requirements.
* If the most recent set of financial statements is for a period earlier than 12 months from the
date of bid, the reason for this should be justified.
BF-46 Section IV. Bidding Forms
[The following table shall be filled in for the Bidder and for each member of a JV]
[Specify proposed sources of financing, such as liquid assets, unencumbered real assets,
lines of credit, and other financial means, net of current commitments, available to meet the
total construction cash flow demands of the subject contract or contracts as specified in
Section III, Evaluation and Qualification Criteria, Sub-Factor 2.2 (Following
Prequalification), or Sub-Factor 2.5.1 (Without Prequalification), as appropriate.]
Financial Resources
No. Source of financing Amount (USD equivalent)
1
3
BF-48 Section IV. Bidding Forms
[Bidders and each member to a JV should provide information on their current commitments
on all contracts that have been awarded, or for which a letter of intent or acceptance has
been received, or for contracts approaching completion, but for which an unqualified, full
completion certificate has yet to be issued, in accordance with Section III, Evaluation and
Qualification Criteria, Sub-Factor 2.2 (Following Prequalification), or Sub-Factor 2.5.1
(Without Prequalification), as appropriate.]
5
Section IV. Bidding Forms BF-49
[Identify contracts that demonstrate continuous construction work over the past [number]
years pursuant to Section III, Evaluation and Qualification Criteria (Without
Prequalification), Sub-Factor 2.4.1. List contracts chronologically, according to their
commencement (starting) dates.]
[Fill out one (1) form per contract, in accordance with Section III, Evaluation and
Qualification Criteria (Without Prequalification), Sub-Factor 2.4.2(a).]
Contract of Similar Size and Nature
Total Contract Amount [insert total contract amount USD [insert exchange rate
and currency(ies)] and total contract amount in
USD equivalent]
[Fill out one (1) form per contract, in accordance with Section III, Evaluation and
Qualification Criteria (Without Prequalification), Sub-Factor 2.4.2(b).]
1. Key Activity No (1): ______: [insert brief description of the Activity, emphasizing
its specificity]
Total Quantity of Activity under the contract: _____________________________________
Contract with Similar Key Activities
Item Information
Contract Identification [insert contract name and number, if applicable]
Award Date [insert day, month, year, e.g., 15 June, 2015]
Completion Date [insert day, month, year, e.g., 03 October, 2017]
Role in Contract
Prime Contractor Management
Subcontractor
[check the appropriate box] Single entity JV member Contractor
Form ACK
Acknowledgement of Compliance with Guidelines for Procurement under
Japanese ODA Loans
A) I, [insert name and position of authorized signatory], being duly authorized by [insert
name of Bidder/members of joint venture (“JV”)] (hereinafter referred to as the “Bidder”) to
execute this Acknowledgement of Compliance with Guidelines for Procurement under
Japanese ODA Loans, hereby certify on behalf of the Bidder and myself that all information
provided in the Bid submitted by the Bidder for [insert Loan No and name of the Project] is
true, correct and accurate to the best of the Bidder’s and my knowledge and belief. I further
certify, on behalf of the Bidder, that:
(i) the Bid has been prepared and submitted in full compliance with the terms and
conditions set forth in the Guidelines for Procurement under Japanese ODA Loans
(hereinafter referred to as the “Guidelines”); and
(ii) the Bidder has not, directly or indirectly, taken any action which is or constitutes a
corrupt, fraudulent, collusive or coercive act or practice in violation of the Guidelines
and is not subject to any conflict of interest as stipulated in the relevant section of the
Guidelines.
<If debarment for more than one year by the World Bank Group is NOT imposed, use the following
sentence B).>
B) I certify that the Bidder has NOT been debarred by the World Bank Group for more
than one year since the date of issuance of Invitation for Bids.1
<If debarment for more than one year by the World Bank Group has been imposed BUT three (3) years
have passed since the date of such debarment decision, use the following sentence B’).>
B’) I certify that the Bidder has been debarred by the World Bank Group for a period more
than one year BUT that on the date of issuance of Invitation for Bids at least three (3)
years had passed since the date of such debarment decision. Details of the debarment
are as follows:
name of the debarred starting date of ending date of reason for debarment
firm debarment debarment
C) I certify that the Bidder will not enter into a subcontract with a firm which has been
debarred by the World Bank Group for a period more than one year, unless on the date
of the subcontract at least three (3) years have passed since the date of such debarment
decision.
1
The starting date should be revised to “request for price quotation,” if the Borrower is selected through
the International Shopping”; to "appointment", if a contractor is selected through the Direct Contracting;
or “Commencement of actual selection/bidding process”, if the Borrower wishes to adopt procurement
procedures other than ICB, Limited International Shopping, International Shopping, or Direct Contracting.
