RA 11111 Building Cost Breakdown
RA 11111 Building Cost Breakdown
WO Current Sty.
S.no Activities WO Sty. Unit Rate RA 1 Amount
S.no (RA1)
BUILDING A
1 1.1 (a) Excavation (0-1.5) 120.00 119.67 CUM 120 ₹ 14,360.76
2 1.1 (b) Excavation(1.5-3) 10.00 69.29 CUM 195 ₹ 13,511.84
3 1.7 Preparation of subbase 174.00 173.83 SQM 95 ₹ 16,513.68
4 1.3 (a) Backfilling 120.00 164.89 CUM 120 ₹ 19,786.75
5 1.1 Supply and laying GSB 26.00 26.07 cum 3150 ₹ 82,133.85
6 2.1 (c) PCC 28.00 14.38 CUM 5500 ₹ 79,068.87
7 2.3 (a) RCC (Footing) 14.00 14.75 CUM 6480 ₹ 95,568.45
8 2.3 (c) RCC(Column) 14.00 16.80 CUM 6840 ₹ 114,877.97
9 2.3 (d) RCC (Beam) 17.81 CUM 6840 ₹ 121,819.72
55.00
RCC (SLAB) 32.44 CUM 6840 ₹ 221,866.60
1.8 Anti termite 174.00 173.83 SQM 95 ₹ 16,513.68
11 2.7 (a) Shuttering (Footing) 25.00 25.96 SQM 350 ₹ 9,084.60
12 2.7 (c) Shuttering (Column) 180.00 200.18 SQM 350 ₹ 70,064.22
13 2.7 (d) Shuttering (Beam) 154.87 SQM 350 ₹ 54,204.05
Shuttering (SLAB) 435.00 243.33 SQM 350 ₹ 85,166.67
6.1 DPC 12.00 11.89 SQM 345 ₹ 4,102.05
6.3 BITUMEN 12.00 11.89 SQM 250 ₹ 2,972.50
3.3 Brickwork Sub Str. 1:4 69.00 33.25 CUM 6200 ₹ 206,176.43
16 2.9 Reinforcement 14.00 11.744 MT 64000 ₹ 751,644.08
Building A Total ₹ 1,979,436.77
Total ₹ 1,979,436.77
GST 18% ₹ 356,298.62
Grand Total ₹ 2,335,735.39
MEASUREMENT SHEET FOR CIVIL WORK FOR BUILDING C
S.No Description No. L B/W H/D Qty Unit
1 Excavation (0-1.5) Total depth 2.57
F1 1 2.35 2.2 1.5 7.76
F2 2 2.2 2 1.5 13.20
F3 5 2 1.8 1.5 27.00
F4 2 1.6 1.4 1.5 6.72
F5 5 2.2 1.4 1.5 23.10
F6 1 1.9 1.13 1.5 3.22
1 0.77 1.23 1.5 1.42
PB BEAM PB1 1 12.25 0.45 0.355
PB2 1 15.17 0.45 0.355 2.42
PB3 1 4.6 0.45 0.355 0.73
PB4 1 15.184 0.45 0.355
PB5 1 7.719 0.45 0.355
PB6 3 9.22 0.45 0.355 4.42
PB7 1 3.51 0.45 0.355 0.56
PB8 1 9.25 0.45 0.355
PB2A 1 3 0.45 0.355 0.48
7 PCC
FOOTING F1 1 2.35 2.2 5.17
F2 2 2.2 2 0.1 0.88
F3 5 2 1.8 0.1 1.80
F4 2 1.6 1.4 0.1 0.45
F5 5 2.2 1.4 0.1 1.54
F6 1 1.9 1.13 0.1 0.21
1 0.77 1.23 0.1 0.09
BEAM PB1 1 12.25 0.43 0.1 0.53
PB2 1 15.17 0.43 0.1 0.65
PB3 1 4.6 0.43 0.1 0.20
PB4 1 15.184 0.43 0.1 0.65
PB5 1 7.719 0.43 0.1 0.33
PB6 3 9.22 0.43 0.1 1.19
PB7 1 3.51 0.43 0.1 0.15
PB8 1 9.25 0.43 0.1 0.40
PB2A 1 3 0.43 0.1 0.13
14.38 CUM
8 RCC (Footing)
F1 1 2.15 2 0.25 1.08
F2 2 2 1.8 0.25 1.80
F3 5 1.8 1.6 0.25 3.60
F4 2 1.4 1.2 0.2 0.67
F5 5 2 1.2 0.2 2.40
F6 1 1.7 1.03 0.35 0.61
1 0.67 1.03 0.35 0.24
Trapazoidal Footings Total 10.40 CUM
9 RCC ( Column)
FOOTING upto Bottom of ROOF
11 Shuttering
FOOTING F1 1 2.15 2 0.25 2.08
F2 2 2 1.8 0.25 3.80
F3 5 1.8 1.6 0.25 8.50
F4 2 1.4 1.2 0.2 2.08
F5 5 2 1.2 0.2 6.40
F6 1 1.7 1.03 0.35 1.91
1 0.67 1.03 0.35 1.19
Total 25.96 SQM
PB PB1 1 12.25 0.45 0.23 11.03
PB2 1 15.17 0.45 0.23 13.65
PB3 1 4.6 0.45 0.23 4.14
