Work Breakdown Structures: Engineering Project Plan

The document outlines a comprehensive work breakdown structure for an engineering project plan, detailing phases such as conceptual planning, definition, design, and construction. Each phase includes specific tasks related to planning, scope definition, discipline support, and completion criteria. Additionally, it includes a detailed construction plan for a house, covering various aspects like foundation work, internal and external installations, and general construction activities.

Uploaded by

kociro5434
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
30 views5 pages

Work Breakdown Structures: Engineering Project Plan

The document outlines a comprehensive work breakdown structure for an engineering project plan, detailing phases such as conceptual planning, definition, design, and construction. Each phase includes specific tasks related to planning, scope definition, discipline support, and completion criteria. Additionally, it includes a detailed construction plan for a house, covering various aspects like foundation work, internal and external installations, and general construction activities.

Uploaded by

kociro5434
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 5

Work Breakdown Structures

 Engineering project plan


o Conceptual
 Planning and Control
 Business plan identifying project opportunity
 Define project objective and information needs
 Identify industry standards for project objectives
 Develop preliminary conceptual schedule and staffing
 Initial planning complete
 Develop appropriation strategy
 Develop management model and staff plan
 Site Assessment
 Identify potential sites
 Define infrastructure requirements
 Define utility needs
 Identify project site
 Assess regulatory and environmental impacts
 Identify permitting requirements
 Recommend site
 Site and planning review
 Scope Definition
 Develop general scope for project objectives
 Evaluate project needs, develop major study list
 Start major studies
 Complete major studies and make recommendations
 Develop specific scope
 Prepare final conceptual schedule
 Provide written scope information
 Discipline Support
 Create deliverables list
 Start flow sheets and design criteria
 Start discipline-specific drawings and equipment list
 Start conceptual layout
 Complete flow sheets and design criteria
 Complete discipline-specific drawings and equipment list
 Complete conceptual layout
 Conceptual Phase Completion
 Prepare conceptual scope and estimate for review
 Evaluate business plan - rework as needed
 Conceptual phase complete
o Definition
 Planning and Control
 Review conceptual plan
 Update project staffing plan
 Develop project contingency and indirect cost factors
 Identify definition phase engineering deliverables
 Scope Definition
 Review studies list
 Provide design requirements
 Establish vendor data requirements/equipment budgets
 Define equipment specifications and list
 Generate piping and instrument drawing (PID)
 Discipline Support
 Review regulatory agency requirements
 Generate general arrangement and site plans
 Develop discipline specific control drawings, lists, specifications
 Evaluate input on feasibility of construction input
 Definition Phase Completion
 Generate scope document (including infrastructure)
 Generate project capital estimate
 Establish project schedule
 Review definition, scope and estimate
 Scope complete/issue cost estimate
 Appropriate project monies
 Project authorized
o Design
 Planning and Control
 Review definition, scope and estimate
 Develop or update project procedures
 Finalize design and construction schedule
 Develop and manage issues list
 Procure long delivery equipment
 Establish and implement procurement and contracting plan
 Plan and staff design phase
 Define engineering presentation and content for specifications and
drawings
 Implement document control
 Establish project monitoring
 Develop project cost control and earned value system
 Finalize deliverables list
 Implement project reporting
 Invoice approval/contract payments
 Procure equipment
 Implement expediting including vendor drawings
 Training start-up plan
 Scope Refinement
 Update project design criteria
 Issue for design: equipment list
 Issue for discipline design: piping and instrument drawings (PIDs)
 Issue for discipline design: general arrangement drawings
(GAs)/site plan
 Equipment specification, bid, vendor selection
 Process equipment functional descriptions
 Discipline Support
 Establish discipline governing code requirements
 Review and finalize discipline standards and specifications
 Start Discipline Design
 Start architectural design
 Start civil design
 Start mechanical design
 Start piping design
 Start structural design
 Start electrical design
 Start instrumentation design
 Implement first quality review
 Vendor drawing review (all disciplines)
 Vendor drawing certification (all disciplines)
 Cross discipline engineering review
 Complete equipment list
 Complete PIDs
 Complete GAs/site plan
 Complete Discipline Design
 Complete architectural design
 Complete civil design
 Complete mechanical design
 Complete structural design
 Complete piping design
 Complete electrical design
 Complete instrumentation design
 Implement second quality review
 Implement code compliance and safety reviews
 Design Phase Completion
 Check and redraft drawings and lists (all disciplines)
 Produce permit drawings and code compliance calculations
(all disciplines)
 Issue engineering for permitting, bidding and construction
 Contractor selection/contract review
 Project complete - close out report, issue drawings of
record
o Construction
 Select construction contractor
 Mobilize on site
 Construction
 Construction complete
 Construction of a House  Waste, water & treatment plan
o Foundation o Scr & equalization basin
 Excavation  Mobilization
 Pour concrete  Equipment set-up
 Cure & strip forms  Walk ways
 Steel Erection  Excavate & backfill
 Columns  Entrance
 Beams  Strip topsoil
 Joists  Excavate & fill
o Internal  Form & pour slab
 Form & pour walls
 Electricity
 Form & pour walks
 Rough-in electrical
 Backfill
 Install and terminate
 Electrical
 HVAC equipment
 Paint & finishes
 Plumbing
o Pump station
 Rough-in plumbing
 Set plumbing fixtures  Set precast station
and trim  Backfill
 Test and clean  Set pumps & vault
o External  Piping
 Electrical
 Masonry Work
o Control building
 Lay masonry
 Install roof drains  Fill
 Tiling in toilet rooms  Excavate & pour footings
 Roofing  Masonry to floor level
 Building Finishes  Pipe & electric under slab
 Paint walls  Form & pour slab
 Tile ceilings  Masonry & openings
 Hang wallpaper  Roof framing
 Carpets  Plumbing
 Hardware  Hvac & electrical
 Finishes
 Fill site
o General construction
 Concrete
 Set equipment
 Piping
 Electrical
 Roads
 Fence
 Finish grade & seed
 Startup & test
 Project substantial
completion
 Engineer & control
 Strip topsoil
 Scr & equalization basin
 Excavate & fill