FHWA Publication No. FHWA HI-95-038 - CH - 7 - Reinforced Embankments On Soft Foundations
FHWA Publication No. FHWA HI-95-038 - CH - 7 - Reinforced Embankments On Soft Foundations
7.1 BACKGROUND
The reinforcement may also reduce horizontal and vertical displacements of the underlying
soil and thus reduce differential settlement. It should be noted that the reinforcement will not
reduce the magnitude of long-term consolidation or secondary settlement of the embankment.
This chapter assumes that all the common foundation treatment alternatives for the
stabilization of embankments on soft or problem foundation soils have been carefully
considered during the preliminary design phase. Holtz (1989) discusses these treatment
alternatives and provides guidance about when embankment reinforcement is feasible. In
some situations, the most economical final design may be some combination of a
conventional foundation treatment alternative together with geosynthetic reinforcement.
Examples include preloading and stage construction with prefabricated (wick) vertical drains,
7.2 APPLICATIONS
Reinforced embankments over weak foundations typically fall into one of two situations -
construction over uniform deposits, and construction over local anomalies (Bonaparte, Holtz,
and Giroud, 1985). The more common application is embankments, dikes, or levees
constructed over very soft, saturated silt, clay, or peat layers (Figure 7-1). In this situation,
the reinforcement is usually placed with its strong direction perpendicular to the centerline of
the embankment, and plane strain conditions are assumed to prevail. Additional
reinforcement with its strong direction oriented parallel to the centerline may also be required
at the ends of the embankment.
The second reinforced embankment situation includes foundations below the embankment
that are locally weak or contain voids. These zones or voids may be caused by sinkholes,
thawing ice (thermokarsts), old streambeds, or pockets of silt, clay, or peat (Figure 7-1). In
this application, the role of the reinforcement is to bridge over the weak zones or voids, and
tensile reinforcement may be required in more than one direction. Thus, the strong direction
of the reinforcing must be placed in proper orientation with respect to the embankment
centerline (Bonaparte and Christopher, 1987).
Biaxial geogrids may also be used as a stabilization layer for embankment construction. This
stabilization geogrid may provide reinforcement strength in the embankment’s longitudinal
direction (see Step 9 in Sections 7.3-2 and 7.3-3). A lightweight geotextile filter, if needed,
can be used in conjunction with the geogrid.
Figure 7-2. Reinforced embankments failure modes (after Haliburton et al., 1978b).
The stability of an embankment over soft soil is usually determined by the total stress
method of analysis, which is conservative since the analysis generally assumes that no
strength gain occurs in the compressible soil. The stability analyses presented in this text
uses the total stress approach, because it is simple and appropriate for reinforcement design
(Holtz, 1989).
It is always possible to calculate stability in terms of the effective stresses using the effective
stress shear strength parameters. However, this calculation requires an accurate estimate of
the field pore pressures to be made during the project design phase. Additionally, high-
quality, undisturbed samples of the foundation soils must be obtained and Ko consolidated-
undrained triaxial tests conducted in order to obtain the required design soil parameters.
Because the prediction of in-situ pore pressures in advance of construction is not easy, it is
essential that field pore pressure measurements using high quality piezometers be made
during construction to control the rate of embankment filling. Preloading and staged
embankment construction are discussed in detail by Ladd (1991). Note that by taking into
account the strength gain that occurs with controlled rate (e.g. staged) embankment
construction, lower strength and therefore lower cost reinforcement can be utilized.
However; the time required for construction may be significantly increased and the costs of
the site investigation, laboratory testing, design analyses, field instrumentation, and
inspection are also greater.
The total stress design steps and methodology are detailed in the following section.
[Note: The subjects of site investigation and laboratory testing, soil shear strength
determination, and field instrumentation are addressed in detail in the following FHWA
references: NHI-01-031 Subsurface Investigations - Geotechnical Site Characterization
(NHI course No. 132031 reference manual{Mayne et al., 2002}); IF-02-034 Geotechnical
Engineering Circular No. 5 Evaluation of Soil and Rock Properties (Sabatini, et al., 2002);
NHI-06-088 Soils and Foundations Workshop (NHI course No. 132012 reference manual
{Samtani and Nowatzki, 2006}); and HI-98-034 Geotechnical Instrumentation (NHI course
No. 132041 reference manual {Dunnicliff, 1988}).]
A. Embankment height, H
B. Embankment length
C. Width of crest
E. External loads
1. surcharges
2. temporary (traffic) loads
3. dynamic loads
F. Environmental considerations
1. frost action
2. shrinkage and swelling
3. drainage, erosion, and scour
STEP 2. Establish the soil profile and determine the engineering properties of the
foundation soil.
A. Classification properties
B. Moisture-density relationships
A. Bearing capacity:
Overall bearing capacity: 2.0
Local bearing capacity (i.e., lateral squeeze type failure): 1.3 to 2.0
A. When the thickness of the soft soil is much greater than the width of the
embankment, use classical bearing capacity theory:
where Nc, the bearing capacity factor, is usually taken as 5.14 -- the value for
a strip footing on a cohesive soil of constant undrained shear strength, cu, with
depth. This approach may underestimate the bearing capacity of reinforced
embankments, as discussed in Section 7.3-3.
A. If the calculated factor of safety is greater than the minimum required, then
reinforcement is not needed. Check lateral embankment spreading (Step 7).
B. If the factor of safety is less than the required minimum, then calculate the
required reinforcement strength, Tg, to provide an adequate factor of safety
using Figure 7-3 or alternative solutions (Section 7.3-3), where:
FS (M D ) − M R
Tg =
R cos(θ − β )
A. If the calculated factor of safety is greater than the minimum required, then
reinforcement is not needed for this failure mode possibility.
In absence of test data, the value of tan φsg may conservatively be taken as 2/3
tan φ’. In absence of test data, the value of ca should be assumed to be 0.
b tan φ sg
FS =
Ka H
Recommendations for strain limits, based on type of fill soil materials and for
construction over peats, are:
A. Check bearing capacity and rotational slope stability at the ends of the
embankment (Steps 5 and 6).
A. Design strengths and modulus are based on the ASTM D 4595 wide width
tensile test. This test standard permits definition of tensile modulus in terms
of: (i) initial tensile modulus; (ii) offset tensile modulus; or (iii) secant tensile
modulus. Furthermore, the secant modulus may be defined between any two
strain points. Geosynthetic modulus for design of embankments should be
determined using a secant modulus, defined with the zero strain point and
design strain limit (i.e., 2 to 10%) point.
