Technical Specification - Lot 1 & 2 - ETHOIPIA
Technical Specification - Lot 1 & 2 - ETHOIPIA
PRIME I Distribution Network Upgrading Strengthening and Modernization Project in Eighteen Towns.( Lot 1
- Holeta , Fitche, Legetafo,Weliso, Shambu , Agaro and Batu Towns; Lot 2- melka werer, Melka Sedi, Hartishek
,Kebribeyah ,Shinilee, Togochale Aleta wendo , Yirgalem , Sawula , Bonga, Tepi )
Part 2- Employer’s Requirements 2
PRIME I Distribution Network Upgrading Strengthening and Modernization Project in Eighteen Towns.( Lot 1
- Holeta , Fitche, Legetafo,Weliso, Shambu , Agaro and Batu Towns; Lot 2- melka werer, Melka Sedi, Hartishek
,Kebribeyah ,Shinilee, Togochale Aleta wendo , Yirgalem , Sawula , Bonga, Tepi )
Part 2- Employer’s Requirements 3
Lot 1- Holeta , Fitche, Legetafo,Weliso, Shambu , Agaro and Batu Towns; Design , supply,
installation on site, testing and commissioning of MV Overhead line & Under Ground cables,
Installation of new distribution transformers, rehabilitation of exiting Transformers and connecting
with the existing loads, removal of existing (replaced) networks.
Lot 2- Melka Werer, Melka sedi, Hartishek ,Kebribeyah ,Shinilee, Togochale, Aleta wendo ,
Yirgalem , Sawula , Bonga, Tepi Towns; Design , supply, installation on site, testing and
commissioning of MV Overhead line & Under Ground cables, Installation of new distribution
transformers, rehabilitation of exiting Transformers and connecting with the existing loads,
removal of existing (replaced) networks.
Objectives of Rehabilitation
The objectives of rehabilitation are:
• to upgrade and strengthen MV existing distribution networks of eighteen (18) urban towns.
• to address problems with infrastructure state, supply quality, voltage regulation, capacity
and losses of the distribution network
• to increase the capacity of the existing distribution network,
• to improve the reliability of the electricity supply
• to reduce distribution technical losses
• to improve voltage profile of the network,
• to connect electricity for new settlement area, commercial and industrial areas
• to connect more customers including those far away from the existing distribution network
The project will thus result in increased economic activities and enable to sustain economic growth
in the first phase thirty-four towns of the seventy-two total towns. In order to meet these objectives
the following electrical network rehabilitation and enhancement work is taken up under this project.
Part 2- Employer’s Requirements 6
• The Contractor will reinforce/replace the MV network to enable it to meet the anticipated
demand in the next fifteen years by collecting the necessary data,
• Reconfigure the network if necessary to improve the network capabilities for better control
& operational efficiency.
• Replace /rehabilitate /add new distribution transformers and other network components
Project Financing
This Project is financed by the World Bank under IDA credit No. IDA V5020. The project bidding
document is developed by Ethiopian Electric Utility (EEU). The consultant will also be responsible
for supervising together with the EEU project implementing unit (PIU).
Employer until operational acceptance of the network is obtained for duration of the Defects
Liability period.
Extent of Works
The Contractor is responsible for the scope of the work detailed below:
Types of Works
The important components of this project are indicated below,
• Walk through survey of the electrical network in the project area from the preliminary maps
provided by the employer along with this bidding document to erect new MV network to
replace the existing lines and add new network as needed,
• Upgrading conductor Size (Sq.mm) of MV lines as per approved design plan
• Installation of MV Underground cables at the identified locations,
• Installation of Auto reclosure and Sectionalizer
• Erection of Load Break Switch in MV network,
• Installation of New Distribution Transformers
• Rehabilitation/Upgrading of existing Transformers as necessary
• Carrying out of all ancillary works necessary for completion of the works.
• Dismantling, demolition and proper handover to the nearest EEU store.
• Remedying of defects during the liability period specified under the contract
• Supplying Operation and maintenance manuals of the project
• Detail Design
• Supply of items including spares,
• Installation of Services including load connection, test and commissioning,
Detail design
Design comprises survey activities and engineering design.
Survey Activities
The survey activities are designed to have several components as follows:
The survey works shall start in order to provide feedback of the proposed plan and an initial review
of the methodology. The contractor is expected to prepare its methodology for the survey and
engineering works and submit with its bid.
In more detail the works to be carried out is inclusive but not limited to the following:
In addition, surveying the location of poles will be carried out according to the following
constraints and rules and other applicable standard practices
A methodology will be developed to classify the condition in terms of importance /urgency. This
will identify the work that will be undertaken by the contractor as part of this contract.
Survey and design to identify and locating new Auto reclosures and sectionalizer, load break
switches and fault passage indicators that will be installed in the MV network under the scope of
the project. The following considerations shall be taken during the location identification work:
Part 2- Employer’s Requirements 10
• Consider identifying the location of autoreclosers to be installed on the outgoing lines from
towns to nearby villages. These autoreclosers are used to protect the downstream network
from unnecessary interruption caused by any fault that happens out of the cities.
• Consider identifying locations for Auto reclosure and line sectionalizers integrated for
switching operation to isolate faults happening within the network. These devices
(autorecloser and line sectionalizers) will be connected in a way to communicate and
coordinate in order to isolate faulty branches of MV lines/networks and automatically
restore services among the healthy part of the network.
• Consider identifying the location of load break switches , fault passage indicators and
section switches design parameters, considerations and preliminary designs.
The contractor shall produce and submit the drawings with the route clearly marked.
• the required drawings for the identification to obtain the way leaves from the authority and
• Once the clearance has been received the required drawings and pegging for the installation
as described in the installation specification.
• Identify locations of new and rehabilitated Distribution Transformers
Part 2- Employer’s Requirements 11
The contractor shall identify during the course of the survey the positions of the installation of new
distribution Transformers, pole mounted and ground mounted. The contractor shall also identify
the locations of the transformers to be rehabilitated if these locations need to be at a different place
than the existing Distribution Transformers to be rehabilitated.
The output will provide the required drawings to ensure that the necessary way leaves are obtained
from the local authority and the drawings for the installation records for the distribution
transformers.
GPS Survey
The activities to be performed under sub-task are listed below.
Design Documentation
The contractor shall submit for approval electromechanical design of overhead lines comprising
detailed line routing and pole spotting with background map line profiles pole loading and sag
tables by applying different load cases.
Design of cable trenches including duct and pipes for street crossings
Details of location, and foundation design for the soil type ,Auto reclosure, sectionalizer and load
break Switch, ,including cable ducts,
Design of pole mounted transformer single line diagram, block diagrams, wiring diagram.
Other structures /designs required for site specific conditions like double line, LV under MV, fibre
optic cables installation, street lights etc to be installed on the concrete poles.
The contractor shall prepare all documentation in accordance with following:
• The size of all documents and drawings shall conform to the ISO standards,
• A1 594mm*841mm, A2 420mm*594mm
• A3 297mm*420mm, A4 210mm*297mm
• Schematic diagrams shall be of A3 or A4.
Part 2- Employer’s Requirements 13
Digital Documentation
Whenever the documents have been produced by means of a computer, the documentation shall
also be submitted on digital media, in the form of CD-ROM.
The digital version of documentation shall be submitted at various stages.The first stage when
documents are submitted for foundation and erection.The Second stage when document for
installation and conductor stringing
The last stage shall be as built documentation.
Design documents shall be produced in AutoCad using software version 2021.
As built Documentation
The contractor shall be prepared as built drawing, & documents in GIS (Quantum or Arch) and
MS words respectively. And also the contractor shall be prepared an asset database under scope
of the project.
Asset database is a basic prerequisite for implementation of Network analysis & simulation for
network planning. The Task of building a GIS database consists of the following activities listed
below.
Porting
This includes the GIS mapping of the Network.
Part 2- Employer’s Requirements 14
The activity under this task is GIS mapping of the network and loaded on Computer hardware.
Updating GIS
Updating the GIS map and database is needed at the end of project completion. The activities under
this sub task are:
Supply of Items
This part of the BOQ includes the supply of materials and equipment and delivery to the
contractor’s stores for use in the project. All the materials and equipment will remain under the
control of the contractor. The costs shall include the design, manufacture, testing according to
specifications, insurance and delivery to contractor’s stores and to the site. Costs shall be provided
for each type of equipment such as conductor Size (Sq.mm), pole types, transformer Size and
generally as provided in the BOQs. The supply of materials and equipment will include:
Installation of Items
The scope of works for the project is identified by the following categorization:
The item includes an appropriate length of XLPE 3x1x240mm2 including all cable accessories and
sealing ends including laying installation and proper termination at both ends.
✓ Preparing the Cable Bed with a protection filling of selected riddled sand or similar
✓ Laying the required cables in the Cable trench
✓ Primary filling with a protection filling of selected riddled sand or similar
✓ Place the yellow plastic Cable Protection sheets over the protection filling
✓ Backfilling of the cable trench
✓ Laying of the Cable marking (warnings tapes)
✓ Restore the surface to its former conditions
✓ GPS measuring of the cables and associated equipments
✓ All joints and terminations shall be well documented
✓ Perform required tests on the equipment and of the filling material
✓ Commissioning
✓ Safety arrangements to avoid accidents while the cable trench is open
• The costs will include any insurance for the transport to the site, loss and installation works,
and all labour. It will also include any joints along the route, cable testing and
commissioning.
MV OH Line Installation
New built and Rehabilitation overhead MV line erection:
The following works shall be performed and can be performed in the existing or in a new line route
a. Erection of new concrete poles including all associated equipment as cross arms, insulators
fittings, stays wires, earthings etc.
b. Installation and connection of Required XLPE covered AAAC conductors
c. Recording GPS points of the poles and associated equipment
d. Perform the required tests on all equipment before installation
e. Test and Commissioning of installed equipment
The following works shall be performed:
Generally, the works to be carried out is inclusive but not limited to design, supply & transport of
purchased materials to work site, erection, testing and commissioning of the following:
• MV OH lines with insulated conductors on spun concrete poles. The conductor Size
(Sq.mm) shall be determined by the Contractor after load flow analysis and selected from
the BOQ schedule and also described in the relevant technical schedules.
• The insulated conductors will be installed according to the manufacturer’s
recommendations, IEC international standards and Equivalent standard. It includes all the
lightning and earthing protection requirements to ensure that the covered cable is fully
protected.
Part 2- Employer’s Requirements 19
• Connection of new MV line with the newly installed and rehabilitated distribution
transformers
• Construction of new MV line from the substations as per approved drawings
• Contractors shall submit OH Line installation design for Employer’s review and approval
• In case of service outage to customers for longer than 8 hours due to on-going works under
the Contract, the Contractor shall have total backup for emergency supply
• The emergency supply should be solved with the existing network by arranging the
necessary switching operations. In the second range by use of temporary solutions as bypass
cables, lines, switchgear etc. to be arranged by the Contractor in the presence of Client
Representative. (Refer to the workplace safety guidance Section 4)
The pole installation will be handled in two parts namely a) Pole planting and b) Dressing of Poles.
The contractor should provide distribution construction and design manual based on the
specification in Installation of distribution lines and approved designs that will be approved by the
client before the installation work is started and the poles will be installed accordingly
Poles Planting
Contractors shall submit pole planting design for Employer’s review and approval.
The works shall include planting of poles for construction & rehabilitation of MV networks and
for the support of the networks and equipment as above.
Poles planting shall be according to specifications given and approved design. The pole planting
shall include the digging of the hole (or pit), transport of the pole to the site, erection of the pole,
earthing of the pole, Concreting of pole foundation with or without reinforcement bar, and the
compaction/closing of the pole foundation. And Pole planting cost shall include pole planting
design, and all the materials and activities listed above.
If Installation of double MV Lines/Feeders is needed, the cost of pole dressing shall be twice of
the respective single pole dressing type.
The Contractors shall submit design of installation of new distribution transformer for Employer’s
review and approval.
It includes supply, installation of double Cross arms Transformer and LV distribution Box base,
installation of distribution transformers and LV distribution box including all required
cabling/wiring, and all balance materials and works listed under dressing of transformer’s poles.
Installation of new Pole mounted Distribution Transformers will include:
• The installation of a new double pole structure, at a selected location during survey. The
double pole structure will be fully dressed as described under transformer pole dressing.
• The transport and installation of new transformer to the site
• Oil testing will be done after transportation of Transformers before installation.
• Installation of an LV distribution box on the pole below the transformer.
Trafo rating Conductor No. Of Shape of the Insulation colour Color of Armour
size mm cores conductor Outer sheath
315 KVA 3x240+1x 4 Stranded Red, Yellow, Grey/Black
and Above 120 Sector shaped Blue & Black
• Oil testing will be done before installation of every transformers after moved to the site
Cost of Installation of new distribution transformers shall include design of distribution transformer
installation, all activities listed above.
The cost of supply Distribution transformers and other accessory materials which shall be quoted
separately under supply part as specified in BOQ
transformers. Rehabilitation of a transformer shall mean the complete replacement of the pole
structure ,installing new LV Distribution Box under the existing transformer and fixing the
necessary fittings (including protection equipment such a
Cost of Transformer’s poles planting shall be included under pole planting cost.
• The installation of a new double pole structure, at selected location during survey to be
agreed with the client to suit to connect to existing LV network. The double pole structure
will be fully dressed as described under transformer pole dressing.
• The transport and installation of the required transformer that has been removed temporarily
before reusing.
• The contractor shall undertake removal of the existing transformer cleaning up, before
reusing, and stopping superficial leakages if any, but not including transformer opening and
overhaul.
• Installation of a new LV distribution box on the pole below the transformer.
Before reinstalling the existing to be rehabilitated transformer, the contractor should do the
following test to be approved by Employer.
• Visual inspection to identify leaky gaskets, broken bushings, corrosion, etc.;
• Insulation or resistance tests;
• Oil tests
• Rated voltage and current tests; and
• load-loss tests
Contractor will need mobile transformers or generators equivalent to 315KVA as a temporary
power supply to make own arrangements if it can take 2-3 days for rehabilitation work of the
existing transformer.
requirement of construction and installation from the contractor. After the construction and
installation are completed, the Employer’s Engineer shall disconnect the ground leads and then
charge the line. The Contractor shall not pay any fees for compensations to the employer or any
departments of the employer or any authority due to the power interruption required for
construction and installation.
However, the contractor shall be responsible for the damages to the Employer’s equipment
and personnel caused by the contractor’s mistake when charging and energizing. And if the
contractor take much hours for power restoration beyond the daily schedule then
The contractor shall pay to the Employer for the extra hours of unsold electric power as per the
Employer national Tariff.
The following dismantling/demolition works and handover to EEU of the materials shall be
performed:
a. Dismantling of the existing conductors
b. Dismantling the existing poles including cross arms, insulators, fittings, stay wires and all
associated equipment
c.
d. All existing MV networks replaced by the new one shall be dismantled, transported
and handed over to EEU stores.
No DISMANTLING SHOULD BE DONE WITHOUT SUPERVISION OF EEU. A detailed
mechanism will be established between the contractor and the client for the best way of handling
this handover. Any materials found to be missing from the dismantling survey list will be charged
to the contractor at the scrap value based on weight, and missing transformers will be charged
based on their KVA rating, both at the current price at the time of contract signing.
materials found to be missing from the dismantling survey list will be charged to the contractor at
the scrap value based on weight, and missing transformers will be charged based on their KVA
rating, both at the current price at the time of contract signing.
Warning labels
Text on warning labels shall be approved by the Engineer.
Warning labels shall have red lightning symbols.
