Screenshot 2024-09-08 at 03.06.04

The document outlines planned temporary engineering speed restrictions across various railway sections, detailing the imposition dates, expected removal dates, and types of work being conducted. Each entry includes specific locations, time losses, and the length of track affected. Overall, the document indicates ongoing maintenance and construction efforts aimed at ensuring railway safety and efficiency.

Uploaded by

niranjan709761
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
13 views2 pages

Screenshot 2024-09-08 at 03.06.04

The document outlines planned temporary engineering speed restrictions across various railway sections, detailing the imposition dates, expected removal dates, and types of work being conducted. Each entry includes specific locations, time losses, and the length of track affected. Overall, the document indicates ongoing maintenance and construction efforts aimed at ensuring railway safety and efficiency.

Uploaded by

niranjan709761
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Date:-07.09.

24
Temporary Engineering Speed Restriction
Planned/ Date of Station Expected date of
S.No SR Time loss Station to KM from KM to Length Work
Unplanned imposition from removal

HTE-NXN SECTION JTL-1(Permissible speed 110 Kmph)


1 Planned 07.09.24 30 2.61 BKPR-PKF JTL-1 481/13 481/11 122 07.10.24 Jackting work on Br-489

2 Planned 05.09.24 OES(7-17) … PKF Yd L-1 486/1 487/1 10.09.24 Rail dolly work
Planned MCZ-KRKR
3 30.08.24 OES+BLW (7-18) …. 504/19 504/17 29.09.24 Protection work in progress
(CON/RNC) JTL-1
Planned MCZ-KRKR
4 17.08.24 OES+BLW (7-18) …. 507/17 507/28 15.09.24 Protection work in progress
(CON/RNC) JTL-1
5 Planned 30.08.24 30+OES(7-17) 2.80 MCZ-BANO 514/19 514/27 250 12.09.24 TRR & Welding work
Planned
6 01.09.24 OES+BLW (8-18) … BANO Yd L-1 518/19 518/29 20.09.24 Extention & Construction of PF-2
(CON/RNC)
Planned
7 01.09.24 OES+BLW (8-18) … BANO Yd M/L 518/26 518/32 10.09.24 Extention & Construction of PF-2
(CON/RNC)
Planned
8 01.09.24 OES+BLW (8-18) … KNRN Yd 525/10 525/18 30.09.24 Construction of PF-1
(CON/RNC)
9 Planned 07.09.24 30+OES(7-17) 2.01 KNRN-TAX 528/5 528/19 323 15.09.24 TRR & welding work
Planned
10 18.07.24 OES+BLW+ SDIR (6- … KNRN-TAX 535/6 535/10 17.09.24 Rock cutting work Adjecent existing line
(CON/RNC) 20)
Planned
11 18.07.24 OES+BLW+ SDIR (6- … KNRN-TAX 537/6 537/13 17.09.24 Rock cutting work Adjecent existing line
(CON/RNC) 20)
Water coming on track & Boulder fallen in
12 Planned 21.08.24 30+OES (D+N) 1.53 KNRN-TAX 537/11 537/13 67 15.09.24
valnerable location
Planned
13 01.08.24 45+OES+BLE(D+N) 0.91 TAX-PBB 541/17 541/24 221 26.09.24 Rock cutting adjecent running line
(CON/RNC)
Time consumed= 9.86 Total time allowed = 9.00 Extra Time 0.86
HTE-GBX SECTION JTL-2

BKPR-PKF JTL-2,Inc.PKF Yd L-
Planned
1 25.03.23 80 … 3 Along with Pt No-102A & 480/10 487/8 PSR Crtified fit for Goods & Coaching train
(CON/RNC) 112B

Planned
2 08.08.24 60 …. BKPR-PKF JTL-2 481/12 481/20 TFA CRS Authorisation
(CON/RNC)
Planned PKF-Yd L/No-4X-Over Pt-
3 24.07.24 30 …. 102A/B & 112A/B
486/06 487/02 TFA Increase speed 15 Kmph to 30 KMPH
(CON/RNC)

Planned
4 25.03.23 80 …. PKF-PKC JTL-2, 487/8 492/24 PSR Crtified fit for Goods & Coaching train
(CON/RNC)
Planned CRS Authorisation
5 29.12.23 90 … PKC-KRKR JTL-2 494/12 498/28 TFA
(CON/RNC)
Planned CRS Authorisation
6 08.08.24 50 … PKC-KRKR JTL-2 498/28 498/38 TFA
(CON/RNC)
Planned
7 29.12.23 90 … PKC-KRKR JTL-2 498/38 502/08 TFA CRS Authorisation
(CON/RNC)

Planned KRKR-MCZ-BANO-
8 12.07.24 90 …. KNRNINC-MCZ&BANO L-3
502/8 524/36 TFA Cartifit fit for goods & coaching train
(CON/RNC)