B. Geotextile seam strength is quantified with the ASTM D 4884 test method,
and is equal to the strength required in the embankment’s longitudinal
direction. Geogrid overlap strength, for longitudinal direction strength, is
quantified with pullout testing (ASTM D 6706).
C. Soil-geosynthetic friction, φsg, based on ASTM D 5321 with on-site soils. For
preliminary estimates, assume φsg = 2/3φ; for final design, testing is
recommended.
D. Geotextile stiffness based on site conditions and experience. See Sect. 7.4-5.
STEP 15. Observe construction and build with confidence (if the procedures outlined in
these guidelines are followed!)
Follow traditional geotechnical practice, except that the first few lifts of fill material
just above the geosynthetic should be free-draining granular materials. This
requirement provides the best frictional interaction between the geosynthetic and fill,
as well as providing a drainage layer for excess pore water to dissipate from the
underlying soils. Other fill materials may be used above this layer as long as the
strain compatibility of the geosynthetic is evaluated with respect to the backfill
materials (Step 8).
When a fill is placed on soft ground, the main driving force is from the weight of the
embankment itself. It may be advantageous to use a lightweight fill material to
reduce the driving forces, thereby increasing the overall global stability of the fill.
The reduction in driving force will depend upon the type of lightweight fill material
used. The geotechnical properties of various types of lightweight fill materials are
discussed in detail in FWHA NHI-06-019 Ground Improvement Methods Reference
The minimum factors of safety previously stated are recommended for projects with
modern state-of-the-practice geotechnical site investigations and laboratory testing.
Those factors may be adjusted depending on the method of analysis, type and use of
facility being designed, the known conditions of the subsurface, the quality of the
samples and soils testing, the cost of failure, the probability of extreme events
occurring, and the engineer's previous experience on similar projects and sites. In
short, all of the uncertainties in loads, analyses, and soil properties influence the
choice of appropriate factors of safety. Typical factors of safety for unreinforced
embankments also seem to be appropriate for reinforced embankments.
When the calculated factor of safety is greater than 1 but less than the minimum
allowable factor of safety for design, say 1.3 or 1.5, then the geosynthetic provides an
additional factor of safety or a second line of defense against failure. On the other
hand, when the calculated factor of safety for the unreinforced embankment is
significantly less than 1, the geosynthetic reinforcement is the difference between
success and failure. In this latter case, construction considerations (Section 7.8)
become crucial to the project success.
Overall Bearing
Reinforcement does not increase the overall bearing capacity of the foundation soil.
If the foundation soil cannot support the weight of the embankment, then the
embankment cannot be built. Thus, the overall bearing capacity of the entire
embankment must be satisfactory before considering any possible reinforcement. As
such, the vertical stress due to the embankment can be treated as an average stress
over the entire width of the embankment, similar to a semi-rigid mat foundation.
The bearing capacity can be calculated using classical soil mechanics methods
(Terzaghi and Peck, 1967; Vesic, 1975; Perloff and Baron, 1976; and U.S. Navy,
If the factor of safety for bearing capacity is sufficient, then continue with the next
step. If not, consider increasing the embankment's width, flattening the slopes,
adding toe berms, or improving the foundation soils by using stage construction and
drainage enhancement or other alternatives, such as relocating the alignment or
placing the roadway on an elevated structure.
Lateral Squeeze
High lateral stresses in a confined soft stratum beneath an embankment could lead to
a lateral squeeze-type failure. Lateral squeeze-type failure of the foundation should
be anticipated if γfill x Hfill > 3cu, (see FHWA Soils and Foundation Manual, FHWA
NHI-06-088 {Samtani and Nowatzki, 2006}) and a weak soil layer exists beneath the
embankment to a depth that is less that the width of the embankment. The shear
forces developed under the embankment should be compared to the corresponding
shear strength of the soil. Approaches discussed by Jürgenson (1934), Silvestri
(1983), and Bonaparte, Holtz and Giroud (1985), Rowe and Soderman (1987a), Hird
and Jewell (1990), and Humphrey and Rowe (1991) are appropriate. The designer
should be aware that the analysis for lateral squeeze is only approximate, and no
single method is completely accepted by geotechnical engineers at present. When the
depth of the soft layer, DS, is greater than the base width of the embankment, general
global bearing capacity and overall stability will govern the design.
2 cu 4.14 cu
FS squeezing = + ≥ 1.3 [7-6]
γ Ds (tan θ ) Hγ
where:
θ = angle of slope.
γ = unit weight of soil in slope.
Ds = depth of soft soil beneath slope base of the
embankment.
H = height of slope.
cu = undrained shear strength of soft soil beneath slope.
Caution is advised and rigorous analysis (e.g, numerical modeling and/or extensive
subsurface investigation with careful evaluation of cu) should be performed when FS
< 2. For factors of safety below 2, cu should be confirmed through rigorous
laboratory testing on undisturbed samples direct simple shear, evaluation of over
consolidation ratio (e.g. Ladd, 1991), or triaxial compression with pore pressure
measurements and/or field vane shear tests. Careful monitoring during construction
will be required with piezometers, surface survey monuments (both within and
outside the toe of the embankment), and inclinometers installed for construction
control.
2 cu 4.14 c u
FS = +
γ Ds (tanθ ) Hγ
Figure 7-6. Local bearing failure (lateral squeeze).
2 cu 4.14 c u
FS squeezing = + ⇒
γ D s (tan θ ) Hγ
Since FSsqueezing is lower than the recommended 1.3, the stability conditions must be
improved. This could be accomplished by either reducing the slope angle, use of
lightweight embankment fill, or by placing a surcharge at the toe (which effectively
reduces the slope angle). In addition, if the resulting factor of safety is less than 2,
refinement of the analysis should be considered as previously discussed (i.e., careful
evaluation of cu, consider performing numerical modeling, and install instrumentation
for construction control).
The next step is to calculate the factor of safety against a circular failure through the
embankment and foundation using classical limiting equilibrium-type stability
analyses. If the factor of safety does not meet the minimum design requirements
(Step 4), then the reinforcing tensile force required to increase the factor of safety to
an acceptable level must be estimated.
This is done by assuming that the reinforcement acts as a stabilizing tensile force at
its intersection with the slip surface being considered. The reinforcement thus
provides the additional resisting moment required to obtain the minimum required
factor of safety. The analysis is shown in Figure 7-3.
