EHS Weekly Report (Week 051 January 27 - February 02, 2025) Bolbok Substation Area)

The EHS Weekly Report for the Bolbok 1 & 2 Solar Power Plant Project covers site activities, including concrete pouring, installation of structures, and material deliveries from January 27 to February 02, 2025. It also includes details on a weekly HSE coordination meeting and provides statistics and weather monitoring for the week. The report emphasizes ongoing safety measures and coordination among teams involved in the project.

Uploaded by

zamaradhaven
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
37 views21 pages

EHS Weekly Report (Week 051 January 27 - February 02, 2025) Bolbok Substation Area)

The EHS Weekly Report for the Bolbok 1 & 2 Solar Power Plant Project covers site activities, including concrete pouring, installation of structures, and material deliveries from January 27 to February 02, 2025. It also includes details on a weekly HSE coordination meeting and provides statistics and weather monitoring for the week. The report emphasizes ongoing safety measures and coordination among teams involved in the project.

Uploaded by

zamaradhaven
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 21

MV & HV Substation Package for Bolbok 1 & 2 Solar

Power Plant Project


EHS WEEKLY REPORT ( WEEK 051 )
As of January 27 - February 02, 2025

February 05, 2025 24-CITICORE-03-0300 1


TABLE OF CONTENTS:

I. Daily Toolbox Meeting


II. Site Activities
III.HSE Activity
IV.WAIR Proof of Submissions
V. HSE Weekly Statistics
VI.Weather Monitoring

February 05, 2025 24-CITICORE-03-0300 2


Daily Toolbox Meeting

February 05, 2025 24-CITICORE-03-0300 3


General Toolbox Meeting: January 28, 2025

February 05, 2025 24-CITICORE-03-0300 4


Site Activities: Concrete Pouring of Firewall 3rd Lift

February 05, 2025 24-CITICORE-03-0300 5


Site Activities: Concrete Pouring Gantry Pedestal

February 05, 2025 24-CITICORE-03-0300 6


Site Activities: Concrete Pouring ( PTR2 Footing )

February 05, 2025 24-CITICORE-03-0300 7


Site Activities: Delivery of Materials ( Power Circuit Breaker )

February 05, 2025 24-CITICORE-03-0300 8


Site Activities: Installation of Rebars ( PTR2 )

February 05, 2025 24-CITICORE-03-0300 9


Site Activities: Installation of Formworks ( Firewall 3rd Lift )

February 05, 2025 24-CITICORE-03-0300 10


Site Activities: Backfilling and Compaction Works

February 05, 2025 24-CITICORE-03-0300 11


Site Activities: Tightening of Bolts ( HVE Steel Structures )

February 05, 2025 24-CITICORE-03-0300 12


Site Activities: Installation of Rebars ( Firewall 3rd Lift )

February 05, 2025 24-CITICORE-03-0300 13


Site Activities: Installation of Groundings ( Cad - Welding )

February 05 2025 24-CITICORE-03-0300 14


Site Activities: Fabrication of C - Channel for Steel Structures

February 05, 2025 24-CITICORE-03-0300 15


Site Activities:Installation of Formworks ( Firewall Final Lift )

February 05, 2025 24-CITICORE-03-0300 16


WAIR Proof of Submissions January 2025

February 05, 2025 24-CITICORE-03-0300 17


HSE Activity: Coordination Meeting

WHAT: HSE Weekly Coordination Meeting ( Week 050 )


WHERE: BOLBOK Site ( Conference Room )
WHEN: January 31, 2025
WHO: Arbutus, CCI EHS Team and Bolbok Safety Team

Attendance and Photos

February 05, 2025 24-CITICORE-03-0300 18


HSE Weekly Statistics as of January 27 - February 02, 2025

February 05, 2025 24-CITICORE-03-0300 19


Weather Monitoring as of January 27 - February 02, 2025

February 05, 2025 24-CITICORE-03-0300 20


THANK YOU!

Rosalie De Roxas Perez


Safety Officer 2
February 05, 2025 24-CITICORE-03-0300 21