1
IN THE HIGH COURT OF SOUTH AFRICA,
FREE STATE DIVISION, BLOEMFONTEIN
Case number: 2288/2022
Reportable: YES/NO
Of Interest to other Judges: YES/NO
Circulate to Magistrates: YES/NO
In the matter between:
RAUBEX/NODOLI CONSTRUCTION JOINT VENTURE Applicant
and
THE MEMBER OF THE EXECUTIVE COUNCIL:
FREE STATE DEPARTEMENT OF POLICE, ROADS
AND TRANSPORT, FREE STATE PROVINCIAL
GOVERNMENT N.O. Respondent
JUDGMENT BY: C REINDERS, J
HEARD ON: 6 OCTOBER 2022
DELIVERED ON: 20 FEBRUARY 2023
[1] On 10 May 2019 the applicant and the respondent entered into a written
contract (essentially based on the New Engineering Contract 3, April 2013- “the
NEC3”) for maintenance of the public road between Sasolburg and Heilbron in the
Free State Province. A dispute arose between the parties culminating in an
2
adjudicator hearing the dispute and handing down his decision (the adjudication
decision/award) on 7 April 2022.
[2] The applicant moves for relief that effect be given to the adjudication award in
the following terms:
“1. The respondent is forthwith to give effect to the adjudication award handed
down on 7 April 2022, a copy of which is annexed hereto to the founding affidavit
marked “C9”;
1.1 Pursuant to the above-mentioned adjudication award, the respondent is
ordered to pay the applicant:
1.1.1 R14 280 737.40 plus VAT less R8 222 621.10, in other words
R8 200 229.91;
1.1.2 Interest on the amount of R14 280 737.40 plus VAT at the rate of 7%
per annum from 26 October 2021 to 31 March 2022; and
1.1.3 Interest on the balance of the amount due of R8 200 229.91 (inclusive
of VAT) at 7% per annum from 1 April 2022 to the date of payment.
1.2 The respondent is ordered to pay the costs of this application on an
attorney and client scale.”
[3] The respondent opposes the relief claimed by the applicant, contending that the
applicant is not entitled to such relief until the arbitration proceedings are finalized
and “an arbitration award is issued in its favour.” In essence it is submitted that the
adjudication decision (including any payment) is suspended pending the dispute
being revised by the arbitrator in terms of the dispute resolution process agreed
upon by the parties. Applicant, so the argument goes, seeks court to give effect to
the decision of the adjudicator not being final and binding as there is no provision in
the NEC3 that the decision should be promptly given effect to or without undue
delay, whilst the arbitration process is still pending.
3
[4] A brief factual background to the application is mostly common cause (or not
seriously disputed) and can be summarized as follows:
4.1 The NEC3 incorporated in the contract is a standard contract used within the
construction industry in terms of which parties can select certain clauses to govern
their rights and obligations and regulate the completion of a specific project. The
contract also envisages the appointment by the employer (the respondent) of a
project manager, with the task to manage the contract on behalf of the employer.
Included in the contract (with the applicable portions annexed to the applicant’s
founding papers) is the dispute resolution (Option W.1) agreed upon by the
parties. Provision is also made in the contract for what is termed ‘compensation
events’ allowing the contractor to claim from the employer additional payment and
extra time to do the work.
4.2 It is not disputed that the applicant claimed for compensation relating to the
national lockdown (Covid-19) during the period March to May 2020, and that the
employer’s instruction on 25 March 2020 to cease work was a compensation
event entitling the applicant to an extension of time and compensation. The matter
was referred for adjudication after a dispute arose between the parties. The
parties duly filed their written submissions and the adjudicator handed down his
award on 7 April 2022.
4.3 Pursuant to the award a trial of correspondence ensued between the parties.
I do not deem it necessary to comprehensively deal with the precise content of
these electronic mails as the content thereof is not in dispute.
4.3.1 It suffices to say that the applicant claimed payment from the
respondent in the amount of R 8 708 861,64 on 13 April 2013. The respondent
(as represented by Mr M Monyane) on even date replied that it wished to
advise the applicant that “it is our instructions to approach the tribunal to
challenge the decision of the Adjudicator” and “…has four weeks to do so.” In a
further response Mr Monyane replied:
4
“Yes the decision of the adjudicator is binding and must thus be referred to
Tribunal if there is dissatisfaction.
By taking a decision to refer it to Tribunal suspend (sic) the payment until final
decision is arrived at.
For now, there is no willingness on our part to pay any amount except the one
already paid to your client.
We will wait for the Tribunal decision.”
4.3.2 The applicant’s attorneys of record responded by stating that referring
the decision to the tribunal does not suspend payment and pointed Mr
Monyane to Option W.1.3 (10) of the contract. On 5 May 2022 the respondent
addressed an email to the attorneys of the applicant and the adjudicator that it
“notify” the applicant and the adjudicator of its “…intention to refer the matter for
arbitration as it is not satisfied about the Ruling made on the 5th April 2022.”
4.4 The applicant hereafter launched this application to have the adjudicator’s
award enforced.