Section IV. Bidding Forms BF-55
D) I certify, on behalf of the Bidder, that if selected to undertake services in connection with
the Contract, the Bidder shall carry out such services in continuing compliance with the
terms and conditions of the Guidelines.
E) I further certify, on behalf of the Bidder, that if the Bidder is requested, directly or
indirectly, to engage in any corrupt or fraudulent action under any applicable law, such
as the payment of a rebate, at any time during a process of public procurement,
negotiations, execution or implementation of contract (including amendment thereof),
the Bidder shall report all relevant facts regarding such request to the relevant section in
JICA (details of which are specified below) in a timely manner.
JICA’s information desk on fraud and corruption (A report can be made to either of
the offices identified below.)
(1) JICA Headquarters: Legal Affairs Division, General Affairs Department
URL: https://www2.jica.go.jp/en/odainfo/index.php
Tel: +81 (0)3 5226 8850
The Bidder acknowledges and agrees that the reporting obligation stated above shall
NOT in any way affect the Bidder’s responsibilities, obligations or rights, under relevant
laws, regulations, contracts, guidelines or otherwise, to disclose or report such request or
other information to any other person(s) or to take any other action, required to or
allowed to, be taken by the Bidder. The Bidder further acknowledges and agrees that
JICA is not involved in or responsible for the procurement process in any way.
_____________________________
Authorized Signatory
[Insert name of signatory; title]
Guarantor: [Insert name and address of place of issue, unless indicated in the letterhead]
We have been informed that [insert name of the Bidder, which in the case of a joint venture
shall be the name of the joint venture (whether legally constituted or prospective) or the
names of all members thereof] (hereinafter called "the Applicant") has submitted or will
submit to the Beneficiary its Bid (hereinafter called "the Bid") for the execution of [insert
description of contract] under the Loan Agreement No.[insert Loan Agreement Number].
At the request of the Applicant, we, as Guarantor, hereby irrevocably undertake to pay the
Beneficiary any sum or sums not exceeding in total an amount of [insert amount in words]
([insert amount in figures]) upon receipt by us of the Beneficiary’s complying demand,
supported by the Beneficiary’s statement, whether in the demand itself or a separate signed
document accompanying or identifying the demand, stating that either the Applicant:
(a) has withdrawn its Bid during the period of bid validity set forth in the
Applicant’s Letter of Bid (“the Bid Validity Period”), or any extension thereto
provided by the Applicant; or
(b) having been notified of the acceptance of its Bid by the Beneficiary during the Bid
Validity Period or any extension thereto provided by the Applicant, (i) has failed to
execute the contract agreement, or (ii) has failed to furnish the Performance Security, in
accordance with the Instructions to Bidders of the Beneficiary’s bidding documents.
Section IV. Bidding Forms BF-57
This guarantee will expire and shall be returned: (a) if the Applicant is the successful Bidder,
upon our receipt of copies of the contract agreement signed by the Applicant and the
Performance Security issued to the Beneficiary in relation to such contract agreement; or (b)
if the Applicant is not the successful Bidder, upon the earlier of (i) our receipt of a copy of
the Beneficiary’s notification to the Applicant of the results of the bidding process; or (ii)
twenty-eight days after the end of the Bid Validity Period.
Consequently, any demand for payment under this guarantee must be received by us at the
office indicated above on or before that date.
This guarantee is subject to the Uniform Rules for Demand Guarantees (URDG) 2010
Revision, ICC Publication No. 758.
_____________________________
[signature(s)]
[Note: All italicized text is for use in preparing this form and shall be deleted from the final
product.]
Section V. Eligible Source Countries of Japanese ODA Loans ESC-1
Contents
Specification............................................................................................................................. 3
Drawings .................................................................................................................................. 6
Scope of Works
Section VI. Works Requirements WR-3
Specification
specification of standards for materials, Plant, other supplies, and workmanship, recognized
international standards should be used as much as possible. Where other particular standards
are used, whether national standards of the Borrower’s country or other standards, the
Specifications should state that materials, Plant, other supplies, and workmanship meeting
other authoritative standards, and which ensure substantially equal performance, as the
standards mentioned, will also be acceptable.
Specific minimum requirements for “social clauses” (common collective name for provisions
under Sub-Clauses 6.1 through 6.24 of the General Conditions), are to be detailed as part of
the Specifications at a level equivalent to the local norms, if they exist and at a level
according to the country’s regulations, or to minimum requirements when no local
regulations exist (see “Line Items to Address Social Clauses” under the Notes for
Preparing a Bill of Quantities, Section IV).