PB4 1 15.184 0.45 0.23 13.67
PB5 1 7.719 0.45 0.23 6.95
PB6 3 9.22 0.45 0.23 24.89
PB7 1 3.51 0.45 0.23 3.16
PB8 1 9.25 0.45 0.23 8.33
PB2A 1 3 0.45 0.23 2.70
Total 88.51 SQM
13 supply and compactiong GSb gr. II 1 1 16.795 10.35 0.15 26.07 cum
Reinforcement No. of Members Cut Length No. of Unit Weight Weight
14 Bars
Footing 2.15 x 2.0
Bottom 1 1 2.20 15 0.89 29.37
Bottom 1 1 2.35 14 0.89 29.28
C2 (.450 x 0.300)
Main Bar 20 MM 4 4 8.221 2.47 324.89
Main Bar 16 MM 4 6 8.221 1.58 311.74
Ring A 4 57 1.276 0.40 114.92
Ring B 4 58 0.824 0.395 75.51
Ring C 4 58 0.498 0.395 45.64
C3 (0.23 x 0.9)
Main Bar 16 MM 5 16 8.271 1.58 1045.45
Main Bar 12 MM 5 2 3.725 0.89 33.15
Ring A 5 40 1.960076 0.395 154.85
Ring B 5 117 0.760076 0.395 175.63
Ring C 5 116 0.310 0.395 71.02
C4(0.230 x 0.450)
Main Bar 16 MM 2 8 8.321 1.58 210.35
Ring A 2 58 1.060076 0.395 48.57
Ring B 2 59 0.76 0.395 35.42
C5(2X0.230 x 0.900)
Main Bar 16 MM 1 18 8.221 1.58 233.81
Main Bar 12MM 1 4 3.725 0.89 13.26
Ring A 1 80 1.960076 0.395 61.94
Ring B 1 352 0.760076 0.395 105.68
Ring C 1 581 0.31 0.395 71.14
PLINTH BEAM
PB1 (230 x 450)
Ring
8mm # 100 c/c ST1 1 1.280 31 0.395 15.67
Roof beam
B1 (230 x 450)
B4 (230 x 450)
B5 (230 x 450)
Ring
8mm # 100 c/c ST1 1 1.280 31 0.395 15.67
Roof slab
1 X2-3, Y1-2 ,S1
Main bar 10#175c/c 1 6.290 17 0.620 66.30
1 5.490 17 0.620 57.86
0.00
1 6.730 11 0.620 45.90
1 7.830 11 0.620 53.40
distrubution bar 2 2 6.000 7 0.395 66.36
2 2 4.130 8 0.395 52.20
0.00
2 X2-3, Y2-3 ,S1 0.00
Main bar 10#175c/c 1 6.290 19 0.620 74.10
1 5.490 19 0.620 64.67
1 1.00
1 6.410 11 0.620 43.72
1 5.310 11 0.620 36.21
distrubution bar 2 2 4.580 7 0.395 50.65
2 2 4.275 8 0.395 54.04
0.00
3 X3-4, Y1-2 ,S1 0.00
Main bar 10#175c/c 1 6.575 17 0.620 69.30
1 5.775 17 0.620 60.87
0.00
1 6.730 12 0.620 50.07
1 7.830 12 0.620 58.26
distrubution bar 2 2 6.000 7 0.395 66.36
2 2 4.645 8 0.395 58.71
0.00
4 X2-3, Y2-3 ,S1 0.00
Main bar 10#175c/c 1 6.575 19 0.620 77.45
1 5.775 19 0.620 68.03
1 1.00
1 6.410 8 0.620 31.79
1 5.310 14 0.620 46.09
distrubution bar 2 2 4.580 7 0.395 50.65
2 2 4.275 8 0.395 54.04
Chatjaa
distrubution bar 2 2 18.200 7 0.395 201.29
2 2 11.800 5 1.395 329.22
extra bar 10@400c/c 2 1 1.850 151 0.620 346.39
Total 11744.44 KG
Foundation
No. L W/B D d column
Found. A1 A2 Trapazoid
F1 2.15 2 0.45 0.25 F1C1 4.30 0.45 0.409
F2 2 1.8 0.45 0.25 F2C1 3.60 0.45 0.355
F3 1.8 1.6 0.4 0.25 F3C2 2.88 0.45 0.223
F4 1.4 1.2 0.35 0.2 F4C4 1.68 0.64 0.167
F5 2 1.2 0.35 0.2 F5C3 2.40 0.36 0.184
F6 1.7 1.03 0.35 F6C5 1.75 0.36
0.67 1.03 0.35 F3C1 2.88 0.45 0.149
Building C
C1 4 0.3 0.45
C2 4 0.3 0.45
C3 5 0.23 0.9
C4 2 0.23 0.45
C5 1 0.83 0.23
1 0.67 0.23
column
Footing Combined
1.075 1.48
0.9 1.25
0.72 0.94
0.336 0.50
0.48 0.66
0 0.00
0.00