Date:-07.09.
24
Temporary Engineering Speed Restriction
Planned/ Date of Station Expected date of
S.No SR Time loss Station to KM from KM to Length Work
Unplanned imposition from removal
HTE-NXN SECTION JTL-1(Permissible speed 110 Kmph)
1 Planned 07.09.24 30 2.61 BKPR-PKF JTL-1 481/13 481/11 122 07.10.24 Jackting work on Br-489
2 Planned 05.09.24 OES(7-17) … PKF Yd L-1 486/1 487/1 10.09.24 Rail dolly work
Planned MCZ-KRKR
3 30.08.24 OES+BLW (7-18) …. 504/19 504/17 29.09.24 Protection work in progress
(CON/RNC) JTL-1
Planned MCZ-KRKR
4 17.08.24 OES+BLW (7-18) …. 507/17 507/28 15.09.24 Protection work in progress
(CON/RNC) JTL-1
5 Planned 30.08.24 30+OES(7-17) 2.80 MCZ-BANO 514/19 514/27 250 12.09.24 TRR & Welding work
Planned
6 01.09.24 OES+BLW (8-18) … BANO Yd L-1 518/19 518/29 20.09.24 Extention & Construction of PF-2
(CON/RNC)
Planned
7 01.09.24 OES+BLW (8-18) … BANO Yd M/L 518/26 518/32 10.09.24 Extention & Construction of PF-2
(CON/RNC)
Planned
8 01.09.24 OES+BLW (8-18) … KNRN Yd 525/10 525/18 30.09.24 Construction of PF-1
(CON/RNC)
9 Planned 07.09.24 30+OES(7-17) 2.01 KNRN-TAX 528/5 528/19 323 15.09.24 TRR & welding work
Planned
10 18.07.24 OES+BLW+ SDIR (6- … KNRN-TAX 535/6 535/10 17.09.24 Rock cutting work Adjecent existing line
(CON/RNC) 20)
Planned
11 18.07.24 OES+BLW+ SDIR (6- … KNRN-TAX 537/6 537/13 17.09.24 Rock cutting work Adjecent existing line
(CON/RNC) 20)
Water coming on track & Boulder fallen in
12 Planned 21.08.24 30+OES (D+N) 1.53 KNRN-TAX 537/11 537/13 67 15.09.24
valnerable location
Planned
13 01.08.24 45+OES+BLE(D+N) 0.91 TAX-PBB 541/17 541/24 221 26.09.24 Rock cutting adjecent running line
(CON/RNC)
Time consumed= 9.86 Total time allowed = 9.00 Extra Time 0.86
HTE-GBX SECTION JTL-2
BKPR-PKF JTL-2,Inc.PKF Yd L-
Planned
1 25.03.23 80 … 3 Along with Pt No-102A & 480/10 487/8 PSR Crtified fit for Goods & Coaching train
(CON/RNC) 112B
Planned
2 08.08.24 60 …. BKPR-PKF JTL-2 481/12 481/20 TFA CRS Authorisation
(CON/RNC)
Planned PKF-Yd L/No-4X-Over Pt-
3 24.07.24 30 …. 102A/B & 112A/B
486/06 487/02 TFA Increase speed 15 Kmph to 30 KMPH
(CON/RNC)
Planned
4 25.03.23 80 …. PKF-PKC JTL-2, 487/8 492/24 PSR Crtified fit for Goods & Coaching train
(CON/RNC)
Planned CRS Authorisation
5 29.12.23 90 … PKC-KRKR JTL-2 494/12 498/28 TFA
(CON/RNC)
Planned CRS Authorisation
6 08.08.24 50 … PKC-KRKR JTL-2 498/28 498/38 TFA
(CON/RNC)
Planned
7 29.12.23 90 … PKC-KRKR JTL-2 498/38 502/08 TFA CRS Authorisation
(CON/RNC)
Planned KRKR-MCZ-BANO-
8 12.07.24 90 …. KNRNINC-MCZ&BANO L-3
502/8 524/36 TFA Cartifit fit for goods & coaching train
(CON/RNC)
Planned MCZ-KRKR
9 30.08.24 OES+BLW (7-18) …. 504/18 504/26 29.09.24 Protection work in progress
(CON/RNC) JTL-2
Planned
10 20.07.24 45+OES (D+N) 2.08 KRKR-MCZ JTL-2 507/16 507/28 210 10.09.24 Rock bolting work in high cutting
(CON/RNC)
Planned MCZ-KRKR
11 17.08.24 OES+BLW (7-18) …. 507/18 507/36 15.09.24 Protection work in progress