Warning labels shall be mounted on all dangerous parts of the installation:
Terminals
All terminals of apparatus or apparatus units shall be clearly marked. However, this marking may
be omitted when the design and arrangement of the apparatus is such that a marking is obviously
unnecessary.
Control equipment
All instruments, indicating devices and control devices shall have identification markings in plain
text or simple symbols or colours. Control devices shall in addition have marking of control
positions (e.g. MANUAL/AUTOMATIC, OPEN/CLOSE) in plain text, simple symbols or colours.
Control cable terminals and, for small load circuits power terminals, shall be clearly marked for
identification.
The marking system shall be logically built up from letters and/or figures in one system consistently
used within the switchgear or control gear.
Internal wiring within switchgear, control gear or apparatus units shall have all wire ends marked,
the marking to include as a minimum the same marking as has the terminal to which the wire end
is connected. The marking shall be carried out with sleeves or similar markers. Tape is not
permitted.
Current and voltage circuits shall also have phase marking and, where necessary, polarity marking.
Protective earth wires shall be marked with green and yellow.
All electronic printed circuit boards shall have type marking. The electronic cubicles shall have
item marking for each circuit board for identification of the circuit board in the schematic diagram.
Lot 2- Melka Werer, Melka Sadi, Hartishek ,Kebribeyah ,Shinilee, Togochale, Aleta wendo ,
Yirgalem , Sawula , Bonga, Tepi Towns; 15/33kV lines Design , supply, installation on site,
testing and commissioning of MV Overhead line & Under Ground cables, Installation of new
distribution transformers, MV line Equipment rehabilitation of exiting Transformers and
connecting with the existing loads, removal of existing (replaced) networks.
For all the towns the distribution network planned based on the actual existing location however,
during final design route path may be changed.
Rehabili
New Load
Final ScopeMV in tated Autorec Section No.of Feeders SW per
Name transfor Beak FPI MV SW
of Towns KM Transfo losure Switch Feeders per lot Lot
mer switch
rmer
Holeta 103.7 33 9 4 4 15 15 4 0
Fitche 58.91 32 8 4 2 12 6 3 1
Legetafo 95.06 46 6 4 3 18 18 3 2
3
Lot 1 Shambu 31.2 10 8 2 1 8 5 2 18 0
Agaro 30.4 15 4 2 1 7 5 2 0
Weliso 43.96 23 10 4 3 9 9 4 0
Batu 76.4 35 3 3 3 9 9 3 0
439.63 194 48 23 17 78 67 21 18 3 3
Melka Werer 23.9 4 8 1 1 11 6 1 0
Melka Sedi 18.3 1 2 1 1 4 2 1 0
Hartishek 30.6 7 4 1 1 2 1 1 0
Kebribeyah 66.62 6 3 1 0 2 1 1 0
Shinilee 14.5 6 1 1 0 3 1 1 0
Lot 2 Togochale 78 4 7 1 0 3 2 1 17 0 1
Aleta wendo 29.9 13 2 1 1 5 5 1 0
Yirgalem 55.55 26 6 3 2 9 8 3 0
Sawula 48.4 27 4 3 1 7 2 3 0
Bonga 47.88 16 9 3 3 13 5 3 1
Tepi 26.5 9 6 1 1 6 4 1 0
440.15 119 52 17 11 65 37 17 17 1 1
Grand Total 879.78 313 100 40 28 143 104 38 35 4 4
Part 2- Employer’s Requirements 29
Rehabila
New Load
Towns Substatio Voltage MV in tion Description Autorecl Section Switchin
No. Region District Feeder Transfor Break FPI
name n , kV km Transfor of Works osure Switch g Station
mer Switch
mer
Holeta
1 26.52 2 8 Feeder 1 1 3 3 0
Holeta L1
Upgrading &
Finfine and
Holeta 15 Transformer
Oromiya zuriya Addis Holeta
2 23.72 7 7 rehabilitatio 1 1 4 4 0
Alem L2
n
4 K03 28.29 0 8 1 1 4 4 0
3 K06 25.17 0 10 1 1 4 4 0
Total 103.7 9 33 4 4 15 15 0
Note :-
∙ The Drawings of the feeders are attached in Appendix C
∙ The optimum location of Line equipment’s might be determined after final (detail) design of the network.
Part 2- Employer’s Requirements 30
Part 2- Employer’s Requirements 31
Rehabilt
New Descripti Load
Towns Substatio Voltage, MV in ation Autorecl Section Switchin
No. Region District Feeder Transfor on of Break FPI
name n kV km Transfor osure Switch g Station
mer Works Switch
mer
1 Zewaye 26.699 1 17 1 1 4 4 0
Feeder
Upgradin
g&
2 Batu Oromia Adama Batu Industry 15 35.06 1 13 Transfor 1 1 4 4 0
mer
rehabilit
ation
3 Hostick 14.641 1 5 1 1 1 1 0
Total 0 76.4 3 35 3 3 9 9 0
Note :-
∙ The Drawings of the feeders are attached in Appendix C
∙ The optimum location of Line equipments might be determined after final (detail) design of the network.
Part 2- Employer’s Requirements 44
Part 2- Employer’s Requirements 45
Part 2- Employer’s Requirements 46
Rehabilit
New Descripti Load
Towns Substatio Voltage, MV in ation Autorecl Section Switchin
No. Region District Feeder Transfor on of Break FPI
name n kV km Transfor osure Switch g Station
mer Works Switch
mer
Feeder
Upgradin
g&
Diredaw
1 Shinele Somali Jijiga Feeder 2 15 14.5 1 6 Transfor 1 0 3 1 0
a
mer
rehabilit
ation
Total 14.5 1 6 1 0 3 1 0
Note :-
∙ The Drawings of the feeders are attached in Appendix C
∙ The optimum location of Line equipments might be determined after final (detail) design of the network.
Feeder
Upgrading &
1 Togochale Somali Jijiga Jijiga Feeder 2 33 78 7 4 2 0 3 2 0
Transformer
rehabilitation
Total 78 7 4 2 0 3 2 0
Note :-
∙ The Drawings of the feeders are attached in Appendix C
∙ The optimum location of Line equipments might be determined after final (detail) design of the network.
Part 2- Employer’s Requirements 51
Rehabilit
New Descripti Load
Towns Substatio Voltage, MV in ated Autorecl Section Switchin
No. Region District Feeder Transfor on of Break FPI
name n kV km Transfor osure Switch g Station
mer Works Switch
mer
Feeder
Upgradin
1 YRG 1 23 2 4 g& 1 1 3 3 0
Yirgalem Sidama Hawassa Yirgalem 15 Transfor
mer
rehabilit
2 YRG 2 23 3 20 1 1 5 4 0
ation
3 YRG 3 9.9 1 2 1 0 1 1 0
Total 56 6 26 3 2 9 8 0
Note :-
∙ The Drawings of the feeders are attached in Appendix C
∙ The optimum location of Line equipments might be determined after final (detail) design of the network.
Part 2- Employer’s Requirements 53
Part 2- Employer’s Requirements 54
Rehabilit
New Descripti Load
Towns Substatio Voltage, MV in ated Autorecl Section Switchin
No. Region District Feeder Transfor on of Break FPI
name n kV km Transfor osure Switch g Station
mer Works Switch
mer
Feeder
Upgradin
1 South SAW 1 10.8 1 0 g& 1 0 1 0 0
Arbamin
Sawla West Sawla 33 Transfor
ch
Ethiopia mer
rehabilit
2 SAW 2 25 2 20 1 1 5 2 0
ation
3 SAW 3 12.6 1 7 1 0 1 0 0
Total 48.4 4 27 3 1 7 2 0
Note :-
∙ The Drawings of the feeders are attached in Appendix C
∙ The optimum location of Line equipments might be determined after final (detail) design of the network.
Part 2- Employer’s Requirements 56
Part 2- Employer’s Requirements 57
Feeder
Bonga 15 36.1 7 16 Upgradin 2 1 9 3 1
1 South g&
Bonga West Bonga Bonga Transfor
Ethiopia Bonga mer
universit 33 3.57 1 0 rehabilit 1 1 3 2 0
2 y ation
3 Miratelo 33 8.26 1 0 1 1 1 0 0
Total 47.9 9 16 4 3 13 5 1
Note :-
∙ The Drawings of the feeders are attached in Appendix C
∙ The optimum location of Line equipments might be determined after final (detail) design of the network.
Part 2- Employer’s Requirements 58
Part 2- Employer’s Requirements 59
TOOLS
To ensure that the system will be enhanced to provide improved security of supplies and improved
reliability, the utility will have to improve the operation and maintenance following the hand over.
To ensure this the contractor will purchase new tools and equipment (for the items stated below),
to use for the installation of the facilities and following the completion of works these items will
be handed over, to EEU free of cost.
The contractor will have to calculate and include the price of these tools and equipment accordingly
in his bid.
The tools that will have to be handed over are stated in the following subsections within.
For the balance of the tools, equipment and materials at the end of the project the client reserves
the right to purchase these items at mutually agreed prices, without any commitment on either
party.
Should these additional items be purchased by the client any taxes and duties shall be payable by
the client.
• Tools for erection and stringing of medium voltage overhead lines with XLPE covered
AAA conductors including jointing and terminating of conductors.
• All kinds of hydraulic, pneumatic and electric tools and their accessories, tensioning tools
and pulling wires, cutting tools, rollers, tightening tools a torque wrenches, spanners and
other special tools.
• The related tool set shall also include appropriated safety equipment as safety belts,
helmets, and gloves, climbing equipment appropriated for concrete poles.
The tool sets shall not include any motorised equipment, vehicles, cranes, generators, compressors
or other very heavy equipment unless so stated separately.
The tools shall be handed over in reasonable order commensurate to the expected fair wear and
tear following the installation of works.
If the tools are expected to be damaged or not last for the installation then additional new set will
have to be ordered and handed over to the client to ensure that a complete working set is handed
over to the utility to continue with the operation and maintenance of the system.
Equipment
The following must be available for appropriate phases of construction:
The following must be available per lot for appropriate phases of construction:
Tools
Part 2- Employer’s Requirements 65
5. GPS instruments 7 11 18
The Bidder shall provide further details of proposed items of equipment using the relevant Form in
Section IV.
Note: The total number of equipment shall be equal to the number of sites during construction
Part 2- Employer’s Requirements 66
In choosing materials and their finishes, due regard shall be given to the humid tropical conditions
under which the distribution lines will operate. In particular the wooden materials shall be dipped
in an anti-termite solution prior to shipment.
Outdoor material and equipment shall be designed and protected for use in exposed, industrially
polluted atmosphere.
Indoor materials and equipment shall be designed and protected for use in buildings, which may
be frequently wet and damp.
All material and equipment to be used shall be in conformance to this Technical Specifications.
Equipment shall be designed for a 40 year life and to facilitate inspection, repairs and maintenance
where continuity of operation is the prime consideration. All apparatus shall also be designed to
ensure satisfactory operation under the atmospheric conditions prevailing at site and under such
sudden variation of load and voltage as may be met with under working conditions on the system,
including those due to fault and short circuit.
The design of the equipment shall also incorporate all reasonable precautions and provisions for
the safety of those concerned in the operation and maintenance of equipment, and of associated
sub-assemblies. Particular attention shall be given to ease of maintenance and fault finding. Test
points and components requiring testing, adjustment or anticipated replacement shall be readily
accessible.
All equipment shall be designed to obviate the risk of accidental short circuit due to animals,
reptiles, birds, insects, mites, rodents or micro-organisms. All equipment shall be designed to
prevent accidental contact with live parts. All equipment shall be designed to operate without
Part 2- Employer’s Requirements 68
undue vibration and with the least practicable amount of noise. All equipment shall be designed to
minimize the risk of fire and any damage that may be caused in the event of fire. Where main and
standby equipment is specified, each shall be housed in separate cubicles.
The equipment and system designs shall incorporate all reasonable precautions and provision for
the safety of those concerned in the erection, operation and maintenance of the works and of
associated works supplied under other contracts. The use of polychlorinated biphenyls (PCBs) is
not permitted in any of the equipment being supplied.
All outdoor apparatus including bushings, insulators and fittings, etc. shall be designed so that
water cannot collect at any point.
All busbars, connections, isolators, fuses, contacts, cable boxes, trunking connections etc. which
form part of the Works shall not exceed the temperature rise values specified in the relevant IEC
publication or equivalent Standard, when operating continuously and at the specified IEC rating or
under short-circuit conditions under the ambient conditions encountered on site.
All rubbing or wearing surfaces shall be machine surfaced. Joints employing a gasket material
shall be so constructed that the packing is maintained under sufficient compression in all parts, so
that an efficient joint can be made without the use of jointing compounds. Gasket material shall be
of the minimum thickness necessary and of proven composition when operating under the
environmental conditions prevailing on site.
Outdoor kiosks, cubicles, etc. shall be adequately ventilated to restrict condensation and provided
with suitable for all weather temperatures. Where ventilation is provided, disposable filters shall
be fitted to prevent dust infiltration. Doors and gaskets shall be waterproof and dust proof.
Design calculations shall be prepared and submitted showing clearly details of all assumptions
made, sources of formulae used and International Specifications and Standards applicable.
Calculation shall be made in accordance with the recommendations and methodology of IEEE 738
and IEC 60287 with the following parameters. However, the contractor shall be required to design
the system/sub-system/components subject to acceptance and approval by the Engineer/Consultant.
Loading Calculations
The conditions stated below shall be used for mechanical loading calculations.
Everyday temperature °C 25
Minimum temperature °C 4
Safety Factors
Safety factors stated below shall be used for mechanical loading calculations.
Conductor system (maximum load) 2.5
Foundations 2.5
Nominal
Maximum Short Circuit LI Withstand PF Withstand
System
System Voltage Level Voltage Voltage
Voltage
kV kV kA kV kV
0.4 0.6 40 - 3/3.63
15 17.5 25 95/115 38/46
33 36 31.5 170/205 70/85
45 52 31.5 250/297 95/115
66 72.5 31.5 325/385 140/170
Part 2- Employer’s Requirements 71
Internal surfaces of equipment and accessories shall be sealed off where necessary by means of
gaskets and blanking off plates.
Packing cases and packing materials shall remain the property of Employer.
All crates, boxes, bundles, etc., required for packing shall be carefully handled at all times and shall
not be tipped, dumped, thrown or pushed from, onto or in any form of transport, during storage or
at any other time.
All bright parts, liable to rust, shall receive a coat of rust-resistant composition and shall be suitably
protected.
The Contractor shall take special precautions to protect bearing journals where they rest on wooden
or other supports likely to contain moisture. At such points, wrapping shall be used which are
impregnated with rust-resistant composition and of sufficient strength to resist chafing through,
when subject to the pressure and movement likely to occur in transit.
All arrangements shall be made for all forms of transport used, to ensure that all items are
transported safely and on time to their destination.
Only reputable carriers, which have regular schedules to the required destination, shall be used.
All facilities, reliability and record of carriers, ports and other depots shall be investigated and
arrangements shall be made to supplement any deficiencies in handling equipment and other
facilities. The number of carriers shall be kept to a minimum and double handling at ports and
depots shall be avoided as far as possible.
The Contractor shall ensure that all warehouses used en route, are suitable and that all items can be
stored without any deterioration or damage from water, sunlight, dust or any other cause.
Consignments shall be sent in complete units and sending partial consignments shall be avoided
when possible.
The Contractor shall make all the necessary arrangements for customs clearance in Ethiopia, the
country of origin, and any countries through which goods pass.
The Contractor shall obtain all the necessary export and import permits and any other documents
required for the transportation of goods. Copies of all forms and documents relating to customs,
permits, packing lists, bills of landing and insurance, etc., shall be forwarded to the Employer.
