SOW - Equipment Installation and Power Supply PC16 R1
SOW - Equipment Installation and Power Supply PC16 R1
CP: 37664
León, Gto. - México
This SOW, valid between 19-Sep-23 and the expiration of the warranty period agreed between the Parties, is entered into
by and between:
And:
Donaldson Entities:
(Hereinafter called “Donaldson” or “Buyer”)
The information contained within is considered confidential and the Supplier shall not disclose this SOW or its contents to
any other Party without written approval from the Buyer.
1. DEFINITIONS
Equipment The Equipment includes all goods and/or services to be delivered as per specifications set
forth in this SOW and it’s appendices.
Contract Administrator An individual employee of each Party designated by that Party as responsible for monitoring
the obligations and performance of this Agreement. A Party may change its designated
Contract Administrator by providing notice to the other Party. In the event of an extended
period of absence of Contract Administrators, the delegate of the Contract Administrator has
all the right to represent and take over responsibilities of the Contract Administrator.
For Donaldson
Contract Administrator: Christopher Reyes
Title: Manager Procurement
E-mail: [email protected]
Tel.: +52 449 910 6165
Delegate: [ ]
For Supplier
Contract Administrator: [ ]
E-mail: [ ]
Tel.: [ ]
Delegate: [ ]
Day(s) Working day(s) specified on the calendar of the ordering Donaldson Entity.
Order A purchase order issued by Donaldson to the Supplier, under which Donaldson sets forth
delivery requirements.
Party/Parties Shall mean an individual party, either Donaldson or Supplier, and Parties collectively refers to
both Donaldson and Supplier.
2. LIST OF APPENDIXES
1. Appendix A Project Scope.
2. Appendix B Documentation Included.
3. Appendix C Consigned Parts List.
4. Appendix D Project Management & Schedule.
5. Appendix E Integration.
6. Appendix F Acceptance Testing.
A.
Project Scope
3. Equipment Identification
Asset Number Asset Name
TBD Equipment installation & power supply Power Core 16
[ ] [ ]
[ ] [ ]
[ ] [ ]
[ ] [ ]
[ ] [ ]
[ ] [ ]
[ ] [ ]
4. Equipment Specifications
4.1. Project Type (check one)
4.1.1. ☐ BTP (Build to Print)
4.1.2. ☒ BTS (Build to Specification)
4.2. Notes
4.2.1. For designs released by Buyer, approved water marked prints will be provided with Order release for all
build-to-print Equipment. Equipment shall only be fabricated from drawings that have been watermarked
with Approved by the Buyer.
4.3. Project Scope Table
If applicable enter X
Scope Requirements Documentation
Supplier Buyer N/A
Design Mechanical See Appendix B
X
See Appendix J
Controls See Appendix K
X
Procurement Supply all materials required to build the Supplier to supply
Equipment. X documentation
Supply of Consigned Parts specifically
listed in this SOW.
X
Purchase all miscellaneous items
(lubrication, fasteners, hoses, fittings, and
other raw materials) required for the X
assemblies to function, whether or not listed
in the Bill of Materials (BOM).
Assembly Assemble all materials and components X See Appendix B
necessary to produce a fully functioning
4.4. Deliverables
The following items are required:
4.4.1. ☒ Schedule (if design is part of scope for the Supplier they must include design review milestone meetings
in the schedule)
4.4.2. ☐ Redline Changes
4.4.3. ☐ Commercial Literature
4.4.4. ☐ Design Approvals (Appendix K Design Approvals is the official record)
4.4.5. ☐ Design Package
4.4.6. ☐ PLC and HMI Programs
Donaldson Company, Inc. Confidential Page 5 of 30
Donaldson Latin America. SOW PC16 enclosure
This SOW considers per this document quotation of below described scope:
a) Relocate current busway.
b) Power supply for PC16 equipment (440 VAC, air & water supply).
c) Equipment placement, alignment, leveling and anchoring.
d) Equipment installation (mechanical assembly and equipment adjustment, and secondary wiring and piping
for PC16 equipment).
e) Miscellaneous modifications for PC16 equipment.
Supports and whole accessories of current busway should be relocated to mount and fix it on its new position.