The following clause may be inserted in the Particular Conditions or the Specification:
Sample Clause: Equivalency of Standards and Codes
Wherever reference is made in the Contract to specific standards and codes to be met by the
materials, Plant, and other supplies to be furnished, and work performed or tested, the
provisions of the latest current edition or revision of the relevant standards and codes in
effect shall apply, unless otherwise expressly stated in the Contract. Where such standards
and codes are national, or relate to a particular country or region, other authoritative
standards that ensure substantial equivalence to the standards and codes specified will be
accepted subject to the Engineer’s prior review and written approval. Differences between
the standards specified and the proposed alternative standards must be fully described in
writing by the Contractor and submitted to the Engineer at least 28 days prior to the date
when the Contractor desires the Engineer’s approval. In the event the Engineer determines
that such proposed deviations do not ensure substantially equal performance, the Contractor
shall comply with the standards specified in the documents.
Alternative Technical Proposals
Employers should decide whether technical solutions to specified parts of the Works are to
be permitted. Alternatives are appropriate in cases where obvious (and potentially less
costly) alternatives are possible to the technical solutions specified in the Bidding
Documents for certain elements of the Works, taking into consideration the comparative
specialized advantage of potential Bidders. For example:
• pile foundations (proprietary methods and different material)
• bridge foundations (open well, caissons, piles, etc.)
• columns, beams, decking (reinforced concrete, prestressed concrete, steel, etc.)
• proprietary methods for post-tensioning concrete
• lining of canals
• pipeline materials, coating, jointing
• road surfacing (asphalt, concrete, etc.)
• transmission tower design and erection
Section VI. Works Requirements WR-5
• street lighting
• offshore foundations
• offshore trestle spans
The Employer should provide a description of the selected parts of the Works with
appropriate references to Drawings, Specifications, Bill of Quantities, and Design or
Performance criteria, stating that the alternative solutions shall be at least structurally and
functionally equivalent to the basic design parameters and specifications.
Such alternative solutions shall be accompanied by all information necessary for a complete
evaluation by the Employer, including drawings, design calculations, technical
specifications, breakdown of prices, proposed construction methodology, and other relevant
details. Technical alternatives permitted in this manner shall be considered by the Employer
each on its own merits and independently of whether the Bidder has priced the item as
described in the Employer’s design included with the Bidding Documents.
WR-6 Section VI. Works Requirements
Drawings
Notes on Drawings
It is customary to bind the drawings in a separate volume, which is often larger than other
volumes of the Contract documents. The size will be dictated by the scale of the drawings,
which must not be reduced to the extent that details are rendered illegible.
A simplified map showing the location of the Site in relation to the local geography,
including major roads, posts, airports, and railroads, is helpful.
The construction drawings, even if not fully developed, must show sufficient details to
enable Bidders to understand the type and complexity of the work involved and to price the
Bill of Quantities.
Section VI. Works Requirements WR-7
Supplementary Information
PART 3 – CONDITIONS OF CONTRACT
AND CONTRACT FORMS
Notes on Conditions of Contract and Contract Forms
The General Conditions of Contract set forth in Part 3, Section VII of these Standard Bidding
Documents for Procurement of Works (version 1.1) published by JICA in October, 2012
(hereinafter referred to as “Standard GC”), are the MDB Harmonized Edition of the
Conditions of Contract for Construction prepared and copyrighted by the International
Federation of Consulting Engineers (Fédération Internationale des Ingénieurs-Conseils, or
FIDIC), FIDIC 2010, all rights reserved. The use of these Standard GC, in all Bidding
Documents/Contracts for construction works financed by Japanese ODA Loans is required,
and they shall be used without any modification. A copy of the Standard GC may be attached
to the Bidding Documents/Contract prepared by the Employer for reference purposes only. If
the General Conditions in the Bidding Documents/Contract prepared by the Employer
contain modifications from the Standard GC, JICA will not consider them valid and the
Standard GC, as defined above, shall apply.
By virtue of a license agreement subscribed between JICA and FIDIC, JICA’s Borrowers
and their implementing agencies are authorized the reproduction and translation of the MDB
Harmonized Edition of FIDIC’s General Conditions of Contract for the exclusive purpose of
preparing Bidding Documents in accordance with these Standard Bidding Documents.
Therefore, Borrowers and their implementing agencies shall abstain from making any use of
the Harmonized Edition of FIDIC’s General Conditions of Contract, distinct from the use
indicated herein.
The Conditions of Contract have been prepared for an ad measurement (unit price or unit
rate) type of contract and cannot be used without major modifications for other types of
contract.
The use of these standard conditions of contract for all civil works will ensure
comprehensiveness of coverage, better balance of rights or obligations between Employer
and Contractor, general acceptability of its provisions, and savings in time and cost for Bid
preparation and review, leading to more economical prices.
Any amendments and additions to the General Conditions, specific to the contract in hand,
should be introduced in the Particular Conditions. A number of such Particular Conditions,
applicable to the above Conditions of Contract, are included in Section VIII.
The Particular Conditions take precedence over the General Conditions—see Sub-Clause
1.5, Priority of Documents, in the General Conditions.
