SPM Cie 2 QP - Set 2

This document is an internal evaluation paper for the Software Project Management course at Velammal Engineering College, detailing the structure of the exam including multiple-choice questions, short answer questions, and long answer questions. It covers topics such as PERT charts, configuration management, risk identification, and network planning models. The exam is scheduled for March 25, 2024, and is worth a total of 50 marks.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
20 views2 pages

SPM Cie 2 QP - Set 2

This document is an internal evaluation paper for the Software Project Management course at Velammal Engineering College, detailing the structure of the exam including multiple-choice questions, short answer questions, and long answer questions. It covers topics such as PERT charts, configuration management, risk identification, and network planning models. The exam is scheduled for March 25, 2024, and is worth a total of 50 marks.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Registration No.

Velammal Engineering College


(An Autonomous Institution, Affiliated to Anna University – Chennai)
Velammal Newgen Park Ambattur – RedHills Road , Chennai-600 066

CONTINUOUS INTERNAL EVALUATION (I)


Subject Code : 21CS317T Marks : 50 Marks
Subject Title : SOFTWARE PROJECT MANAGMENT Date : 25.03.2024
Department : CSE Time : 8.40 am to 10.20 am
Year / Sem : III/VI
Answer ALL Questions
PART-A(MCQ) (6x1 = 6 marks)
Q. Questions Marks CO Blooms
No Level
1. PERT chart’s full name is________. CO3 C1
Evaluation and Review Techniques for Programs
Evaluation of Programs and Robotic Techniques
Assessment of Programs and Robotics
Technology for Program Evaluation and Rating
2. The path which moves along the activities having total float zero, in the network CO3 C2
diagram is called________
1. Free float
2. Critical path
3. Total float
4. Independent float
3. The amount of time by which an activity can be delayed without affecting project CO3 C2
completion time is
1)Free float 2)Total float3)Independent float 4)Activity float
4. What combines procedures and tools to manage different versions of CO4 C1
configuration objects that are created during the software process?
a) Change control
b) Version control
c) SCIs
d) None of the mentioned
5. CO4 C2
Which of the following option is not tracked by configuration management tools?
a) Tracking of change proposals
b) Storing versions of system components
c) Tracking the releases of system versions to customers
d) None of the mentioned
6. CO4 C2
Which of the following is not a Software Configuration Management Activity?
a) Configuration item identification
b) Risk management
c) Release management
d) Branch management
PART-B (8 x 2 = 16 marks)

7. What is meant by free float and interfering float CO3 C1


8. What is meant by work breakdown structure CO3 C1
9. What are the approaches for identifying risk CO3 C1
10. What is activity on arrow approach in network modeling CO3 C1
11. Illustrate the use of Earned Value Analysis CO4 C2
12. What are the activities involved in contract management CO4 C1
13. List the techniques used in Visualizing project progress CO4 C2
14. Design Gantt chart for representing the progress of the project CO4 C6
PART-C (2 x 14 = 28 marks)

15. (a) Elaborate the activities of Network Planning Models (14) CO3 C6
(OR)
15. (b) Design the network planning model for the activities given below (14) CO3 C6
and find out critical path
Activity Predecessor Duration(week
Activity s)
A - 6
B - 4
C A 3
D B 4
E B 3
F - 10
G E,F 3
H C,D 2

16. (a) Explain about Software Configuration Management (14) CO4 C2


(OR)
16. (b) Explain about Cost Monitoring and Project tracking (14) CO4 C2