Current cables must be used too, for the busway connection after it’s realocation, in that way must be considered to
change the cables trajectory according to the new busway position.
4.5.1.2 Before busway relocation, supplier must relocate existing connection of 3 equipment to a near existing busway.
Should consider busplugs relocation and primary electrical connection from busplug to each equipment. Consider
approximated distance from each equipment to busplugs, and current consumption according to below chart:
Supplier must consider inside of the scope, platform availability to make the height work.
4.5.2 Power supply for PC16 equipment: It will be supplier’s responsibility to connect the primary power supply to
power core equipment (440 VAC, air and water) – separated lay out will be shared to confirm in detail the
connection points.
4.5.2.1 In case of electrical power supply must be considered 440 VAC. The busplugs and fuses will be delivered
to supplier; but must consider the busplugs and fuses connection in current busways, primary wiring should
be provided, considering conduit pipes, supports for pipes and finally the cables connection in every
equipment. Phase sequence must be confirmed before powering up each equipment.
Below is shown only as reference, lay out for the equipment connection. It will be supplier’s responsibility
to consider the wire gauge according to the full load amperage and busplugs capacity shown in below charts.
BUSWAY 1 BUSWAY 7
FLA BUS PLUG DISTANCE FLA BUS PLUG DISTANCE
EQUIPMENT EQUIPMENT
(A) (A) (m) (A) (A) (m)
UPENDER LH 5.0 30 11 GASKET CHILLER 9.0 30 31
UPENDER RH 5.0 30 19 END CAP 1 MEDIA CONDITION 60.0 100 9
UNWIND 20.0 30 15 END CAP 1 MOLD CONDITION 1 42.0 60 11
SINGLEFACER FLUTE DARTER 117.0 200 16 END CAP 2 MOLD CONDITION 2 42.0 60 16
SF FOAM MIX TRANSFORMER 40.3 60 17 END CAP 2 GEL DIAL SYSTEM 2 40.0 60 11
SF SEALBEAD MELTER 40.3 60 17 END CAP 1 GEL DIAL SYSTEM 1 40.0 60 16
SF TACKBEAD MELTER 40.3 60 16 END CAP PUR DISPENSE 53.6 60 17
PREHEAT STATION SLOT DIE 5.0 30 17 END CAP CHILLER 9.0 30 16
MEDIA ACCUMULATOR 65.0 100 15 WRAPPER 12.0 30 37
CARTIDGE 53.0 100 16 GASKET PUR DISPENSER 53.6 60 27
LEFT STACKER 46.2 100 10 GASKET HEATER PANEL 1 94.0 200 29
RIGHT STACKER 46.2 100 18 GASKET HEATER PANEL 2 97.0 200 35
STACKER CHILLER 9.0 30 11 GASKET HEATER PANEL 3 81.0 200 38
STACKER PUR DISPENSER 53.6 60 10 CONVEYORS 2 10.4 30 7
STACKER CURE SYSTEM 86.0 200 10 CONVEYORS 3 20.8 30 7
GASKET SYSTEM 117.0 200 26 ENCLOSURE GASKET 10.0 30 31
CONVEYORS 1 14.3 30 16 A/C ENCLOSURE GASKET 60.0 100 31
CONVEYORS 4 21.7 30 38 TORIT 15.0 30 39
BUSWAY 8
FLA BUS PLUG DISTANCE
EQUIPMENT
(A) (A) (m)
SIDE PANEL 48.4 60 25
SP PUR DISPENSER & MELTER 39.0 60 22
SP POLYOLEFIN DISPENSER & MELTER 21.0 30 17
END CAP FINAL CURE 1 60.0 100 12
END CAP FINAL CURE 2 60.0 100 10
END CAP FINAL CURE 3 60.0 100 11
DEMOLD 53.0 60 9
ENCLOSURE STACKER & END CAP 10.0 30 22
A/C ENCLOSURE STACKER & END CAP 1 60.0 100 22
A/C ENCLOSURE STACKER & END CAP 2 60.0 100 22
A/C ENCLOSURE STACKER & END CAP 3 60.0 100 22
A/C ENCLOSURE STACKER & END CAP 4 60.0 100 22
Indicated distances on charts already include distance from connection point and height from floor to the
busway connection height. Below is shown layout that indicates how the busway is placed and installed
currently on the plant.