The Particular Conditions (PC) complement the General Conditions (GC) to specify data and
contractual requirements linked to the special circumstances of the country, the Employer,
the Engineer, the sector, the overall project, and the Works. It is good practice to have a list
of tax and custom regulations applicable in the country, to be provided as non-binding
general information, attached to the Bidding Documents.
Part A, the Contract Data of the PC, includes data to complement GC in a manner similar to
the way in which the Bid Data Sheet complements the Instructions to Bidders.
Part B, the Specific Provisions of the PC, consists of a set of provisions prepared by JICA
which shall be used without modification. In addition to the provisions prepared by JICA,
country- or project-specific provisions for PC must also be prepared in each case.
Whoever drafts the PC should be thoroughly familiar with the provisions of the GC and with
any specific requirements of the Contract. Legal advice is recommended when amending
provisions or drafting new ones. Note that the PC provisions take precedence over those
in the GC.
[Note to the Employer: The General Conditions of Contract set forth in Part 3, Section VII of
these Standard Bidding Documents for Procurement of Works (version 1.1) published by
JICA in October, 2012 (hereinafter referred to as “Standard GC”), are the MDB
Harmonized Edition of the Conditions of Contract for Construction prepared and
copyrighted by the International Federation of Consulting Engineers (Fédération
Internationale des Ingénieurs-Conseils, or FIDIC), FIDIC 2010, all rights reserved.
Instead of attaching a copy of the Standard GC, the Employer may use the following
introductory text.]
The General Conditions governing this Contract shall be Conditions of Contract for
Construction MDB Harmonized Edition, prepared and copyrighted by the International
Federation of Consulting Engineers (Fédération Internationale des Ingénieurs-Conseils, or
FIDIC), FIDIC 2010, all rights reserved, (hereinafter referred to as “Standard GC”). This
publication is exclusive for the use of JICA’s Borrowers and their project implementing
agencies as provided under the License Agreement dated August 1st, 2008, between JICA
and FIDIC, and, consequently, no part of this publication may be reproduced, translated,
adapted, stored in a retrieval system or communicated, in any form or by any means, whether
mechanical, electronic, magnetic, photocopying, recording or otherwise, without prior
permission in writing from FIDIC, except by the parties above and only for the exclusive
purpose of preparing this Contract.
The General Conditions of Contract are available on the JICA’s website shown below:
http://www.jica.go.jp/english/our_work/types_of_assistance/oda_loans/oda_op_info/guide/tender/index.html
Part A, Contract Data of the PC, includes data to complement the GC in a manner similar to
the way in which the Bid Data Sheet complements the Instructions to Bidders.
Part B, the Specific Provisions of the PC, consists of a set of provisions prepared by JICA
which shall be used without modification. In addition to the provisions prepared by JICA,
country- or project-specific provisions for PC must also be prepared in each case.
Note that the PC provisions take precedence over those in the GC.
[Specific Provisions of the PC are intended to address country, project, and contract specific
requirements not covered by the GC. Whoever drafts the Specific Provisions should be
thoroughly familiar with the provisions of the GC and with any specific requirements of the
contract. Legal advice is recommended when amending provisions or drafting new ones.
The Standard Specific Provisions prepared by JICA and inserted in this Part B of the PC
shall be used without modification.]
Sub-Clause 4.1 Replace in the third paragraph: “as defined by the Bank” with
Contractor’s General “as defined by the Loan Agreement between the Bank and the
Obligations Borrower”.
Sub-Clause 6.2 [When applicable, exemption from duties and taxes shall be
Rates of Wages and indicated.]
Conditions of Labour
Sub-Clause 13.5 The following text should be added at the end of Sub-Clause
Provisional Sums 13.5:
“As an exception to the above, the Provisional Sum for the cost
of the DB shall be used for payments to the Contractor of the
Employer’s share (one-half) of the invoices of the DB for its
fees and expenses, in accordance with GC 20.2. No prior
instruction of the Engineer shall be required with respect to the
work of the DB. The Contractor shall produce the DB invoices
and satisfactory evidence of having paid 100% of such invoices
as part of the substantiation of those Statements submitted under
Sub-Clause 14.3, which contain requests for payment under the
Provisional Sum toward the cost of the DB. The Engineer’s
certification of such Statements shall be based upon such
invoices and such evidence of payment by the Contractor.
Contractor’s overhead, profit, etc., shall not be included in the
provisional sums for the cost of the DB.”
Sub-Clause 14.1 [When applicable, exemption from duties and taxes shall be
The Contract Price indicated in sub-paragraph (b).]
PC-6 Section VIII. Particular Conditions (Part B: Specific Provisions)
Sub-Clause 14.15 Replace the entire Sub-Clause 14.15 with the following:
Currencies of Payment
The Contract Price shall be paid in the currency or currencies in
which the bid price was expressed in the Letter of Bid. If more
than one currency is so named, payments shall be made as follows:
Sub-Clause 15.6 Replace the entire Sub-Clause 15.6 with the following:
Corrupt or Fraudulent
Practices If the Employer determines, based on reasonable evidence, that
the Contractor has engaged in corrupt, fraudulent, collusive or
coercive practices, in competing for or in executing the
Contract, then the Employer may, after giving 14 days notice to
the Contractor, terminate the Contract and expel him from the
Site, and the provisions of Clause 15 shall apply as if such
termination had been made under Sub-Clause 15.2
[Termination by Employer].
Should any employee of the Contractor be determined, based on
reasonable evidence, to have engaged in corrupt, fraudulent or
coercive practice during the execution of the work then that
employee shall be removed in accordance with Sub-Clause 6.9
[Contractor’s Personnel].
Sub-Clause 20.6 Replace the entire Sub-Clause 20.6 with the following:
Arbitration
Any dispute between the Parties arising out of or in connection
with the Contract not settled amicably in accordance with Sub-
Clause 20.5 above and in respect of which the DB’s decision (if
Section VIII. Particular Conditions (Part B: Specific Provisions) PC-7
any) has not become final and binding shall be finally settled by
arbitration. Arbitration shall be conducted as follows:
(a) if the contract is with foreign contractors (or if the lead
partner is a foreign contractor, in case of JV), international
arbitration with proceedings administered by the
International Chamber of Commerce (ICC) and conducted
under the ICC Rules of Arbitration; by one or more
arbitrators appointed in accordance with said arbitration
rules.
(b) if the Contract is with domestic contractors, arbitration with
proceedings conducted in accordance with the laws of the
Employer’s country.
The place of arbitration shall be a neutral location determined in
accordance with the applicable rules of arbitration; and the
arbitration shall be conducted in the language for
communications defined in Sub-Clause 1.4 [Law and
Language].
The arbitrators shall have full power to open up, review and
revise any certificate, determination, instruction, opinion or
valuation of the Engineer, and any decision of the DB, relevant
to the dispute. Nothing shall disqualify representatives of the
Parties and the Engineer from being called as a witness and
giving evidence before the arbitrators on any matter whatsoever
relevant to the dispute.
Neither Party shall be limited in the proceedings before the
arbitrators to the evidence or arguments previously put before
the DB to obtain its decision, or to the reasons for
dissatisfaction given in its Notice of Dissatisfaction. Any
decision of the DB shall be admissible in evidence in the
arbitration.
Arbitration may be commenced prior to or after completion of
the Works. The obligations of the Parties, the Engineer and the
DB shall not be altered by reason of any arbitration being
conducted during the progress of the Works.
Section IX. Annex to the Particular Conditions - Contract Forms CF-1
Table of Forms
Letter of Acceptance
[Insert letterhead paper of the Employer]
[Insert date]
This is to notify you that your Bid dated [insert date] for execution of the [insert name of
the Contract and identification number, as given in the Contract Data] for the Accepted
Contract Amount of the equivalent of [insert amount in words and figures] [insert name
of currency], as corrected and modified in accordance with the Instructions to Bidders, is
hereby accepted by our Agency.
You are requested to furnish the Performance Security within 28 days in accordance with
the Conditions of Contract, using for that purpose one of the Performance Security Forms
included in Section IX, Annex to the Particular Conditions - Contract Forms, of the
Bidding Documents
Authorized Signature:
Name and Title of Signatory:
Name of Agency:
Contract Agreement
THIS AGREEMENT made the [insert day] day of [insert month], [insert year], between
[insert name of the Employer] (hereinafter “the Employer”), of the one part, and [insert
name of the Contractor] (hereinafter “the Contractor”), of the other part:
WHEREAS the Employer desires that the Works known as [name of the Contract]
should be executed by the Contractor, and has accepted a Bid by the Contractor for the
execution and completion of these Works and the remedying of any defects therein,
The Employer and the Contractor agree as follows:
1. In this Agreement words and expressions shall have the same meanings as are
respectively assigned to them in the Contract documents referred to.
2. The following documents shall be deemed to form and be read and construed as
part of this Agreement. This Agreement shall prevail over all other Contract documents.
(i) the Letter of Acceptance;
(ii) the Letter of Bid ;
(iii) the addenda Nos [insert addenda numbers, if any] (if any);
(iv) the Particular Conditions ;
(v) the General Conditions;
(vi) the Specification;
(vii) the Drawings;
(viii) the completed Schedules; and
(ix) the Acknowledgement of Compliance with Guidelines for
Procurement under Japanese ODA Loans.
For the purpose of interpretation, the priority of the listed documents shall be in
accordance with the above listed order.
3. In consideration of the payments to be made by the Employer to the Contractor as
specified in this Agreement, the Contractor hereby covenants with the Employer to
execute the Works and to remedy defects therein in conformity in all respects with the
provisions of the Contract.