[5] The applicability of the dispute resolution provisions of the contract (NEC3) that
governs the relationship between the parties is not in dispute. The main bone of
contention between the parties relates to the aforementioned clause W1.3 (10) which
reads:
“The Adjudicator’s decision is binding on the Parties unless and until revised by
the tribunal and is enforceable as a matter of contractual obligation between the
Parties and not as an arbitral award. The Adjudicator’s decision is final and
binding if neither Party has notified the other within the times required by this
contract that he is dissatisfied with a decision of the Adjudicator and intends to
refer the matter to the tribunal.”
[6] The dispute between the parties is accordingly the question whether the
adjudication award which the applicant seeks to enforce, is binding in the event that
the award was referred for arbitration in terms of the aforementioned dispute
resolution provisions in view of W1.3(10). Counsel held different views and both in
5
their heads of argument and in submission before me, referred me to case law in
support of such views.
[7] Applicant placed reliance, amongst others, on the case of Tubular Holdings
(Pty) Ltd v DBT Technologies (Pty) Ltd1 where the court concluded that the notice
of dissatisfaction does not suspend the obligation to give effect to the decision. The
applicable clause in Tubular Holdings stated that the decision of the Dispute
Adjudication Board is binding on the parties and should be promptly given effect to,
whereas in Steffanuti Stocks (Pty) Ltd v S8 Property (Pty) Ltd2 the applicable
dispute resolution clause included the wording “without undue delay.”
[8] Counsel for respondent sought to distinguish the aforementioned case law by
submitting that reliance on such case law is misplaced as in casu clause W1 does
not contain any provision that that the adjudicator’s decision should be given effect to
“promptly” (or without unduly delay), but instead the clause provides that the decision
is enforceable as a contractual obligation. Relying on, inter alia, Britstown
Municipality v Beunderman (Pty) Ltd3and Blue Circle Projects (Pty) Ltd v
Klerksdorp Municipality 4 in respect of the finality of an arbitrator’s award, he
submitted that the decision of the adjudicator the matter at hand is not final and
binding whilst the arbitration process is still pending. I pause to mention that
Britstown pertains to an award made by an arbitrator, whilst Blue Circle Projects
dealt with the opinion of a mediator.
[9] Recently, the Supreme Court of Appeal comprehensively dealt with the legal
principles applicable to the status of an adjudicator’s award in Framatome v Eskom
Holdings SOC Ltd5 (‘Framatome’). The summary of the judgment reads:
“Construction contract – contract providing for dispute resolution process through
adjudication – adjudicator’s award final and binding on the parties until and unless
set aside on review – High Court erred in not enforcing the award.” In my view
Framatome put this issue to bed. I find it apposite however to quote liberally from
1 2013 JDR 2441 (GSJ)
2 2014 (1) SA 244 (GSJ)
3 1967 (3) SA 154 (C)
4 1990 (1) SA 469 (T)
5 (357/2021) [2021] ZASCA 132 (1 October 2021)
6
the applicable paragraphs of the unanimous judgment penned by Mathopo JA on
behalf of the full bench. All emphases are that of myself.
9.1 The appeal in Framatome emanated from the Gauteng South Division and
concerned a dispute that arose between the parties in relation to whether the
project manager’s notification (and assessment) amounted to a compensation
event. The trial court had declined an order to enforce the award by the
adjudicator. Although the applicable edition of the NEC3 was that with
amendments of June 2006, the principles in terms of the dispute resolution
process (and more specifically clause W1.3 (10)) are identical to that of the
application that serves before me for adjudication.
9.2 Having set out the background to the appeal, Mathopo JA addressed in
paragraph [20] the issue whether the high court correctly declined the order of
enforcement and referred to the judgment of Radon Projects (Pty) Ltd v NV
Properties (Pty) Ltd & Another,6 where the process of adjudication (and its
purpose) was comprehensively dealt with and described.
9.3 Clause W.1.3 (10) was quoted and the court concluded by holding “…It is
clear that only the arbitration is the appropriate forum. In argument before us,
Eskom conceded that the dispute has been referred to arbitration.”7
9.4 The arguments tendered by counsel for the respondents, were found to be
without merit. Mathopo JA held:
“[23] If the interpretation contended for by Eskom is correct, it will
substantially undermine the effectiveness of the scheme of adjudication. It is
plain that the purpose of adjudication was to introduce a speedy mechanism
for settling disputes in construction contracts on a provisional interim basis
and requiring the decisions of adjudicators to be enforced pending the final
determination of disputes by arbitration. As far as the procedure is concerned,
adjudicators are given a fairly free hand. They are required to act impartially
6 [2013] ZASCA 83; [2013] 3 All SA 615 (SCA); 2013 (6) SA 345 (SCA) (31 May 2013) para 3-5.
