Electrical Power Distribution in Hospitals
Electrical Power Distribution in Hospitals
Faculty of Engineering
Electrical Power and Machines Department
Project title
Supervised by:
Prof. Dr. Ibrahim Helal
Presented by
Project title
Supervised by:
1|Page
➢ Table of content ........................................................................2
➢ Chapter 1: introduction ..........................................................7
o 1.1 hospital design criteria ..................................................... 7
o 1.2 Objectives ............................................................................... 8
o 1.3 Project description ............................................................. 8
2|Page
o 3.10 Power factor correction ............................................. 80
o 3.11 Earthing calculations ................................................... 81
o 3.12 Single Line Diagram ..................................................... 83
3|Page
o 7.1 INTRODUCTION .............................................................107
o 7.2 Transformer Construction .........................................107
o 7.3 Classification of transformers ..................................109
o 7.4Types of Distribution transformers: .......................113
o 7.5 ENERGY LOSSES IN TRANSFORMER .....................117
4|Page
o 10.2-Types of UPS .................................................................134
5|Page
CHAPTER (1)
INTRODUCTION
Distribution system is one of the greatest industrial systems in the
world. With the progress of human civilization, there has been a rapid
increase in the production and use of electrical energy. When designing a
commercial power system, special studies, experiences, and knowledge must
be comprised to evaluate the best performance of the system either at present
or at future. A lot of terms should be taken into consideration to achieve the
desired goals of constructing such a system. These terms may comprise safety,
reliability, adequate cost, high performance, and ease of maintenance.
➢ Medical Departments 15
8|Page
a) Ground floor consists of:
Ground floor
9|Page
b) First floor consists of:
First floor
10 | P a g e
c) Second floor consists of:
Second floor
11 | P a g e
d) Third floor consists of:
Third floor
12 | P a g e
e) Fourth floor consists of:
Fourth floor
13 | P a g e
CHAPTER (2)
CONCEPT DESIGN
2.1 Types of loads
It is important to determine types of loads to determine the way that would be
used to feed the load.
Some of HVAC loads for Elevators load BMS and light current
corridors and waiting room
area
14 | P a g e
2.2 Load estimation
It is an important phase to get initial load of project then account the demand
factor relationship between connected loads and the actual demand imposed
on the system.
in this chapter we concern in first load estimation before any detailed designs.
➢ Lighting loads
o It’s divided into two types one for indoor lighting (Spaces,
Corridors and General Lighting) and outdoor lighting (Cosmetic
Lighting, Lighting of outdoor squares and Stairs Lighting)
o Lighting loads cover both: Normal and Emergency Lighting.
➢ Loads of Small Electrical Appliances
o Includes appliances used in offices, Sockets feed refrigerators and
televisions.
➢ Air Conditions Loading
o Includes Cooling and Heating appliances.
➢ Electrical Loads for Water Equipment
o It covers water pumps, water boilers and firefighting.
15 | P a g e
➢ Elevator Loads
o Called Dynamic Loads, also cover movable stairs loads.
➢ Medical loads
a) Lighting
▪ According to NEC – Table 220.12:
Lighting Load = 27070 * 22
= 595540 VA
= 596 kVA
b) Sockets
▪ According to IEEE – Table 5:
Sockets Load = 27070 * 1 * 11
= 297770 VA
= 298 kVA
16 | P a g e
c) Air Conditioning
▪ According to IEEE – Table 7:
Air Conditioning Load for Hotels
= 6 VA/ft2
So, We Consider for Hospitals
= 8 VA/ft2
= 8 * 11 * 27070
= 2382160 VA = 2382 kV
e) Fire Protection
▪ According to IEEE – Table 11:
Area / Floor = 27070 / 5
= 5414 m2 (* 11)
= 59554 ft2
Load of Fire Protection
= (60/50) * 120
= 144 kW (/ 0.8)
= 180 kVA
17 | P a g e
f) Water Heater
▪ According to IEEE – Table 10:
We Have 250 Patient
So, Heaters Load = 2.5 * 200
= 500 kW (/ 0.8)
= 625 kVA
g) Kitchen Load
▪ According to IEEE – Table 12:
Kitchen Load = 300 kW (/ 0.8)
= 375 kVA
18 | P a g e
h) Elevators Load
▪ According to Egyptian Code for Feeding:
We Have 10 Elevators
So, Elevators Load = 10 * 9
= 90 kVA
19 | P a g e
• The Hospital Has 27 Neonatal Incubators
Neonatal Incubators Load
= 27 * 1000 = 27 kW (/0.8) = 34 kVA
2. Cardiac Catheterization
3. X-Ray
20 | P a g e
• X-Ray Load=65kW (/0.8)
= 82
• CT Load = 80 kW (/0.8)
= 100 kVA
21 | P a g e
6. Kidney dialysis machine
• We Have 37 Bed
22 | P a g e
➢ According to Power Supply Connection Guide The main of the two-
voltage installations medium and low Distributor room will be provided
and building will feed through 11kv M.V network from two different
loops to achieve high level of reliability of power flow.
2.3 ZONING
➢ It is important phase to get number of distribution panels which feed
loads and imagine how this boards will be fed from upper panels.
➢ Each panel will supply load for radius within the limits 40 to50m to
avoid high voltage drop.
➢ Each Critical rooms will feed from separate panel is supplied from
isolation transformer.
23 | P a g e
• Ground Floor
24 | P a g e
• First floor
25 | P a g e
• Electrical room in first floor
• Second Floor
26 | P a g e
• Electrical Rooms in Second Floor
27 | P a g e
• Third Floor
28 | P a g e
• Fourth Floor
29 | P a g e
CHAPTER (3)
DESIGN CALCULATIONS
3.1. Lighting distribution
3.1.1 Manual calculation
Steps:
• Determine room dimensions (L, W, and H).
• Specify the electrical power and the efficacy of the chosen luminaire.
• Calculate room utilization factor (UF).
• Choose the appropriate maintenance factor (MF).
• Specify the suitable lux according to Egyptian code.
• Calculate the number of lamps required.
31 | P a g e
UF = 0.46
Maintenance factor
32 | P a g e
➢ Select project luminaires
From different catalogs we determine our luminaires to be used
for this project depending on:
o Types of lamps to be used and its availability
o Types of ballast (electronic to improve P.F)
o Types of cover (prismatic, opal)
33 | P a g e
o With or without battery
o Type of ceiling recessed or surface mounting
o Determine the suitable color temperature and color
rendering index used 4000K.
o Determine the suitable IP and IK.
➢ Luminaires used:
▪ For surface mounting
34 | P a g e
▪ For Recessed Mounting
IP65 IP 44 Ip20
35 | P a g e
▪ For wall mounted for roof: ALVA HUS NR BELYSNING
15W /840 1005LM HV
➢ Positioning of luminaire:
36 | P a g e
37 | P a g e
3.1.3 Example from project plans:
❖ dialysis department
38 | P a g e
❖ operation room
❖ Kitchen
39 | P a g e
❖ Patient room
❖ ICU
40 | P a g e
❖ Nursery Department
41 | P a g e
3.2 socket distribution
Distribution of sockets is depending on function of each area and considering
Egyptian code regulations.
42 | P a g e
43 | P a g e
➢ Form medical load according to the Hospital design standards
• Legend used
44 | P a g e
3.2.1 Example for socket distribution in different rooms.
• Kidney Dialysis
Department
• Outpatients
Clinics
45 | P a g e
• Isolating Rooms
• Operations Room
46 | P a g e
• Preparation Room
47 | P a g e
• Offices
• Nursery Units
48 | P a g e
• Patients Accommodation
Our project has central HVAC, it will separate to two sections according to
type of supply Fan coil unit will be supplied from disconnect switch
49 | P a g e
connected to distribution board And Motor Control Center (MCC) which
will supply chiller, chiller pump, air handling unit and exhaust fan.
➢ Sample from fan coil unit loads were be prepared from mechanical
engineer
50 | P a g e
➢ Motor Control Center
51 | P a g e
➢ Air handling unit load
52 | P a g e
❖ Sizing of disconnect switch for
FCU
𝑃
• 𝐼= 𝑥 1.25
𝑉 𝑥 0.8
❖ MCC is fed by multicore cable its size will be according to load shown in
the schedule of the mechanical engineer as above from the main panel.
❖ Elevator
• The project includes 10 elevators.
• The elevator load = 15 kW.
❖ total Elevator load = 150 kW.
• It is fed from the emergency main panel and connected to it by a
disconnect switch.
53 | P a g e
❖ Fire Fighting pump
• The FFP load = 206HP= 160KW
• It is fed directly from the transformer.
• In case of failure of the transformer, it is fed from Diesel Generator
54 | P a g e
This table show sample of load classified to be critical
▪ 3.4.2 procedure
➢ Distribute the loads of each panel approximately equally on the three
phases to avoid unbalance between the phases which require ovel sizing
of cables.
➢ Divide the different load types which has different demand factor on the
three phase to obtain the diversified load of the panel.
