Chart

The document outlines a project timeline with tasks, start and end dates, and durations. Key phases include Planning, Define Goals, Defining Scope, Requirements Gathering, System Design, Implementation, Testing, and Deployment. Each task has specific dependencies and durations, indicating a structured approach to project management.

Uploaded by

npamplinalstu
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
2 views

Chart

The document outlines a project timeline with tasks, start and end dates, and durations. Key phases include Planning, Define Goals, Defining Scope, Requirements Gathering, System Design, Implementation, Testing, and Deployment. Each task has specific dependencies and durations, indicating a structured approach to project management.

Uploaded by

npamplinalstu
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

TASK START DATE END DATE DURATION 15-Sep 25-Sep 5-Oct

Planning 15-Sep 22-Sep 8


Planning 8
Define Goals 23-Sep 25-Sep 3
Defining Scope 26-Sep 28-Sep 3 Define Goals 3
Defining Resources 29-Sep 1-Oct 3 Defining Scope 3
Requirements Gathering 2-Oct 8-Oct 7
Defining Resources 3
System Design 9-Oct 22-Oct 14
Implementaton 23-Oct 19-Nov 28 Requirements Gathering 7
Testing 20-Nov 3-Dec 14 System Design
Deployment 4-Dec 7-Dec 4
Implementaton
Testing
Deployment
25-Sep 5-Oct 15-Oct 25-Oct 4-Nov 14-Nov 24-Nov 4-Dec

8
3
3
3
7
14
28
14
4