4.5.2.2 Due to enclosure installation for stacker and end cap equipment, supplier should consider to adjust the
height of 7th and 8th busways from 5.28m to 6m.
4.5.2.3 In case of pneumatic power supply, supplier must connect indicated equipment according to layout to
individual valves that already exist on current pneumatic installation. Below is shown layout of current
pipes configuration.
Just for reference is shown layout that indicates connection points to current
existing piping. According to chart, distance for piping should be considered.
Pipes type must be Airnet AW6060 T6, 3/4" diameter and blue painted. Supplier
will be responsible to get all connectors and required tools to pipe and connect
equipment to primary air power supply and should consider to install a 3/4" ball
valve in every connection point.
DISTANCE
EQUIPMENT
(m)
UNWIND 15
SINGLEFACER FLUTE DARTER 9
AIR CARTS 8
CARTIDGE 13
MEDIA ACCUMULATOR 1 13
MEDIA ACCUMULATOR 2 13
STACKER PUMPS 8
LEFT STACKER 10
RIGHT STACKER 13
STACKER PUR DISPENSER 10
STACKER CURE SYSTEM 13
SIDE PANEL 8
SIDE PANEL PUR DISPENSER 13
CONVEYOR 13
END CAP PUMPS 7
END CAP 1 GEL DIAL SYSTEM 1 19
END CAP PUR DISPENSE 8
END CAP 2 GEL DIAL SYSTEM 2 14
DEMOLD 20
GASKET SYSTEM 10
GASKET PUR DISPENSER 11
GASKET PUMPS 9
EXTRA 1 10
EXTRA 2 10
EXTRA 3 10
EXTRA 4 10
EXTRA 5 10
EXTRA 6 10
EXTRA 7 10
4.5.2.4 In case of water supply, supplier must connect indicated equipment according to layout to the water softener
installed on radial seal line. Below is shown layout only as reference and distance from water softener to
each equipment connection point (pipes height must be 6m above the floor level).
M type copper pipe must be considered for the equipment connection to the water softener.
REMARK: In order to be able to perform the whole height work for equipment power supply,
supplier must consider inside of the scope platform availability and certified personnel (DC-3
certification is required for involved personnel in height work).
4.5.2.5 Pipes must be identified and signaled according to below Donaldson Construction Standard chart that shows
color standard for pipes.
Supplier will be responsible from unloading remaning crates/pallets from PC16 equipment from trucks place inside
of the plant on designated area and also for the equipment placement according to layout.
Below is shown draft schedule for the remaining equipment arrival and installation (to be considered equipment
availability for maneuvers) in order to consider estimated days for the equipment availability.
SEPTEMBER OCTOBER NOVEMBER DECEMBER
Week 39 40 41 42 43 44 45 46 47 48 49
Date 9/25 to 9/29 10/2 to 10/6 10/9 to 10/13 10/16 to 10/20 10/23 to 10/27 10/30 to 11/3 11/6 to 11/10 11/13 to 11/17 11/20 to 11/24 11/27 to 12/1 12/4 to 12/8
Section 1
Eq. Arrival 1 2
Installation 1 2 3 4 5 6 7
Stacker
Eq. Arrival 1 2
Installation 1 2 3 4 5
Side Panel
Eq. Arrival 1 2
Installation 1 2 3 4 5
End Cap
Eq. Arrival 1 2
Installation 1 2 3 4 5 6 7 8
Gasket
Eq. Arrival 1 2
Installation 1 2 3 4 5 6 7 8
4.5.3.2 Inside of scope supplier must consider to unpack the crates/pallets, coordinate the equipment placement according
to layout (separately dislclosed), level and align vs marked center line (3m offset line should be used as reference)
and the equipment anchoring (anchors will be provided from equipment manufacturers).
Will be supplier’s responsibility the final disposition of waste after unpacking the crates/pallets or
performing the whole work even for the power supply or equipment installation and adjustments.
4.5.3.3 In case of alignment, supplier must consider laser equipment (theodolite) to level and tram equipment per
installation instructions. Details as follows must be considered:
1. Include recording of level and tram values. The vendor can use their standard methods to record the
level and tram data; if none exist have vendor use a data sheet separately disclosed.
