Estimation and Coasting
Estimation and Coasting
2.5
Item No Particulars of Item Units Nos Length Width Depth Quantity
1 Earth Work Excavation Cums
1.Long Wall 2 6.9 1.1 1.4 21.252
2.Short Wall 2 3.7 1.1 1.4 11.396
Total 32.648
6 Plastering
Inside cums
1.Long Wall 2 5 4 0.015 0.6
2.Short Wall 2 4 5 0.015 0.6
Total 1.2
Out side cums
1.Long Wall 2 0.015
2.Short Wall 2 0.015
Total
375 12243
380 5316.96
300 4833.6
Area
20 37.2044
0.1539
Contingencies Charges= 5%
Work Charge Establishment=2%
390 25833.6
110
=
104.6914
430.4094
535.1007
stablishment=2%
Item No Particulars of Item Units Nos Length Width Depth Quantity
1 Earth Work Exacvation Cums 1 22.69 1.1 1.6 39.9344
Total 39.9344
2 PCC In Foundation Cums 1 22.69 1.1 0.2 4.9918
Total 4.9918
3 Brick Work In Foundation Cums
1st Step 1 22.69 0.8 0.3 5.4456
2nd Step 1 22.69 0.6 0.3 4.0842
Plinth 1 22.69 0.4 0.8 7.2608
Total 16.7906
4 DPC Cums 1 22.69 0.4 0.015 0.13614
Total 0.13614
5 Brick Work In Super Structure Cums 1 22.69 0.3 3.4 23.1438
Total 23.1438
Center line
Rate(m3) Cost(Rs) Remarks
22.69
0.75
1.35
6.3 1.54434452114805
10.3 3.0886890422961
3
22.6886890422961
1.749286
1.544345
Item No Particulars of Item Units Nos Length Width Depth Quantity
1 Earth Work Exacvation Cums
1.Long Wall 2 5.8 0.5 3.5 20.3
2.Short Wall 2 4.8 0.5 3.5 16.8
Total 37.1
2 Brick work in Foundation Cums
1.Long Wall
1st Footing 2 5.8 0.5 0.8 4.64
2nd Footing 2 5.7 0.4 1.5 6.84
Plinth 2 5.6 0.5 1.2 6.72
18.2
2.Short Wall
1st Footing 2 4.8 0.5 0.8 3.84
2nd Footing 2 4.7 0.4 1.5 5.64
Plinth 2 4.6 0.5 1.2 5.52
15
Total 33.2
3 Brick work in Superstructure Cums
1.Long Wall 2 5.8 0.3 2 6.96
2.Short Wall 2 4.6 0.3 2 5.52
12.48
Rate(m3) Cost(Rs) Remarks
375 13912.5
Steps With Same Sides
Item No Particulars of Item Units Nos Length Width Depth
1 Earth Work Exacvation Cums 1 1.9 0.95 0.1
2 Concrete In Exacvation Cums 1 1.9 0.95 0.1
3 Brick Work In Steps
1st Step Cums 1 1.8 0.9 0.2
2nd Step Cums 1 1.8 0.6 0.15
3rd Step Cums 1 1.8 0.3 0.15
Total
4 Finishing 20mm Cement Plaster Cums
Treads
Risers
Ends
0.324
0.162
0.081
0.567
Av
des
Quantity Rate(m3) Cost(Rs) Remarks
0.704
0.528
0.69
0.3375
0.18
0.054
1.2615
Item No Particulars of Item Units Nos Length Width Depth
1 Quantity Of Metal Cums 1 1000 3.7 0.12
2 Stone Grit and Binder or Paint Cums
1.Coat of Painting
Stone Grit,20mm [email protected] cum % 1 1000 3.7 0.0135
Binder Road Tar or Asplault 220 kg % 1 1000 3.7 2.2
2.Coat of Painting
Stone Grit,20mm [email protected] cum % 1 1000 3.7 0.0075
Binder Road Tar or Asplault 120 kg % 1 1000 3.7 1.2
3 Concrete Road For Surface Cums
1.Cement Concrete Surface 1 1000 3.7 0.08
2.Cement Concrete Surface 1 1000 3.7
Quantity Rate(m3) Cost(Rs) Remarks