All parts shall be clearly marked to facilitate easy sorting and erection.
All parts shall be boxed in suitable crates or containers to facilitate handling in a safe and secure
manner. Drain holes shall be provided and secure manner. Drain holes shall be provided in crate
bottoms where necessary. Each crate or container shall be marked clearly on the outside of the
crate to show where the weight is bearing and the correct position for the slings. Each crate or
container shall also be marked with the contract number and port of destination.
Material intended for different locations in Ethiopia shall be packed separately and packages shall
be clearly identifying the destination.
Part 2- Employer’s Requirements 73
It shall be ensured that all labels, marking and colour coding on crates, boxes or containers are
clear, legible, and waterproof, not affected by sunlight and are securely fixed or painted thereon.
Standard markings such “Lift here”, “No hooks”, “Fragile”, etc. shall be applied as necessary. Oil,
Paint and other hazardous or inflammable materials shall be marked accordingly, including “flash
point”, recommended storage temperatures and detailed instructions for use.
Packing Case Labeling
Each packing case shall be indelibly marked with its own:
• individual Serial Number;
• the Employer’s Name;
• the Contract Number;
• the Contractor’s or Contractors’ Name;
• Contractor’s or Contractors’ Agent in Ethiopia and his address;
• gross and net weight in kilograms; case measurements
• descriptions of contents;
• country of origin;
• and all necessary Slinging and Stacking instructions;
Each case shall contain a fully detailed packing list in a sealed waterproof envelope. Three copies
of each packing list shall be sent to the Employer prior to dispatch.
Transport
The Contractor shall inform himself fully as to all available transport facilities, road width, and
axle load limitations, loading gauges and any other requirements and shall ensure that equipment
as packed for transport shall conform to the relevant limitations. Any cost arising from the use of
roads or tracks, including tolls, shall be borne by the Contractor.
The Contractor shall ensure by his own inquiries that the facilities available for unloading and
bearing capacities of wharf’s at the port of entry is adequate for his proposed plant and equipment.
The Contractor shall be responsible for obtaining from the relevant authorities all permissions
necessary to use docking, off-loading, highway, and bridge facilities required for the transportation
of contract materials and plant.
The Contractor shall be responsible for transport of all goods to the various sites including
importation, offloading, warehouse storage, etc., and all costs and expenses involved in transport
from the manufacturer’s works to the sites.
2.6 ADDITIONAL SPECIFIC REQUIREMENTS
In addition to the above specified packing, labeling and transport requirements, the following
additional requirements shall be adhered to for the listed equipment and materials.
Cables and Conductors
All Cables and Conductors referred to in Technical Specifications shall be placed on drums, reels
or delivered in coils as appropriate.
Part 2- Employer’s Requirements 74
Drums, reels and coils shall be labeled with the following in addition to the labeling requirements
stated above:
• Serial Number;
• cable/conductor type/size/stranding, etc.;
• number of cores;
• exact cable length;
• gross and net weight;
• year of manufacture;
• drum measurements;
• purchaser’s name;
• supplier’s name;
• drum dimensions;
• Contractor’s or Contractor’s agent in Ethiopia and his address;
• Contract number;
• Country of origin;
• And any necessary handling instructions.
This information shall be on fixed metal or plastic plates.
In the case of wooden drum the above information shall additionally be marked on the flange. The
position of the cable or conductor nose and the direction for rolling as indicated by an arrow shall
be marked on the other flange. All markings shall be clearly and indelibly made.
The maximum weight of any loaded drum shall not exceed 3500 kg.
Each length of cable or conductor shall be durably sealed before shipment to prevent ingress of
moisture. The drums, reels and coils shall be lagged or covered with suitable material to provide
physical protection for the cables during transit and during storage and handling operations. The
lagging shall provide suitable protection against all climatic conditions prevailing during transport
and on site.
The drums or reels shall be non-returnable and shall have the following dimensions:
• max diameter 2280 mm;
• max width 1140 mm;
• Spindle hole 76 mm diameter.
The spindle hole shall be reinforced with galvanised steel plates. All accessories shall be carefully
packed so that they are fully protected during transport and handling operations and in storage.
Particular care should be exercised in packing and shipment to prevent damage or distortion of
members during transit. Normally bundles of steel material shall not exceed 1000 kilograms in
weight.
The Employer shall be present at the unloading of individual bundles upon delivery at the
designated delivery points.
The Contractor/Contractor shall advise the Employer at least 2 weeks in advance of delivery.
The bolts, nuts, washers, pack washer, spalnuts, Ubolts, plates, etc., shall be packed in bulk in
strong containers, suitable for lengthy storage without danger of white rust being formed. They
shall be segregated according to size and length.
The method of packing, shipping and marking shall be approved by the Employer.
All equipment/material, including accessories, shall be packed and securely clamped against
movement in robust wooden packing cases to ensure safe transit from the manufacturer's works to
the delivery sites.
Equipment/material liable to deterioration by seawater, moisture, or ingress of foreign matter shall
be totally sealed in strong polythene bags.
Each packing case shall be indelibly marked with its own individual serial number, the Employer's
name, the Contract number, the Contractor's name, Contractor's Agent in Ethiopia and his address,
gross and net weights in kilogram’s, description of contents, case measurements, country of origin,
and all necessary slinging and stacking instructions.
Each case shall contain a fully detailed packing list in a sealed waterproof envelope.
Three copies of each packing list shall be sent to the Employer prior to dispatch.
2.7 Erection tools for the use of the Employer
At the end of the Construction period, the Contractor shall hand over to the Employer complete
sets of erection tools and equipment in type and quantities specified in the Scope of Work.
The sets of tools to be handed over by the Contractor shall be delivered to the project in new
condition. The Bidder shall submit with his bid a separate, priced detailed/itemized price list of
tools as “supply only” that he is intending to buy for the implementation of the project.
The final list of each tool set shall be submitted for approval prior to shipping of tools.
The tool sets shall comprise the whole range of tools necessary for doing all works for the erection
stages as necessary for the respective work.
The tools shall include
▪ Tools for erection and stringing of medium voltage overhead lines with XLPE
covered AAA conductors including jointing and terminating of conductors.
Part 2- Employer’s Requirements 76
▪ All kinds of hydraulic, pneumatic and electric tools and their accessories,
tensioning tools and pulling wires, cutting tools, rollers, tightening tools a torque wrenches,
spanners and other special tools.
▪ The related tool set shall also include appropriated safety equipment as safety
belts, helmets, and gloves, climbing equipment appropriated for concrete poles.
The tool sets shall not include any motorized equipment, vehicles, cranes, generators, compressors
or other very heavy equipment unless so stated separately.
The tools shall be handed over in reasonable order commensurate to the expected fair wear and tear
following the installation of works.
If the tools are expected to be damaged or not last for the installation then additional new set will
have to be ordered and handed over to the client to ensure that a complete working set is handed
over to the utility to continue with the operation and maintenance of the system.
2.8 Bid Submittal Requirements
Technical Submittals Required with the Bid
Technical Submittals required with the Bid shall include:
• Guaranteed Technical Characteristic Schedules provided
• (Bidders may use additional pages annexed to the Schedule to complete their response. No
alteration shall be made to the Schedule)
• outlined dimension/general arrangement drawings showing layout of components;
• descriptive literature giving full technical details of equipment offered;
• Type Test Certificates;
• detailed reference lists of clients/customers already using equipment offered;
• details of Manufacturer’s Quality Assurance Policy/ Programme;
• deviations from specifications;
• Recommended spares, special tools and test equipment.
Technical submittals required following award of Contract include:
• detailed dimensions/arrangement/layout/schematic/wiring drawings of equipment;(for
simple products)
• general arrangement drawings, including shipping details, outline details, and foundation
loading requirements; (for complex products)
• interface drawings including any special mounting and wiring requirements; (where
appropriate)
• detailed drawings including assembly, nameplate, and wiring and control schematic
drawings; (switchgear and complex products)
• detail installation and commissioning instructions;
• detail Civil Works drawings (where required);
• programme for production and testing;
• Factory Test Reports.
Part 2- Employer’s Requirements 77
When IEC, ISO, BS or National Standards are referred to the edition used shall be that current at
the date of Bid, together with any amendment issued to that date.
Where the use of a standard other than IEC, ISO or BSI is agreed then this standard shall be used,
where applicable. Where other standards are proposed in place of IEC, ISO or BSI Standards,
confirmation shall be provided that the provisions of the standards are equivalent to or exceed those
of the equivalent IEC, ISO or BSI standards.
Copies of any standards proposed in substitution for IEC, ISO or BSI standards must be submitted
with the Bid accompanied where necessary by English translations of the appropriate sections.
Notwithstanding any descriptions, drawings or illustrations which may have been submitted with
the Bid, all details other than those shown in the ‘Deviation from the Technical Specification
Schedule’ and approved by the Employer shall be deemed to be in accordance with the
Specification and the standard specifications and codes referred to therein.
No departures from the specification except those shown in the ‘Deviation from the Technical
Specification Schedule’ and approved by the Employer are to be made without the written approval
of the Employer.
These quality management requirements shall apply to all activities including design, procurement,
manufacturing, inspection, testing, packing, shipping, storage and commissioning (when
applicable).
Part 2- Employer’s Requirements 79
The Contractor and any major sub-suppliers shall also have Quality Systems certified as complying
with the requirements of ISO 9001 applicable to manufacturing and design of supplied materials.
Minor sub-suppliers should preferably have similar quality certification however, if they do not the
Contractor’s Quality System shall apply.
It is preferred the Contractor be certified as complying with ISO 14001 and regardless of any such
certification the management system must provide for all due care and responsible protection of
the environment and the specified environmental protection measures are not to be seen as a
limiting responsibilities in respect of environmental obligations.
Documents submitted by the Contractor, including those provided by sub-suppliers, in the course
execution of the Supply will not be accepted unless they include evidence that they have been
verified by the Contractor.
The Contractor shall clearly identify all quality records that will be used for the Contract. The
Employer may undertake an inspection or quality audit of the Contractor’s or sub-suppliers’
facilities at any time. Full quality records of all procurement and manufacture shall be made
available at the start of factory inspection and testing of equipment.
The Contractor shall have an overall documented Quality Assurance Plan capable of providing
assurance all equipment, materials and services meet the Employer requirements.
The Contractor shall have a quality assurance unit or at minimum a designated Quality Plan officer.
The Contractor shall perform periodic documented reviews of his Supply and quality controls to
assure conformance to the program.
If the Employer decides to witness the Factory Acceptance Test than the sample of up to 10% of
total produced volume of product shall be taken and subjected to the sample/ acceptance tests as
stated in relevant standards for that product.
In the event of any sample from any batch not passing these tests, an additional second and third
sample shall be taken from the same batch. If one of these also fails under test the batch from which
it has been taken shall be rejected in full.
All plant shall be subjected to all routine tests set out in relevant IEC standards, including any
optional tests which the Project Manager considers to be applicable. One item of each type of plant
shall be subjected to all type tests set out in relevant IEC standards. Type tests may be dispensed
with if the Contractor furnishes evidence to the satisfaction of the Project Manager that the relevant
type tests have already been performed on identical equipment at an independent testing laboratory
or witnessed by an independent testing agency.
testing agency and which confirm that the equipment has design performance equal to or better
than that specified.
Design performance tests shall be conducted on all major components, assemblies and sub-systems
over the full range of specified environmental and electricity supply condition.
Routine Tests
Routine tests shall be carried out on all components, sub-assemblies, assemblies and subsystems.
The Contractor's test plan shall fully describe all such routine tests. The routine tests shall include:
• All components and modules shall be inspected and tested for quality in accordance with
accepted sampling procedures. All sub-assemblies, assemblies, and subsystems shall be
individually inspected, tested and aligned or adjusted;
• All routine tests nominated in relevant international standards or recommended by the
manufacturers of each component or element of the computer subsystem and the man-machine
interface subsystem;
• Interface tests on every data modem and communications channel interface. Interface
characteristics shall be measured in accordance with the procedures and standard test circuits
described in the ITU-T recommendations;
Mandatory factory acceptance tests (FAT) shall be performed for all major electrical plant such as
distribution transformers, insulators, underground cables, and conductors and any other such
equipment that the Employer considers to require FAT. The specifications of individual equipment
that form part of these bid documents provide all equipment requiring FAT. From these
specifications, the Contractor shall prepare a comprehensive list of equipment that shall be subject
to FAT and shall submit for approval an inspection and test plan, and associated procedures and
record sheets, at least one month before the date of any planned factory tests.
The Contractor shall submit for approval an inspection and test plan, with associated procedures
and record sheets, at least one month before the date of any planned factory tests.
Factory test reports shall include current calibration records of all measuring apparatus used in the
tests.
No plant shall be dispatched from the factory to site prior to receiving the Project Manager’s
notification that the factory tests were satisfactory. The Project Manager may request that additional
Part 2- Employer’s Requirements 82
tests be conducted if he is not satisfied that the factory tests have demonstrated that the plant is
acceptable.
2
Prior to 56 days before the time Insulator
first shipment /10 Days
2
Prior to 56 days before the time Insulator
first shipment /10 Days
Company Name: Document No.
ETHIOPIAN ELECTRIC UTILITY EEU/EQRD/04-230
Title:
Issue No. Page 84 of 433
Technical Specifications for 15KV and 33KV Surge Arrestors. 1
Standard Title
IEC International Electro-technical Commission
IEC-60071-1 Insulation co-ordination Part 1 Definitions, principles
and rules
IEC-60071-2 Insulation co-ordination Part 2 Application guide
IEC 60099-4 Surge arresters - Part 4 Metal-oxide surge arresters
without gaps for a.c. systems
IEC 60099-5 Surge arresters - Part 5 Selection and application
recommendations
IEC TC 37 Artificial Pollution testing of Surge Arresters
IEEE C62.1 Surge Arresters for Alternating Current Power Circuits
NEMA LA1 Surge Arresters
BS EN ISO 1461 Hot dip galvanized coatings on iron and steel articles
DESIGN
The surge arresters shall be of the zinc oxide (ZnO) type without spark gaps. The surge
arresters shall be delivered complete with NEMA pattern mounting brackets for mounting
on steel cross arm and bearers. The surge arresters shall conform to IEC 60099-4 where
applicable together with draft IEC TC 37 WG4 suitable for given service conditions.
Use
The arresters will used to protect:
▪ Distribution transformers with the LIWV/BIL level of which are as
specified in the technical schedules.
▪ Interface between overhead line and cables
▪ Interface with substation at terminal poles
▪ Intermediate positions on distribution overhead lines
The surge arresters shall meet the following Performance Characteristics requirements:
Any weather-exposed steel parts shall be hot-dip galvanized.
Basic CHARACTERISTICSof Surge Arresters
Rated frequency 50 Hz 50 Hz
Signed: ___________________
Date: ____________________
Company: _________________
Company Stamp
SCOPE
This Specification covers the design, manufacturing, testing, supply, delivery and performance
requirements of 15kV and 33kV Pole mounted Dropout Fuses.
SYSTEM PARAMETERS& Service Conditions
REFERENCE StandardS
The equipment supplied shall conform to the latest edition of the appropriate IEC standards and/or
other recognized international standards. In particular:
Specification/ Title
Standard Number
IEC 60060 High Voltage Test Techniques
IEC 60129 Alternating Current disconnectors and Earth Switches
IEC 602822 High Voltage fuses. parts 2: Expulsion and similar fuses
IEC 60383 Tests on insulators of ceramic material or glass for
overhead lines with nominal voltage greater than 1000V
IEC 60437 Radio Interference test on high voltage insulators
IEC 60507 Artificial pollution tests on high voltage insulators to be
used on A.C. systems.