2. Permanent monuments need to be installed in the floor as a reference plane parallel to the equipment
centerline.
3. If trying to optically align equipment without monuments, pick a feature believed to be square and
use as a reference. For example, a reference plane could be created perpendicular to the center shaft
of the corrugated sheet turret center shaft.
4. Alignment service should consider to make rolls or frame adjustments as needed (instructions will
disclosed separately).
5. Align rolls to a 0.001” per foot tolerance (equipment alignment will take approx 2 days to complete)
4.5.4 Equipment installation and start-up: Since equipment suppliers are coming for the equipment installation and
start-up; handwork support is needed in order to make the mechanical assembly, equipment adjustment, and
secondary wiring and piping for PC16 equipment as required according to AMT or installation supervisors.
According to below schedule, mechanical and electrical technicians support is needed. These people must be able
to perform the equipment adjustments and mechanical/electrical connections as required.
OCTOBER NOVEMBER DECEMBER
Week 40 41 42 43 44 45 46 47 48 49
Date 10/2 to 10/6 10/9 to 10/13 10/16 to 10/20 10/23 to 10/27 10/30 to 11/3 11/6 to 11/10 11/13 to 11/17 11/20 to 11/24 11/27 to 12/1 12/4 to 12/8
Section 1
Mech technician 2 2 2 2 2 2 2 2 2 1 1 1 1 1
Elec technician 2 2 2 2 2 1 1 1 1 1
Stacker
Mech technician 2 2 2 2 2 1 1 1 1 1
Elec technician 2 2 2 2 2 1 1 1 1 1
Side Panel
Mech technician 2 2 2 2 2 2 2 2 2 2
Elec technician 2 2 2 2 2 2 2 2 2 2
End Cap
Mech technician 2 2 2 2 2 2 2 2 2 2
Elec technician 2 2 2 2 2 2 2 2 2 2
Gasket
Mech technician 2 2 2 2 2 2 2 2 2 2
Elec technician 2 2 2 2 2 2 2 2 2 2
Supplier must provide conventional tools for all mechanical and electrical work.
Separately, guides for equipment installation, leveling, alignment and adjustments will be provided after PO
submission. Also the AMT members and the equipment manufacturers will provide guidance during the equipment
installation and start-up.
Donaldson Company, Inc. Confidential Page 13 of 30
Donaldson Latin America. SOW PC16 enclosure
4.5.5 Miscelalleuos modifications for PC16 equipment: In case of the current accumulator equipment, supplier must
perform on site, equipment modification in order to be able to install the paint spraying system.
According to below drawing, plates of accumulator’s main body should be drilled and screw thread must be made.
In that way, drill with magnetic base and required tools will be required to modify the equipment’s plates.
Inside of scope supplier must provide the bolts and all required stuff to make the paint sprayer assembly. Secondary
wiring and piping should be considered to.
B.
Documentation Included
5. Documentation
The following selected documents are applicable and incorporated into this SOW.
C.
Consigned Parts
List
6. Consigned Parts
Table 2 Consigned Parts List
1. Supplier is to receive, inventory and notify the Buyer’s Project Manager when each
consigned part is delivered to Supplier’s facility. A copy of the pack list is to be provided to
Buyer’s Project Manager.
2. The obligations related to consigned parts are laid out under section 12.2.1.
D.
Project Management &
Schedule
7. Project Management & Schedule
1. Project Management
1. Supplier shall provide a Project Manager who will be responsible for the Supplier’s
project management activities and communications to the Buyer. The Supplier’s Project Manager
will remain in this position from the start to the finish of the project unless both Parties agree to a
change.
2. Change Management
1. All proposed changes to this SOW or associated documents must be approved by the
Buyer’s Project Manager before proceeding with the change.
1. Any changes that affect price and/or delivery must be approved by the Buyer’s
Project Manager before proceeding with the change.
2. Buyer will not pay for any changes that have not followed this process.
3. All identified deliverables must be met before PCN (Project Change Notice)
approval. Identified deliverables can include any of the following:
1. Redline drawings with BOM(s).
2. New drawings or sketches.
3. Documented proof of issues and defective parts.
4. Engineering change costs.
5. Impacts to schedule changes.
2. An Excel workbook named SOW PCN Log will be provided by Buyer and maintained by
Supplier to document approved changes.