444
49.95
8.14
27.75
4.44
296
Estimation Of Isolated RCC Footing Which 1 x 1m Size
Item No Particulars of Work Units Nos Length Width Depth
1 Earth Work Exacvation Cums 1 1 1 1.3
2 PCC In Foundation (1:3:6) Cums 1 1 1 0.1
Total
3 RCC Works Cums
1. Footing without Slope 1 1 1 0.3
2. Footing with Slope
v=(h/4)(A1+A2+(SQRT(A1*A2))) 1 1 1 0.45
3. Column Below GL 1 0.4 0.4 0.45
4. Column GL TO Plinth 1 0.4 0.4 0.75
5. Column Plinth To Slab 1 0.3 0.3 3
Total
4 Earth Work Foundation Cums
Total Exacvation-PCC-RCC Below GL 1 1 1 1.3
Total
5 Reinforcement
Reinforcement In Footing
Size Of Reinforcemnt Mesh In Footing 0.9 0.9
Length Of Bars= 0.9+2(9D) 1.116
No.of Bars=(Distance/Spacing)+1 10
Total Reinforcement In Both Ways 20
Total Length Of The Bars 22.32
Unit Weight Of Reinforcement
Total Quantity Of Reinforcement
Reinforcement In Column
Length Of Bars= 0.9+2(9D)
h 1 x 1m Size
Quantity Rate(m3) Cost(Rs) Remarks
1.3 Unit Weight Of Reinforcement/m =(D 2/162
0.1
0.1
0.3
1
0.1755 0.16
0.072
0.12
0.27
0.9375
0.6525
0.6525
0.888888888889
19.84
ht Of Reinforcement/m =(D 2/162)
Estimation Of Slab
Item No Particulars of Work Units Nos Length Width
1 R.C.C. work I: 2 : 3 Cums 1 6.3 3.3
2 Steel Bars Cums
1.Main bars 12 mm dia. Details 24 cm c/c
26.2508333333333
Length Of The Bar 27 3.436
2.Bendup Bars 12 mm dia. Details 24 cm c/c
26.25
Length Of The Bar 26 3.516
Total
3.Distribution Bars 6mm [email protected] kg/m 180mm c/c
11.1111111111111
Length Of The Bar 12 6.328
Two Bars At Top Both Sides 6 6.328
Two Bars At Bottom Both Sides 6 6.328
Total
Total Qunatity Of Steel in Quintal
Total Cost
Add 5% Continegencies Charges
Total Cost Of Steel And Concrete
Depth Quantity Rate(m3) Cost(Rs) Remarks
0.12 2.4948 675 1683.99
92.772 3.436
91.416 3.516
184.188
163.9273
75.936 6.328
37.968
37.968
151.872 Sum Of Quantities
33.41184 Quantities*Unit Weight
1.973392 515 1016.297
2700.287
135.0143
2835.301
Estimation Of Beam
Item No Particulars of Work Units Nos Length Width Depth
1 R.C.C. work I: 2 : 3 Cums 1 8.6 0.4 0.75
2 Steel Bars With Bendups Cums
1.Main Bars 22mm Dia @2.98 kg/m
Length Of The Bar 4 8.916
Total Quanity In Kg
2.Bendup Bars 20mm Dia @2.47 kg/m
Length Of The Bar 4 9.53
Total Quanity In Kg
3.Top Bars 12mm Dia @0.89 kg/m
Length Of The Bar 2 8.736
Total Quanity In Kg
4.Stirrups 10mm Dia 120mmc/c @0.62 kg/m
Length Of The Bar 10 2.42
Total Quanity In Kg
5.Stirrups 10mm Dia 200mmc/c @0.62 kg/m
Length Of The Bar 12 2.42
Total Quanity In Kg
5.Stirrups 6mm Dia 350mmc/c @0.22 kg/m
Length Of The Bar 14 2.42
Total Quanity In Kg
Total Quantity Of Steel In Quintal
Total Cost
Add 3% Continegencies Charges
2% Work Charge Establishment
Total Charges