IEC 60694 Common specification for high voltage switchgear and
control gear standards.
NEMA SG2 High Voltage fuses.
IEEE C37.41 Design tests for high voltage fuses, distribution enclosed
single pole switches, fuse disconnecting switches and
accessories.
ANSI C37.42 American national Standard Specifications for
Distribution Cutouts and Fuse Links.
dESIGN
General
The dropout shall be designed and manufactured to IEC60282 and the requirements of this
specification. The dropout fuse shall be supplied as a complete unit incorporating the fuse base with
its fuse carrier. All current carrying parts be of electrolytic high conductivity copper with the
contacts hard drawn copper ad siliver-plated. The dropout fuse shall withstand the specified impulse
and power frequency voltages in all applicable mounting positions including angle mounting.
DEFINITION
Dropout Fuse
It is that in which the fuse holder automatically drops into an open position after the fuse has
interrupted the circuit.
Fuse Holder
A fuse holder is an assembly of a fuse tube together with parts necessary to enclose and provide
means of making contact with the conducting element and the fuse contacts. The fuse holder does
not include the fuse link.
Fuse Link
A fuse link is a replaceable part of the assembly, consisting of the conducting element. It is
usually to be replaced on circuit interruption to restore the fuse to the operating conditions.
Fuse link removing Eye
A hole in the fuse holder or fuse unit which is provided for receiving a fuse hook or switch hook
for inserting or removing the fuse into/out of the fuse support.
Terminal (Terminal Connector)
A terminal is a connector for attaching a conductor to electrical apparatus.
Rated Interrupting Current
The rated interrupting current of a fuse is the designated highest available R.M.S short-circuit
current at which the fuse is designed to perform its disconnection function under stated
conditions.
Recovery Voltage
Recovery voltage is the voltage, which occurs across the terminals of a pole of a circuit
interrupting device after an interruption of the current.
Break Distance
The break distance of a fuse or switch is the minimum open-gap distance between the live parts
when the fuse holder is in the open position.
ELECTRICAL PERFORMACE CHARACTERISTICS
The manufacturer shall submit Manufacturing Quality Assurance Plan (QAP) for approval & the
same shall be followed during manufacture and testing.
The material for final inspection shall be offered by the Supplier only under packed condition. The
owner shall select samples at random from the packed lot for carrying out acceptance tests.
Packing and Marking
The following information shall be legibly and indelibly marked on BOTH sides of the carton:
a) Manufacturer’s name and catalogue number
b) Rated Voltage and Current
c) Purchase Order Number
d) Description of contents and gross mass
e) Handling or lifting instructions where applicable
The following information shall be legibly and indelibly marked on the individual package:
a) Manufacturer’s name and catalogue number
b) Rated Voltage, Current and frequency.
c) Speed Class
d) Batch Number (Carton Only)
e) Precautions in handling (Link Only)
2 Country of
manufacture
3 Type
Pole Mounted
4 Type tested Yes
5 Standards IEC/ VDE
6 Rated operating Line kV 15
Voltage
7 Maximum Equipment kV 24
Voltage
8 Impulse withstand kVp 125
voltage (1.2/50 μs, dry)
phase to earth
9 Power frequency
withstand voltage (1
min., wet)
9.1 phase to earth kV 50
9.2 across isolating distance kV 76
10 Impulse withstand kVp
voltage (1.2/50 μs, dry)
10.1 phase to earth kV 75
10.2 Across isolating distance kV 95
11 Rated frequency Hz 50
12 Rated current A 100
13 Rated interrupt kA 12
capacity
14 Creepage distance Mm 525
phase to ground
15 Fuse type Link- K
current time
characteristics
16 Operation single phase
drop out fuse
is melted
2 Country of
manufacture
3 Type Pole Mounted
Date: ____________________
Company: _________________
Technical Specifications for single core Aluminium U/G Cables on 15kV system.
Scope
This specification covers the design, manufacture, testing and delivery of medium voltage of 15kV voltage
level, single core XLPE insulated underground cable having stranded compacted aluminium conductor,
Copper tape screen, armoured with aluminium wire, and extruded PVC over sheath.
The cable for the 15kV system shall be a standard with maximum cable rating voltage of 24kV (at mean sea
level - msl). This will cater for installations at altitudes up to 3000m.
Service Conditions
Item Parameter
Altitude 3000m above msl
Annual Rainfall 1250mm
Period of exceptional Rains June to September
Ambient Air Temperatures:
Average +300c
Minimum -50c
Maximum 500c
Relative Air Humidity 70%
Wind Velocity:
Maximum wind( height above ground level)
0-30m 35m/s
30-50m 45m/s
Isoceraunic Level Upto100 thunderstorm days/year
Seismic Zone Zone 4
Values
No Voltage Characteristics
Guaranteed Technical particulars (G.T.P.) for 15kV Single Core Aluminum U/G
Cable (1X240mm2)
GTP for 15kV Under Ground single core Offered
S.No Unit Required Value
Aluminum Cable (1X240mm2) Value
1 Manufacturer
2 Country of origin
3 Type designation U.G.
IEC60502,
4 Standard IEC, BS
IEC60228,BS50182
5 System rated Voltage kV 15
5.1 Maximum System rated Voltage kV 17.5
5.2 Maximum cable rating Voltage kV 24
5.3 Cable voltage kV Uo/U/Um(12/20/24)
GTP for 15kV Under Ground single core Offered
S.No Unit Required Value
Aluminum Cable (1X240mm2) Value
6 Number of cores Single
6.1 Minimum conductivity of cable
7 Number of wires in each conductor number 30
8 Diameter of conductor after compaction mm 17.6-19.2
9 Shape of conductor Compacted stranded
conductor with the
circular shape as per
IEC60228-2004 Table 2-
class 2
10 Normal cross sectional area of Cable mm² 1Cx240
11 Conductor details
11.1 Material Aluminum
11.2 Design IEC 60228
11.3 overall diameter mm
12 Conductor screen
Extruded XLPE semi
12.1 Material
conductive
12.2 thickness, mm 1mm
Maximum dielectric stress at conductor
13 kV/cm
screen (assumed smooth)
14 Insulation
14.1 Material XLPE
minimum radial thickness of insulation
14.2 between conductor screen & core screen mm 5.5
(R01)
15 Insulation Screen
Extruded XLPE semi
15.1 material
conductive
15.2 Thickness 1mm
16 Metalic screen
16.1 material Copper
16.2 Thickness (R02) mm 0.1
Maximum DC resistance of conductor of
17 cable at 20°C (respectively as per Number 3 of ohm/km 0.125
cable lists)
Maximum AC resistance of conductor/ km of
18 cable at 90°C (respectively as per Number 3
of cable lists) ohm/km
Equivalent star reactance of three phase of
19 circuit of 50 Hz, (respectively as per Number ohm/km N/A
3 of cable lists)
GTP for 15kV Under Ground single core Offered
S.No Unit Required Value
Aluminum Cable (1X240mm2) Value
Maximum DC resistance of metallic screen of
20 cable at 20°C (respectively as per Number 3 ohm/km N/A
of cable lists)
Maximum electric capacitance per core of
21 cable (respectively as per Number 3 of cable µF N/A
lists)
Maximum charging current per conductor of
22 cable at nominal voltage, (respectively as per mA/km N/A
Number 3 of cable lists)
Current carrying capacity in soil at 20°C
23 A 415
(respectively as per Number 3 of cable lists)
Maximum value of tangent of dielectric loss
24 angle of cable at normal frequency at a N/A
conductor temperature of 20°C
Conductor short circuit current carrying
capacity (for 1 second) with cable loaded with
25 nominal current before short circuit and final kA/s 22.68
conductor temperature of 250°C (respectively
as per Number of cable lists)
Metallic sheath short circuit current carrying
capacity (for 1 second) with cable loaded with
26 kA/s N/A
nominal current before short circuit and final
sheath temperature of 250°C
Nominal overall diameter of complete cable,
27
mm
No smaller than 12
Minimum radius of bending in which cable
28 times of the outer
can be
sheath
28.1 laid direct in ground or in air
28.2 in ducts
with cable placed in position adjacent to joints
28.3 m
and terminations
28.4 laid direct in ground or in air m
28.5 in ducts m
with cable placed in position adjacent to joints
28.6 m
and terminations
29 Separation sheath/Bedding Material
29.1 Material extruded PVC or PE
29.2 minimum thickness mm 1.3
30 Galvanized aluminium alloy armor
GTP for 15kV Under Ground single core Offered
S.No Unit Required Value
Aluminum Cable (1X240mm2) Value
a. Number of strips/wire
b. Size (thickness x width) mm
c. diameter of aluminum alloy armor mm 2.5
31 Nominal Thickness of PVC Sheath
a. Minimum thickness mm 2.4
b. Colour Black
c. Weather proof paint mm
32 End Cap
33 operating factor for ambient temperature in
a. At 300c
b. At 350c
c. At 400c
d. At 450c
Group factor for following number of cables
34
laid
a. 3 numbers
b. 4 numbers
c. 5 numbers
d. 6 numbers
35 Standard delivery length per drum m 500±2%
36 Weight per drum kg
Maximum Drum length that can be provided
37 m
by the manufacturer
38 Embossing Manufacturer name,
buyer name, type &
voltage rating of
cable, month-year of
Mfg, P.O.No. & date
39 Sequential length at every mater To be provided by
printing only in White
colour
Signed: __________________
Date ___________________
Company: __________________
Technical Specifications for single core Aluminium U/G Cables on 33kV system.
Scope
This specification covers the design, manufacture, testing and delivery of medium voltage of 33kV voltage
level, single core XLPE insulated underground cable having stranded compacted aluminium conductor,
Copper tape screen, armoured with aluminium wire, and extruded PVC over sheath.
The cable for the 33kV system shall be a standard with maximum cable rating voltage of 36kV (at mean sea
level - msl). This will cater for installations at altitudes up to 3000m.
Service Conditions
Item Parameter
Altitude 3000m above msl
Annual Rainfall 1250mm
Period of exceptional Rains June to September
Ambient Air Temperatures:
Average +300c
Minimum -50c
Maximum 500c
Relative Air Humidity 70%
Wind Velocity:
Maximum wind( height above ground level)
0-30m 35m/s
30-50m 45m/s
Isoceraunic Level Upto100 thunderstorm days/year
Seismic Zone Zone 4
Reference Standards
The cables supplied under this Section of the Contract shall conform to the latest edition of the appropriate
IEC standards or other recognized international standards, in particular:
IEC60060 High voltage test techniques
IEC60071 Insulation co-ordination
BS 7870-4.10 33kV stranded power cables
IEC60228 Conductors of insulated cables and their resistance
IEC60229 Tests on cable over sheaths
IEC60230 Impulse tests on cables and accessories
Power cables with extruded insulation and their accessories for rated voltages from 1
IEC60502
kV up to 30 kV
Common test methods for insulating and sheathing materials of electric cables and
IEC60811
optional cables
IEC60885 Electrical test methods for electric cables
IEC Power cable accessories with rated voltages up to 30 kV
ASTM D2303 Inclined plane non-tracking test method.
DIN/VDE0273 Cross linked Polyethylene Insulated Cables.
DIN 46391 Cable Delivery Drums
IEC 60183 Guide to the selection of high voltage cables
IEC 60332-3 Test on electric cables under fire condition, Test on Bunched wires or cables
Design and Construction
Construction Details:
The single core underground cable shall be designed for maximum voltage rating of 36kV. The cable shall
comprises of compacted stranded aluminium conductor, with extruded semi-conducting shielding, cross-
linked polyethylene insulation, semi-conducting shielding , copper tape screened, armoured with aluminium
alloy wire and the cable shall be bedded with extruded PVC, and sheathed overall with blue PVC.
Conductors
The conductor shall be a stranded circular compacted conductor of aluminium of cross-section as required
for cable class 2 conductors in accordance with IEC 60228.
Conductor Screen
The conductor screening shall be extruded semi-conducting material (Tapes are not acceptable) to exclude
all air voids. The screen should consist of a layer of at least 1mm thick extruded semi-conductive compound
bonded to the conductor.
Insulation
The insulation shall consist of high quality cross-linked polyethylene (XLPE) with suitable thickness for a
voltage rating of Uo/U/Um(19/33/36)kV which is used for 33 kV systems at 50 Hz. Uniform thickness of
insulation shall be within the permissible values as per IEC Standards; eccentricity check shall be carried
out to ensure this.
Insulation Screen
The insulation screen consists of an extruded layer of non-metallic, semiconducting compound
extruded over the insulation. The extruded semi-conducting layer shall consist of bonded or cold
strippable semi-conducting compound capable of removal for jointing or terminating. The screen
should consist of a layer of at least 1mm thick extruded semi-conductive compound bonded to the insulation.
Metal screen
The metal screen shall be double copper tapes. The minimum thickness of copper tape screen should be
0.1mm. The dimension, physical and electrical requirements of the copper tape shall be as per IEC standard.
Separation sheath/Bedding
The separation sheath comprises a layer of extruded PVC or PE applied under the armour .The
nominal thickness is calculated by 0.02Du + 0.6mm where Du is the fictitious diameter under the
sheath in mm. The nominal separation sheath thickness shall not be less than 1.2mm.
Armour
The armour consists of round aluminium alloy wire armour applied helically over an extruded separation
sheath. The armour diameter should be as per IEC60502-2-2014 Table 9.
Outer sheath
The over sheath shall consist of an extruded layer of blue PVC complying with the requirements of
compound ST2 type specified in IEC 60502. The outer sheath shall be spark tested in accordance with IEC
62230. The outer sheath shall be extruded PVC blue in colour, containing a termite repellent additive.
The nominal oversheath thickness is calculated by 0.035D+1 where D is the fictitiuous diameter
immediately under the oversheath in mm.
Values
No Voltage Characteristics
Date ___________________
Company: __________________
The Power Cable Joints and Terminations shall comply with the latest editions of and amendments
to, the standards/specifications listed below:
General
Joints and terminations shall be supplied in complete kit form with all materials and components
required to complete the installation. A complete set of instructions for the joint/termination shall
also be included in each kit.
Cold shrink, pre-moulded joints/terminations or a suitable alternative shall be offered for XLPE
cables and for transition joints.
Resin (acrylic or polyurethane) joints or suitable alternatives shall be offered for LV joints.
If accepted, supplier shall be requested to conduct one week training program for 20 jointers in
Ethiopia for joints and terminations that have not been specified here but have been established to
have equal performance as the ones specified.
All components shall be capable of being stored without damage or deterioration at temperatures
up to 50oC. The material expiry date shall be marked on all packages, where appropriate.
Details of all equipment, tools and protective clothing required to complete the joint/termination
shall be included with each joint termination.
MV Cable Types and Their Accessories
MV cables are either three or single core cables with round compact stranded aluminium or copper
conductor.
Three core MV cable has semi-conducting conductor shield, XLPE insulation, semi-conducting
insulation shield, copper screening tape or copper wire mesh screen, fillers and binding tape, three
core bedding, galvanized steel wire armor and PVC/HDPE over sheath as detailed in this
Specification.
Single core cable has semi-conducting conductor shield, XLPE insulation, semi-conducting
insulation shield, copper tape and wire screen, armor bedding, non-magnetic wire armor and
PVC/HDPE over sheath as detailed in this Specification.
Terminations, joints and other accessories for 15kV and 33kV cables shall be offered for the
following cable sizes:
• Straight Joint
• Transition (HYBRID) Joint
• Outdoor Termination
• Indoor Termination
Connectors and Terminals
Connectors and terminals shall of such design that they are not over stressed under normal cyclic
loading and fault conditions, and shall not limit the rating of the cables which they join.