1. PCN’s are managed with separate POs that will be issued at agreed upon dates
but not later than the end of the project for any changes that affect scope, price, or
delivery.
Table 4 EC Responsibilities
PCN Value Authorization Method Authorization Responsibility
< $200 N/A Supplier to include in SOW PCN Log
$200 ≤ $1,000 Verbal or Written Buyer’s Project Manager or Process Engineer
> $1,000 Written Buyer’s Project Manager
3. Schedule
1. A project milestone schedule is required with the Supplier’s quote. During the project the
Supplier’s Project Manager will maintain a schedule and inform the Buyer’s Project Manager of
any deviations to the project schedule on a weekly basis. This schedule will become an element
of the Order and will be utilized in monitoring and evaluating Supplier’s performance.
2. The schedule must contain the following milestones (as agreed upon with Buyer’s Project
Manager):
Design Reviews, Procurement, Assembly, Power On, Setup and Testing, Integration, FAT,
Crating, and Ship Date.
4. Buyer’s Contacts List
1. Process Engineer is Enrique de la Cruz García, Tel: +52 449 212 8330,
E-mail: [email protected].
2. Donaldson Buyer is Christopher Reyes, Tel: +52 449 910 6165,
E-mail: [email protected]
3. Other [ INSERT TITLE ], [ INSERT NAME ], Tel: [ INSERT PHONE ], E-mail: [
INSERT E-MAIL ].
5. Supplier’s Contacts List (optional)
1. Application engineer is [ INSERT NAME ], Tel: [ INSERT PHONE ], E-mail: [
INSERT E-MAIL ].
2. Sales contact is [ INSERT NAME ], Tel: [ INSERT PHONE ], E-mail: [ INSERT E-
MAIL ].
3. Other [ INSERT TITLE ], [ INSERT NAME ], Tel: [ INSERT PHONE ], E-mail: [
INSERT E-MAIL ].
E.
Integration
8. Integration at Supplier’s Facility
1. Integration
1. Buyer representatives may be onsite during setup and debug phases of the project as
required.
2. Supplier will be responsible for receiving, placing, aligning, and providing all utilities for
operation of all Equipment in the Supplier’s facility. The integration of all Buyer supplied
equipment listed in the consigned parts area of this SOW is included in the scope. The Equipment
will be positioned and aligned so as to produce product as if it were in production.
3. Raw materials will be supplied by the Buyer.
4. Buyer will be responsible for setting up the following Equipment:
5. Supplier will be responsible for maintaining all supplied Equipment in good working
order and operate as per instructions provided by the Buyer.
1. If applicable, Supplier to prepare dispense Equipment, including flushing system,
prior to shipping according to Buyer’s instruction. Buyer will provide supervision for
flushing and cleaning activities.
6. Dedicated office space with internet access for Buyer’s personnel shall be provided
during all visits by the Buyer.
7. Supplier shall provide for removal to landfill all materials consumed during setup, debug,
FAT, and validation of Equipment at Supplier’s facility.
8. Supplier shall provide personnel to act as operators during FAT and validation at
Supplier’s facility.
9. Integration shall be done using the electrical power found at the final Equipment
destination.
F.
Acceptance
Testing
9. Acceptance Testing
1. Pre-FAT Activities
1. Buyer reserves the right to inspect the Equipment at any time at the Supplier’s facility.
2. Supplier to submit pre-FAT deliverables:
1. ☐ Mechanical Checkout
2. ☐ Electrical Checkout
3. ☐ Setup Document
4. ☐ Safety Checkout
5. ☐ Functional Tests
3. Supplier and Buyer to determine when FAT begins.
G.
Shipping and
Installation
10. Shipping
1. Equipment Final Destination
1. The address for delivery is: INCOTERM Ex-Works
2. Overview
1. Type of Shipment
☐ Domestic Truck
☐ International Truck
☐ International Container
2. Shipping Method
☐ Dedicated
☐ LTL (Less Than Load)
3. Trade Secret Shipment
☐ Yes
☐ No
4.Supplier is responsible for packaging and preparing Equipment for shipment.