The analysis consists of determining the most critical failure surface(s) using
conventional limiting equilibrium analysis methods. For each critical sliding surface,
the driving moment (MD) and soil resisting moment (MR) are determined as shown in
A number of procedures have been proposed for determining the required additional
reinforcement, and these are summarized by Christopher and Holtz (1985), Bonaparte
and Christopher (1987), Holtz (1990), and Humphrey and Rowe (1991). The basic
difference in the approaches is in the assumption of the reinforcement force
orientation at the location of the critical slip surface (the angle ß in Figures 7-3a and
7-3b). It is conservative to assume that the reinforcing force acts horizontally at the
location of the reinforcement (ß = 0). In this case, the additional reinforcing moment
is equal to the required geosynthetic strength, Tg, times the vertical distance, y, from
the plane of the reinforcement to the center of rotation, or:
ªMR = Tg y [7-6a]
as determined for the most critical failure surface, shown in Figure 7-3a. This
approach is conservative because it neglects any possible reinforcement reorientation
along the alignment of the failure surface, as well as any confining effect of the
reinforcement.
In each method, the depth of the critical failure surface must be relatively shallow,
i.e., y in Figure 7-3a must be large, otherwise the geosynthetic contribution toward
increasing the resisting moment will be small. On the other hand, Jewell (1988) notes
that shallow slip surfaces tend to underestimate the driving force in the embankment,
and both he and Leshchinsky (1987) have suggested methods to address this problem.
In the latter case, the shearing resistance of the foundation soils just below the
embankment is insufficient to maintain equilibrium. Thus, in both cases, the
reinforcement must have sufficient friction to resist sliding on the reinforcement
plane, and the geosynthetic tensile strength must be sufficient to resist rupture as the
potential sliding surface passes through the reinforcement.
The forces involved in the analysis of embankment spreading are shown in Figure 7-4
for the two cases above. The lateral earth pressures, usually assumed to be active, are
In the case where an MSE or RSS structure is founded at the end of the embankment
(but not supporting a bridge structure) the length b may be taken as the reinforcement
length, L, of the MSE or RSS structure. An MSE or RSS structure should only be
included at the end of an embankment after the foundation soil has been adequately
improved (i.e., through surcharging) to support such structures or other ground
improvement techniques are employed, such as stabilization berms, lightweight fill,
etc.
Excessive deformation of the embankment and its reinforcement may limit its
serviceability and impair its function, even if total collapse does not occur. Thus, an
analysis to establish deformation limits of the reinforcement must be performed. The
most common way to limit deformations is to limit the allowable strain in the
geosynthetic. This is done because the geosynthetic tensile forces required to prevent
failure by lateral spreading are not developed without some strain, and some lateral
movement must be expected. Thus, geosynthetic modulus is used to control lateral
spreading (Step 7). The distribution of strain in the geosynthetic is assumed to vary
linearly from zero at the toe to a maximum value beneath the crest of the
embankment. This is consistent with the development of lateral earth pressures
beneath the slopes of the embankment.
For the assumed linear strain distribution, the maximum strain in the geosynthetic
will be equal to twice the average strain in the embankment. Fowler and Haliburton
(1980) and Fowler (1981) found that an average lateral spreading of 5% was
reasonable, both from a construction and geosynthetic property standpoint. If 5% is
the average strain, then the maximum expected strain would be 10%, and the
geosynthetic modulus would be determined at 10% strain (Equation 7-3). However,
If cohesive soils are used in the embankment, then the modulus should be determined
at 2% strain to reduce the possibility of embankment cracking (Equation 7-4). Of
course, if embankment cracking is not a concern, then these limiting reinforcement
strain values could be increased. Keep in mind, however, that if cracking occurs, no
resistance to sliding is provided. Further, the cracks could fill with water, which
would add to the driving forces.
Most embankments are relatively long but narrow in shape. Thus, during
construction, stresses are imposed on the geosynthetic in the longitudinal direction,
i.e., along the direction of the centerline. Reinforcement may be also required for
loadings that occur at bridge abutments, and due to differential settlements and
embankment bending, especially over nonuniform foundation conditions and at the
edges of soft soil deposit.
Because both sliding and rotational failures are possible, analysis procedures
discussed in Steps 6 and 7 should be applied, but in the direction along the alignment
of the embankment. This determines the longitudinal strength requirements of the
geosynthetic. Because the usual placement of the geosynthetic is in strips
perpendicular to the centerline, the longitudinal stability will be controlled by the
strength of the transverse seams.
See Section 7.4 for a determining the required properties of the geosynthetic.
Although not part of the stability analyses, both the magnitude and rate of settlement
of the embankment should be considered in any reinforcement design. There is some
evidence from finite element studies that differential settlements may be reduced
Time required for settlement can be substantially decreased with foundation drains.
Consolidation of soft ground using vertical drains is a technique used since the 1920s.
Today, the most common method is the use of wick drains, which can best be
described as prefabricated vertical drains (PVDs), since drainage is via pressure, and
not by wicking. PVDs are used to accelerate consolidation of soft saturated
compressible soils under load. The most common use of PVDs is to accelerate
consolidation for approach embankments at bridges or other embankment
construction over soft soils, where the total post construction settlement is not
acceptable.
When PVDs are used to accelerate settlement, the subsoil must meet the following
criteria:
• Moderate to high compressibility.
• Low permeability.
• Full saturation.
• Final embankment loads must exceed maximum past pressure.
• Secondary consolidation must not be a major concern.
• Low-to-moderate shear strength.
The evaluation, design, cost, specification, and construction with PVDs are discussed
in detail in FWHA NHI-06-019 Ground Improvement Methods Reference Manual –
Volume I (Elias et al., 2006). Filtration of the PVD geotextile should be evaluated
following the guidelines in Chapter 2 of this manual.
See Section 7.8 for details on site preparation, special construction equipment,
geosynthetic placement procedures, seaming techniques, and fill placement and
compaction procedures.
It has been our experience that the more potential contractors know about the overall
project, the site conditions, and the assumptions and expectations of the designers, the
more realistically they can bid; and, the project is more successful. Prebid and
preconstruction information meetings with contractors have been very successful in
establishing a good, professional working relationship between owner, design
engineer, and contractor. Partnering type contracts and a disputes resolution board
can also be used to reduce problems, claims, and litigation.