The Employer is committed to the use of compression tools approved by Employer. The range of
connectors/terminals offered shall be suitable for compression by a range of dies interchangeable
with standard equipment’s, such as Pfisterer/Burndy/Klauke tools. The number of different dies
should be kept to a minimum.
The ends of connectors/terminals shall be suitably chamfered or coned to facilitate insertion of the
conductors. Connectors shall have a solid central barrier to facilitate the insertion of the Conductor
to the correct depth.
The following items of information shall be clearly stamped on each connector/terminal.
(a) Manufacturers’ name or trade mark and also the letters Employer.
(b) The conductor size (metric) for which the connector/terminal is suitable.
(e) The sequence of die action, i.e. the starting point and finishing point.
Compounds or greases for improving contact between the connector/terminal and the conductor are
permitted. They must, however, be chemically neutral to the connector/terminal and conductor
materials and must be pre-filled into the connectors/terminals, being supplied.
Connector/terminal materials shall not react chemically with the cable conductors to which they are
connected.
Terminals for pole top terminations of 15kv and 33kV cables shall be of the post type capable of
accepting a tap off connector.
Components supplied with adhesive coatings shall have means to prevent the coated surfaces from
adhering to each other.
Joints/terminations for armoured or shielded cables shall include all items needed for wire or tapes
clamping. Rings shall be provided for such application.
The recovered thickness of insulation over the connector shall be uniform and equal to or greater
than the cable insulation thickness as given in IEC 60502.
The protection provided by the galvanized steel wire armoring shall be reinstated over the joint.
Electric field stress control shall be provided on the joint/termination.
Joints shall provide waterproofing, mechanical and electrical protection, and be completely sealed
from cable jacket to cable jacket. Joints shall accommodate crossing of the cores.
Terminations shall be designed to provide a complete moisture seal, including the crotch area of
multi-core cables and complete rejacketing of the individual cores, conforming to Class 1
terminations as per IEEE 48. It shall be generally suitable for indoor and outdoor installation, be
resistant to ultra violet radiation and chemical attack.
The minimum creep age distances for outdoor cable terminations shall be:
Adhesives used shall have softening temperatures of not less than 90 °C; be compatible with other
components and after curing shall not flow at temperatures of normal service.
(a) Dimensions must correspond with those shown on the manufacturer's drawing.
(b) The ends of connectors/terminals shall be suitably chamfered or coned to facilitate insertion
of the conductors.
(d) All components and instructions shall be included in the joint/termination package.
Sample test certificates shall be provided at suitable intervals during manufacture agreed between
the Contractor and the Employer. The test certificate must indicate that the samples chosen have
undergone the checks listed in (a) – (e) above and have been successful. In addition, it should state
that the samples do not suffer from any other defects which could render them unsatisfactory in use.
At agreed intervals, the Contractor shall notify the Employer at least two weeks in advance of
delivery so that the Employer may, if he wishes, choose the samples to be tested and included on
the test certificates.
Type Tests
The Contractor/Contractor shall provide documentary proof in the form of Certified Test
Certificates that the assembled equipment and its component parts been successfully typetested by
an independent testing authority in accordance with quoted Standards. Test Certificates as evidence
of successful completion of type tests shall be submitted as part of the Bid.
Acceptable independent testing Authorities include the following: KEMA - Holland, CESI - Italy,
EDF - France and IREQ, - Quebec, Canada. Approval of type tests certificates supplied by any
other authority is subject to the written acceptance of Employer.
The extent of type testing required for specific consignments shall be at the discretion of the
Employer. The Contractor shall provide a separate schedule of costs for individual type tests.
Technical Schedules
Joints and Terminations (to be completed for each joint/termination type/size)
at up to 50ºC __________
Company Stamp
The Power Cable Accessories shall comply with the latest editions of and amendments to, the
standards/specifications listed below:
Accessories
Bituminous Filling Compounds
Filling compounds offered shall be suitable for operation at temperatures consistent with the
operation of the cable under normal, cyclic and fault conditions. Compound shall be supplied in
sealed tins of 12.5 kg of equivalent weight.
PVC Tape
A general purpose PVC insulating tape with good weathering, electrical and mechanical properties
shall be offered. This tape shall be in accordance with IEC 60454, shall be 25 mm in width and
shall be supplied in roll lengths of 20 m. The tape shall be suitable for operation at temperatures up
to 90oC.
Petrolatum Tape
Petrolatum (denso) tape for protection of the electrical contacts and metals. The tape offered shall
not deteriorate in contact harsh chemicals and shall not crack or harden have by time.
Miscellaneous Accessories
For the existing paper insulated cables the following items shall be supplied, to the appropriate
International Standards:
2. Oil Impregnated Paper Separator (Core Spreaders) for jointing 3core cables.
c) All accessories must be clearly labelled and identification marks must be clearly
distinguishable.
Sample test certificates shall be provided at suitable intervals during manufacture agreed between
the Contractor and the Employer.
The test certificate must indicate that the samples chosen have undergone the checks listed above
and have been successful. In addition, it should state that the samples do not appear to suffer from
any other defects which could render them unsatisfactory in use.
At intervals agreed, the Contractor should notify the Employer in advance of delivery so that the
Employer may, if he wishes, choose the samples to be tested and included in the test certificates.
Type Tests
Type tests shall be carried out at the Employer's request and shall be priced separately. The tests
shall be carried out in accordance with the appropriate National or International standard.
Type/Design Tests may (at the Employer's discretion) be dispensed with if the
Contractor/Contractor furnishes evidence to the Employer's satisfaction that the relevant tests have
already been performed on identical equipment. In this case the Contractor/Contractor shall provide
documentary proof in the form of Certified Test Certificates that the assembled equipment and its
component parts been successfully typetested by an independent testing authority in accordance
with the relevant clauses of referenced Standards. Test Certificates as evidence of successful
completion of type tests shall be submitted as part of the Bid.
Acceptable independent testing Authorities include the following: KEMA - Holland, CESI - Italy,
EDF - France and IREQ, - Quebec, Canada. Approval of type tests certificates supplied by any
other authority is subject to the written acceptance of the Employer.
Technical Schedules
Accessories
(To be completed for each product type/size)
Signed: __________________
Date: ___________________
Company: __________________
Company Stamp
Product 6 – Fittings
All equipment shall perform without being unduly stressed under normal, cyclic loading and fault
conditions and shall not limit the rating of the conductor on which they are used.
The ends of the connectors and lugs shall be suitably chamfered or coined to facilitate insertion of
the conductors. Straight connectors shall have a solid central barrier to facilitate the insertion of the
correct depth.
Conductor connectors and lugs shall be able to accommodate typical variations in dimensions of
conductors supplied by different manufacturers and shall be of a material which will not react
chemically with the conductors to which they are attached.
Insulator fittings and tension connectors for use in line terminations or anchor points shall be
capable of withstanding a tension force of 70kN.
All fittings shall comply with the latest editions of and amendments to, the standards/specifications
listed below:
String Fittings
All connecting fittings between the conductor and the tower steelwork such as a clevis to tongue,
shackle to plate or link which are subject to a tensile load in service shall comply with IEC 61284
except that each fixing pin shall be secured by a threaded nut and a split pin. A backing washer is
not required and the unthreaded shank of the fixing pin shall extend 3 mm through the clevis or
shackle. The nut shall, during erection, be tightened to the end of the thread and be backed by a
phosphor bronze or austenitic stainless steel split pin. Adequate bearing area between fittings shall
be provided and point contacts shall be avoided wherever this is possible without adversely affecting
the flexibility of the fitting.
Fittings made of steel or malleable iron shall be and hot dip galvanized to 630 g/m2 (320 g/m2 for
connecting material). All bolts and nuts shall comply with the relevant standard requirements for
bolts and nuts and shall, unless otherwise specified, be locked by locknuts. The mechanical strength
of the fittings shall be not less than 100kN. All fittings which could be the subject of direct or
indirect lightning or short circuit current shall withstand at least 31.5 kA for 1 second without
alteration of their electrical or mechanical performance values.
Hinge
Universal fitting for tension or suspension string.
Oval eye ball
Universal fitting for tension or suspension string. Ball shall fit IEC 16A socket. Mechanical strength
for this product is 70KN.
Oval eye socket
Universal fitting for tension or suspension string. Socket shall fit IEC 16A ball. Mechanical strength
for this product is 70KN.
Thimble clevis
Fitting for tension string equipped by preformed dead end clamp.
Tap connectors
Tap connectors shall be made of high purity aluminum.
Contractor shall assure that each connector has the following information stamped on: conductor
size (metric) in a way of 250/150 (i.e. run/tap):
Contractor shall supply the complete manual of suitable dies for each compression type connector.
Manual shall cater for all major manufacturers of compression tools (i.e.Pfisterer, Klauke, Burndy,
Chance etc.).
Other Connectors
All connectors shall be made of high purity aluminum or copper respectively.
Contractor shall assure that each connector has the following information stamped on:
All below mentioned connectors shall be supplied filled by conductive protection grease and
removable plastic plug.
Contractor shall assure that each joint has the following information stamped on:
Test Certificates
Type/Design Tests may (at the Employer's discretion) be dispensed with if the
Contractor/Contractor furnishes evidence to the Employer's satisfaction that the relevant tests have
already been performed on identical equipment. In this case the Contractor/Contractor shall provide
documentary proof in the form of Certified Test Certificates that the assembled equipment and its
component parts been successfully typetested by an independent testing authority in accordance
with the relevant clauses of referenced Standards. Test Certificates as evidence of successful
completion of type tests shall be submitted as part of the Bid.
Approval of type tests certificates supplied by any authority is subject to the written acceptance of
the Employer.
The Contractor shall submit to the Employer certified triplicate copies of test certificates, giving the
results of the tests as required. No materials shall be despatched until the test certificates have been
received by the Employer and the Contractor has been informed that they are acceptable.
The test certificates must show the actual values obtained from the tests in the units used in this
Specification and not merely confirm that the requirements have been met.
Test Certificates shall also carry further information regarding details of the order and drum lengths.
Product 7 – Preformed Ties
Distribution Top Ties, Side Ties and Dead End ties manufactured of Aluminum clad steel to secure
conductors in the top and side grooves of distribution insulators.
The Preformed Binding Ties shall comply with the latest editions of and amendments to, the
standards/specifications of IEC 61284:1997 Overhead Lines – Requirements and Tests for
Fittings.
Each tie is furnished with neoprene tie tube component; the tie tube is detached and applied over
the conductor.
All Dead Ends shall be supplied with a Thimble Clevis as shown in the attached drawings.
Aluminum cladding shall be a minimum of 10% of the nominal tie wire diameter.
Slip strength of the Top and Side Ties shall be a minimum of 15% UTS of the conductor. Slip
strength of the Distribution Dead Ends shall have a minimum of 95% of conductor UTS.
All Distribution Top and Side Ties shall be designed for an insulator neck diameter of 76 mm.
Each fitting shall be color coded to Identify conductor diameter ranges and shall cover all
conductors as stated below.
Conductors are All Aluminium Alloy Conductors following the DIN 48201/6 sizes.
Test Certificates
Type/Design Tests may (at the Employer's discretion) be dispensed with if the
Contractor/Contractor furnishes evidence to the Employer's satisfaction that the relevant tests have
already been performed on identical equipment. In this case the Contractor/Contractor shall provide
documentary proof in the form of Certified Test Certificates that the assembled equipment and its
component parts been successfully typetested by an independent testing authority in accordance
with the relevant clauses of referenced Standards. Test Certificates as evidence of successful
completion of type tests shall be submitted as part of the Bid.
Approval of type tests certificates supplied by any authority is subject to the written acceptance of
the Employer.
The Contractor shall submit to the Employer certified triplicate copies of test certificates, giving the
results of the tests as required. No materials shall be dispatched until the test certificates have been
received by the Employer and the Contractor has been informed that they are acceptable.
The test certificates must show the actual values obtained from the tests in the units used in this
Specification and not merely confirm that the requirements have been met.
Test Certificates shall also carry further information regarding details of the order.
Technical Schedules
Material
Length (mm) - Distribution Tie
Length (mm) - Side Tie
Length (mm) - Dead End
Slip Strength – Top Tie /Side Tie
Slip Strength – Dead End
Colour Code
Signed __________________
Date ___________________
Company __________________
Company Stamp
Product 8 – MV Insulators
This specification applies to covers Design, Manufacture, Testing and supply of 15KV composite
tension insulators to be used for power lines for outdoor services.
CODES & STANDARDS:
Materials, equipment and methods used in the manufacture of 15kv Composite Tension insulators
shall conform to the latest edition of the following International Standard.
SERVICE CONDITIONS
Item Parameter
Altitude Any altitude up to 3000m
Annual Rainfall 1250 mm
Period of exceptional Rains June to September
Ambient Air Temperatures:
Average +300c
Minimum -50c
Maximum 500c
Relative Air Humidity 70%
Wind Velocity:
Maximum wind ( height above
ground level) 0-30m 35m/s
30-50m 45m/s
Isoceraunic Level Up to100 thunderstorm days/year
Seismic Zone Level 3 & 4
MAJOR DESIGN CRITERIA
The Insulators shall be designed and assembled to meet the high quality, safety and reliability and
are capable of withstanding a wide range of environmental conditions. And it ensure that no
moisture, water or external substance reach the core.
Polymeric Insulators shall consist of THREE parts, at least two of which are insulating parts:-
(a) Core- the internal insulating part
(b) Housing- the external insulating part
(c) Metal end fittings.
CORE
It shall be a glass-fiber reinforced epoxy resin rod of high strength (FRP rod). Glass fibers and
resin shall be optimized in the FRP rod. Glass fibers shall be Boron free electrically corrosion
resistant (ECR) glass fiber or Boron free E-Glass and shall exhibit both high electrical integrity
and high resistance to acid corrosion. The matrix of the FRP rod shall be Hydrolysis resistant. The
FRP rod shall be manufactured through Pultrusion process. The FRP rod shall be void free.
i. HOUSING:
The FRP rod shall be covered by a seamless sheath of a silicone elastomeric/silicone rubber
compound or silicone alloy compound of a minimum thickness of 3mm minimum. It shall be one-
piece housing using Injection Molding Principle to cover the core. The elastomeric housing shall
be designed to provide the necessary creepage distance and protection against environmental
influences. Housing shall conform to the requirements of IEC 61109/92-93 with latest
amendments.
ii.WEATHER SHEDS
The composite polymer weather sheds made of a silicone elastomeric/silicone rubber compound
or silicone alloy compound shall be firmly bonded to the sheath, vulcanized to the sheath or
molded as part of the sheath and shall be free from imperfections It should protect the FRP rod
against environmental influences, external pollution and humidity. The weather sheds should have
silicon content of minimum 30% by weight. The strength of the weather shed to sheath interface
shall be greater than the tearing strength of the polymer. The interface, if any, between sheds and
sheath (housing) shall be free from voids.
Silicon rubber should have the following characteristics:
Mechanical Unit Minimum value high Minimum value liquid
characteristics temperature silicone rubber (LSR)
vulcanized (HTV)
Density g/cm3 1.1 0.9
Hardness Shore A 60 40
Breaking stress N/mm 3.5 4.5
Breaking % 200 350
elongations
Tear strength N/mm 12 17
End fitting of the insulator should transmit the mechanical load to the core. They shall be made of
Galvanized steel, spheroidal graphite cast iron, malleable cast iron or forged steel. They shall be
connected to the rod by means of a controlled compression technique. Metal end fittings shall be
suitable for ball and socket eye hardware of respective specified mechanical load and shall be
hot dip galvanized after, all fittings have been completed. The material used in fittings shall be
corrosion resistant. As the main duty of the end fittings is the transfer of mechanical loads to the
core the fittings should be properly attached to the core by a coaxial or hexagonal compression
process & should not damage the individual fibers or crack the core. The gap between fitting and
sheath shall be sealed by a flexible silicone elastomeric/silicon rubber compound or silicone alloy
compound sealant. System of attachment of end fitting to the rod shall provide superior sealing
performance between housing, i.e. seamless sheath and metal connection. The sealing must be
moisture proof. The dimensions of end fittings of insulators shall be in accordance with the
standard dimensions stated in IEC.