Total Cost Of Material
Quantity Rate(m3) Cost(Rs) Remarks
2.58 675 1741.5
35.664 8.916
106.27872
38.12 9.53
94.1564
17.472 8.736
15.55008
24.2 2.42
15.004
29.04 2.42
18.0048
33.88 2.42
7.4536
2.564476 515 1320.7051
3062.2051
91.866154
61.244103
153.11026
3215.3154
Stations Of Chainage Length Height Mean Height(d) Central Area (Bd) Side Area (Sd2)
10 300 2
11 330 1.2 1.6 16 5.12
12 360 1.16 1.18 11.8 2.7848
13 390 0.5 0.83 8.3 1.3778
14 420 0.18 0.34 3.4 0.2312
15 450 1.6 0.89 8.9 1.5842
16 480 0.6 1.1 11 2.42
17 510 1.2 0.9 9 1.62
18 540 0.39 0.795 7.95 1.26405
19 570 0.7 0.545 5.45 0.59405
20 600 1.1 0.9 9 1.62
Total Area (Bd+Sd2) Length (L) Quantity(Bd+Sd2)xL
21.12 30 633.6
14.5848 30 437.544
9.6778 30 290.334
3.6312 30 108.936
10.4842 30 314.526
13.42 30 402.6
10.62 30 318.6
9.21405 30 276.4215
6.04405 30 181.3215
10.62 30 318.6
Total 3282.483
PEP CLASS Center Line Method
Item No Particulars of Work Units Nos Length Width Depth
1 EarthWork Exacuation Cums 1 24.4 0.9 1.6
2 PCC in Foundation Cums 1 24.4 0.9 0.2
3 Brick Work In Foundation Cums
Step-1 1 24.4 0.7 0.2
Step-2 1 24.4 0.5 0.2
Plinth 1 24.4 0.4 1
Brick Work In Walls 1 24.4 0.4 1
Total
4 Earth Work Back Filling Cums 1 6.2 5.2 1
5 Flooring C.C Cums 1 7 6 0.02
Flooring L.C Cums 1 7 6 0.08
Contingency Charges 2%
WCE 3%
Total Cost
Contingency Charges 2%
WCE 3%
Total Cost
Quantity Rate(m3) Cost(Rs) Remarks
35.136 70 2459.52
4.392 4900 21520.8
3.416
2.44
9.76
9.76
25.376 1500 38064
32.24 70 2256.8
0.84 5400 4536
3.36 6000 20160
Total 88997.12
1779.9424
2669.9136
93446.976
od
Quantity Rate(m3) Cost(Rs) Remarks
21.6
13.536
35.136
2.7
1.692
4.392
2.044
1.372
1.42
1.02
5.6
4.16
5.6
4.16
25.376
32.24
0.84
3.36
PEP CLASS- Long Wall Short Wall Method
Item No Particulars of Work Units Nos Length Width Depth
1 EarthWork Exacuation Cums
Long Wall 2 11.7 1.1 1
Short Wall 3 5.2 1.1 1
Total
2 PCC in Foundation Cums
Long Wall 2 11.7 1.1 0.3
Short Wall 3 5.2 1.1 0.3
Total
3 Brick Work In Foundation Cums
Step-1
Long Wall 2 11.4 0.8 0.2
Short Wall 3 5.5 0.8 0.2
Step-2
Long Wall 2 11.3 0.7 0.1
Short Wall 3 5.6 0.7 0.1
Step-3
Long Wall 2 11.2 0.6 0.1
Short Wall 3 5.7 0.6 0.1
Step-4
Long Wall 2 11.1 0.5 0.1
Short Wall 3 5.8 0.5 0.1
Plinth
Long Wall 2 11 0.4 0.8
Short Wall 3 5.9 0.4 0.8
Contingency Charges 2%
WCE 3%
Total Cost
Quantity Rate(m3) Cost(Rs) Remarks
25.74
17.16
42.9
7.722
5.148
12.87
3.648
2.64
1.582
1.176
1.344
1.026
1.11
0.87
7.04
5.664 IS-1200 ,28-PARTS
26.1
27.468
22.68
50.148
1.512
1.8
0.45
3.762
46.386
32.24
1.7985
5.5275
PEP CLASS- Long Wall Short Wall Method
Item No Particulars of Work Units Nos Length Width Depth
1 EarthWork Exacuation Cums
Long Wall 2 10.6 0.9 1.5
Short Wall 2 2.8 0.9 1.5
