Rightpdf - Screw Pump Installation and Operation Instructions - Watermark
Rightpdf - Screw Pump Installation and Operation Instructions - Watermark
,LTD
Contents
Part I Installation 1-5
Part II 6-8
1. Horizontal installation
Generally, it is installed horizontally on the bottom of the plate, grouted and
bolted to ensure firm installation and reduce noise and vibration.
After the pump is fixed with bolts, the whole pump device shall be inspected
to ensure that motor shaft keep in a line with pump axis.
2. Vertical installation
If the pump must be installed vertically, the approval of the production
company must be obtained before installation. All pipework shall be
supported independently during installation.
For safety, slings should be used when handling the pump head and the
whole pump unit (pump, gearbox, motor, etc.). The lifting position depends
on the specific structure of the pump. It should be operated by experienced
personnel to avoid damage to the pump and casualties.
If there is a ring bolt, it can only be used to lift the part where the eyebolts
are located.
1.3.2 Storage
This paper also describes the work that should be done when the pump is
used with low frequency.
Short term storage
If the pump needs to be stored for less than 6 months,, it is recommended to
take the following measures.
1. Put the pump indoors as far as possible, if cannot, at least add a shield and
keep the environment around it dry.
2. If the pump is installed with drain plug, remove it. At the same time, the
cover plate of the observation hole should be removed to dry the pump
thoroughly.
3. If a packing seal is used, loosen the packing gland, fill as much grease as
possible into the stuffing box, and then tighten the gland nut manually. If
water flushing device is used in packing chamber, lubricating grease is not
required. It is recommended to add a small amount of clean oil.
4. For the storage of motor, gearbox and driving devices, please refer to the
manufacturer's introduction of relevant parts.
Long-term storage
If the storage time of the pump exceeds 6 months, in addition to the above
requirements, the following measures should be taken regularly (once every 2-
3 weeks).
1. Rotate the pump rotor for at least three-quarters of a turn to prevent the
rotor from seizing the stator.
2. Caution: each rotation should not exceed two cycles to avoid damage to
rotor and stator components.
There should be a ground wire on the electric drive, and they should be
properly connected . When checking the speed of the motor when it is
electrified, the start and stop should be completed instantaneously to prevent
idling or pressurizing the upstream equipment (check the steering arrow on the
pump nameplate). Electrical equipment shall include suitable insulation to
ensure safe operation of the pump.
2.1 Idling
No idling pump! Even a few turns will immediately damage the stator.
Continuous idling will have destructive consequences.
Note:
Before changing the direction of the pump, consult our company to make the
pump suitable for new working conditions.
2.3.1 Packing
If the pump is equipped with packing seal (packing is non-asbestos material),
the position of packing gland should be adjusted during the initial operation of
the pump. When the new packing is used, it should be compressed by
tightening the nuts on the gland manually, which should last for about 3 days.
In the following week, gradually tighten the gland to make the overflow rate
reach the recommended value in the table below. Under normal conditions, a
small amount of leakage helps to cool and lubricate the packing. A properly
adjusted gland will keep the packing from leaking.
Typical overflow rate at packing gland
Shaft diameter 50mm, 2 drops per minute
50mm shaft diameter 75mm, 3 drops per minute
75mm shaft diameter 100mm, 4 drops per minute
100 mm shaft diameter 125 mm, 5 drops per minute
125mm shaft diameter 160mm, 6 drops per minute
When the pump works normally, a small amount of leakage at the gland
caused by the medium is allowed, which helps to lubricate the packing.
However, when transporting corrosive or abrasive media, leakage is not
expected. In this case, the gland should be tightened during the operation of
the pump to prevent medium leakage or external air from entering the
packing.
In particular, for hazardous media, it should be considered to set up a
discharge device in the packing chamber.
Caution: special care must be taken in adjusting the cover during the
operation of pump
Noise standard
1. Noise at the distance of 1 m from the pump shall not exceed 85dB.
2. The noise value measured by a typical pump device does not include other
sound sources and the noise reflected by buildings.