Lighting 0.9
socket 0.4
55 | P a g e
➢ Spare will be around 20% and space around 10
𝑉𝑚𝑎𝑥 −𝑉𝑚𝑖𝑛
➢ Voltage balance % = ∗ 100
𝑉𝑎𝑣𝑔
56 | P a g e
57 | P a g e
58 | P a g e
59 | P a g e
60 | P a g e
61 | P a g e
62 | P a g e
63 | P a g e
64 | P a g e
3.5 Circuit breaker ratings and cable CSA
➢ CB calculations
𝑷
𝑰𝒏 = 𝒙 𝟏. 𝟐𝟓
√𝟑 𝒙 𝑽 𝒙 𝟎. 𝟖
➢ Cable calculations
𝐼𝑛
𝐼𝑐 =
𝐷𝐹 𝑜𝑟 𝐶𝐹
Where 𝐼𝑐 : Cable Current
𝐼𝑛 : Rated Current of CB
65 | P a g e
Used cable
66 | P a g e
L.V circuit breaker used
16, 20, 25, 32, 25, 32, 40, 50, 63, 800, 1000, 1250, 2000, 3200, 4000 A
40, 50, 63, 80, 80, 100, 125, 160, 1600 A
rating
100, 125 A 250, 320, 400, 630
A
picture
67 | P a g e
3.6 Voltage drop calculations
𝑆
1- 𝐼𝑏 = 𝐼𝑏 load current
√3∗𝑉
2- From elsewedy get mV/A/m value
3- V.D (Volt) = (mV/A/m)*Length*𝐼𝑏 /1000
%V.D= (V.D/380)*100
𝑆𝑠𝑐
𝐼𝑠𝑐 =
√3 ∗ 𝑉
220
𝑅𝑡𝑟𝑎𝑛𝑠 =
𝐼𝑠𝑐
68 | P a g e
3.8 Example from our project:
o Calculation for SMDB-G1
69 | P a g e
o Calculation for ELPP-F2-2
70 | P a g e
o Calculation of elevator feeder
71 | P a g e
o Calculation of ECMCC-F2 feeder
o
72 | P a g e
o Result of all panel of project
73 | P a g e
74 | P a g e
75 | P a g e
3.9 Bulk equipment
❖ 3.9.1 Transformer
• We have two Main Distribution Boards one of them feed motor control
centers and other one feed remaining loads.
• each Board is separated to two sections coupled with mechanical
interlock.
• MDB1-sec1 feeds 1087 KW demand load
• MDB1-sec2 feeds 1193KW demand load
• MDB-MCC1 feeds 1222 KW demand load
• MDB-MCC2 feeds 1127KWd demand load
• So, we use four transformers each one 2MVA and it will provide a
suitable backup if any failure occurs.
❖ 3.9.2 Generator
We have two emergency distribution boards.
• EMDB has total demand load=306KW.
So, we will use Generator (1) with 320KW standby generator.
• EMDB-MCC total demand load=870KW for emergency HVAC and
firefighting pump
We will use standby generator (2) 880KW
76 | P a g e
Generator (1)
Generator (2)
77 | P a g e
❖ 3.9.3 UPS
• Critical load is 144KW so select UPS from ABB data sheet
❖ 3.9.4 MV Distributor
o Will use to supply transformers of hospital from utility network.
o It has been described to be consisted of MCSet cells that is supplied from
Schneider electric and has and has this technical data shown below
▪ 16 Cell = 4 + 10 + 2
▪ 4: Incoming.
▪ 10: Outgoing.
▪ 2: Bus Coupler & Riser.
78 | P a g e
3.9.5 Ring main unit (RMU)
o It is used to connect transformers to
create an open loop is supplied from the
distributor.
o It contains protection devices of
transformer.
79 | P a g e
3.10 Power factor correction
Improving the power factor results in less current being drawn, therefore less
electricity costs, less heat and greater longevity of the electrical system
• For MDB-sec1:
√3𝑉 2
• 𝑄𝐶 =
𝑋𝐶
80 | P a g e
3.11 Earthing calculations
▪ Calculation of main earthing conductor
81 | P a g e
▪ Calculation of earth resistance multiple rods in hollow square
82 | P a g e
▪ TN-C-S system will be used in application like offices and rooms except
medical department like operation room and I.C.U IT system will be
used.
83 | P a g e
CHAPTER (4)
LIGHTING DESIGN
4.1-Introduction
Electrical power nowadays plays a great part in life of towns and cities, and
progress of countries. Hence a good distribution of electrical power is an
important factor for development. In this chapter we present the basis of
indoor lighting design, which include the illumination calculations.
Light is the prime factor in the human life as all activities of human depend
upon the light. Where there is no natural light, a source of artificial light was
needed. Light may be produced by passing electric currents through filaments
as in the incandescent lamps, through arcs between carbon or metal rods, or
through suitable gases as in neon and other gas tubes. In some forms of lamps
the light is due to fluorescence excited by radiation arising from the passage of
electricity through mercury vapor.
