The inspection report for the Uluberia Plant dated 07.03.2025 details the evaluation of a 3.5 X 1500 mm coil, noting that approximately 50% of the coil is acceptable due to edge waviness issues. Several compliance deficiencies were identified, including missing rolling conditions and test methods as per EN 10025-2:2019. The report concludes with a total accepted tonnage of 25 MT from an initial 32.19 MT, with 7 MT requiring rectification.

Uploaded by

devesh.chauhan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
36 views5 pages

TSL Coil Inspection Report

The inspection report for the Uluberia Plant dated 07.03.2025 details the evaluation of a 3.5 X 1500 mm coil, noting that approximately 50% of the coil is acceptable due to edge waviness issues. Several compliance deficiencies were identified, including missing rolling conditions and test methods as per EN 10025-2:2019. The report concludes with a total accepted tonnage of 25 MT from an initial 32.19 MT, with 7 MT requiring rectification.

Uploaded by

devesh.chauhan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 5

ULUBERIA PLANT INSPECTION REPORT

□ HM1 □ HM2 □ HM3 □ GP1 □ GP4 □ TM □ TM □ FACTORY □ EXTERNAL □ STAGE □ FINAL


REPORT DATE PO NO-NA JOB NO- NA
07.03.2025
SUPPLIER □ INHOUSE □ DRG NO- NA QTY-32.19 MT
Dated-NA
ITEM- INSPECTION SCHEDULE DATES
I II III IV V
3.5 X 1500 mm COIL(Cast-A288259, Batch ID-K512850731)
REPORTING SEQUENCE 1. MATERIAL AVAILABLITY □ 5. RECTIFICATIONS □ 9. REINSPECTION □
AS PER APPLICABLE 2. PROGRESS □ 6. WORKMANSHIP □ 10. GALVANIZING □
3. DIMENSIONS □ 7. TESTING AND CERTIFICATES □ 11. ACCEPTANCE □
4. CLARIFICATION AND DEVIATIONS □ 8. FINISHING /PAINTING/MARKING □ 12. OTHER DETAIL □

Visual and Dimensional Inspection


Reference:
EN 10025-2: 2019 S355 JR
TC No: TATA/24/02/2025/S355JR/01 Dated 24 Feb 2025

3.5 X 1500 mm COIL (Cast-A288259, Batch-K512850731), Coil is Leveled after DE coiling and shearing of coil done
for 9150 mm length.

1. From Starting of DE-coiling, Approx. 25 Ton Coil, edge waviness observed up to 5 mm. Hence after leveling it is
found within limits, hence Acceptable.

Approx. 7 Ton of Coil, DE coiled hence after, edge waviness observed 10-24 mm and after leveling found 6 to 18 mm.
Hence we can utilize only max 50 percent of total coil weight and rest will be treated as Scrap and not usable.

2. Rolling condition missing as per Clause 3 of EN 10025-2:2019


3. Deoxidation methods as per Clause 6.2 Missing
4. CE value missing as per Clause 7.2.3
5. Sample orientation for tensile, bend, impact missing in TC
6. Test methods as per clause Clause 10.1 missing in TC
7. Percentage elongation reference gauge length missing in TC.

INSPECTION DATE TONNAGE/QTY AS PER TONNAGE/QTY TONNAGE/QTY TO BE TONNAGE/QTY REJECTED


07.03.2025 PO / JOB NO- ACCEPTED- 25 MT RECTIFIED-7 MT
32.19 MT

SUPPLIER SIGNATURE & STAMP CUSTOMER/TPI NAME & INSPECTOR NAME & SIGNATURE
SIGNATURE

Doc no -SL/SOP/HMS/QCD/01/F-09 Issue Number-01 Issued on-01.04.2023


ULUBERIA PLANT INSPECTION REPORT

Reference Picture

Decoiling, Before Leveling

Doc no -SL/SOP/HMS/QCD/01/F-09 Issue Number-01 Issued on-01.04.2023


ULUBERIA PLANT INSPECTION REPORT

Doc no -SL/SOP/HMS/QCD/01/F-09 Issue Number-01 Issued on-01.04.2023


ULUBERIA PLANT INSPECTION REPORT

Reference Picture

After Leveling

Doc no -SL/SOP/HMS/QCD/01/F-09 Issue Number-01 Issued on-01.04.2023


ULUBERIA PLANT INSPECTION REPORT

---------------End Report------------

Doc no -SL/SOP/HMS/QCD/01/F-09 Issue Number-01 Issued on-01.04.2023

You might also like