1. Buyer’s preference is for Supplier to hire a professional packing company.
2. Deviation from any requirement requires written pre-approval by Buyer’s Project
Manager.
3. Supplier must comply, at a minimum, with the shipping preparation requirements
summarized below.
1. Following are general requirements that apply to ALL types of shipments:
1. The Equipment must be disassembled, packaged and prepared for shipment via
the Type of Shipment specified.
2. The Equipment may be disassembled only to the extent required for shipment.
3. Anything disconnected or disassembled must be uniquely labeled for ease of
reassembly.
4. All joints that must be disconnected for shipment must be labeled and have a bag
containing the required reassembly hardware securely attached to the Equipment it was
removed.
5. Moving and flexible components must be braced to ensure safe arrival at
destination.
6. Loose components must be protectively wrapped and packaged securely.
7. All Equipment tooling as identified by Buyer’s Project Manager must be:
1. Packaged together. For example, all LH Winder Tooling shall be in one
package.
2. Easily accessible for customs agents (if applicable); preferably on a
separate skid.
8. One (1) hard copy set of As-Built, B-size electrical drawings must be included
and shipped inside each electrical panel.
9. The Equipment must be secured to a skid which is larger than the Equipment,
such that all elements of the Equipment reside within the boundaries of the skid.
10. Each skid must be secured to the trailer or container, and braced, to ensure that
the Equipment stays fixed and does not topple over, roll off or separate from the skid.
11. Buyer reserves the right to witness disassembly, skidding, crating and loading
onto the trailer(s) or into the container(s). Buyer’s Project Manager must be notified no
less than two (2) weeks in advance of these activities.
12. All final package sizes and weights must be sent to Buyer’s Project Manager no
less than one (1) week before the loading date.
13. Photographs
1. All Equipment must be photographed (all four sides) before AND after
plastic has been applied.
2. Photos must be taken of the final loading onto the trailer(s) or into the
container(s).
3. Photos must be organized by the trailer and sent to Buyer’s Project
Manager.
14. Center of Gravity and pick points should be marked on outside of each package.
15. All Equipment shipped in an enclosed trailer must be covered or draped with 6
mil minimum plastic.
16. If shipment is designated trade secret, all plastic used should be black or opaque.
17. All Equipment shipped on an unenclosed trailer must be securely wrapped and
sealed on all sides, including bottom, with marine grade shrink poly film.
18. Enclosed, air ride trailers required.
1. Flatbed or double-drop trailers may only be used if package dimensions
exceed enclosed trailer dimensions.
2. If open trailers are used:
1. Major welded components and crates should be designed for
non-permit loads.
2. All Equipment must be covered with tarps after loading on
trailer.
3. Enclosed, air ride trailer sizes provided as a reference:
Trailer Dimensions Interior Measurement
Load
Length Width Height
o Start-up all Equipment just as they were at the integration site, in conjunction
with Buyer’s personnel.
5. Supplier will provide technician(s) on-site at plant to train Buyer’s plant personnel in
proper and safe Equipment operation.
H.
After-Sales
Support
12. AFTER-SALES SUPPORT
1. Spare Parts:
1. Supplier warrants that for all critical spare parts to service for the Equipment(s) delivered
under the Order shall be available to the Buyer during the operational life of the items or 5 years
after the date of the last delivery under the Order, whichever is later. Such warranty excludes
spare parts that are readily available in the market without the need for custom design, purchased
from other manufacturers on a need-by basis as well as parts which Supplier produced or let
produce based on Buyer’s input of custom design.
If after such period, the Supplier or its sub-supplier discontinues the manufacture of the
aforementioned items and does not provide for another qualified source, the Supplier shall make
available to the Buyer all drawings, specifications and/or know-how which will enable the Buyer
to service, and to make, have made or procure said Goods, all subassemblies, spare parts, and
service under a royalty-free license which is hereby granted.