Once the design strength requirements have been established, the appropriate geosynthetic
must be selected. In addition to its tensile and frictional properties, drainage requirements,
construction conditions, and environmental factors must also be considered. Geosynthetic
properties required for reinforcement applications are given in Table 7-1. The selection of
appropriate fill materials is also an important aspect of the design. When possible, granular
fill is preferred, especially for the first few lifts above the geosynthetic.
b. Hydraulic
Piping resistance Apparent opening size
Permeability Permeability
Constructability Requirements:
Tensile strength Grab strength
Puncture resistance Puncture resistance
Tear resistance Trapezoidal tear
Longevity:
UV stability (if exposed) UV resistance
Soil compatibility (where required) Chemical; Biological
NOTE: 1. See Table 1-3 for specific test procedures.
The tensile strength and modulus values should preferably be determined by an in-soil tensile
test. From research by McGown, Andrawes, and Kabir (1982) and others, we know that in-
soil properties of many geosynthetics are markedly different than those from tests conducted
in air. However, in-soil tests are not yet routine nor standardized, and the test proposed test
methods need additional work. The practical alternate is to conservatively use a
representative (i.e., wide strip) tensile test as a measure of the in-soil strength. This point is
discussed by Christopher and Holtz (1985) and Bonaparte, Holtz, and Giroud (1985).
Therefore, strength and modulus are based on testing of wide specimens. ASTM D 4595,
Standard Test Method for Tensile Properties of Geotextiles by the Wide-Width Strip Method,
is used for geotextiles, and ASTM D 6637 Standard Test Method for Determining Tensile
Properties of Geogrids by the Single or Multi-Rib Tensile Method with Method B or C (wide
specimen) is used for geogrids. These test standards permits definition of tensile modulus in
terms of: (i) initial tensile modulus; (ii) offset tensile modulus; or (iii) secant tensile
modulus. Furthermore, the secant modulus may be defined between any two strain points.
Geosynthetic modulus for design of embankments should be determined using a secant
modulus, defined with the zero strain point and design strain limit (i.e., 2 to 10%) point.
The following minimum criteria for tensile strength of geosynthetics are recommended.
1. For ordinary cases, determine the design tensile strength Td (the larger of Tg
and Tls) and the required secant modulus at 2 to 10% strain.
2. The ultimate tensile strength Tult obviously must be greater that the design
tensile strength, Td. Note that Tg includes an inherent safety factor against
overload and sudden failure that is equal to the rotational stability safety
factor. The tensile strength requirements should be increased to account for
installation damage, depending on the severity of the conditions.
3. The strain of the reinforcement at failure should be at least 1.5 times the
secant modulus strain to avoid brittle failure. For exceptionally soft
foundations where the reinforcement will be subjected to very large tensile
stresses during construction, the geosynthetic must have either sufficient
strength to support the embankment itself, or the reinforcement and the
embankment must be allowed to deform. In this case, an elongation at rupture
of up to 50% may be acceptable. In either case, high tensile strength
geosynthetics and special construction procedures (Section 7.8) are required.
4. If there is a possibility of tension cracks forming in the embankment or high
Depending on the strength requirements, geosynthetic availability, and seam efficiency, more
than one layer of reinforcement may be necessary to obtain the required tensile strength. If
multiple layers are used, a granular layer of 8 to 12 in. (200 to 300 mm) must be placed
between each successive geosynthetic layer or the layers must be mechanically connected
(e.g., sewn) together. Also, the geosynthetics must be strain compatible; that is, the same
type of geosynthetic should be used for each layer.
For soil-geosynthetic friction values, either direct shear or pullout tests should be utilized. If
test values are not available, Bell (1980) recommends that for sand embankments, the soil-
geosynthetic friction angle is from 2/3φ up to the full φ of the sand. Since these early
recommendations, a number of direct shear and pullout tests have been performed on both
geogrids and geotextiles and the recommendations still apply. It is recommended that in the
absence of tests, a soil-geosynthetic friction angle of 2/3 φ should be conservatively used for
granular fill placed directly on the geosynthetic. For clay soils, friction tests are definitely
warranted and should be performed under all circumstances.
The creep properties of geosynthetics in reinforced soil systems are not well established. In-
soil creep tests are possible but are far from routine today. For design, it is recommended
that the working stress be kept much lower than the creep limit of the geosynthetic. Values
of 40 to 60% of the ultimate stress are typically satisfactory for this purpose. Live loads
versus dead loads also must be taken into account. Short-term live loadings are much less
detrimental in terms of creep than sustained dead loads. And finally, as discussed in Section
7.3-3 Step 11, the relative rates of deformation of the geosynthetic versus the consolidation
and strength gain of the foundation soil must be considered. In most cases, creep is not an
issue in reinforced embankment stability.
COVER MATERIAL
Some to most aggregate
CONSTRUCTION Fine sand to + 2 in. Coarse aggregate with
with diameter greater than
(50 mm) diameter diameter up to one-half
one-half proposed lift
gravel, rounded to proposed lift thickness,
thickness, angular and
subangular may be angular
sharp-edged, few fines
Low ground
pressure equipment
(4 psi)
Moderate/Low Moderate High
6 to 12 in.
(150 to 300 mm) {30 kPa}
Initial Lift
Thickness Medium ground
pressure equipment
(> 4 psi, < 8 psi)
Moderate High Very High
{>30 kPa,<60 kPa}
Medium ground
pressure equipment
(> 4 psi, < 8 psi)
Moderate/Low Moderate High
12 to 18 in.
(300 to 450 mm) {>30 kPa,<60 kPa}
Initial Lift
Thickness High ground
pressure equipment
(> 8 psi)
Moderate High Very High
{>60 kPa}
NOTES:
1. For special construction techniques such as prerutting, increase geosynthetic survivability requirement one
level.
2. Placement of excessive initial cover material thickness may cause bearing failure of soft subgrades.
3. Note that equipment used for embankment construction (even High Ground Pressure equipment) have
significantly lower ground contact pressures than equipment used for roadway construction (Table 5-2).
NOTES:
1. Acceptance of geotextile material shall be based on ASTM D 4759.
2. Acceptance shall be based upon testing of either conformance samples obtained using Procedure A of ASTM
D 4354, or based on manufacturer’s certifications and testing of quality assurance samples obtained using
Procedure B of ASTM D 4354.
3. Minimum; use value in weaker principal direction. All numerical values represent minimum average roll
value (i.e., test results from any sampled roll in a lot shall meet or exceed the minimum values in the table).
Lot samples according to ASTM D 4354.