Lubrication
For pumps with bearings installed, check periodically if grease is sufficient. If
replenishment is required, grease should be added to one third of the full
bearing cavity at the end of the bearing chamber.
Bearings need to be inspected regularly to maintain optimum performance. The
inspection is best carried out during the regular maintenance period when the
user stops the pump.
For high temperature or other harsh working conditions, the bearing must be
inspected frequently. Users are advised to customize the appropriate
maintenance plan or maintenance cycle. Replenish grease or similar products.
Part III Cleaning before pump operation
During cleaning in production line (CIP), the flow rate (i.e. pump speed)
should be increased as much as possible to obtain the best cleaning effect.
Assembly:
Assembly is the reverse of the above steps
When installing the stator (R020), check whether the orientation of the
stator (R020) is correct. The chamfered section of the stator (R020)
should face (viewed from the shaft end of the pump):
Wrong
Correct
Eccentric press in,
Press in to center position easy to break the joint
Wrong
Correct The joint is easy to break due to
Press in the A-A axis the deflection when pressing in
Installation of coupling rod and universal joint
Press the universal joint bushing (R074) to its 2/3 position with a tool;
Adding lubricating oil into the joint of rotor and plug-in transmission shaft;
Slide pin sheath (R071);
Lubricate the inner surface of the universal joint sheath (R072) with
lubricating oil to make it slide;
Push the coupling rod (R070) into the end of the joint;
Use a screwdriver to pry up the universal joint rubber sheath (R072), and
exhaust the air in the universal joint. Installed in place, and then install the
tightening strap (R406/R407).
Malfunctions
Motor overheating
Pump can not start
maintenance instructions to use RoNice eccentrie helical
Seal leakage
totorpump, it can be operated with no trouble.
Check the axial clearance at the coupling rod connection. Check that the bushing is
installed correctly.
Check whether there are foreign impurities inside the pump. Disassemble the pump,
remove foreign matters and replace worn parts.
The stator or rotor is worn. Remove the pump and replace worn parts.
Universal joint parts are worn. Replace worn parts and inject special grease.
The temperature of conveying medium is too high, and the expansion of stator is too
large. Check the temperature and install the rotor with diameter less than the specified
size.
The packing seal is too tight or worn. Loosen or tighten the packing gland. Replace the
damaged packing.
Too much solid content and/or solid size. Reduce the running speed of the pump, and
can be installed with a mesh size appropriate screen. Increase the liquid ratio.
When the pump is not allowed to operate, the solid material precipitates and solidifies.
Clean the pump in time.
When the temperature falls below a certain limit, the liquid hardens. Heat pump.
The stator swells and is not suitable for the medium to be transported. Select suitable
stator material. Use rotors smaller than the specified diameter.
The bearing of the pump driving device is defective. Replace the corresponding bearing.
The mechanical seal is defective. Check the sealing surface and O-ring. If necessary,
replace the corresponding defective parts.
Part number
Corresponding accessory
name Outlet Nut Support Stator Pulling rod Suction Seal ring
Part number
Corresponding accessory Mechanical seal mechanical seal connecting base Reducer motor Rotor coupling rod coupling rod
name base bushing
Part number
Part VI Accessories details of the whole set of pump
Panel size: 48 x 48 mm
Hole size: 45.5 x 45.5 mm
Panel interface:
First Display (PV)
Display measurement
Display various prompts according to the
instrument
Second Display (SV)
Display the given value
Display various parameter values according to
the instrument
Movement indication
OUT1: Heating indicator, light is on when working output
OUT2: Refrigerating indicator, light is on when working output
ALM: Alarm output indicator, light is on when working output
AT: Self-setting indicator, light is on when self-setting
Copper hammer
Socket wrench C-clamp set
(Plastic hammer)
Wuhan Ronice Pump Device Co.,Ltd