2022 04 LEED Case-Study A4 Low
2022 04 LEED Case-Study A4 Low
The Circle
Case study
37,000 m2
Project area
180,000 m2
Rental area
80,000 m2
Park
2009 – 2014
Planning period
2015 – 2021
Construction period
Flughafenstrasse
u
Fl
Parkhausring Butzenbüelrin
g
B
Terminal
e
ss
tra
ns
afe
gh
Flu
n g
u sri
ha
rk
Pa
nft
lring
Vorfahrt Anku
nbüe
Butze
1
A5
The Circle
Airport Park
Shopping
34
ft
kun
An
ahrt
A51
Vorf
Butz
Pa r enbü
k h a u s ri n g elrin
g
Flug
hafe
nstras
ing se
üelr
nb
tze
Bu
A51
Flu
gh
afe
ns
tra
ses
Parties involved
A51
in the project
Werfts
trasse
Flughofs
Flughafen Zürich AG holds 51 % of the shares in the Circle and Swiss Life
49 %. The construction project was implemented by the general
contractor HRS. The LEED® certification was supported by Intep during
the planning phase and by Amstein+Walthert from the construction
phase onwards.
Energy piles
The core of the energy supply is the anergy grid heating for a self-
sufficient heat and cold supply. The continuous base connecting all six
buildings stands on a total of 1150 foundation piles. 850 of these are
thermally activated. This means that a plastic pipe is laid in them as a
loop in which a liquid circulates, enabling energy exchange with the
ground. In this way, the ground serves as a heat storage: In summer, the
excess heat that cannot be used directly is stored temporarily in the
ground. The building can be cooled by removing the heat. In winter, the
stored heat is drawn back from the underground, making the Circle
almost self-sufficient in terms of heat supply. At the same time, more
than half of the excess heat generated during the cooling process is
reused. To cover an extraordinary peak demand in winter, the Circle is
also connected to the airport’s own combined heat and power plant.
Energy piles under construction. Distribution of the pipelines from the energy piles.
CCF-façade
The glass façade of the Circle is designed as a Closed Cavity Façade
(CCF) and meets the highest insulation standards. The CCF façade is a
two-layer construction in which the space between the inner and outer
The concrete ceilings are
thermally activated. skin is completely closed. Dry, clean air is constantly fed into the cavity to
prevent condensation on the façade. The outside climate is constantly
monitored by the control electronics and the amount of dry air produced
is adjusted accordingly. This reduces energy consumption to a minimum.
Due to the special design with the up to 13.5 meter cantilevered façade
which thus protrudes over the cantonal road leading along the building,
a completely new construction was required. The solution found prevents
the formation of ice, which could become a hazard for people and
vehicles moving directly below. At the same time, the façade meets the
strict LEED® and Minergie requirements for insulation values.
The overhanging sloping façade.
Photovoltaics
Photovoltaic panels were installed on the roofs of the six buildings to
generate electricity. Due to fixed infrastructures on the roofs, such as the
façade access system or cooling units, but also because of their use as
terraces, a total of 1861 photovoltaic modules have been installed on just
3005 m2 from a total roof area of 26,800 m2. These have an inclination of
10 degrees and are aligned at an angle of 185 degrees. The output is
599 kWp and the annual yield is 624,155 kWh according to calculations.
This corresponds to about 2.5 % of the Circle’s annual power
requirement.
Energy efficiency
of tenant interior fitting
The furnishing of the interiors in the tenant fit-out is also subject to strict
specifications. At least 70 % of the machines and equipment are certified
according to the Energy Star label. All open-plan office areas are
controlled with daylight sensors, the remaining areas with occupancy
sensors.
There are 370 train, 400 tram and 790 bus connections to the airport
every day. The Circle is also easy to reach for motorized individual traffic
directly on the freeway and cantonal road. Of 509 parking spaces in the
underground car park, 7 are equipped with electric charging stations.
These are located in the public area directly at the entrance / exit.
Germany
Basel
Zurich
Bern
Switzerland < 30
30 – 60
60 – 90
Italy 90 – 120
With the redesign, ecological upgrades were made. Thus, the diversity of
the habitats could be increased. 7200 m2 of the existing forest were
transformed into an open forest with a high variety of species. 12,600 m2
of existing meadows were transformed into natural grasslands with a
large diversity of flowers and insects. Ponds and field shrubs were also
upgraded to achieve a higher biodiversity.
Water-saving faucets
The amount of potable water consumed depends largely on the tenants
and their interior design. For this reason, they must also comply with
LEED® specifications regarding water reduction. This applies to the
faucets whose flow rate is limited. The toilets are equipped with two
buttons for a small and a large amount of water and the urinals are
operated without water. Exceptions are the rooms in the outpatient
medical center as well as hotel and convention.
Waste management
The disposal of waste and the recycling of reusable materials was given
special attention in the Circle already during the construction phase. The
various fractions produced were disposed of separately or sent for
recycling. 75 % of the waste was recycled.
Adhesives and sealants, paints and coatings comply with strict limits
on chemical emissions so as not to impair the health and well-being of
users.
Peak coverage
Recooling External initial operating phase
CHP plant
airport TABS
Floor heating
Radiators
Air conditioning
Heat
Chillers,
heat pumps
Cold
TABS
Floor cooling
Free-cooling Industrial cooling
Air conditioning
Decentralised Refrigeration
Geothermal hot water
piles production
Hot water
for use
Operating modes
Heat pump-mode
Heat pump- /chiller-mode
Chiller-mode Free-cooling