Various forms of incandescent bodies are the sources of light and the light
emitted by such bodies depend upon its temperature. Energy is radiated into
the medium by a body which is hotter than the medium surrounding it, in the
form of electromagnetic waves of various wavelengths.
In this chapter
We will talk about the lighting distribution system in Hospital Our project is
consists of:
85 | P a g e
4- second floor (Obstetrics and gynecology-nursery department- Patients
Accommodation Department(
5- third floor (Patients Accommodation Department)
6- fourth floor (Patients Accommodation Department- Doctors and nurses
accommodation(
• Luminous flux
The quantity of visible light radiation emitted by a light source per second and
its unit is "Lumen or Lm".
• Lumen
It is the unit of luminous flux and it is defined as the luminous flux per unit
solid angle from a source of candle power. Lumen = candle power*solid angel.
• Illumination (Lux)
Is the quantity of luminous flux falling vertically on a surface & is measured by
Lumen\m2 or Lux and is represented by symbol "E".
• Lux
It is defined as the illumination of the inside of the sphere of radius 1m at the
center of which there is a source of 1 candle power.
86 | P a g e
• Luminous (lamp) efficacy
Is the ratio between the quantity of luminous flux emitted from the lamp and
the power consumed in the lamp and its unit is Lumen\Watt.
• Ballast
Is a device used with the gas discharge lamp to fix the lamp current during
discharge to provide the necessary starting and operating electric conditions.
• Mounting height
Is the vertical distance between fixture surface and the work plane.
• Maintenance factor
Is the ratio between the illumination of lamps under normal conditions in the
presence of dust, dirty accumulation and the illumination when everything is
clean as it depends on the degree of cleaning (equals to 0.8 at normal
condition)
87 | P a g e
• Color rendering index (CRI)
measurement of the degree to which the appearance of a surface color under a
given light source.
There different types of luminaries that can be used in indoor and outdoor in
lighting design.
1. Recessed
shape
2. Surface mounted
88 | P a g e
4.3.2- Housing types
1- Type of ceiling.
2- Lamp type.
3- IP (index protection).
4- Housing type.
7- Mirror type.
4.3.3-Types of lamps
1. Incandescent Lamps
89 | P a g e
➢ Advantages
• They have a low initial cost.
• They offer an excellent color rendition.
• This type of lighting can easily be dimmed.
• They have a much cheaper initial cost.
• The light up instantly when turned on.
➢ Disadvantages
• Short average operating Life (750-2500 hours).
• Low efficiency compared to other lighting options (10-17 lumens per
watt).
• Create high temperature.
• Higher energy costs.
Fluorescent lamps use about 25% of the energy used by incandescent lamp to
provide the same amount of illumination (efficacy of 30–110 lumens per
watt).
90 | P a g e
➢ Advantages
• It with the lower energy costs.
• Give off a lot less heat than other types of lights.
• They have a much longer life span than many other bulbs.
• High Efficiency.
➢ Disadvantages
• They can be a health and safety risk.
• Fluorescent lamps are a non-linear load and generate harmonic
currents in the electrical power supply.
• Simple inductive fluorescent lamp ballasts have a power factor of less
than unity.
• The disposal of phosphor and particularly the toxic mercury in the tubes
is an environmental issue.
91 | P a g e
• They last up to 10 times longer.
2. Tube Fluorescent
➢ Advantages
• Long Life and low light depreciation.
• Very high efficiency hence highly energy efficient.
• Very short run-up time and quick re-strike.
• Very High Lumen Output.
• Ideally suited for fog, dust and rainfall conditions.
• An economic alternative to high pressure mercury vapor and metal
halide lamps.
• Most HPS lamps can operate in any position.
92 | P a g e
➢ Disadvantages
• The light produced is a golden white color, which may not be
appropriate for certain applications.
• Once started can take from five to ten minutes to reach full light output.
• End of life is characterized by on-off-on cycling.
• Once started can take from five to ten minutes to reach full light output.
• They also require at least a one minute cool-down to re-strike.
• Continued operation can damage the lamp ballast if not replaced
quickly.
➢ Advantages
• Most energy efficient light source Commercially available, with an
efficacy of 100 to 185 lumens per watt.
• Most lamps will restart immediately after interruption of power supply
but require some time to come up to full brightness.
• Provides superior uniformity of light distribution over all HID lamps.
• Have excellent lumen maintenance.
93 | P a g e
➢ Disadvantages
• Most expensive lamp to install.
• Run time to full light output is the longest (7 to 15 minutes).
• Requires special disposal considerations.
• These lamps have poor color rendering characteristics
➢ Advantages
• 3-5 times more efficient and produce a
much higher quality light compared to
incandescent bulbs.