7 At paragraph [22].
7
and permitted to take the initiative in ascertaining the facts and the law. Sight
should not be lost of the fact that adjudication is merely an intervening,
provisional stage in the dispute resolution process. Parties still have a right of
recourse to litigation and arbitration. Only a tribunal may revise an
adjudicator’s decision. As that decision has not been revised, it remains
binding and enforceable…”
9.5 The court dealt with the submission by Eskom that the adjudicator exceeded
his jurisdiction and the proper procedure had not been followed, and found that
even this aspect did not entitle Eskom not to comply with the adjudicator’s award:
… The adjudicator formulated the dispute with the understanding and appreciation
of what the parties contemplated. It is trite that if upon an application for
enforcement of an adjudication decision, it is found that the adjudicator did not
have the requisite jurisdiction, his decision will not be binding or enforceable’.8
Mathope JA proceeded to state: “A determination of whether or not Framatome’s
quotation was valid under the Contract and whether the process for the deemed
acceptance of that quotation requires an analysis of the facts. This is an issue
which the arbitrator will deal with in due course. That said, it is clear that the
decision of the adjudicator is binding and enforceable. 9 At paragraph [29] it was
held that …’In the final analysis, the question to be asked is whether the
adjudicator’s determination is binding on the parties. The answer to that question
turns on whether the adjudicator confined himself to a determination of the issues
that were put before him by the parties. If he did so, then the parties are bound by
his determination, notwithstanding that he may have fallen into an error.10
The respondent did not attack the granting of the relief claimed by applicant on the
basis that the adjudicator did not confine himself to a determination of the issues
put before him. It can thus be accepted that the adjudicator indeed confined
himself to such issues before him and the parties are consequently bound by his
determination. Whether the adjudicator was correct in his findings is for the
arbitrator to decide.
8 At paragraph [25]
9 At paragraph [26]
10 The court referred to Carillion Construction Limited v Devonport Royal Dockyard Ltd [2005] EWHC
778 (TCC) at paragraph 63.
8
[10] Counsel for respondent pressed on me to exercise my discretion in declining to
enforce the adjudicator’s award in view of the fact that arbitration proceedings were
pending and, as conveyed from the bar, submissions by the parties had already
been furnished to the arbitrator. In Framatone arbitration proceedings in respect of
the adjudicator’s decision was, like in this instance, already instituted and pending.
Despite this aspect being dealt with thoroughly as indicated in the above mentioned
paragraphs of the judgment, the court did not apply any discretion leading to a
dismissal of the appeal. In fact, Mathopo JA concluded: … ‘To my mind, no justifiable
reason exists for not fully giving effect to the adjudicator’s award. Refusing to comply
with the payment award of the adjudicator is disingenuous.’
The appeal was upheld, the order of the trial court was set aside and replaced with
the order as prayed for by the appellant (as applicant) in the trial court.
[11] Applying the facts of this application to the principles enunciated by and
findings of the Supreme Court of Appeal in Framatome, I am satisfied that the
applicant has made out a proper case for the relief claimed. Despite the able
arguments proffered by counsel for the respondent to convince me that the
application should be dismissed in view thereof that the award of the adjudicator is
not final (due to it being subject to review by the arbitrator) and the application is
accordingly premature, I have not been so convinced. Counsel for applicant
submitted that a proper case for the relief claimed was made out. I agree with her.
The respondent made payment of only R 8 222 621.10. The notice of motion
embodies the precise wording of the adjudicator’s award which includes a calculation
of this amount being subtracted from the amount of R 14 280 737.40 (plus VAT), as
well as interest as set out in paragraphs 11.2 and 11.3 of the award. I was not called
upon to review the adjudicator’s award and thus refrain from any comments in
respect of the wording of the order and the paragraphs relating to interest. It seemed
that the respondent did indeed make certain payments, but the amount so
mentioned is different from that which is indicated to be subtracted in the arbitration
award that I am being requested to enforce. In my view it would be up to the parties
to calculate the correct amounts due to the applicant in terms of the award.
9
[12] There is no reason why costs should not follow the event. Although counsel for
applicant pressed on me to award costs on a scale as between attorney and client.
In my view the respondent, as an organ of state holding the purse of the public, was
at liberty to defend its view on the issues raised.
[13] Accordingly I make the following order:
13.1 The respondent is forthwith to give effect to the adjudication award of Adv. A
Gautschi SC dated 5 April 2022 and handed down on 7 April 2022 as annexed to
the applicant’s founding affidavit and marked “CS9”.
13.2 Pursuant to the adjudication award, the respondent is ordered to pay the
applicant:
13.2.1 R14 280 737.40 plus VAT less R8 222 621.10, in other words
R8 200 229.91;
13.2.2 Interest on the amount of R14 280 737.40 plus VAT at the rate of 7%
per annum from 26 October 2021 to 31 March 2022; and
13.2.3 Interest on the balance of the amount due of R8 200 229.91 (inclusive
of VAT) at 7% per annum from 1 April 2022 to the date of payment.
13.3 The respondent is ordered to pay the costs of this application.
C REINDERS, J
On behalf of applicant: Ms J Harwood
Instructed by: Hewlett Bunn Inc.
c/o Lovius Block Attorneys
BLOEMFONTEIN
10
On behalf of respondent: Adv BS Mene SC
Instructed by: State Attorneys
BLOEMFONTEIN