Planned MCZ-KRKR
9 30.08.24 OES+BLW (7-18) …. 504/18 504/26 29.09.24 Protection work in progress
(CON/RNC) JTL-2
Planned
10 20.07.24 45+OES (D+N) 2.08 KRKR-MCZ JTL-2 507/16 507/28 210 10.09.24 Rock bolting work in high cutting
(CON/RNC)
Planned MCZ-KRKR
11 17.08.24 OES+BLW (7-18) …. 507/18 507/36 15.09.24 Protection work in progress
(CON/RNC) JTL-2
Planned
12 02.08.24 30 2.80 KRKR-MCZ JTL-2 509/02 509/08 127 07.09.24 Cross level Variation
(CON/RNC)
Planned
13 12.07.24 80 … MCZ-BANO 514/6 514/40 TFA Speet Potential of curve
(CON/RNC)
Planned
14 12.07.24 60 …. MCZ-BANO 515/6 516/8 TFA CRS Authorisation
(CON/RNC)
Planned
15 05.08.24 45+OES (D+N) 0.90 ORGA-NXN L/No-2 554/34 555/02 48 10.09.24 Rectification of Embankment at HB-50
(CON/RNC)

Time consumed= 5.78

RNC-LAD-BICI-TORI Section S/L (Permissible speed 110 Kmph)


30+OES+BLW +
1 Planned 06.09.24 3.68 BICI-BODG 503/10 504/10 904 10.09.24 TRR work
SLO+SDIR (8-18)
Time consumed= 3.68 Total time allowed = 7.00 Save Time -3.32
Temporary Engineering Speed Restriction
Planned/ Date of Station Expected date of
S.No SR Time loss Station to KM from KM to Length Work
Unplanned imposition from removal

MURI-CNI Section S/L (Permissible speed 110 Kmph)

1 Planned 24.08.24 45+OES (8-17) 1.51 ILO-TRAN 345/12 345/11 50 10.09.24 U/C track Newly launched NHS
45+OES+SDIR
2 Planned 19.07.24 1.51 ILO-TRAN 341/18 341/17 72 10.10.24 U/C track Newly launched NHS
(D+N)
3 Planned 20.07.24 75 0.61 TUL Yd M/L 322/12 322/11 72 28.09.24 Launching of boxes Br No 395
Time consumed= 3.63 Total time allowed = 5.00 Save Time -1.37
MURI-BRKA Section S/L (Permissible speed 110 Kmph)

1 Planned 30.08.24 30 + OES (D+N) 1.58 MURI-BLNG 354/07 354/08 59 20.09.24 U/C track Newly Launched NHS

2 Planned 07.08.24 75 0.61 HRBR-GRE 383/14 383/15 40 20.09.24 Post work of TRT

3 Planned 26.08.24 15 … MAEL Yd L-3 1002/A 1003/A 20.09.24 Post Box Pushing work
Time consumed= 2.19 Total time allowed =
4.00 Save Time -1.81
HTE-MURI Section UP/L (Permissible speed 100 Kmph w.e.f 28.01.21)

1 Planned 15.08.24 75+OES(D+N) 0.81 SLF Yd UP/M/L 359/5 359/37 806 15.09.24 U/C track
Pass coutiously+ SDIR
2 Planned 28.07.24 …. KITA-GATD 378/31 379/29 27.09.24 Boulder falling zone
(D+N)
3 Planned 01.09.24 OES+BLW+SDIR(7-18) … NKM-RNC 417/1 417/27 02.10.24 Rail dolly work
Time consumed= 0.81 Total time allowed = 5.00 Save Time -4.19
HTE-MURI Section DN/L (Permissible speed 100 Kmph w.e.f 28.01.21)
Rock cutting and Birsa ROB foundation
1 Planned 17.08.24 OES+BLW(6.30-18.30) …. HTE-RNC 423/32 423/12 16.09.24
work
2 Planned 07.09.24 OES+SDIR(7-16) …. RNC-NKM 417/26 417/22 31.09.24 Rail dolly work

3 Planned 06.09.24 OES(7-17) … TIS Yd M/L 408/8 408/4 10.09.24 Guard Rail & track maintanance work

4 Planned 06.09.24 30 1.53 TIS-GAG 395/30 395/28 50 09.09.24 IMR in SEJ

5 Planned 29.08.24 OES+BLW+SDIR(8-17) …. JONA Yd DN/M/L 384/6 383/30 20.09.24 Packing work

6 Planned 28.08.24 SLO+BLW(18-6) …. JONA-KITA 382/2 378/2 10.10.24 Mansoon patrolling


Time consumed= 1.53 Total time allowed = 5.00 Save Time -3.47
MURI-KSX Section DN/L (Permissible speed 110 Kmph )
1 NIL

Time consumed= 0.00 Total time allowed= 2.00 Save Time -2.00
KSX-MURI Section UP/L ( Permissible speed 110 Kmph)
1 NIL

Time consumed= 0.00 Total time allowed = 2.00 Save Time -2.00