4. Recommend survivability of candidate “Very High” survivability geotextile(s) be demonstrated on a
field/project basis or the use of a “High” survivability geotextile as a sacrificial layer.
OPENING CHARACTERISTICS
Opening Size Direct measure mm Opening Size > D50 of aggregate above geogrid
Most reinforcement analyses assume that the fill material is granular. In fact, in the past the
use of cohesive soils together with geosynthetic reinforcement has been discouraged. This
may be an unrealistic restriction, although there are problems with placing and compacting
cohesive earth fills on especially soft subsoils. Furthermore, the frictional resistance between
geosynthetics and cohesive soils is problematic. It may be possible to use composite
embankments. Cohesionless fill could be used for the first 18 to 36 in. (0.5 to 1 m); then the
rest of the embankment could be constructed to grade with locally available materials.
• Project Description: A 4-lane highway is to be constructed over a peat bog. Alignment and
anticipated settlement require construction of an embankment with an
average height of 6.5 ft. See project cross section figure.
GIVEN DATA
• Geosynthetic - geotextile (a geogrid also may be used for this example problem; however,
this example represents an actual case history where a geotextile was used)
• Stability Stability analyses of the unreinforced embankment were conducted with the STABL
computer program. The most critical condition for embankments on soft soils is end-
of-construction case; therefore, UU (unconsolidated, undrained) soil shear strength
values are used in analyses.
DEFINE
A. Geotextile function(s):
SOLUTION
A. Geotextile function(s):
Primary - reinforcement (for short-term conditions)
Secondary - separation and filtration
DESIGN
Considering depth of embedment (i.e., shearing will have to occur through the embankment
for a bearing capacity failure) the bearing capacity is more accurately computed (see
Meyerhof) as follows.
Nc = 4.14 + 0.5 B/D where, B = the base width of the embankment (~ 100 ft),
and
D = the average depth of the soft soil (~ 15 ft)
Nc = 4.14 + 0.5 (100 ft / 15 ft) = 7.5
qult = 100 psf x 7.5 = 750 psf
with a geotextile, and assuming that the geotextile will result in an even distribution of the
embankment load over the width of the geotextile (i.e., account for the slopes at the
embankment edges),
Add berms to increase bearing capacity. Berms, 10 ft wide, can be added within the existing
right-of-way, increasing the base width to 120 ft. With this increase in width,
Nc = 4.14 + 0.5 (120 ft / 15 ft) = 8.14
qult = 100 psf x 8.1 = 814 psf
and,
B. Lateral squeeze
From FHWA Foundation Manual (Cheney and Chassie, 1993) -
If γfill x Hfill > 3c, then lateral squeeze of the foundation soil can occur. Since Pmax =
900 psf is much greater than 3c, even considering the crust layer (c = 200 psf), a rigorous
lateral squeeze analysis was performed using the method by Jürgeson (1934). In this method,
the lateral stress beneath the toe of the embankment is determined through charts or finite
element analysis and compared to the shear strength of the soil. This method indicated a
safety factor of approximately 1 for the 100 ft base width. Adding the berm and extending
the reinforcement to the toe of the berm decreases the potential for lateral squeeze as the
lateral stress is reduced at the toe of the berm. The berms increased FSSQUEEZZE to greater
than 1.5.
Also, comparing the reinforced design with Figure 7-5 indicates that the reinforced
structure should be stable.
The critical unreinforced failure surface is found through rotational stability methods. For
this project, STABL4M was used and the critical, unreinforced surface FS = 0.72. As the
soil supporting the embankment was highly compressible peat, the reinforcement was
assumed to rotate such that β = θ (Figure 7-3 and Eq. 7-4b). Thus,
M R + Tg R
FS req = ≥ 1.3
MD
1 .3 M D − M R
Tg =
R
Feasible - yes. Geosynthetics are available which exceed this strength requirement,
especially if multiple layers are used. For this project, an installation damage factor of
approximately equal to 1.0, and 2 layers were used:
Bottom: 6,000 lb/ft
Top: 12,000 lb/ft
The use of 2 layers allowed the lower cost bottom material to be used over the full
embankment plus berm width, while the higher strength and more expensive geotextile was
only placed under the embankment section where it was required.
b tan φ sg
FS =
Ka H
26 ft × tan 23
FS =
0.27 × 6.5 ft
FS > 6, OK
For cohesionless sand and gravel over deformable peat use Є = 10%
From Step 7,
use TL = Tls = 53 kN/m for reinforcement and seams in the cross machine (X-MD) direction
B. seam strength
Tseam $ 3,560 lb/ft with controlled fill placement
C. soil-geosynthetic adhesion
from testing, per ASTM D 5321, Nsg $ 23○
Use a Very High Survivability geotextile (from Tables 7-2 and 7-3). Therefore, from Table 7-4, the
survivability of candidate geotextile reinforcements shall be demonstrated on a field/project basis or a
“High” survivability geotextile, meeting the minimum average roll values listed below, may be used
as a sacrificial layer.
ASTM Minimum
Property Test Method Strength
Grab Strength D 4632 1400 N (315 lbs)
Tear Resistance D 4533 500 N (110 lbs)
Puncture Strength D 6241 2750 N (620 lbs)
Description
This work shall consist of furnishing and placing construction geotextile in accordance with the
details shown in the plans, these specifications, or as directed by the Engineer.
Materials
Geotextile and Thread for Sewing
The material shall be a woven geotextile consisting only of long chain polymeric filaments or
yarns formed into a stable network such that the filaments or yarns retain their position relative to
each other during handling, placement, and design service life. At least 95 percent by mass of the
of the material shall be polyolefins or polyesters. The material shall be free from defects or tears.
The geotextile shall be free of any treatment or coating which might adversely alter its hydraulic
or physical properties after installation. The geotextile shall conform to the properties as
indicated in Table 1.
Thread used shall be high strength polypropylene, polyester, or Kevlar thread. Nylon threads will
not be allowed.
Geotextile Approval
Source Approval
The Contractor shall submit to the Engineer the following information regarding each
geotextile proposed for use:
If the geotextile source has not been previously evaluated, a sample of each proposed geotextile
shall be submitted to the Olympia Service Center Materials Laboratory in Tumwater for
evaluation. After the sample and required information for each geotextile type have arrived at the
Olympia Service Center Materials Laboratory in Tumwater, a maximum of 14 calendar days will
be required for this testing. Source approval will be based on conformance to the applicable
values from Table 1. Source approval shall not be the basis of acceptance of specific lots of
material unless the lot sampled can be clearly identified, and the number of samples tested and
approved meet the requirements of WSDOT Test Method 914.