4. The Employer hereby covenants to pay the Contractor in consideration of the
execution and completion of the Works and the remedying of defects therein, the
Contract Price or such other sum as may become payable under the provisions of the
Contract at the times and in the manner prescribed by the Contract.
IN WITNESS whereof the parties hereto have caused this Agreement to be executed in
accordance with the laws of [insert the laws of the borrowing country] on the day, month
and year specified above.
CF-4 Section IX. Annex to the Particular Conditions - Contract Forms
for and on behalf of the Employer for and on behalf the Contractor
in the presence of in the presence of
Witness, Name, Signature, Address, Date Witness, Name, Signature, Address, Date
Section IX. Annex to the Particular Conditions - Contract Forms CF-5
Contract Agreement
THIS AGREEMENT made the [insert day] day of [insert month], [insert year], between
[insert name of the Employer] (hereinafter “the Employer”), of the one part, and [insert
name of the Contractor] (hereinafter “the Contractor”), of the other part:
WHEREAS the Employer desires that the Works known as [name of the Contract]
should be executed by the Contractor, and has accepted a Bid by the Contractor for the
execution and completion of these Works and the remedying of any defects therein,
The Employer and the Contractor agree as follows:
1. In this Agreement words and expressions shall have the same meanings as are
respectively assigned to them in the Contract documents referred to.
2. The following documents shall be deemed to form and be read and construed as
part of this Agreement. This Agreement shall prevail over all other Contract documents.
(i) the Letter of Acceptance;
(ii) the Letter of Technical Bid ;
(iii) the Letter of Price Bid
(iv) the addenda Nos [insert addenda numbers, if any] (if any);
(v) the Particular Conditions ;
(vi) the General Conditions;
(vii) the Specification
(viii) the Drawings;
(ix) the completed Schedules; and
(x) the Acknowledgement of Compliance with Guidelines for
Procurement under Japanese ODA Loans.
For the purpose of interpretation, the priority of the listed documents shall be in
accordance with the above listed order.
3. In consideration of the payments to be made by the Employer to the Contractor as
specified in this Agreement, the Contractor hereby covenants with the Employer to
execute the Works and to remedy defects therein in conformity in all respects with the
provisions of the Contract.
4. The Employer hereby covenants to pay the Contractor in consideration of the
execution and completion of the Works and the remedying of defects therein, the
Contract Price or such other sum as may become payable under the provisions of the
Contract at the times and in the manner prescribed by the Contract.
CF-6 Section IX. Annex to the Particular Conditions - Contract Forms
IN WITNESS whereof the parties hereto have caused this Agreement to be executed in
accordance with the laws of [insert the laws of the borrowing country] on the day, month
and year specified above.
for and on behalf of the Employer for and on behalf the Contractor
in the presence of in the presence of
Witness, Name, Signature, Address, Date Witness, Name, Signature, Address, Date
Section IX. Annex to the Particular Conditions - Contract Forms CF-7
Performance Security
Option 1: (Demand Guarantee)
Guarantor: [Insert name and address of place of issue, unless indicated in the
letterhead]
We have been informed that [insert name of Contractor, which in the case of a joint
venture shall be the name of the joint venture] (hereinafter called "the Applicant") has
entered into Contract No. [insert reference number of the contract] dated [insert date]
with the Beneficiary, for the execution of [insert name of the contract and brief
description of the Works] (hereinafter called "the Contract").
At the request of the Applicant, we as Guarantor, hereby irrevocably undertake to pay the
Beneficiary any sum or sums not exceeding in total an amount of [insert amount in
figures] ([insert amount in words]),1 such sum being payable in the types and proportions
of currencies in which the Contract Price is payable, upon receipt by us of the
Beneficiary’s complying demand supported by the Beneficiary’s statement, whether in
the demand itself or in a separate signed document accompanying or identifying the
demand, stating that the Applicant is in breach of its obligation(s) under the Contract,
without the Beneficiary needing to prove or to show grounds for its demand or the sum
specified therein.
This guarantee shall expire, no later than the [insert the day] day of [insert month],
[insert year] 2, and any demand for payment under it must be received by us at this office
indicated above on or before that date.
1
The Guarantor shall insert an amount representing the percentage of the Accepted Contract Amount
specified in the Letter of Acceptance, less provisional sums, if any, and denominated either in the
currency(cies) of the Contract or a freely convertible currency acceptable to the Beneficiary.
2
Insert the date twenty-eight days after the expected completion date as described in GC Clause 11.9.
The Employer should note that in the event of an extension of this date for completion of the Contract,
CF-8 Section IX. Annex to the Particular Conditions - Contract Forms
This guarantee is subject to the Uniform Rules for Demand Guarantees (URDG) 2010
Revision, ICC Publication No. 758, except that the supporting statement under Article
15(a) is hereby excluded.