INSPECTION & TESTING
Insulators offered shall be manufactured with the same configuration & raw materials as used in
the insulators for which design & type test reports are submitted. The manufacturer shall submit a
certificate for the same.
DESIGN TESTS:
For polymeric insulators it is essential to carry out design test as per clause 4.1 of IEC 61109 / 92-
93 with latest amendments. The design tests are intended to verify the suitability of the design,
materials and method of manufacture (technology). When a composite insulator is submitted to the
design tests, the result shall be considered valid for the whole class of insulators, which are
represented by the one tested and having the following characteristics:
• Same materials for the core, and sheds and same manufacturing method
• Same material of the fittings, the same design, the same method of
attachment;
• Same or greater layer thickness of the shed material over the core (including a
sheath where used );
• Same or smaller ratio of the highest system voltage to insulation length;
• Same or smaller ratio of all mechanical loads to the smallest core diameter
between fittings
• Same or greater diameter of the core.
• Tracking and erosion and low current arc discharge.
The tested composite insulators shall be identified by a drawing giving all the dimensions
with the manufacturing tolerances.
Manufacturer should submit test reports for Design Tests as per IEC - 61109 (clause -5) along with
the bid. Additionally following tests shall be carried out or reports for the tests shall be submitted
after award of contract: UV test: the test shall be carried out in line with clause 7.2 of ANSIC29.
ACCEPTANCE TESTS:
The test samples after having withstood the routine test shall be subject to the following
acceptance tests in order indicated below:
Title:
Issue No. Page 149 of
Technical Specifications for 15KV and 33KV Surge Arrestors. 1
433
ROUTINE TESTS:
Every polymeric insulator shall withstand mechanical routine test at ambient temperature
tensile load at RTL corresponding to at least 50 % of the SML for at least 10 sec.
TESTS DURING MANUFACTURE:
Marking
Each insulator shall bear a marking as per ANSI or IEC Standards, Identifying the
following (English):
a. Manufacturer name.
b. Year of manufacturing.
c. Designation number.
d. Cantilever strength (Combined M&E strength Tension insulator).
e. Country of origin.
f. Purchase order No. & Date
g. Property of EEU
H. Maximum voltage
The manufacturer shall submit Manufacturing Quality Assurance Plan (QAP) for approval
& the same shall be followed during manufacture and testing. The material for final
inspection shall be offered by the Supplier only under packed condition. The owner shall
select samples at random from the packed lot for carrying out acceptance tests.
9 Packing
9.1.1 Packing protection Against corrosion , dampness, heavy rains, breakage
and vibration
9.1.2 Packing for Robust wooden non returnable packing case with all
accessories and spares the above protection and identification labels.
9.1.3 Packing identification In each packing case, following details are required
label :
i) Individual serial number
ii) Purchaser’s name
iii) Purchase order number (along with SAP
item code , if any) & date
iv) Equipment Tag no. (if any)
v) Destination
vi) Manufacturer / Supplier’s name
vii) Address of manufacturer’s / supplier’s its
agent
viii) Description and quantity
ix) Country of origin
x) Month and year of manufacturing
xi) Case measurement
xii) Minimum failing load in kg
xiii) Gross and net weight in kilograms
xiv) All necessary slinging and stacking
instructions.
9.2 Handling and Storage Manufacturer instruction shall be followed. Detail
handling & storage instruction sheet / manual need
to be furnished before commencement of supply.
The successful bidder shall get approval from the client for its specifications and
drawings before proceed to the mass production.
SCOPE OF SUPPLY
Test Voltage to
17
Ground
Minimum specific
18 525mm
Creepage distance
19 Minimum Phase to
280mm
phase clearance
20 Height of insulator 390Mm
21 Mounting Stud 38.1Mm
diameter
22 Stud length – 245Mm
overall/thread
23 Net Weight 2.6-Kg
Guaranteed Technical Particulars for 15kv Composite Tension insulators
Guaranteed Technical Particular
Sr. No. Description
Required by EEU Offered by bidder
1 Manufacturer
2 Country of origin
3 Type designation Composite Tension type Insulator
4 Standard IEC61952-2008/IEC 61109
5 Material of Watershed Silicon rubber
6 Material of Core Fiberglass rod
7 Material of end fitting Galvanized steel
8 Weather shield Colour Grey
9 System Voltage Highest 17.5KV
Highest Voltage of the 24 KV
Equipment U max as per
10
IEC at 3000mt above Sea
level
11 Maximum Design
5KN
Cantilever load
1 Manufacturer
2 Country of origin
12 25KN
Specified tensile load (STL)
13 12.5KN
Specified cantilever load (SCL)
14
Power Frequency Withstand Voltage
95 KV
15 Lightening Impulse with stand Voltage 250 KV
16 Minimum puncture Voltage
1 Manufacturer
2 Country of origin
Composite Tension type
3 Type designation
Insulator
4 Standard IEC61952-2008/IEC 61109
Material of
5 Silicon rubber
Watershed
6 Material of Core Fiberglass rod
7 Material of end Galvanized steel
fitting
8 Weather shield Grey
Colour
System Voltage 36KV
9
Highest
Highest Voltage of 52KV
the Equipment U
10 max as per IEC at
3000mt above Sea
level
11 Maximum Design
5KN
Cantilever load
15 Lightening Impulse
250 KV
with stand Voltage
Minimum puncture
16
Voltage
Test Voltage to
17
Ground
Minimum specific
18 1080mm
Creepage distance
Minimum phase to
19 480mm
phase clearance
20 Length of insulator 643mm
21 Mounting Stud 17.8mm
diameter
22 Stud length – 550mm
overall/thread
23 Net Weight 2Kg
of alternative proposals
Signed __________________
Date ___________________
Company __________________
Company Stamp
IEC 60502 Insulation for the Conductors for the voltages 6.35/11
kV up to and including 19/33 kV
IEC 60228 Conductors of insulated cable
EN-BS 50182 Conductors for Overhead lines
IEC 60060 High voltage test techniques
IEC 60104 Aluminium-magnesium-silicon alloy wire for overhead
line conductors
IEC 60229 Tests on cable over sheaths which have a special
protective function and are applied by extrusion
IEC 60287 Electric Cables -Calculation of the current rating
IEC 60811 Common test methods for insulated and sheathing
materials
IEC 60889 Hard drawn aluminium wire for overhead line
conductors
IEC 61089 Round wire concentric lay overhead electrical stranded
conductors
BS 3242 All Aluminium Alloy Conductor
ASTM D2303 Inclined plane non-tracking test method.
ASTMB399 AAAC conductors
Electrical Data
Short-circuit Currents
The Insulated overhead line cable shall withstand the thermal and mechanical effects of
any short-circuit that can appear on the line as per IEC standard.
Insulation Level
The Insulated overhead line cable shall be designed for the following insulation levels.
The outer diameter of the compacted conductor shall be 95% (± 1% for 7- and 19-wire
constructions, ± 1,5% for 37/61-wire constructions) of the diameter given above.
The compacted conductor minimum breaking load shall be at least 95% of the value given
above and dc resistance of shall not exceed the value given above by more than 5%.
Covering insulation
XLPE Insulation
The covering shall consist of a cross-linked polyethylene compound, which shall comply
with there quirements according to BS EN 50397 -2006 Table 1 or as per IEC60502.
It shall be possible to remove the covering material without damage to conductor.
The XLPE covering insulating material shall be of track resistant and UV stabilized
(weather resistant) as per Standard Specified.
The colour and average thickness of the covering insulation shall be as stipulated below:
Nominal Voltage 15 kV ………colour BLACK …………………………thickness 4.5
±0.1 mm
Nominal Voltage 33 kV………..colour Red……………………………..thickness
8±0.1 mm
The hardness of the covering XLPE shall be such that it should not get damaged by the kite
string and suitable for fixing insulation piercing Arc Protectors.
The covering shall be fully pressure extruded and dry cured so as to provide a uniform
thickness throughout the length of the conductor.
Water blocking
Suitable water blocking material shall be incorporated between the conductor and the
covering during the extrusion process to prevent the migration of water along the
conductor.
The water blocking material shall be of contrasting colour to that of the conductor.
The water blocking material shall not affect the inter-strand conduction and also not affect
the adhesion between the conductor and the XLPE cover.
Water blocking material shall be stable at maximum operating temperature of 900C and full
technical particulars with regard to the above shall be furnished with the offer.
Insulated end cap
The Insulated End Cap shall be suitable for effectively sealing the end terminal of the
covered conductors. The inner diameter of the Cap shall be such that it shall tightly fit to
the covered conductors to prevent entry of moisture.
Testing and Inspection
Acceptance of material
Each separate consignment of material shall be accepted or rejected by the Employer,
depending on the results of tests carried out on the consignment.
Acceptance tests shall be carried out on samples from not less than 10% of the individual
lengths of conductor wire to be included in any one consignment.
Each sample shall be of sufficient length to provide one test specimen for each of the
specified tests.
If any one sample fails to pass any one of the tests nominated for the conductor/wire, then
samples shall be taken from every drum in the consignment and any drum length from
which a sample proves defective shall be rejected. On no account shall any rejected
material be presented again for test unless with the written approval of, and under
conditions determined by the Employer.
Raw conductor tests
Hard Drawn Stranded Aluminium Alloy Conductors will be subject to tests according to:
• IEC 61089 (1991-05).
• DIN 48200-6
• BS_EN 50182:2001
Drum Dimensions
Drum Dimensions
Drum Dimensions
2. Conductor screen
Minimum thickness of conductor screen 0.5mm
3. INSULATION AS PER BS EN 50397 -2006
Table 1
Insulation thickness (mm) >4.5 ±0.1 mm
Insulation material XLPE
Insulation colour Red
Drum Dimensions
Signed: __________________
Date ___________________
Company: __________________
Class 1 2 3 4 5 6 7
8 m, 9 m,10 m, 11 m, 12 m, 13 m and 14 m
Design Requirements
The poles shall present the most pleasing appearance possible consistent with the strength
and serviceability requirements. The poles shall be round-conical. Poles may be designed
as pre-stressed spun concrete poles (hollow) or pre-stressed concrete poles.
The pole shall be capable of withstanding all specified loadings. The pole shall withstand
the loads without failure and without exceeding any specified deflection limitations.
Holes shall be provided for mounting of earth conductor supports, cross arms and all other
pole mounted equipment for construction and service conditions. “Basic” holes
arrangement is shown on attached sketch and shall be provided on all pole top sections, but
the Supplier shall seek further clarification from the Purchaser during the design period.
Poles shall withstand the loading conditions, including specified overload factors. The pole
design shall include allowances for loads from handling, transportation, and erection
without failure, permanent deformation, or damage to the pole when handled according to
the Supplier’s instructions.
Poles shall be designed so that the ultimate strength of the pole exceeds the required
strength calculated from the factored loads applied to the pole multiplied by required factor
of safety. The point of fixity on the pole shall be considered at ground line which is not
less than 1/6 of actual pole length measured from the butt of the pole.
Poles shall be designed so that the cracking strength of the pole exceeds the required
strength calculated from the service loads applied to the pole.
Poles shall be designed in combination with the appropriate column load applied along the
pole axis as a result of the stays, braces, etc.
Poles shall be designed to withstand a one-point (tilting) pickup during erection. The
Supplier shall include the weight of the pole with all insulators and hardware attached The
poles shall be designed for two-point pickup for horizontal handling and double line
network in case of narrow corridor.In addition may carry LV or other fiber optic lines along
the route. All pickup points shall be clearly shown on the fabrication drawings. All poles
shall be designed for the loads generated from handling and erecting without exceeding the
cracking moment capacity of the poles.
The design of each pole shall be performed using the applicable codes and standards.
Pole design and design calculations shall be the responsibility of the Supplier. However,
all the design shall be submitted to the Purchaser for approval.
The design shall be such as to keep the number of different parts as small as possible and
to facilitate transport, erection and inspection. Pockets and depressions likely to hold water
shall be avoided and, if not avoidable, shall be properly drained.
Every pole shall be equipped by earthing terminal made of bronze, brass or stainless steel,
embedded (or otherwise permanently fixed) into concrete surface of pole located 2.6 to 2.8
meters from pole butt. The bolt/nut size on terminal shall not be less than size M12.
Approval of Designs
The Supplier shall submit for approval loading diagrams for each type of structure before
proceeding with detail design.
After the agreement to the structure design, the Supplier shall prepare and submit General
Arrangement and Erection drawings.
For each scenario and load case, design calculations including the maximum reactions
(moments, shears, and axial loads, including safety factors) in poles at the ground line or
point of fixity, stay wire loads, deflections, and analyzed stress reactions.
After the Supplier's proposal has been accepted, the Supplier shall submit to the Purchaser
four copies of each fabrication drawing. One set of these drawings will be returned to the
Supplier with indication of review corrections. Where a correction is required, four revised
copies shall be resubmitted to the Purchaser. These revised copies shall be marked
“Revised” and dated.
Final fabrication drawings for each different framing pattern and pole calculations for each
load case shall be submitted to and approved by the Purchaser before release of order for
manufacture.
All design and detail drawings shall be reviewed and approved by the Purchaser before
pole manufacture.
All final drawings shall become the property of the Purchaser, who shall have full rights to
reproduce and use them.
The cement used in manufacture of the pole shall be of Portland cement) conforming to
relevant BS. Use of Portland-blast furnace, high alumina or sulphate-resisting cement
requires Purchaser’s approval.
Coarse aggregates shall be clean, tough, crushed stone conforming to relevant BS. The
nominal size of aggregates shall not exceed 14 mm.
Water shall be clean, free from undesirable amounts of oils, acids, alkalis, salts, organic
materials, or other deleterious substances.
Admixtures shall conform to relevant BS and can be used if approved by the Purchaser.
Water-cement Ratio and Total Aggregate-cement Ratio
A simple and convenient system of accurately varying the water supply to the concrete
mixers shall be installed with gauges marked so that the amount fed into the mixer may
easily be ascertained.
The water/cement ratio for the various classes of concrete shall be determined by trial
mixes. In no case, shall the water/cement ratios used in the Works, be allowed to exceed
by more than 5 percent, those proposed in the concrete mix design and confirmed as
acceptable by the trial mixes.
Efficient means shall be provided for determining the moisture content of the sand and
coarse aggregate at all times.
The Supplier shall be required to have an accurate knowledge of the moisture content of
all sand and coarse aggregates as they reach the mixer and he shall make such adjustments
to the mix as are necessitated by change in the moisture content of the aggregates.
For ordinary Portland cement concrete, including the Portland-blast furnace cement
concrete, rapid hardening Portland cement concrete or sulphate resistant Portland cement
concrete the proportion of cement to total aggregate shall not be less than 1:5.
Strength of Concrete
The strength and other data for concrete are defined on the basis of standard tests. The
compressive strength of concrete to be determined from test on the 150 mm cubes at the
age of 28 days in accordance to Ethiopian code of standard cylindrical or cubical specimens
of other sizes may be used with conversion factors determined from a comprehensive series
of tests. The tensile strength shall be determined by test, in accordance with relevant
standards. The modulus of elasticity to be used in design should be determined by test.
Since, it is not only depending on the concrete strength but also on the material use such as
aggregates used.