(CON/RNC) JTL-2
Planned
12 02.08.24 30 2.80 KRKR-MCZ JTL-2 509/02 509/08 127 07.09.24 Cross level Variation
(CON/RNC)
Planned
13 12.07.24 80 … MCZ-BANO 514/6 514/40 TFA Speet Potential of curve
(CON/RNC)
Planned
14 12.07.24 60 …. MCZ-BANO 515/6 516/8 TFA CRS Authorisation
(CON/RNC)
Planned
15 05.08.24 45+OES (D+N) 0.90 ORGA-NXN L/No-2 554/34 555/02 48 10.09.24 Rectification of Embankment at HB-50
(CON/RNC)
Time consumed= 5.78
RNC-LAD-BICI-TORI Section S/L (Permissible speed 110 Kmph)
30+OES+BLW +
1 Planned 06.09.24 3.68 BICI-BODG 503/10 504/10 904 10.09.24 TRR work
SLO+SDIR (8-18)
Time consumed= 3.68 Total time allowed = 7.00 Save Time -3.32
Temporary Engineering Speed Restriction
Planned/ Date of Station Expected date of
S.No SR Time loss Station to KM from KM to Length Work
Unplanned imposition from removal
MURI-CNI Section S/L (Permissible speed 110 Kmph)
1 Planned 24.08.24 45+OES (8-17) 1.51 ILO-TRAN 345/12 345/11 50 10.09.24 U/C track Newly launched NHS
45+OES+SDIR
2 Planned 19.07.24 1.51 ILO-TRAN 341/18 341/17 72 10.10.24 U/C track Newly launched NHS
(D+N)
3 Planned 20.07.24 75 0.61 TUL Yd M/L 322/12 322/11 72 28.09.24 Launching of boxes Br No 395
Time consumed= 3.63 Total time allowed = 5.00 Save Time -1.37
MURI-BRKA Section S/L (Permissible speed 110 Kmph)
1 Planned 30.08.24 30 + OES (D+N) 1.58 MURI-BLNG 354/07 354/08 59 20.09.24 U/C track Newly Launched NHS
2 Planned 07.08.24 75 0.61 HRBR-GRE 383/14 383/15 40 20.09.24 Post work of TRT
3 Planned 26.08.24 15 … MAEL Yd L-3 1002/A 1003/A 20.09.24 Post Box Pushing work
Time consumed= 2.19 Total time allowed =
4.00 Save Time -1.81
HTE-MURI Section UP/L (Permissible speed 100 Kmph w.e.f 28.01.21)
1 Planned 15.08.24 75+OES(D+N) 0.81 SLF Yd UP/M/L 359/5 359/37 806 15.09.24 U/C track
Pass coutiously+ SDIR
2 Planned 28.07.24 …. KITA-GATD 378/31 379/29 27.09.24 Boulder falling zone
(D+N)
3 Planned 01.09.24 OES+BLW+SDIR(7-18) … NKM-RNC 417/1 417/27 02.10.24 Rail dolly work
Time consumed= 0.81 Total time allowed = 5.00 Save Time -4.19
HTE-MURI Section DN/L (Permissible speed 100 Kmph w.e.f 28.01.21)
Rock cutting and Birsa ROB foundation
1 Planned 17.08.24 OES+BLW(6.30-18.30) …. HTE-RNC 423/32 423/12 16.09.24
work
2 Planned 07.09.24 OES+SDIR(7-16) …. RNC-NKM 417/26 417/22 31.09.24 Rail dolly work
3 Planned 06.09.24 OES(7-17) … TIS Yd M/L 408/8 408/4 10.09.24 Guard Rail & track maintanance work
4 Planned 06.09.24 30 1.53 TIS-GAG 395/30 395/28 50 09.09.24 IMR in SEJ
5 Planned 29.08.24 OES+BLW+SDIR(8-17) …. JONA Yd DN/M/L 384/6 383/30 20.09.24 Packing work
6 Planned 28.08.24 SLO+BLW(18-6) …. JONA-KITA 382/2 378/2 10.10.24 Mansoon patrolling
Time consumed= 1.53 Total time allowed = 5.00 Save Time -3.47
MURI-KSX Section DN/L (Permissible speed 110 Kmph )
1 NIL
Time consumed= 0.00 Total time allowed= 2.00 Save Time -2.00
KSX-MURI Section UP/L ( Permissible speed 110 Kmph)
1 NIL
Time consumed= 0.00 Total time allowed = 2.00 Save Time -2.00