_____________________
[signature(s)]
[Note: All italicized text (including footnotes) is for use in preparing this form and shall
be deleted from the final product.]
the Employer would need to request an extension of this guarantee from the Guarantor. Such request
must be in writing and must be made prior to the expiration date established in the guarantee. In
preparing this guarantee, the Employer might consider adding the following text to the form, at the end
of the penultimate paragraph: “The Guarantor agrees to a one-time extension of this guarantee for a
period not to exceed [six months][one year], in response to the Beneficiary’s written request for such
extension, such request to be presented to the Guarantor before the expiry of the guarantee.”
Section IX. Annex to the Particular Conditions - Contract Forms CF-9
By this Bond [insert name of Principal] as Principal (hereinafter called “the Contractor”)
and [insert name of surety] as Surety (hereinafter called “the Surety”), are held and firmly
bound unto [insert name of the Employer] as Obligee (hereinafter called “the Employer”)
in the amount of [insert the amount in words and figures], for the payment of which sum
well and truly to be made in the types and proportions of currencies in which the Contract
Price is payable, the Contractor and the Surety bind themselves, their heirs, executors,
administrators, successors and assigns, jointly and severally, firmly by these presents.
WHEREAS the Contractor has entered into a written Agreement with the Employer dated
the [insert date] day of [insert month], [insert year], for [insert name of contract and
brief description of Works] in accordance with the documents, plans, specifications, and
amendments thereto, which to the extent herein provided for, are by reference made part
hereof and are hereinafter referred to as the Contract.
NOW, THEREFORE, the Condition of this Obligation is such that, if the Contractor shall
promptly and faithfully perform the said Contract (including any amendments thereto),
then this obligation shall be null and void; otherwise, it shall remain in full force and
effect. Whenever the Contractor shall be, and declared by the Employer to be, in default
under the Contract, the Employer having performed the Employer’s obligations
thereunder, the Surety may promptly remedy the default, or shall promptly:
(1) complete the Contract in accordance with its terms and conditions; or
(2) obtain a Bid or Bids from qualified Bidders for submission to the Employer
for completing the Contract in accordance with its terms and conditions, and
upon determination by the Employer and the Surety of the lowest responsive
Bidder, arrange for a Contract between such Bidder and Employer and make
available as work progresses (even though there should be a default or a
succession of defaults under the Contract or Contracts of completion arranged
under this paragraph) sufficient funds to pay the cost of completion less the
Balance of the Contract Price; but not exceeding, including other costs and
damages for which the Surety may be liable hereunder, the amount set forth in
the first paragraph hereof. The term “Balance of the Contract Price,” as used
in this paragraph, shall mean the total amount payable by Employer to
Contractor under the Contract, less the amount properly paid by Employer to
Contractor; or
(3) pay the Employer the amount required by Employer to complete the Contract
in accordance with its terms and conditions up to a total not exceeding the
amount of this Bond.
The Surety shall not be liable for a greater sum than the specified penalty of this Bond.
Any suit under this Bond must be instituted before the expiration of one year from the
date of the issuing of the Taking-Over Certificate.
CF-10 Section IX. Annex to the Particular Conditions - Contract Forms
No right of action shall accrue on this Bond to or for the use of any person or corporation
other than the Employer named herein or the heirs, executors, administrators, successors,
and assigns of the Employer.
In testimony whereof, the Contractor has hereunto set his hand and affixed his seal, and
the Surety has caused these presents to be sealed with his corporate seal duly attested by
the signature of his legal representative, this [insert day] day of [insert month], [insert
year].
SIGNED ON on behalf of
By in the capacity of
In the presence of
SIGNED ON on behalf of
By in the capacity of
In the presence of
[Note: All italicized text (including footnotes) is for use in preparing this form and shall
be deleted from the final product.]
Section IX. Annex to the Particular Conditions - Contract Forms CF-11
Demand Guarantee
Guarantor: [Insert name and address of place of issue, unless indicated in the
letterhead]
We have been informed that [insert name of Contractor, which in the case of a joint
venture shall be the name of the joint venture] (hereinafter called “the Applicant”) has
entered into Contract No. [insert reference number of the contract] dated [insert date of
the contract] with the Beneficiary, for the execution of [insert name of contract and brief
description of Works] (hereinafter called "the Contract").
At the request of the Applicant, we as Guarantor, hereby irrevocably undertake to pay the
Beneficiary any sum or sums not exceeding in total an amount of [insert amount in
figures] ([insert amount in words])1 upon receipt by us of the Beneficiary’s complying
demand supported by the Beneficiary’s statement, whether in the demand itself or in a
separate signed document accompanying or identifying the demand, stating either that the
Applicant:
(a) has used the advance payment for purposes other than the costs of mobilization
in respect of the Works; or
(b) has failed to repay the advance payment in accordance with the Contract
conditions, specifying the amount which the Applicant has failed to repay.