The un-tensioned steel reinforcement shall be free from loose rust, scale, oil or grease and
shall comply with the requirements of relevant BS.
For bond and anchorage the surface of ribbed bars or pre-stressing steel shall be such that
adequate bond is obtained the concrete, permitting the full force that is assume in design,
to be developed in the reinforcement.
All drawings, calculations and details shall be available before commencement of any type
tests.
Pole Marking
All poles shall be equipped by weather proof marking at the distance of 3 meters from pole
butt. The mark shall consist of:
• Year of manufacture;
• Totals length of pole;
• Pole Strength ( kN);
• Standard used for manufacturing;
• Depth mark “▼ 3 m”.
• “Property of EEU”
Inspection
The Supplier shall make adequate tests and inspections to determine that each of the poles
furnished is in strict accordance with this specification. At the request of the Purchaser,
the Supplier shall submit a quality assurance report to the Purchaser prior to the
transportation of each pole and shall include the following minimum information:
• Minimum and maximum tip wall thicknesses and steel coverage (to inside and
outside) measurements shall be made at 76 mm from the tip;
• Minimum and maximum butt wall thicknesses and steel coverage (to inside and
outside) measurements shall be made at 76 mm from butt;
• Condition of pole interior and evidence of exposed rings or reinforcement steel;
• Proper hole and insert locations and sizes;
• Evidence of cracking during or after two-point handling;
• Actual manufactured pole weight;
• Report of any repairs made to the pole;
• Date of manufacture and inspection(s); and
• Inspector’s seal.
All material and workmanship shall be subject to inspection, examination, and test for
conformance to the requirements of this specification by the Purchaser. The inspection,
examination, or testing could be done at any time during material procurement,
manufacturing, storage periods, transit, or at the pole destination.
The shall have free entry, at all times, while work is being carried on, to all parts of the
Supplier's plant where manufacture of the project's poles is being performed. The Supplier
shall afford the Purchaser reasonable facilities, without charge, to satisfy the Purchaser that
the poles are being manufactured in strict accordance with this specification.
The Supplier shall furnish certified test reports to the Purchaser, upon request, showing the
results of all of the tests required by this specification and applicable reference
specifications.
Tests shall be in accordance with all applicable standard specifications and codes.
Failure of the Supplier to comply with these specifications will be sufficient reason for
rejection of any or all poles which do not comply with these specifications.
Details of all test procedures contained herein and methods of measuring and recording test
loads and deflections shall be specified by the Supplier and approved by the Purchaser prior
to manufacture. The tests will be done on site.
Material procurement for test poles shall be identical to material procurement procedures
for regular production run poles.
The design load testing of any specific pole shall be on a full-scale basis. Costs for such
testing shall be the responsibility of the Supplier included in the poles price, shall be.
The number, location, direction, holding time, sequence, and increments of the test loads
along with the number, location, and direction of deflection readings for an individual pole
test shall be approved by the Purchaser prior to pole testing.
The method of attaching the test loads to the pole, applying the test loads, measuring and
recording the test loads, and measuring and recording the deflections shall be approved by
the Purchaser prior to pole testing.
A full report listing results shall be submitted to the Purchaser after completion of all tests.
Copies of mill test reports shall be included in the load test report. The report shall also
include a complete description of the load tests with diagrams and photographs. If required,
the Supplier shall provide the Purchaser with Method of full scale testing: upright or
horizontal and descriptions, tools, and drawings describing the above test.
Use of any factory tested poles to meet order requirements shall be determined by the
Purchaser.
Company __________________
Company Stamp
Product 12 - Galvanized Steel Cross arms
Scope
This Technical Specification covers the design, fabrication, tests, inspection, packing and
delivery of hardware accessories used in overhead electrical distribution systems. The
reference to specifications or organizations together with any drawings or loading diagrams
shall be considered part of the specification.
List of Items:-
⮚ Hoop 60mmx5mmx400mm
Item Parameter
Altitude Altitude up to 3000m
Annual Rainfall 1250mm
Period of exceptional June to September
Rains
Ambient Air Temperatures:
Average +300c
Minimum -50c
Maximum +500c
Relative Air Humidity 70%
Wind Velocity:
Maximum wind( height
above ground level) 35m/s
0-30m 45m/s
30-50m
Isoceraunic Level Up to 100 thunderstorm days/year
Seismic Level No records of any activity
Reference Standards
Reference to standards and/or specifications herein shall be interpreted to mean the latest
revision unless noted.
Design, materials and fabrication shall be in accordance with latest edition of international
Codes and Standards listed hereafter:
The hardware accessories shall present the most pleasing appearance possible consistent
with the strength and serviceability requirements.
Material
All material shall be in accordance with relevant standards referred to within this
specification.
Bolts and other connecting materials shall be grade 6.8 according to EN ISO 1461.
Manufacture
All parts forming the structure shall be fabricated in accordance with drawings approved
by the Purchaser.
1.1. Tolerances
The permitted variation (tolerance) from a stated for cross arm shall be as follows
a) length shall be as ± 5 mm
b) Holes diameter ± 1%
1.2. Welding
All welding shall, as much as is practicable, follow the AWS Standard.
All structural welds will have one hundred (100%) per cent penetration minimum.
All welding shall be done using automatic equipment or ASME/ EN BS qualified welders.
1.3. Galvanizing
After the fabrication has been entirely completed, steel cross arms shall be hot dip
galvanized to minimum of 630 g/m2.
All hollow members shall be galvanized both inside and outside surfaces. No double dip
galvanizing process is allowed.
Bolts, washers & nuts shall be galvanized to full length to minimum 320 g/m2.
Nuts may be re-tapped after galvanizing and then shall be suitably protected from rust by
grease.
Marking
All parts of shall be appropriately marked. All marking shall be indelible and clearly visible
after galvanizing. Pieces which are part of a structure shall be marked with structure type
number, followed by the proper assembly item and other identification marks such as
“Property of EEU”.
QUALITY ASSURANCE
1.4. GENERAL
The Supplier shall adopt suitable quality assurance program and procedures to ensure that
all activities are being controlled as necessary. The Supplier shall indicate following in the
quality assurance plan -Hold Point "A stage in the material procurement or workmanship
process beyond which work shall not proceed without the documented approval of
designated individuals or organizations."
The Purchaser's written approval is required to authorize work to progress beyond the Hold
Points indicated in approved quality plans. Notification Point Steel "A stage in material
procurement or workmanship process for which advance notice of the activity is required
to facilitate witness." If the Purchaser does not attend after receiving documented
notification in accordance with the agreed procedures and with the correct period of notice
then work may proceed.
1.5. QUALITY PLANS
The Supplier shall draw up for each section of the work quality plans which shall be
submitted to the Purchaser for approval at least two weeks prior to the commencement of
work on the particular section. Each quality plan shall set out the activities in a logical
sequence and, unless advised otherwise, shall include the following:
▪ Quality and strength of raw materials used. All materials used shall be of reputed
make only.
▪ Performance figures as supplied by the Bidder in the schedule of guaranteed
particulars.
▪ Satisfactory operation during the guarantee period of one year from the date of
commissioning, or 18 months from the date of acceptance of the equipment by the
Purchaser following delivery, whichever is the earlier.
▪ The offered surface treatment shall protect the treated metal from corrosion for a
period of not less than five years from the date of delivery.
▪ Physical and Chemical composition test certificate of raw material shall be
submitted by vendor.
The successful bidder shall get approval from the client for its specifications and drawings
before proceed to the mass production.
INSPECTION AND TESTING
1.8. INSPECTION
All the tests and inspection shall be made at the place of manufacture unless otherwise
especially agreed upon by the manufacturer and purchaser at the time of purchase. The
manufacturers shall afford the inspector representing the purchaser and all reasonable
facilities without charge, to satisfy him that material is being furnished in accordance with
the Specification. The purchaser has the right to have tests carried out at his own cost by an
independent agency whenever there is a dispute regarding the quality of supply.
1.9. TEST
▪ Acceptance and routine tests: All routine tests shall be carried out and the supplier
shall furnish the complete Guaranteed Technical Particular as per BS4360, BS EN
10025-3 in the presence of EEU representative in the appendix A.
▪ Tensile Test and Bend test: The test shall be carried out as per BS4360; BS EN
10025-3 and test certificate shall be furnished at the time of inspection.
13.6 N (%) % -
13.7 Cu (%) % -
13.6 N (%) % -
13.7 Cu (%) % -
15kV T-off Cross arm for single line supporting pole (150mmx75mmx2000mm(6.4/9)
U-shaped)
13.6 N (%) % -
13.7 Cu (%) % -
13.6 N (%) % -
13.7 Cu (%) % -
13.6 N (%) % -
13.7 Cu (%) % -
15kV Cross arm for arrester and drop out fuse (150mmx75mmx3000mmx6.4/9mm)
U-shaped
Item Guaranteed value
Description Unit
No. Required Offered
1 Manufacturer
2 Country of origin
3 Manufacturing capacity per month
4 Steel section utilized
5 Grade of steel 43A
BS4360 ,EN10025-3
6 Steel Standard applied
or equivalent
7 Tensile strength N/mm2 430 to 580
▪ Yield strength of Angle-cross N/mm2
275
arm
Complete dimension of Angle-cross
8
arm for suspension
a. Length mm 3000
b. Width mm 200
c. depth mm 75
d. Thickness mm 9
Details of Galvanization method
9 utilized standard/specification Hot dip galvanized
conforming to
10 Thickness of galvanization(Min) µm 85
11 Net weight per piece kg
As per the drawing
12 Size and no. of predrilled holes
attached
13.6 N (%) % -
13.7 Cu (%) % -
13.6 N (%) % -
13.7 Cu (%) % -
13.6 N (%) % -
13.7 Cu (%) % -
Hoop 60mmx5mmx400mm
8 Complete dimension
a. Length mm 595
b. Width mm 100
c. Thickness mm 10
Details of Galvanization method
9 utilized standard/specification Hot dip galvanized
conforming to
10 Thickness of galvanization(Min) µm 85
11 Net weight per piece kg
As per the drawing
12 Size and no. of predrilled holes
attached
13.6 N (%) % -
13.7 Cu (%) % -
8 Complete dimension
a. Length mm 815
b. Width mm 100
c. Thickness mm 10
Details of Galvanization method
9 utilized standard/specification Hot dip galvanized
conforming to
10 Thickness of galvanization(Min) µm 85
11 Net weight per piece kg
As per the drawing
12 Size and no. of predrilled holes
attached
13.6 N (%) % -
13.7 Cu (%) % -
The Tenderer shall set out below a tabulated statement showing clearly section by section
Compliance and departures from the Specification and details of alternative proposals. The
tenderer will be deemed to have complied with the Specification in all respects and as
written unless qualified in this Schedule.
of alternative proposals
Signed __________________
Date ___________________
Company __________________
Position in Company _______________
Company Stamp
• BS 6722 Recommendations for Metric Plate and Sheet. Thickness and width
– length combinations for metallic materials
• BS EN 485 (1-4) Aluminium and Aluminium alloys. Sheet, strip and plate
• BS EN 573 (1-4) Aluminium and Aluminium alloys. Chemical composition
and form of wrought product
• BS EN 515 Aluminium and Aluminium alloys. Wrought products, temper
designations
• BS 5499-5 Graphical symbols and signs
• BS EN ISO 1461 Hot dip galvanised coating on iron and steel articles
General Design
Danger, number plates, phase identification and name plates shall be manufactured from
flat sheet aluminium 1 mm thick to BS EN 485 and shall be capable of being bent into an
arc of a radius 100 mm without damage.
A baked enamel or equivalent finish is required. This shall include a transparent lacquer
capable of blocking the ultraviolet rays of the sun and preventing their discolouring
influence. The corners of the plates shall be rounded up to. The edges of the plate shall be
smooth to prevent any injury to a bare hand. The finish of the plates shall be done in such
a way that the plate shall not rust, or lose its colour on exposure to the weather, and the
surface of the plate shall not chip or form any cracks or blisters. Letters are to be plain, not
embossed, except on the name plates where the letter may be raised.
Danger Plates
Pole Type
The pole danger plates shall be as shown on the pole drawing
The lettering shall be 25 mm height and colors shall be as approved by the Employer
Purchaser will state it’s preference for voltage number in each order.
Plate will have 4 slots (in each corner) for 10mm wide stainless steel band.
Plate will have 2 slots (in each corner) for 10mm wide stainless steel band.
The inscription shall be 20 mm height and colors shall be approved by the Employer
Plate will have 2 slots (in each corner) for 10mm wide stainless steel band.
They shall be manufactured from 1mm thick aluminium round (100 mm diameter).
One bolt hole 6mm diameter shall be made in the centre of the plate.
A4 stainless steel bolts set in a plastic bag shall be supplied together with every set of 3
plates (RYB) of this type.
Type/Design Tests may (at the Purchaser's discretion) be dispensed with if the Supplier
furnishes evidence to the Purchaser's satisfaction that the relevant tests have already been
performed on identical plates and labels. In this case a certified Test Certificates shall be
submitted with the Bid for evaluation.
Routine Tests
All plates shall be visually inspected at production stage to verify design, smoothness of
finish and rounding of edges. One percent of the plates shall be measured to ensure they
conform to the dimensions set out in this specification.
Thickness 0.1 mm
Company Stamp
EARTHING ROD
Scope
This specification covers the design, manufacture, supply, and delivery and performance
requirements of earthing materials.
service conditions
Item Parameter
Altitude Any altitude up to 3000m
Annual Rainfall 1250mm
Period of exceptional Rains June to September
Ambient Air Temperatures:
Average +250c
Minimum -50c
Maximum 450c
Relative Air Humidity 70%
Wind Velocity:
Maximum wind( height above
ground level) 0-30m 35m/s
30-50m 45m/s
Isoceraunic Level Upto100 thunderstorm days/year
Seismic Level No records of any activity
Reference standards
Standard Title
Number
IEC-60364 Electrical installation of buildings (Earthing
arrangements and protective conductors.
IEC 60228 Conductors of insulated cables
The ANSI C114.1 Recommended practice for earthing of industrial and
commercial power systems
BS 7884 Copper and copper cadmium conductors for overhead
Electric traction and power transmission systems
BS6485 PVC covered conductors for overhead power lines
BS EN 10137 Weldable steels
materials supplied shall conform to the latest edition of the appropriate IEC standards and/
or other recognised international standards. In particular,
Design
Earth Rods
Solid copper clad steel earthing rods for earthing of low voltage lines and high voltage
equipment. The rods shall be extensible and suitable for driving into the ground by a hand
held hammer.
The copper exterior shall be electrolitycally applied to the steel core to form a metallurgical
bond between the steel core and the copper. The copper thickness shall not be less than
0.33mm. Earthing rods of the steel bar (low carbon steel) type with an external copper tube
are not acceptable. Earth rods shall be 3000mm in length and not less than 15mm in
diameter. The rods shall have a 60-degree conical driving point, for electrode entry into the
ground. At each installation the rods shall be driven so that than 500mm below the finished
ground level. A minimum of four rods shall be provided for each transformer.
Earthing Accessories
Earthing accessories shall include but not limited to,
Earth Rod Couplings
Removable electrode connectors for earth rods for attaching 70mm² stranded galvanised
steel. The clamp shall have a high copper content alloy body suitable for direct burial and
include stainless steel U-bolts, isometric nuts and spring washers. The clamp shall be
suitable for connection of two conductor tails in the right angle direction. The clamp shall
be suitable for both parallel and right angle alignment of the conductor to the earth rod
axis.