• Metal Halide lights have a very high colour
temperature (up to 5500 K) in many cases
depending on the particular mix of metal
halides.
• For high-intensity applications and industrial lighting, Metal Halide
lights can be very useful.
➢ Disadvantages
• Horizontal operation may severely reduce lamp life.
• Some lamp types require 2 to 5 minutes to warm-up before giving full
• light output and 10 minutes to cool-down.
94 | P a g e
6. Mercury Vapor Lamp
The mercury vapor lamp produces light when the electrical current passes
through a small amount of mercury vapor. The lamp consists of two glass
envelopes: an inner envelope in which
the arc is struck, and an outer
protective envelope. The mercury
vapor lamp, like the fluorescent lamp,
requires a ballast designed for its
specific use.
➢ Advantages
• Three times as efficient as incandescent.
• Available in a wide variety of ratings, colors, sizes and shapes.
• Relatively low unit cost
• High average rated life (about 24,000 hours when operated on a 10
hour cycle).
o This is 24 times longer life than incandescent.
➢ Disadvantages
• Poor lumen maintenance compared to other HID sources.
• Mercury lamp ballasts are noisy.
• Special dimming ballast is required to dim mercury lamps.
95 | P a g e
• Require a maximum warm-up period of five to seven minutes before
giving full light output
• they are the most inefficient source of light
➢ LED SYSTEM
96 | P a g e
➢ Advantages
• Very High average lifetime can reach 15k hr
• Efficacy can reach 95%
• Color rendering index can reach 95%
• Variety of color temp
• Dimmable
• High power factor (electronic ballast)
➢ Disadvantages: High price.
97 | P a g e
CHAPTER (5)
SOCKETS
5.1 Introduction
• Sockets are the electrical outlets, which supply the electrical equipment&
instruments by its needed power (current & voltage) Distribution of different
typesof sockets in a building depend mainly on the type and use of that building.
• The position and height of the sockets in all electrical installations should not be
selected in a random way.
• The wiring of many houses is spoilt by placing socket outlets indiscriminately
regard to the position of the character of the apparatus to be connected to them.
1. Normal Sockets
2. Power Sockets
3. Waterproof Sockets
4. U.P.S Sockets
5. Three phase sockets
99 | P a g e
• Ups feeds inverter which converts DC current to AC
current &feeds socket
1. Wall Mounted:
2. furniture Mounting
100 | P a g e
3. Floor Mounted
a. For under floor trucking system is required enables a quick and neat
installation of all the new buildings as well as for
the refitting of modern facilities, airports and
office areas, and cables and equipment for power,
communications, and data processing, yet
permitting the clean combination of several
different cable layouts within the same trucking.
b. Must have IP very high (IP:67).
Explosion proof
101 | P a g e
CHAPTER (6)
CABLES
Cables are used to carry energy reliably between source and utilization, in
carrying this energy, there are heat losses generated in the cable that must be
dissipated equipment, the ability to dissipate these losses depends on how the
cables have been installed.
• Single core
102 | P a g e
• Double core
• Triple core
• Multi core
103 | P a g e
Aluminum Copper
C.S. A Larger Smaller
• Insulation
- The insulation provided on each conductor of a cable by mainly PVC (Poly Vinyl
Chloride), XLPE (Crosslinked Polyethylene), RUBBER (Various Types of Rubber).
- The insulating material is based on operating temperature.
XLPE 90oC
RUBBER – EPR IE-2, EPR IE-3, EPR IE-4, SILICON IE-5 150oC
• Inner Sheath
- it is used in multi-core cables.
104 | P a g e
- It works as a binder for insulated conductors together in multi-core power
cables and provides bedding to armor/braid.
- This portion of the cable is mainly made of PVC( PVC ST-1, PVC ST-2 ),
RUBBER (CSP SE-3, CSP SE-4, and PCP SE-3, PCP SE-4, HOFR SE-3 HOFR SE-
4, HD HOFR SE-3 ).
• Bedding
• Armoring.
a. Protect the cable from mechanical stresses while laying or bending.
b. Providing an earthing shield to the current-carrying conductors as well as it
is also used for earthing purposes of the cable for safety.
105 | P a g e
• Outer Sheath
This is the outermost cover of the cable normally made of PVC (Poly Vinyl
Chloride), RUBBER (Various Types of Rubber), Low Smoke Halogen Free (LSHF).
- Often the same material as the bedding.
- It is provided over the armor for overall mechanical, weather, chemical, and
electrical protection.
- The outer sheath is the protection offered to the cable not much electrically but
more mechanically.