2. Storage and ownership of Buyer property:
1. Supplier shall maintain a current inventory list of all Buyer property in case Buyer
provides to Supplier any parts, software, tools, gauges, equipment directly or through another 3rd
party for the design or manufacture of the Equipment. Any such item shall: a) become and shall
be identified/labeled as property of Buyer; b) be held by Supplier on consignment at Supplier’s
risk; c) be used exclusively for Buyer; and d) be subject to disposition by Buyer at any and all
times and upon demand they shall be returned to Buyer. The Supplier shall perform incoming
inspection of consigned parts and immediately notify Buyer of any issues related to form, fit and
function. The Supplier shall adequately store and maintain any Buyer property and consigned
parts and keep proper inventory and inspection records therefor which shall be available to Buyer
upon request.
3. Guaranteed service turnaround time during the operational life of the Equipment:
1. Once the Supplier has been contacted related to an Equipment failure, Supplier is
expected to be available to provide immediate assistance for resolution during its office hours. In
case the office hours of the Supplier don’t overlap with those of the Buyer, Supplier will
accommodate to provide support outside of its own office hours.
In case the failure cannot be resolved remotely, Supplier (or its subcontractor) is expected to
service the Equipment physically within 48 hours after last incident call on Buyer’s site. In case
the Supplier fails to service the Equipment within the times stated above, Buyer has the right to
contract with a third party for service intervention. In such case and unless the warranty period
has expired, the warranty would remain in-tact.
I.
Supplier Quote
Supplier to fill in
13. PRICE
1. Price:
1. Supplier agrees to execute this Agreement for a fixed lump-sum price valid for the entire
life of the Agreement, including any postponements for the complete delivery of material and/or
services required for the execution of the Agreement, and for any items not listed but necessary
for the safe and economical execution of Supplier's scope and supply of services.
Supplier can provide its quotation in its own form(at), however is requested to fill in below table
nonetheless.
Supplier to fill in below table:
5 Shipment
[INSERT DATE]
4. Agreed Incoterm (as per 2020):
Agreed Incoterm If FCA If CPT
FCA At Supplier [SPECIFY PORT/AIRPORT OF
IMPORT OR DONALDSON
FACILITY]
5. Exceptions:
1. All exceptions to the RFQ or its attachments must be clearly defined in the Quote
Exceptions Request Form.
This SOW has been issued in two identical copies of which the Parties each have received one.
Signature: Signature:
Name: Name:
Title: Title:
J.
Design By
Supplier
14. DESIGN BY SUPPLIER
1. Specifications:
1. For projects requiring design by Supplier:
1. All required deliverables listed in Section 4.4 Deliverables must be provided to
Buyer.
2. All specifications listed in Appendix B Documentation must be followed.
2. Ownership
1. All design records, models, drawings, etc. are the property of the Buyer.
2. Buyer may choose to review and request copies of the design at any time.
3. Design Approvals:
1. Should the design and/or Equipment fail to meet the requirements listed, the Supplier will
be responsible for taking appropriate corrective actions to expeditiously rectify the issue so that it
meets the requirements or is formally accepted by the Buyer’s Project Manager.
2. The design approval form located in Appendix K will be used as the official project
design approval record. Buyer’s Project Manager will formally approve the design and authorize
any applicable milestone payments.
K.
Design Approvals
15. Design Approvals
This form will serve as the official design approval record.
1. Approval Scope:
☐ Criteria Design Review (CDR)
☐ Preliminary Design Review (PDR)
☐ Final Design Review (FDR)
☐ Other ______________________
2. Project Information:
1. Purchase Order Number: [ ]
2. Supplier Name: [ ]
3. Equipment Name: [ ]
3. Design Checklist/Scope:
1. Design Checklist / Scope Document: [ ]
4. Review Information:
1. Design Review Date: [DATE]
2. Design Review Location: [ ]
5. Signatures:
L.
Testing
Approvals
16. Testing Approvals
This form will serve as the official project testing approval record.
1. Approval Scope:
☐ Factory Acceptance Test (FAT)
☐ Site Acceptance Test (SAT)
☐ Other ______________________
2. Project Information:
1. Purchase Order Number: [ ]
2. Supplier Name: [ ]
3. Equipment Name: [ ]
3. Testing Criteria:
1. Testing Criteria / Protocol Document: [ ]
4. Testing Information:
1. Test Date: [DATE]
2. Test Time: [ ]
3. Test Location: [ ]
5. Signatures: