progress of SNI yard modification for connection of 3rd & 4th line BTBR-SNI
S.N. NAME OF WORK SCOPE OF UNIT ON DATE COMMULAT
WORK PROGRESS IVE
1 FOUNDATION CASTING 113 Nos nil 46
2 MAST ERECTION 92 Nos nil 46
3 MAST GROUTING 92 Nos nil 46
4 BRACKET ERECTION 167 Nos nil 74
5 CATENARY WIRE WIRING 13 shots nil 6
6 CONTACT WIRE WIRING 13 shots nil 6
7 ATD ERECTION 24 Nos nil 12
8 DROPPERING & CLIPPING 41 span nil 19
9 BRACKET ADJUSTMENT 167 Nos nil 74
10 SED CHECKING 8.35 TKM nil 3.7
11 ATD ADJUSTMENT 24 Nos nil 12
12 ISOLATOR ERECTION 3 Nos nil 2
13 SECTION INSULATOR ERECTION 6 Nos nil 5
14 TOWER WAGON CHECKING 8.35 TKM nil 3.7
15 BOND ERECTION 90 Nos nil 45
16 AT ERECTION 3 Nos nil 3
17 TURNOUT ERECTION 2 Nos nil 1
18 X-OVER ERECTION 1 Nos nil 1
BALANCE
67
46
46
93
7
7
12
22
93
4.65
12
1
1
4.65
45
0
1
0