A demand under this guarantee may be presented as from the presentation to the
Guarantor of a certificate from the Beneficiary’s bank stating that the advance payment
1
The Guarantor shall insert an amount representing the amount of the advance payment and
denominated either in the currency(ies) of the advance payment as specified in the Contract, or in a
freely convertible currency acceptable to the Employer.
CF-12 Section IX. Annex to the Particular Conditions - Contract Forms
referred to above has been credited to the Applicant on its account number [insert
number] at [insert name and address of Applicant’s bank] .
The maximum amount of this guarantee shall be progressively reduced by the amount of
the advance payment repaid by the Applicant as specified in copies of interim statements
or payment certificates which shall be presented to us. This guarantee shall expire, at the
latest, upon our receipt of a copy of the interim payment certificate indicating that ninety
(90) percent of the Accepted Contract Amount, less provisional sums, has been certified
for payment, or on the [insert day] day of [insert month], [insert year],2 whichever is
earlier. Consequently, any demand for payment under this guarantee must be received by
us at this office on or before that date..
This guarantee is subject to the Uniform Rules for Demand Guarantees (URDG) 2010
Revision, ICC Publication No. 758, except that the supporting statement under Article
15(a) is hereby excluded.
____________________
[signature(s)]
[Note: All italicized text (including footnotes) is for use in preparing this form and shall
be deleted from the final product.]
2
Insert the expected expiration date of the Time for Completion. The Employer should note that in the
event of an extension of the time for completion of the Contract, the Employer would need to request an
extension of this guarantee from the Guarantor. Such request must be in writing and must be made
prior to the expiration date established in the guarantee. In preparing this guarantee, the Employer
might consider adding the following text to the form, at the end of the penultimate paragraph: “The
Guarantor agrees to a one-time extension of this guarantee for a period not to exceed [six months][one
year], in response to the Beneficiary’s written request for such extension, such request to be presented
to the Guarantor before the expiry of the guarantee.”
Section IX. Annex to the Particular Conditions - Contract Forms CF-13
Demand Guarantee
Guarantor: [Insert name and address of place of issue, unless indicated in the
letterhead]
We have been informed that [insert name of Contractor, which in the case of a joint
venture shall be the name of the joint venture] (hereinafter called "the Applicant") has
entered into Contract No. [insert reference number of the contract] dated [insert date]
with the Beneficiary, for the execution of [insert name of contract and brief description
of Works] (hereinafter called "the Contract").
At the request of the Applicant, we, as Guarantor, hereby irrevocably undertake to pay the
Beneficiary any sum or sums not exceeding in total an amount of [insert amount in
figures] ([insert amount in words])1 upon receipt by us of the Beneficiary’s complying
demand supported by the Beneficiary’s statement, whether in the demand itself or in a
separate signed document accompanying or identifying the demand, stating that the
Applicant is in breach of its obligation(s) under the Contract, without the Beneficiary
needing to prove or show grounds for its demand or the sum specified therein.
1
The Guarantor shall insert an amount representing the amount of the second half of the Retention
Money or if the amount guaranteed under the Performance Guarantee when the Taking-Over
Certificate is issued is less than half of the Retention Money, the difference between half of the
Retention Money and the amount guaranteed under the Performance Security and denominated either
in the currency(ies) of the second half of the Retention Money as specified in the Contract, or in a
freely convertible currency acceptable to the Beneficiary.
CF-14 Section IX. Annex to the Particular Conditions - Contract Forms
A demand under this guarantee may be presented as from the presentation to the
Guarantor of a certificate from the Beneficiary’s bank stating that the second half of the
Retention Money as referred to above has been credited to the Applicant on its account
number [insert account’s number] at [insert name and address of Applicant’s bank] .
This guarantee shall expire no later than the [insert day] day of [insert month], [insert
year] 2, and any demand for payment under it must be received by us at the office
indicated above on or before that date.
This guarantee is subject to the Uniform Rules for Demand Guarantees (URDG) 2010
Revision, ICC Publication No. 758, except that the supporting statement under Article
15(a) is hereby excluded.
____________________
[signature(s)]
[Note: All italicized text (including footnotes) is for use in preparing this form and shall
be deleted from the final product.]
2
Insert the same expiry date as set forth in the Performance Security, representing the date twenty-eight
days after the completion date described in GC Clause 11.9. The Employer should note that in the
event of an extension of this date for completion of the Contract, the Employer would need to request
an extension of this guarantee from the Guarantor. Such request must be in writing and must be made
prior to the expiration date established in the guarantee. In preparing this guarantee, the Employer
might consider adding the following text to the form, at the end of the penultimate paragraph: “The
Guarantor agrees to a one-time extension of this guarantee for a period not to exceed [six months][one
year], in response to the Beneficiary’s written request for such extension, such request to be presented
to the Guarantor before the expiry of the guarantee.”
URL:http://www.jica.go.jp