106 | P a g e
CHAPTER (7)
TRANSFORMER
7.1 INTRODUCTION
107 | P a g e
108 | P a g e
1 Oil filter valve 11 Grounding terminal
1) CORE TYPE
The core-type transformer encloses the core i.e. the primary and secondary
windings were wound on a separate lamps and around a closed iron ring so
that the windings are well visible, but they hide the core limbs, Only the upper
109 | P a g e
and lower yoke of the core are visible, cylindrical coils, easy maintenance, It is
Preferred for low voltage transformers and it has single magnetic circuit.
2) SHELL TYPE
The core of the shell-type transformer is made of laminated silicon steel
sheets placed on top of one another. The coils are wound around the central
section of the core; the core of a shell type encloses the windings and the core
hides the major part of the windings, sandwich coils, hard maintenance, It is
preferred for high voltage transformer, flux is divided into two different path
so core loss or iron loss is less in shell type transformer than core type
transformer and it has double magnetic circuit.
➢ Types of transformers
1. Step-up transformers
110 | P a g e
A "step-up transformer" allows a device that requires a high voltage power
supply to operate from a lower voltage source. The transformer takes in the
low voltage at a high current and puts out the high voltage at a low current.
2. Step-down transformers
3. Isolation transformers
112 | P a g e
3) Measuring
transformers
• voltage transformer
• current transformer
• Autotransformer- Tapped autotransformer
113 | P a g e
7.4 Types of Distribution transformers: -
There are two types of the distribution transformers
114 | P a g e
13- Air Dryer including Silica Gel
14- Wheel
➢ Construction
1) Core
2) L.V terminal
3) Resilient spacer
4) H.V terminal
7) Tapping link
9) Earthing
115 | P a g e
10) Yoke clamping and wheelbase
11) Roller
116 | P a g e
➢ The main difference between the two types are summarized in the
below table.
Low cost compared with dry type High cost compared with oil type
The coupling between the coils isn't perfect. So whole of magnetic flux
produced by primary coil does not get linked with the secondary. However in
a shell type transformer these losses are less. In shell type transformer the
primary and secondary are wound over each other
117 | P a g e
7.5.2 Eddy currents
Ferromagnetic materials are also good conductors, and a solid core made
from such a material also constitutes a single short-circuited turn throughout
its entire length. Eddy currents therefore circulate within the core in a plane
normal to the flux, and are responsible for resistive heating of the core
material. The eddy current loss is a complex function of the square of supply
frequency and Inverse Square of the material thickness
The alternating current in the coils repeatedly takes the iron core through
complete cycle of magnetization. So energy is lost due to hysteresis
The alternating current in the transformer may set its parts into vibrations
and sound may be produced. This sound produced is called humming. Thus a
part of energy is lost in the form of sound energy due to the alternating
magnetic field causes fluctuating forces between the primary and secondary
windings
118 | P a g e
7.5.6 Stray losses
119 | P a g e
CHAPTER (8)
L.V SWITCHGEAR
Switchgear is a broad term that describes a wide variety of switching devices
that all fulfill a common need: controlling, protecting, and isolating power
systems.
Examples:
➢ Rated voltages
• Rated operational voltage Ue:
The rated operational voltage Ue of a circuit of an assembly is the value of
voltage which, combined with the rated current of this circuit, determines its
application.
120 | P a g e
• Rated impulse withstands voltage Uimp (of a circuit of an
assembly)
The peak value of an impulse voltage of prescribed form and polarity which
the circuit of an assembly is capable of withstanding without failure under
specified conditions of test and to which the values of the clearances are
referred.
➢ Rated currents
• Rated current In
The rated current of a circuit of an assembly is stated by the manufacturer,
taking into consideration the ratings of the components of the electrical
equipment within the assembly, their disposition and application.
121 | P a g e
normally given in kA rms.
• Rated frequency
The rated frequency of an assembly is the value of the designed frequency and
to which the operating conditions are referred.
- Europe: 50 Hz
- America: 60 Hz
• Category
122 | P a g e
8.2 types of LV circuit breakers
123 | P a g e
• during short circuit condition, the current rises suddenly, causing
electromechanical displacement of plunger associated with a tripping coil or
solenoid. The plunger strikes the trip lever causing immediate release of latch
mechanism consequently open the circuit breaker contacts.
MCCB commonly used when load currents exceed the capabilities of miniature
circuit breakers. They are also used in applications of any current rating that
require adjustable trip settings, which are not available in plug-in circuit
breakers and MCBs.
124 | P a g e
induces a magnetic field in a solenoid coil located inside the breaker – this
magnetic induction trips a contact and current is interrupted. As a complement
to the magnetic protection mechanism, MCCBs have internal arc dissipation
measures to facilitate interruption.
The current keeps on flowing when the circuit is open so there is a need to
extinguish the electrical arc to prevent it from reformation. Different dielectric
materials like oil or gases are used and for Air circuit breakers, atmospheric
air as a dielectric is used.