Total
2 PCC in Foundation Cums
Long Wall 2 10.6 0.9 0.3
Short Wall 2 2.8 0.9 0.3
Total
3 Brick Work In Foundation Cums
Step-1
Long Wall 2 10.3 0.6 0.3
Short Wall 2 3.1 0.6 0.3
Step-2
Long Wall 2 10.2 0.5 0.3
Short Wall 2 3.2 0.5 0.3
Plinth
Long Wall 2 10.1 0.4 0.6
Short Wall 2 3.3 0.4 0.6
Total
4 Brick Work In Super Structure
Long Wall 2 10 0.3 3.5
Short Wall 2 3.4 0.3 3.5
Total
Contingency Charges 2%
WCE 3%
Total Cost
d
Quantity Rate(m3) Cost(Rs)
28.62
7.56
36.18 70 2532.6
5.724
1.512
7.236 4900 35456.4
3.708
1.116
3.06
0.96
4.848
1.584
15.276 3200 48883.2
21
7.14
28.14 3800 106932
Total 193804.2
3876.084
5814.126
203494.4
PEP CLASS Center Line Method
Item No Particulars of Work Units Nos Length Width Depth
1 EarthWork Exacuation Cums 1 39 1.1 1
2 PCC in Foundation Cums 1 39 1.1 0.3
3 Brick Work In Foundation Cums
Step-1 1 39.3 0.8 0.2
Step-2 1 39.4 0.7 0.1
Step-3 1 39.5 0.6 0.1
Step-4 1 39.6 0.5 0.1
Plinth 1 39.7 0.4 0.8
Total
4 Brick Work In Super Structure 1 39.8 0.3 4.2
Deductions
Doors 2 1.2 0.3 2.1
Windows 4 1 0.3 1.5
Selves 2 1 0.15 1.5
Lintel On Doors 2 1.6 0.3 0.13
Lintel On Windows 4 1.4 0.3 0.21
Lintel On Shelves 2 1.4 0.3 0.05
Total Deductions
Total Bricks In Super Structure
4 DPC Cums 1 39.7 0.4 _
5 White Wash
Inner Walls 1 44 4.2
Deduction
Doors 2 1.2 2.1
Windows 4 1 1.5
Selves 2 1 1.5
Total Deductions
Total Inner Walls Paints
Outer Walls 1 35 4.2
Deduction
Doors 2 1.2 2.1
Windows 4 1 1.5
Total Deductions
Total outer Walls Paints
Quantity Rate(m3) Cost(Rs) Remarks
42.9 21.2
12.87 18.9
40.1
6.288
2.758
2.37 0.002 13050
1.98
12.704
26.1
50.148
184.8 M2
5.04
6
3
14.04
170.76
147 M2
5.04
6
11.04
135.96
Item No Particulars of Item Units Nos Length Width Depth Quantity
1 Earth Work Exacvation Cums 1 20.25 0.9 1 18.225
Total 18.225
2 PCC In Foundation Cums 1 20.25 0.9 0.3 5.4675
Total 5.4675
3 Brick Work In Foundation Cums
1st Step 1 20.25 0.7 0.3 4.2525
2nd Step 1 20.25 0.6 0.2 2.43
3rd Step 1 20.25 0.5 0.2 2.025
Plinth 1 20.25 0.4 0.6 4.86
Total 13.5675
4 DPC Cums 1 20.25 0.4 8.1
Total 8.1
5 Brick Work In Super Structure Cums 1 20.25 0.3 3.7 22.4775
Total 22.4775
Deductions
Doors 1 1.2 2.2 0.3 0.792
Windows 6 1 1.5 0.3 2.7
Shelves 2 1 1.9 0.15 0.57
18.4155
Rate(m3) Cost(Rs) Remarks
20.25
m2
Reduced Level of Ground along center line of proposed road from chainage 20 to 30 m is given b
Gradient Value=chainage Length/Gradient=30/150=0.2
Chainage RL of Ground RL Of Formation Depth D Mean Depth(DM) b x dm
20 105 108 3
21 105.6 107.8 2.2 2.6 26
22 105.44 107.6 2.16 2.18 21.8
23 105.9 107.4 1.5 1.82999999999999 18.3
24 105.42 107.2 1.78 1.63999999999999 16.4
25 105.3 107 1.7 1.73999999999999 17.4
26 105 106.8 1.8 1.74999999999999 17.5
