Land Scape
Land Scape
SECTION
DSECRIPTION TOTAL COST US$
NO.
1 LAND SCAPE AND SITE WORK
a Land development $ 8,216.94
b Pavement $ 19,006.70
c Trees $ 700.00
f Grass $ 4,875.00
j Mechanical $ 46,407.71
Approved by:
LANDSCAPE
UNIT RATE
ITEM DESCRIPTION UNIT QUANTITY AMOUNT US $
US $
1 1M³ Ordinary Soil Excavation of 1 Meter Depth for drainage Cu.m 227.84 $ 5.84 $ 1,330.59
6 Cross arm A1 Channel UNP 1.8 M (Galvanized-Begel) Set 1.00 $ 110.00 $ 110.00
7 Cross arm A2 Channel UNP 2.0 M (Galvanized-Begel) Set 1.00 $ 170.00 $ 170.00
8 Braco for support arm (127)(Begel) Set 5.00 $ 28.00 $ 140.00
9 Helical/ Filaca Set 6.00 $ 4.00 $ 24.00
10 Climber Protection Unit 1.00 $ 9.00 $ 9.00
11 Warning Sign Unit 1.00 $ 9.00 $ 9.00
12 Treckschoor (Assembly) Unit 1.00 $ 145.00 $ 145.00
13 Druckschoor (Assembly) Set 1.00 $ 885.00 $ 885.00
14 Parralel Groove Connector (AL) 35-150 mm2 Set 3.00 $ 5.00 $ 15.00
15 Construction Material ( Stone, Sand, Cement, Iron & Wire) Unit 1.00 $ 15.00 $ 15.00
16 Painting Unit 1.00 $ 22.00 $ 22.00
Generator cummins 200 kva genset 200 kva silent
SPECIFICATION :
Mark : Cummins
Engine Type : 6CTAA 8.3 G2
Power Output : 200 Kva / 160 Kw
Cylinder NO. : 6
17 Unit 1.00 $ 15,000.00 $ 15,000.00
Bore x Stroke : 114.0 x 135.0 mm
Piston Displ. : 8.300 Ltr
fuiel comsumtion (L/H) : 34.00 (75% Load) / 45.40 (100%
Load)
Oil Capacity : 23.8 Ltr.
Silent Genset
1 Part 1
2 Concrete pole 12m 200 dAN un 2.00 $ 875.00 $ 1,750.00
3 Ligthing Arester 24 KVA set 1.00 $ 502.00 $ 502.00
4 Fuse Cut out set 1.00 $ 501.00 $ 501.00
5 Pin post insulator 24 KVA set 2.00 $ 51.00 $ 102.00
6 Cross ARM for pin insulator (100 x50x4x1800) set 2.00 $ 84.00 $ 168.00
7 Performed Wire 16 mm2 (filca) un 6.00 $ 0.95 $ 5.70
8 Termination for Clam ALwire 150mm un 6.00 $ 2.80 $ 16.80
9 termination for Clam AL wire 35 - 50mm un 9.00 $ 2.25 $ 20.25
1 Part 2
2 base transformer
3 Dist. Transformer 200 KVA D Y zn5-3 pHASE 20 KV - 400V (Traf un 1.00 $ 17,000.00 $ 17,000.00
4 iselrwere/base transformer complate accesories . set 1.00 $ 1,003.60 $ 1,003.60
1 Part 3
2 Low Voltage Material
3 Dist. Panel with Circuit breaker 630A & 4 outgoing breaker 2 Set 1.00 $ 1,960.00 $ 1,960.00
4 Galvanized pipe 3" 6m un 3.00 $ 112.00 $ 336.00
5 L cureve galvanized Pipe 3" un 6.00 $ 28.00 $ 168.00
6 Galvanized pipe 1/2" (6m) un 1.00 $ 17.00 $ 17.00
7 NYY 1x70mm2 m 40.00 $ 36.00 $ 1,440.00
8 Coopel wire 1 x 50mm2 m 60.00 $ 7.00 $ 420.00
9 Termination clamps for al wire CT cu 70 - 120 un 24.00 $ 7.00 $ 168.00
10 Temination Clamps for AL wire 2p 70 - 120 un 16.00 $ 4.00 $ 64.00
11 Termination clapms coopel wire 25-95mm un 16.00 $ 6.00 $ 96.00
12 cable lags CU 120 mm2 un 8.00 $ 8.00 $ 64.00
13 Pole protection (penghalang panjat) un 1.00 $ 9.00 $ 9.00
14 warning sign ( tanda bahaya) un 1.00 $ 9.00 $ 9.00
15 constuction material ( stone sand, cement, iron , wire) un 2.00 $ 20.00 $ 40.00
16 Painting un 2.00 $ 22.00 $ 44.00
Sub Total ` $ 47,271.85
UNIT RATE
ITEM DESCRIPTION UNIT QUANTITY AMOUNT US $
US $
i CCTV Installation Plane set 1.00 $ 15,000.00 $ 15,000.00
1 Bullet Colour Camera 4 MP
2 Dome Colour Camera 4 MP
3 LED Monitor 32 inch
4 Digital Video Recorder (DVR)
5 Coaxial cable RG 59 + Power
6 Acording to Spesification
Sub Total ` $ 15,000.00
j Mechanical
1 Gal Pipe DN65 lm 65.00 $ 12.96 $ 842.21