The geotextile samples shall be cut from the geotextile roll with scissors, sharp knife, or other
suitable method which produces a smooth geotextile edge and does not cause geotextile
ripping or tearing. The samples shall not be taken from the outer wrap of the geotextile nor
the inner wrap of the core.
Acceptance Samples
Samples will be randomly taken by the Engineer at the job site to confirm that the geotextile
meets the property values specified.
Approval will be based on testing of samples from each lot. A "lot" shall be defined for the
purposes of this specification as all geotextile rolls within the consignment (i.e., all rolls sent
to the project site) which were produced by the same manufacturer during a continuous
period of production at the same manufacturing plant and have the same product name. After
the samples and manufacturer's certificate of compliance have arrived at the Olympia Service
Certificate of Compliance
The Contractor shall provide a manufacturer's certificate of compliance to the Engineer which
includes the following information about each geotextile roll to be used:
Approval Of Seams
If the geotextile seams are to be sewn in the field, the Contractor shall provide a section of
sewn seam which can be sampled by the Engineer before the geotextile is installed.
The seam sewn for sampling shall be sewn using the same equipment and procedures as will
be used to sew the production seams. The seam sewn for sampling must be at least 2 meters
in length. If the seams are sewn in the factory, the Engineer will obtain samples of the
factory seam at random from any of the rolls to be used. The seam assembly description shall
be submitted by the Contractor to the Engineer and will be included with the seam sample
obtained for testing. This description shall include the seam type, stitch type, sewing thread
type(s), and stitch density.
Construction Requirements
Geotextile Roll Identification, Storage, and Handling
Geotextile roll identification, storage, and handling shall be in conformance to ASTM D 4873.
During periods of shipment and storage, the geotextile shall be stored off the ground. The
geotextile shall be covered at all times during shipment and storage such that it is fully protected
from ultraviolet radiation including sunlight, site construction damage, precipitation, chemicals
that are strong and acids or strong bases, flames including welding sparks, temperatures in excess
of 70o C, and any other environmental condition that may damage the physical property values of
the geotextile.
Small soil piles or the manufacturer’s recommended method shall be used as needed to hold the
geotextile in place until the specified cover material is placed.
Should the geotextile be torn or punctured or the sewn joints disturbed, as evidenced by visible
geotextile damage, subgrade pumping, intrusion, or roadbed distortion, the backfill around the
damaged or displaced area shall be removed and the damaged area repaired or replaced by the
Contractor at no expense to the Contracting Agency. The repair shall consist of a patch of the
same type of geotextile placed over the damaged area. The patch shall be sewn at all edges.
If geotextile seams are to be sewn in the field or at the factory, the seams shall consist of two
parallel rows of stitching, or shall consist of a J-seam, Type Ssn-1, using a single row of stitching.
The two rows of stitching shall be 25 mm apart with a tolerance of plus or minus 13 mm and
shall not cross, except for restitching. The stitching shall be a lock-type stitch. The minimum
seam allowance, i.e., the minimum distance from the geotextile edge to the stitch line nearest to
that edge, shall be 40 mm if a flat or prayer seam, Type SSa-2, is used. The minimum seam
allowance for all other seam types shall be 25 mm. The seam, stitch type, and the equipment
used to perform the stitching shall be as recommended by the manufacturer of the geotextile and
as approved by the Engineer.
The seams shall be sewn in such a manner that the seam can be inspected readily by the Engineer
or his representative. The seam strength will be tested and shall meet the requirements stated in
this Specification.
Embankment construction shall be kept symmetrical at all times to prevent localized bearing
capacity failures beneath the embankment or lateral tipping or sliding of the embankment. Any
fill placed directly on the geotextile shall be spread immediately. Stockpiling of fill on the
geotextile will not be allowed.
The geotextile shall be pretensioned during installation using either Method 1 or Method 2 as
described herein. The method selected will depend on whether or not a mudwave forms during
placement of the first one or two lifts. If a mudwave forms as fill is pushed onto the first layer of
Method 1
After the working platform, if needed, has been constructed, the first layer of geotextile shall
be laid in continuous transverse strips and the joints sewn together. The geotextile shall be
stretched manually to ensure that no wrinkles are present in the geotextile. The fill shall be
end-dumped and spread from the edge of the geotextile. The fill shall first be placed along
the outside edges of the geotextile to form access roads. These access roads will serve three
purposes: to lock the edges of the geotextile in place, to contain the mudwave, and to provide
access as needed to place fill in the center of the embankment. These access roads shall be
approximately 5 meters wide. The access roads at the edges of the geotextile shall have a
minimum height of 0.6 meters when completed. Once the access roads are approximately 15
meters in length, fill shall be kept ahead of the filling operation, and the access roads shall be
kept approximately 15 meters ahead of this filling operation as shown in the Plans. Keeping
the mudwave ahead of this filling operation and keeping the edges of the geotextile from
moving by use of the access roads will effectively pre-tension the geotextile. The geotextile
shall be laid out no more than 6 meters ahead of the end of the access roads at any time to
prevent overstressing of the geotextile seams.
Method 2
After the working platform, if needed, has been constructed, the first layer of geotextile shall
be laid and sewn as in Method 1. The first lift of material shall be spread from the edge of
the geotextile, keeping the center of the advancing fill lift ahead of the outside edges of the
lift as shown in the Plans. The geotextile shall be manually pulled taut prior to fill placement.
Embankment construction shall continue in this manner for subsequent lifts until the
uppermost geotextile layer is completely covered with 0.3 meters of compacted fill.
Measurement
High strength geotextile for embankment reinforcement will be measured by the square meter for
the ground surface area actually covered.
Payment
The unit contract price per square meter for “High Strength Geotextile For Embankment
Reinforcement”, shall be full pay to complete the work as specified.
The construction procedures for reinforced embankments on soft foundations are extremely
important. Improper fill placement procedures can lead to geosynthetic damage, nonuniform
settlements, and even embankment failure. By the use of low ground pressure equipment, a
properly selected geosynthetic, and proper procedures for placement of the fill, these
problems can essentially be eliminated. Essential construction details are outlined below.
The Washington State DOT Special Provision (see Section 7.6) provides additional details.