125 | P a g e
The air act as a resistance to the arc. Air acts as an insulator and forces arc to
extinguish faster. It also prevents the arc to reform when it reaches zero, in
case of alternating current, during its change in cycle. For high voltage
applications like electrical substations, pressurized air is used so that circuit
breakers can be used in those high voltage applications. In high voltage
applications, pressurized air as a dielectric is used as it has a higher value of
dielectric constant than atmospheric air.
8.2.4 Selectivity (Discrimination) between circuit breakers:
Discrimination of protection devices is essential in a LV installation and must
be considered as from the design stage. In industrial process management,
discrimination is essential to guarantee continuity of supply. Discrimination
(selectivity) is achieved by automatic protective devices if a fault condition,
Occurring at any point in the installation, is cleared by the protective device
located immediately upstream of the fault, while all other protective devices
remain unaffected.
126 | P a g e
trip-current setting of circuit-breaker A. For this maximum condition, both A
and B will trip.
No-discrimination when A opens before B (or A and B simultaneously).
127 | P a g e
B) Discrimination based on stepped time delays
This method is implemented by adjusting the
time-delayed tripping units, such that
downstream relays have the shortest
operating times, with progressively longer
delays towards the source. In the two-level
arrangement shown, upstream circuit breaker
A is delayed sufficiently to ensure total discrimination with B
128 | P a g e
Discrimination is total if Isc B < Ii A(instantaneous).
When closing a switch to energize a circuit there is always the possibility that
an unsuspected short-circuit exists on the circuit. For this reason,
load-break switches are assigned a fault-current making rating, i.e. successful
closure against the electrodynamic forces of short-circuits current is assured.
Such switches are commonly referred to as “fault-make load-break” switches.
Upstream protective devices are relied upon to clear the short-circuit fault
129 | P a g e
make or to break current and no rated values for these functions are given in
standards. It must, however, be capable of withstanding the passage of short-
circuit currents and is assigned a rated short time withstand capability,
generally for 1 second.
8.5 Contactor
The contactor is a solenoid-operated switching device
which is generally held closed by (a reduced) current
through the closing solenoid. Contactors are designed to
carry out numerous close/open cycles and are commonly controlled remotely
by on-off pushbuttons.
8.6 Fuses
Fuses break a circuit by controlled melting of the fuse element
when a current exceeds a given value for a corresponding
period of time; the current/time relationship being presented
in the form of a performance curve for each type of fuse.
130 | P a g e
CHAPTER (9)
GENERATOR
9.1-Purpose
131 | P a g e
9.2 The Main Parts of Diesel Generator
1) Prime Power:
The maximum power available for a varying electrical load for unlimited
hours. A 10% overload is available for 1 hour in 12.
Restrictions are often placed upon the average value of the varying load,
typically 70% of the prime power and also on the overload operation
which typically is for a maximum of 25 hours per year.
Where the load is not variable such as exporting to the Grid then the
Prime Power definition is not used and Continuous Operation Power
132 | P a g e
(COP) is used. If the number of hours at a non variable load are limited
and not as high as COP then sometimes the rating of Limited Time
Running (LTP) is used in place of COP.
2) Standby Power:
The maximum power available with a varying load for the duration of the
interruption of the normal source power. No overload is available with a
Standby rating.
Restrictions are generally placed upon the average load, typically 70% of
the Standby Ratings and hours limitations are imposed of usually 500
hours per year but sometimes 200 hours per year.
133 | P a g e
CHAPTER (10)
UPS
10.1 introduction
The purpose of a UPS is to provide emergency power (usually by a
lead/acid battery) to a load when it senses that the input power source
has failed. They are different from emergency power systems or standby
generators because they provide near-instantaneous protection from
power interruption by using a battery (which can be a super capacitor or
flywheel).
• The battery itself usually has a short runtime (about 5-20 minutes),
but it should be enough to either save all that precious
data/progress that you have made, gracefully shut everything down,
or fix the problem that caused the outage.
• A UPS can be used to protect hardware like data centers, computers,
and other electrical equipment where an unexpected surge/sag can
cause serious problems like data loss, business disruption, and even
injuries or fatalities.
The offline/standby UPS is the most basic out of the three. It provides
light surge protection and battery back-up. During normal operations, it
gets its power from its main power source (generally an AC outlet). Once
it senses that the main power source goes beyond acceptable limits or
fails, it switches to the “offline/standby” battery where it will then go to
134 | P a g e
the DC/AC inverter – as such, there will be a small transfer time between
the main power source and battery.