27 104.1 106.6 2.5 2.14999999999998 21.5
28 104.62 106.4 1.78 2.13999999999998 21.4
29 104 106.2 2.2 1.98999999999997 19.9
30 103.3 106 2.7 2.44999999999997 24.5
Abstract Of Estimation
Sl.No Descripition Quantity Units Rate Per Unit
1 Earth Work 8709.34199999993 Cums 275 Rs/m3
chainage 20 to 30 m is given below
Amount Unit
2395069 Rs
Reduced Level of Ground along center line of proposed road from chainage 20 to 30 m is given
Gradient Value=chainage Length/Gradient=40/200=0.2
Chainage RL of Ground RL Of Formation Depth D Mean Depth(DM) b x dm
20 71 72 1
21 71.25 72.2 0.95 0.975000000000001 15.6
22 70.9 72.4 1.5 1.225 19.6
23 71.25 72.6 1.35 1.425 22.8
24 70.8 72.8 2 1.675 26.8
25 70.45 73 2.55 2.275 36.4
26 70.2 73.2 3 2.775 44.4
27 70.35 73.4 3.05 3.02500000000001 48.4
28 69.1 73.6 4.5 3.77500000000001 60.4
29 69.45 73.8 4.35 4.425 70.8
30 69.7 74 4.3 4.325 69.2
from chainage 20 to 30 m is given below
Total
3.Distribution Bars 6mm [email protected] kg/m 180mm c/c
11.1111111111111
Length Of The Bar At Mid 11.11111 6.628
Bars At Top Both Sides 8.444444 6.628
Bars At Bottom Both Sides 8.444444 6.628
Total
Total Qunatity Of Steel in Quintal
Total Cost
Add 5% Continegencies Charges
Total Cost Of Steel And Concrete
Absract of Cost
Sl.No Items Of Work Quantity Units Rate Unit of Cost
1 Volume of Concrete 4.752 m3 375
2 Steel bars 3.713104 Q 4000
Depth Quantity Rate(m3) Cost(Rs) Remarks
0.2 4.752
103.4507 3.808
208.6813
185.7264
73.64444 6.628
55.96978
55.96978
185.584
3.713104
Amount
Estimation Of Beam
Item No Particulars of Work Units Nos Length Width Depth
1 R.C.C. work I: 2 : 3 Cums 1 8.4 0.4 0.6
2 Steel Bars With Bendups Cums
1.Main Bars 22mm Dia
Length Of The Bar 4 8.716
Total Quanity In Kg
2.Bendup Bars 22mm Dia
Length Of The Bar 4 9.316
Total Quanity In Kg
3.Top Bars 20mm Dia
Length Of The Bar 3 8.716
Total Quanity In Kg
4.Stirrups 6mm Dia 120mmc/c
Length Of The Bar 14 2.088
Total Quanity In Kg
5.Stirrups 10mm Dia 200mmc/c
Length Of The Bar 9 2.088
Total Quanity In Kg
5.Stirrups 6mm Dia 350mmc/
Length Of The Bar 13.71429 2.088
Total Quanity In Kg
Total Quantity Of Steel In Quintal
Total Cost
Add 3% Continegencies Charges
2% Work Charge Establishment
Total Charges
Total Cost Of Material
Quantity Rate(m3) Cost(Rs) Remarks
2.016
28.63543 2.088
6.299794
2.961306
Estimation Of Beam
Item No Particulars of Work Units Nos Length Width Depth Quantity
1 Earth Work Exacvation Cums 1 2 2 2.6 10.4
2 PCC Cums 1 2 2 0.08 0.32
3 RCC Works Cums
Cylindrical Volume 1 0.275786 0.275786
Rectangular Volume 1 0.32 0.32 1.6 0.16384
Trapizoidal Volume 1
v=(h/4)(A1+A2+(SQRT(A1*A2))) 2.84544
4 Steel Reinforcement Cums
Rate(m3) Cost(Rs) Remarks
4
0.1024