A. Prepare subgrade:
1. Cut trees and stumps flush with ground surface.
2. Do not remove or disturb root or meadow mat.
3. Leave small vegetative cover, such as grass and reeds, in place.
4. For undulating sites or areas where there are many stumps and fallen trees,
consider a working table for placement of the reinforcement. In this case, a
lower strength sacrificial geosynthetic designed only for constructability can be
used to construct and support the working table.
3. Geotextiles should be sewn as required with all seams up and every stitch
inspected. Geogrids may be joined to hold adjacent rolls together or maintain
overlaps by ties, clamps, cables, etc.
SEQUENCE OF CONSTRUCTION
1. LAY GEOSYNTHETIC IN CONTINUOUS TRAVERSE STRIPS, SEW STRIPS TOGETHER.
2. END DUMP ACCESS ROADS.
3. CONSTRUCT OUTSIDE SECTIONS TO ANCHOR GEOSYNTHETIC.
4. CONSTRUCT OUTSIDE SECTION TO “SET” GEOSYNTHETIC.
5. CONSTRUCT INTERIOR SECTIONS TO TENSION GEOSYNTHETIC.
6. CONSTRUCT FINAL CENTER SECTION
Figure 7-7. Construction sequence for geosynthetic reinforced embankments for extremely
weak foundations (from Haliburton, Douglas and Fowler, 1977).
(b)
(c)
Special considerations are required for widening of existing roadway embankments founded
on soft foundations. Construction sequencing of fill placement, connection of the
geosynthetic to the existing embankment, and settlements of both the existing and new fills
must be addressed by the design engineer. Analytical techniques for geosynthetic
reinforcement requirements are the same as those discussed in Section 7.3.
Two example roadway widening cross sections are illustrated in Figure 7-11. The addition
of a vehicle lane on either side of an existing roadway (Figure 7-11a) is feasible if the traffic
can be detoured during construction. In this case, the reinforcement may be placed
continuously across the existing embankment and beneath the two new outer fill sections.
Placing both new lanes to one side of the embankment (Figure 7-11b) may allow for
maintaining one lane of traffic flow during construction. With the new fill placed to one side
of the existing embankment, the anchorage of the geosynthetic into the existing embankment
becomes an important design step.
Both the new fill sections and the existing fill sections will most likely settle during and after
fill placement, although the amount of settlement will be greater for the new fill sections.
The existing fills settle because of the influence of the new, adjacent fill loads on their
foundation soils. The amount of settlements is a function of the foundation soils and amount
of load (fill height). When fill is placed to one side of an embankment (Figure 7-11b) the
pavement may need substantial maintenance during construction and until settlements are
nearly complete. Alternatively, light-weight fill could be used to reduce the settlement of the
new fill and existing sections.
For soft subgrades, where a mud wave is anticipated, construction should be parallel to the
alignment with the outside fill placed in advance of the fill adjacent to the existing
embankment. For firm subgrades, with no mudwave, fill may be placed outward,
perpendicular to the alignment.
(a)
(b)
Figure 7-11. Reinforced embankment construction for roadway widening; a) fill placement
on both sides of existing embankment; b) fill placement on one side of the
existing fill.
Special considerations are required for constructing large reinforced areas, such as parking
lots, toll plazas, storage yards for maintenance materials and equipment, and construction
pads. Loads are more biaxial than conventional highway embankments, and design strengths
and strain considerations must be the same in all directions. Analytical techniques for
geosynthetic reinforcement requirements are the same as those discussed in Section 7.3.
Because geosynthetic strength requirements will be the same in both directions, including
across the seams, special seaming techniques must often be considered to meet required
strength requirements. Ends of rolls may also require butt seaming. In this case, rolls of
different lengths should be used to stagger the butt seams. Two layers of fabric should be
considered, with the bottom layer seams laid in one direction, and the top layer seams laid
perpendicular to the bottom layer. The layers should be separated by a minimum lift
thickness, usually 12 in. (300 mm), soil layer.
For extremely soft subgrades, the construction sequence must be well planned to
accommodate the formation and movement of mudwaves. Uncontained mudwaves moving
outside of the construction can create stability problems at the edges of the embankment. It
may be desirable to construct the fill in parallel embankment sections, then connect the
embankments to cover the entire area. Another method staggers the embankment load by
constructing a wide, low embankment with a higher embankment in the center. The outside
low embankments are constructed first and act as berms for the center construction. Next, an
adjacent low embankment is constructed from the outside into the existing embankment; then
the central high embankment is spread over the internal adjacent low embankment. Other
construction schemes can be considered depending on the specific design requirements. In
all cases, a perimeter berm system is necessary to contain the mudwave.
An alternate approach of embankment construction on soft soils may be used when time
constraints are critical to the success of the project. Column supported embankments (CSE)
with a geosynthetic reinforced load transfer platform are designed to transfer the load of the
embankment through the soft compressible soil layer to a firm foundation, thus eliminating
the construction wait time for dissipation of pore water pressures and minimizing settlement
of the foundation soils. This technology was first used in Sweden in 1971, and has been used
successfully on projects in the U.S. since 1994.
The key advantage to CSE is that construction may proceed rapidly in one stage. One major
benefit of CSE technology is that it is not limited to any one-column type. Where the
infrastructure precludes high-vibration techniques, the type of column used for the CSE
system may be selected to minimize or eliminate the potential for vibrations. If contaminated
soils are anticipated at a site, the column type may be selected so that there are no spoils from
the installation process. The designer has the flexibility of selection of the most appropriate
column for the project. Total and differential settlement of the embankment may be
drastically reduced when using CSE over conventional approaches. A potential disadvantage
of CSE is often initial construction cost when compared to other solutions. However, if the
time savings when using CSE technology is included in the economic analysis, the cost may
be far less than other solutions.
CSE may be used whenever an embankment must be constructed on soft compressible soil.
To date, the technology has been limited to embankment heights in the range of 33 feet (10
m). CSE technology reduces post construction settlements of the embankment surface to
typically less than 2 to 4 in. (50 to 100 mm). A generalized summary of the factors that
should be considered when assessing the feasibility of utilizing CSE technology on a project
is presented in FHWA NHI-06-020, Ground Improvement Methods Reference Manual –
Volume II.
ASTM, Annual Books of ASTM Standards, (2006). Volume 4.13 Geosynthetics, American
International, West Conshohocken, Pennsylvania.
Bell, J.R. (1980). Design Criteria for Selected Geotextile Installations, Proceedings of the
1st Canadian Symposium on Geotextiles, pp. 35-37.