135 | P a g e
3. Line-Interactive Uninterruptible Power Supply
136 | P a g e
➢ Types of Uninterruptible Power Supplies according to
Design
137 | P a g e
➢ Modular ups has some advantages over conventional ups
1. Add redundancy
The surest way to increase availability of power is to add redundancy to
the UPS system and to minimize its maintenance and repair time.
2. Minimize downtime
Because the UPS modules in a DPA are independent, they can be online
swapped without risk to the critical load and without the need to power
down or transfer to raw mains supply. So engineers can work on the UPS
without interrupting operations. Swap-out time is only 15–20 minutes
and is very safe and you never have to switch off your load.
138 | P a g e
CHAPTER 11
ATS
11.1 Introduction
Since the ATS is connected to both primary and backup power sources, it
serves as an intermediary between equipment and the power supplies, acting
as an electrical relay. An ATS can also act as a redundant, rack-mounted power
supply for equipment that is connected to a power source only one cord.
139 | P a g e
go out in a house for a short period of time. While inconvenient in a home, a
similar power loss in a business setting can be costly, as data can become
corrupt or be lost entirely during the interruption.
140 | P a g e
system unknowingly to us causing a power outage days/weeks
later.
142 | P a g e
Generator
a- Normal loads: such as lighting and outlets. Such loads are fed from only
one source (the main), hence if the main is off, these loads will be off.
b- Emergency loads: such as emergency lighting and lifts. These loads are
normally fed from the main source and in case of main power failure; the
emergency generator will feed such loads as a backup source through the ATS
system till the main source is on again.
143 | P a g e
c- Important loads: such as hospital operation and intensive care rooms.
These loads could be fed from three different backup sources, the main
source, the emergency generator, and the uninterrupted power supply (UPS).
In case of fault in the main source and the emergency generator, these
important loads can be fed from the UPS through the transfer switch (TS).
Such important loads are off-line fed from the UPS through the TS, hence
should accept the small shut down period due to the transition of the TS. This
transfer switch (TS) may also be automatic, and in this case static switches are
recommended for their fast-switching response
It should be noted that all loads are categorized according to the customer
requires and load priorities, hence determining equipment sizes and the
overall cost. Transformer size is determined by the sum of all loads while
generator size is chosen depending on the sum of emergency, important and
critical loads. The UPS capacity should cover both important and critical loads.
145 | P a g e
c- Synchronization: In case of the utilization of more than one backup
sources, such as two emergency generators or the main itself consists of main
transformer and main generator, synchronization conditions (same voltage,
frequency, phase sequence and phase shift) should be considered before
transferring the power through the ATS.
The basic function of the proposed ATS is to transfer the loads to the
generator in case of main failure then back to the main in healthy condition.
The sequence of operation can be summarized as:
1) In case of main source failure detection, disconnect the loads from the
main.
3) If the generator output voltage is stable and reach the required value,
4) If the main is back and stable, disconnect the loads from the generator
146 | P a g e
CHAPTER (12)
EARTHING SYSTEM
12.1 introduction
The earthing system is the total set of measures used to connect an electrically
conductive part to earth. The earthing system is an essential part of power
networks at both high- and low-voltage levels.
1) Ground conductor.
2) Connection between the ground conductor
and the ground electrode.
3) Ground electrode.
First, the NEC code (1987, 250-83-3) requires a minimum ground electrode
length of 2.5 meters (8.0 feet) to be in contact with soil.
147 | P a g e
But, there are three variables that affect the ground resistance of a ground
system:
148 | P a g e
Soil resistivity:
149 | P a g e
12.4 Earthing system classifications:
• TT system.
• TN-S system.
• TN-C-S system
• TN-C system
• IT system
1- TT systems:
150 | P a g e
2- TN-S system:
This is probably the most usual earthing system in the world, with the
Electricity Supply Company providing an earth terminal at the
incoming mains position. This earth terminal is connected by the supply
protective conductor (PE) back to the star point (neutral) of the
secondary winding of the supply transformer, which is also connected at
that point to an earth electrode. The earth conductor usually takes the
form of the armor and sheath (if applicable) of the underground supply
cable.
TN-S system
151 | P a g e
3- TN-C-S system
In this system, the installation is TN-S, with separate neutral and protective
Conductors. The supply, however, uses a common conductor for both the
neutral and the earth .This combined and neutral system is sometimes called
the 'protective and neutral conductor' (PEN) the “combined neutral and
earth” conductor (CNE). The system, which is shown In Fig is most usually
protective multiple earth (PME) system.
4- TN-C system:
152 | P a g e
TN-C system
system
5- IT system:
The installation arrangements in the IT systems are the same for those of the
TT system. However, the supply earthing is totally different. The IT system
can have an unearthed supply, or one which is not solidly earthed but is
connected to earth through a current limiting impedance. IT system is
shown in Fig:
IT system
system
153 | P a g e