2 Gal Pipe DN40 lm 70.00 $ 10.58 $ 740.39
3 Gal Pipe DN32 lm 100.00 $ 7.62 $ 762.30
4 Gal Pipe DN25 lm 55.00 $ 7.20 $ 396.17
Brass Hose Cock DN15, Gal Mal FF Elbow 90 0 DN15, Brass
Gate Valve , PTFE Tape 12mm IOM, Gal Mal FF Union , GAL
5 Ls 1.00 $ 2,500.00 $ 2,500.00
MAL SOCKET, other fitting and all accessorries
11 supply and install PHD 605 jet pump include all accessories unit 1.00 $ 500.00 $ 500.00
WATER DRILLING WORKS
Drill pilot holl with 2 inch diameter and reaming to 4 inch
12 diameter to suite final 4inch casing m 50.00 $ 50.00 $ 2,500.00
13 Supply and installation of 4 inch diameter guide casing m 6.00 $ 500.00 $ 3,000.00
14 Supply and installation of 2 internal diameter ABS Casing m 45.00 $ 85.00 $ 3,825.00
15 Supply and installation of 2 slotted PVC AW m 18.00 $ 7.24 $ 130.38
16 Setup calibrate and run down hole logger for self potensial Set 1.00 $ 1,000.00 $ 1,000.00
17 and
Boreresistivity
cleaning and development Hour 10.00 $ 50.00 $ 500.00
18 Sanitary seal - cement/clay grout Sum 1.00 $ 1,000.00 $ 1,000.00
19 Bore completion and capping at the end of the well Sum 1.00 $ 500.00 $ 500.00
head,blind
PUMPING flange
TEST bolted incluiding installation of sounding
20 Preliminary testing Hour 1.00 $ 200.00 $ 200.00
21 Step draw down test 4 steps at 50%,75%,100% and 120% Hour 4.00 $ 1,000.00 $ 4,000.00
of the designed
Contractor yield,one
is required hour each
to record step
the PH,TDS, and the EC of
22 the water before during and after the pump testing Hour 24.00 $ 50.00 $ 1,200.00
24 Pumping test report & seft yield ananlysis bore Set 4.00 $ 250.00 $ 1,000.00
constrcution AND
PUMPSETS & ithology,casing
WELLHEAD details and photos
Suplly and installation of grundfos submersible pump.The
expected flow is 25lps @ 200m head to enable pumping to
reservoir.Control panel C/W IP55 enclousure manual on/off
auto swith.Run fault lights 24hr 7 day time clock and no
flow protection;inculide low water level protector,motor
temperature cut off sensor current over load Complete
25 1.00 $ 4,500.00 $ 4,500.00
protection.voltage regulator and pressure sensor auto shut Set
off.Using well master DN 150 for pump connection
1 3 3 2 2 1.00 11.00
2 3 6 2 4 1.50 16.50
3 3 9 2 6 2.00 22.00
4 3 12 2 8 2.50 27.50
5 3 15 2 10 3.00 33.00
6 3 18 2 12 3.50 38.50
8 3 24 2 16 4.50 49.50
10 3 30 2 20 5.50 60.50
13 3 39 2 26 7.00 77.00
15 3 45 2 30 8.00 88.00
20 3 60 2 40 10.50 115.50
23 3 69 2 46 12.00 132.00
25 3 75 2 50 13.00 143.00
30 3 90 2 60 15.50 170.50
35 3 105 2 70 18.00 198.00
40 3 120 2 80 20.50 225.50
45 3 135 2 90 23.00 253.00
50 3 150 2 100 25.50 280.50
60 3 180 2 120 30.50 335.50
70 3 210 2 140 35.50 390.50
80 3 240 2 160 40.50 445.50
90 3 270 2 180 45.50 500.50
100 3 300 2 200 50.50 555.50
150 3 450 2 300 75.50 830.50
200 3 600 2 400 100.50 1105.50
250 3 750 2 500 125.50 1380.50
NOTE:
Travel time is 20km/hr average and return trip is 30km/hr average
TABLE OF HAULING COST
Ave. Haul Cycle Time No. of Trips No. of Dump Total Hauling
Hauling Output Total Unit Cost
Dist. T DT Trucks Cost
(km) (min) (n) (N) (cu.m./hr) (US$/hr) (US$/cu.m.)
Hauling Output
=Nxnx5
= maximum is 124 m3/hr.
UNIT RATES DATA BASE
DELIVERY COST
Cement
DELIVERY COST
DELIVERY COST
DELIVERY COST
DELIVERY COST
Asphalt
DELIVERY COST
DELIVERY COST
DELIVERY COST
DELIVERY COST