Bonaparte, R., Holtz, R.R. and Giroud, J.P. (1985). Soil Reinforcement Design Using
Geotextiles and Geogrids, Geotextile Testing and The Design Engineer, J.E. Fluet, Jr.,
Editor, ASTM STP 952, 1987, Proceedings of a Symposium held in Los Angeles, CA,
July 1985, pp. 69-118.
Cheney, R.S. and Chassie, R.G. (1993). Soils and Foundations Workshop Manual, HI-88-
099, 395 p.
Christopher, B.R. and Holtz, R.D. (1985). Geotextile Engineering Manual, FHWA-TS-
86/203, 1044 p.
Christopher, B.R. and Holtz, R.D. (1989). Geotextile Design and Construction Guidelines,
FHWA-HI-90-001, 297 p.
Elias, V., Welsh, J., Warren, J., Lukas, R., Collin, J.G. and Berg, R.R. (2006). Ground
Improvement Methods; FHWA NHI-06-019 Volume I and NHI-06-020 Volume II; NHI
course No. 132034 reference manual; 536 p and 520 p.
Fowler, J. and Haliburton, T.A. (1980). Design and Construction of Fabric Reinforced
Embankments, The Use of Geotextiles for Soil Improvement, Preprint 80-177, ASCE
Convention, pp. 89-118.
Haliburton, T.A., Anglin, C.C. and Lawmaster, J.D. (1978a). Testing of Geotechnical Fabric
for Use as Reinforcement, Geotechnical Testing Journal, American Society for Testing
and Materials, Vol. 1, No. 4, pp. 203-212.
Haliburton, T.A., Anglin, C.C. and Lawmaster, J.D. (1978b). Selection of Geotechnical
Fabrics for Embankment Reinforcement, Report to U.S. Army Engineer District, Mobile,
Oklahoma State University, Stillwater, 138p.
Haliburton, T.A., Douglas, P.A. and Fowler, J. (1977). Feasibility of Pinto Island as a Long-
Term Dredged Material Disposal Site, Miscellaneous Paper, D-77-3, U.S. Army
Waterways Experiment Station.
Hird, C.C. and Jewell, R.A. (1990). Theory of Reinforced Embankments, Reinforced
Embankments - Theory and Practice, Shercliff, D.A., Ed., Thomas Telford Ltd., London,
UK, pp. 117-142.
Humphrey, D.N. and Rowe, R.K. (1991). Design of Reinforced Embankments - Recent
Developments in the State of the Art, Geotechnical Engineering Congress 1991, McLean,
F., Campbell, D.A. and Harris, D.W., Eds., ASCE Geotechnical Special Publication No.
27, Vol. 2, June, pp. 1006-1020.
Humphrey, D.N. and Holtz, R.D. (1989). Effects of a Surface Crust on Reinforced
Embankment Design, Proceedings of Geosynthetics '89, Industrial Fabrics Association
International, St. Paul, MN, Vol. 1, pp. 136-147.
Humphrey, D.N. (1987). Discussion of Current Design Methods by R.M. Koerner, B-L Hwu
and M.H. Wayne, Geotextiles and Geomembranes, Vol. 6, No. 1, pp. 89-92.
Humphrey, D.N. and Holtz, R.D. (1987). Use of Reinforcement for Embankment Widening,
Proceedings of Geosynthetics '87, Industrial Fabrics Association International, St. Paul,
MN, Vol. 1, pp. 278-288.
Jewell, R.A. (1988). The Mechanics of Reinforced Embankments on Soft Soils, Geotextiles
and Geomembranes, Vol. 7, No. 4, pp.237-273.
Jürgenson, L. (1934). The Shearing Resistance of Soils, Journal of the Boston Society of
Civil Engineers. Also in Contribution to Soil Mechanics, 1925-1940, BSCE, pp. 134-
217.
Koerner, R.M., Editor (1990). The Seaming of Geosynthetics, Special Issue, Geotextiles and
Geomembranes, Vol. 9, Nos. 4-6, pp. 281-564.
Ladd, C.C. (1991). Stability Evaluation During Staged Construction, 22nd Terzaghi Lecture,
Journal of Geotechnical Engineering, American Society of Civil Engineers, Vol. 117,
No. 4, pp. 537-615.
McGown, A., Andrawes, K.Z., and Kabir, M.H. (1982). Load-Extension Testing of
Geotextiles Confined in Soil, Proceedings of the Second International Conference on
Geotextiles, Las Vegas, Vol. 3, pp. 793-798.
Perloff, W.H. and Baron, W. (1976). Soil Mechanics: Principles and Applications, Ronald,
745 p.
Rowe, R.K. and Mylleville, B.L.J. (1989). Consideration of Strain in the Design of
Reinforced Embankments, Proceedings of Geosynthetics '89, Industrial Fabrics
Association International, St. Paul, MN, Vol. 1, pp. 124-135.
Rowe, R.K. and Soderman, K.L. (1987a). Reinforcement of Embankments on Soils Whose
Strength Increases With Depth, Proceedings of Geosynthetics '87, Industrial Fabrics
Association International, St. Paul, MN, Vol. 1, pp. 266-277.
Sabatini, P.J., Bachus, R.C., Mayne, P.W., Schneider, J.A. and Zettler, T.E. (2002). GEC
No. 5 – Evaluation of Soil and Rock Properties, Geotechnical Engineering Circular No.
5, FHWA IF-02-034, 385 pp.
Samtani, N.C. and Nowatzki, E.A. (2006). Soils and Foundations Workshop Reference
Manual, FHWA NHI-06-088, NHI course No. 132012 reference manual.
Silvestri, V. (1983). The Bearing Capacity of Dykes and Fills Founded on Soft Soils of
Limited Thickness, Canadian Geotechnical Journal, Vol. 20, No. 3, pp. 428-436.
Terzaghi, K. and Peck, R.B. (1967). Soil Mechanics in Engineering Practice, 2nd Edition,
John Wiley & Sons, New York, 729 p.
U.S. Department of the Navy (1986). Foundations and Earth Structures, Design Manual 7.2,
Naval Facilities Engineering Command, Alexandria, VA, (can be downloaded from
http://www.geotechlinks.com)
Wager, O. (1981). Building of a Site Road over a Bog at Kilanda, Alvsborg County, Sweden
in Preparation for Erection of Three 400kV Power Lines, Report to the Swedish State
Power Board, AB Fodervävnader, Borå, Sweden, 16p.