Split bolt connectors designed for the connection of hard drawn copper conductors up to
35mm² cross sectional area. The connectors shall have metric dimensioned flats on the
head to permit holding the fitting with an adjustable jaw wrench. All the threads shall be
isometric. Thread length shall be sufficient to clamp two conductors of 35mm². The nut
shall be of isometric hexagonal form and dimensions. The slot width shall be 8.3mm
minimum and the slot depth shall readily accommodate two 7.65mm diameter
uncompressed conductors with the nut applied two full turns, The split bolt hall be made
from hard drawn brass with an electro-tinned finish.
Earth Rod Driving Head
The driving head shall be of high strength steel, threaded to fit the Earth Rod Couplings.
The design shall ensure that there is direct driving head to rod contact when the rod driving
force is applied. The driving head shall be suitable for reuse.
Clamps and Connectors
A full range of clamps and connectors will be required with the earthing material. All
clamps and connectors shall be constructed in high strength copper alloy bodies and
screws. They shall be suitable for use with the earthing conductor sizes and with the earth
rods. The Supplier shall provide a catalogue showing the full range of clamps and
connectors on offer together with dimensions in each case.
Inspection And Testing
Type Tests
In addition to the tests as per the standards mentioned, the following tests shall be
conducted.
a) Jacket Adherence Test
A 450mm length of rod cut at one end to a 45 degree point shall be driven between two
steel clamping plates or the jaws of a vice set 1mm less than the diameter of the rod so as
to expose the bond between the jacket and the rod. Peeling of the jacket by the steel plates
or the jaws of the vice is acceptable, but there shall be no evidence of separation of the
jacket from the steel core.
b) Bend Test
There shall be no evidence of cracking of the jacket if at room temperature a length of rod
is rigidly held in a clamp or vice and the free end bent by applying a force normal to the
rod at a distance from the clamping device equal to 40 times the rod diameter. The
magnitude of the force and the direction of application shall be such that the rod is
permanent bent through a 30 degree angle. There should be no evidence of cracking or
splitting of the steel or the copper.
Circular copper
drawn stranded
Company Stamp
3. The width and thickness of the tape shall be 200 mm and 2.5 mm respectively and
the length of the tape per reel shall be 40 m.
4. The tape shall have the following words written on both the top and bottom part of
it and it shall be on one side of the tape only:
a) Top part of the tape – shall be written along the tape repeatedly twenty (20)
times on every one (1) meter of the tape. The size of the picture shall be 37 mm high and
6 mm thick.
The space between the Top and Bottom print shall be maintained as 55 mm.
5. The quality of the print shall be of an indelible nature and in black.
6. The cable warning tape shall function effectively for at least 40 years.
7. The offered warning tape shall conform to applicable codes and standards,
8. The Purchaser shall approve the written layout and words of the cable warning tape
markings.
1. Material Polythene
2. Color RED
3. Width of Tape mm 200
4. Thickness of Tape mm 2.5
5. Length of Tape m 40
Item Description Unit Required Offered
Company Stamp
All Cable Ducts shall comply with BS EN 61386-1:2008 and the following:
1) The legend ‘Electric Cable Duct’ shall be permanently and clearly marked on the
duct
2) Class 1 ducts for power cables shall be non-coilable/ semi-rigid in either twin
walled or smooth outer wall, manufactured in either UPVC or HDPE; each duct type shall
have a smooth inner surface.
3) Class 2 ducts for low voltage service cables and pilot/telephone cables shall be
uPVC or MDPE. Smoothed walled with a smooth inner surface.
5) End of ducts shall be cleanly cut square with the longitudinal axis of the duct.
6) Each duct length shall be supplied with a straight coupler incorporated in one end
and designed to be a close push fit onto a plain end of a duct with the same nominal
diameter. The duct ends shall be suitable for application without the use of adhesive
materials.
7) Ducts Bends manufactured in either HDPE, uPVC or MDPE shall have either a
smooth outer and inner surface, twin walled bend shall have corrugated outer and a smooth
inner surface. Each bend shall incorporate a coupler in one end and shall be suitable for
application without the use of adhesives.
9) Hockey Stick shall be manufactured from uPVC. The end of the hockey stick shall
be so designed to be a close push fit into the end of a duct or bend with the same nominal
diameter. After installation the long end of the hockey stick shall be exposed to the full
range of climatic conditions encountered in Ethiopia.
10) Adaptors shall be supplied for all straight couplings of ducts of varying sizes where
required. Adaptors shall be suitable for application without the use of adhesive materials.
11) Bends, joints or couplings, etc. shall not present any internal projections or
impedance to the installation or withdrawal of cables.
12) The cable duct wall thickness shall be tested to meet the following requirements:
• Class 1 – All ducts (UPVC& HDPE) intended for low voltage mains
distribution cables, for medium voltage power cables and for high voltage
power cables to give 450 N compression strength at 750C;
• Class 2 – All ducts (UPVC& MDPE) intended for low voltage service cables
and pilot/telephone cables to give 450 N compression strength at 500C.
As the design stress and the physical properties of uPVC, HDPE, and MDPE are different,
duct bore/wall thickness ratios shall be different.
All ducts that are to be buried shall retain their shape (less than 5% deformation) under
crushable pressure of 750 N/m for Class 1 and in excess of 450 N/m for Class 2.
Technical Data Schedule – Guaranteed Characteristic
Company Stamp
2) The material used for the tile must be rot-proof, resistant to a wide variety of virgin
and tipped soil conditions, be able to withstand termite activities and shall be impervious
to water.
3) The tile shall meet all requirements of BS EN 50520 - Cover plates and cover tapes
for the protection and location warning of buried cables.
4) The width, thickness and length of the tile shall be 300 mm, 12 mm, 1000 mm
respectively.
5) The tile ends shall be cleanly cut, square with longitudinal axis of the tile and shall
have no sharp edges, shall be drilled with a 12 mm hole with centre 150 mm and 25 mm
from the end with a suitable peg or cable tie provided to enable tiles to be connected
together.
6) The tile shall have the following words written on both the top and bottom part of
it and it shall be on one side of the tape only.
Top part of the tile –“CAUTION” shall be written along the tape repeatedly seven (7) times
on every one (1) meter of the tape. The size of the characters shall be 37 mm high and
6 mm thick. The spacing between each character shall also be kept at 2 mm. A maximum
space of 37 mm shall also be maintained between each “CAUTION” word.
Bottom part of the tile -“BURIED ELECTRIC CABLE BELOW” shall be written along
the tape repeatedly two (2) times on every 1 meter of the tape. The size and thickness of
each character shall be the same as above. However, the spacing between each word shall
be 13 mm.
The space between the Top and Bottom print shall be maintained as 55 mm.
7) The quality of the print shall be of an indelible nature and in black.
8) The cable warning tile shall function effectively for at least 40 years.
9) The Purchaser shall approve the written layout and words of the cable warning tile
markings.
10) Testing certification to confirm the tile adheres to the impact requirements of
BSEN50520 shall be provided by the Supplier.
1. Material Polythene
2. Color Yellow
3. Width of Tile 300 mm
4. Thickness of Tile 12 mm
5. Length of Tile 1000 mm
Item Description Unit Required Offered
Company Stamp
The different requirements included in the standards have been introduced in order to fulfill
the End-User expectations:
e) Electro-Magnetic Compatibility,
Item Parameter
Altitude from Sea Level Any altitude up to 3000m
Annual Rainfall 1250mm
Period of exceptional Rains June to September
Ambient Air Temperatures:
Average +300c
Minimum -50c
Maximum 550c
Relative Air Humidity 70%
Wind Velocity:
Maximum wind( height above
ground level) 0-30m 35m/s
30-50m 45m/s
Isoceraunic Level Upto100 thunderstorm days/year
Seismic Zone Level 3 & 4
REFERENCE Standards
The materials supplied shall conform to the latest edition of the appropriate IEC standards
and/or other recognized international standards. In particular:
Specification/Standard Title
Number
Degrees of protection of enclosures for low-voltage
IEC 60144
switchgear and control gear
IEC 60269-1 Low Voltage Fuses
IEC60408 Low voltage air‐break switches, air‐break disconnectors
and fuse‐combination units
IEC 61439 Low Voltage Switchgear and Control gear
● IEC/TR 61439-1: General rules b
● IEC 61439-2: Power switchgear and control gear
assemblies b
● IEC 61439-3: Distribution boards intended to be operated
by ordinary persons (DBO)
● IEC 61439-4: Particular requirements for assemblies for
construction sites (ACS)
● IEC 61439-5: Assemblies for power distribution in public
networks
● IEC 61439-6: Busbar trunking systems (busways)
● IEC/TS 61439-7: Assemblies for specific applications
such as marinas, camping sites, market squares, electric vehicles
charging stations.
DIN 43620 Low voltage high rupturing capacity fuses with blade
contacts
BS 5486-part 12 Low voltage switchgear and control gear assemblies
Box DESIGN
General
The requirement is for a standard box design to accommodate
The circuit breakers are connected between the bus bars in the Box and the outgoing cables
for distribution loads.
Neutral Bar
The neutral bar shall be rated at the full rating of the phase bus bars. It shall be insulated
from the frame of the distribution box but a bolted link shall be provided to connect it to
the frame.
Earth bar
A copper earth bar shall be fitted near the bottom of the Distribution box. A number of
copper lugs shall be provided bolted to the earth ready to accept outgoing cables. The earth
bar shall be insulated from the frame but connected to the neutral bar by a removable
strap/bar.
The bottom of the box shall have a 3.15 mm thick steel plate for securing the
outgoing/incoming cables. The plate shall be provided with knockout holes suitable for
cable sizes indicated. The bottom plate shall be provided with two air vents with perforated
M.S. sheet of 1.25mm thick welded from inside. Suitable size of stainless steel cable glands
should be provided for these holes.
A complete set of screw type compression cable glands shall be provided with each box
suitable for outdoor use with those cables specified in the schedules. The glands shall not
be PVC or plastic. Each gland shall be capable of carrying the short circuit current rating
of its associated cable and be provided with such fittings necessary for fixing in tapped or
untapped entry hole.
Alternatively 70mm pipe with smoothed edges of suitable size shall be welded with each
hole where the cable can enter and then sealed with a suitable hardening compound to act
as a gland. The compound can be a flexible bitumastic setting compound.
Ventilation
Four sets of louvers shall be provided on the sides or doors to ensure that the temperature
inside the enclosure is not substantially different from that of the atmosphere. The louvers
shall be backed with perforated M.S. sheet of 1.25 mm welded from inside the LV
Distribution Box. The nuts, bolts, washers used in the box shall be galvanized to avoid
corrosion.
Finishing
All sheet metal works shall undergo the 7 tank chemical and mechanical cleaning process
before final paint. The entire box shall be duly acid treated.
Two coats of red oxide and two coats of final paints shall be applied. Colour of
outside/inside surface shall be mentioned in this specification. Electrostatic painting with
oven drying will also be acceptable.
M.S. parts such as Bolts& Nuts, washers etc. shall be electro galvanized for non-electrical
use.
Size of Box
The box shall be of standard design and size to take up to outgoing and incoming circuits
and also shall includes the transformer meter.
Earthing
The box shall have a solid earthing point and an earthing bar for the earthing of the
outgoing cables. Box earthing point shall be provided both on the inside and the outside of
the box, to allow earthing according to local requirements.
The door hinges shall not be visible from outside. Minimum 3 Nos. Hinges per door made
of heavy duty MS Sheet of minimum length of 75 mm shall be provided from inside. The
hinges shall be of such design to prevent them from malfunctioning due to inadvertent
rusting
Miscellaneous
All joints for current carrying parts shall be made using non-magnetic stainless steel bolts
or brass, 2 nuts & spring washers. The nuts and bolts should be of hexagonal type with
groove for bolt.
Electrolytic grade copper bus bars are mounted on epoxy resin cast bus insulators fixed on
suitable fixing arrangement. The bus bars shall be conveniently placed so as to provide
adequate clearance from the body of the box conforming to the relevant standard.
The distribution boxes shall be duly wired with suitable size of PVC insulated copper flat.
Cable glands of sufficient size and cable cleats for support of the cables shall be provided.
The bus bars size will be 10X40mm and shall be fitted with lugs of suitable size for
receiving the incoming cables from the transformer. Proper arrangement shall be made for
connection between the bus bars and the MCCBs and outgoing cables. Sufficient space
shall be provided for bending and termination of the cables. Access shall be provided for
insertion of clip on meters for taking load readings on the feeders.
The Danger marking with fluorescent paint shall be provided on one door and a danger
plate shall be riveted on another door, on front side.
Cable Terminations
Cable terminations shall be provided for the transformer incoming cables to the Busbars as
well as the outgoing circuits.
MCCBS
GENERAL
These MCCB’s shall be conforming to IEC61439 or any other relevant standard.
MCCB is to be provided with over load trip release with inverse time current characteristics
for overload protection and magnetic trip release for instantaneous tripping in the wake of
Short-Circuits. The characteristics shall be as follows:
Multiple of rated current(Ir) Tripping time( T)
10 In < 100msec
The Distribution Box shall have 1 Nos. of 3 pole MCCBs per circuit to control and protect
outgoing circuits. The MCCBs shall be manually operated type and shall have quick make
quick break mechanism.
The Terminal Connector strips of the MCCB shall be projecting out of the MCCB for
minimum length of 40 mm on bus bar side and 60 mm on outgoing cable side connected
through lugs.
All nut bolts used for assembly and connections shall be of non-magnetic stainless steel
only.
The MCCB’s shall be marked with ‘Brand Name’ of manufacture and Ics in kA by
embossing only whereas other particulars may be marked as per the manufacturers standard
practice.
The contacts of MCCB should be self-wiping type so as to keep the contacts clean and
milli-volt drop low.
PHOTOELECTRIC CONTROL SWITCH
REQUIREMENTS
Rated current 10 A
Terminal shall be suitable for copper conductors. The switch shall be equipped with a
connecting cable. Connecting cable shall be made of multi-core stranded copper of at
least 1.5 mm2 cross section. Connecting cable must have black, weather-resistant sheath.
The length of the cable shall be at least 1.5m.
The light sensitiveness of the switch shall be adjustable. The switches shall be adjusted
to sensitiveness of 10 lux before dispatch from the manufacturer's works in case such
an adjustment is tedious to do in operation. The switch shall have a delay mechanism
against nuisance switching e.g. due to sudden darkness.
Preference shall be given to switches integrating the sensitive part and the switching
part.
Type Tests
Type tests shall be carried out on Distribution boxes being offered, in accordance with the
relevant IEC/ BS standard.
ON COMPLETE LV DISTRIBUTION BOX
Routine Tests
These tests shall be carried out per IEC at the manufacture’s works to ensure that the
product is in accordance with the design offered. The manufacturer shall supply a
certificate indicating the result of the entire test carried out on the equipment.
ACCEPTANCE TESTS
The Acceptance test procedure for any delivery of the equipment are as follows:
• Visual inspection
• Checking of the results of the routine and type tests
• Carrying out all or part of tests mentioned in the routine test
• Checking of conformity to specification
TESTING & MANUFACTURING FACILITIES:
The bidder must clearly indicate the testing facilities available in the works of the
manufacturer and whether the facilities are adequate to carry out all routine acceptance and
type tests.
• Power operated shearing machine
• Power operated press brake.
• Power operated power presses
• Welding machines,
• Assembling tools.
Each unit shall be provided with a rating plate of weatherproof material showing the
following items indelibly marked.
• Manufacturer's Name,
• Manufacturer's Code Number,
• Manufacturer's Serial Number,
• Year of Manufacture,
• Voltage Rating,
• Current Rating,
• Short Circuit Rating,
• Gross Weight.
• Property of EEU , logo
Packing and marking
Pole mounted distribution box shall be packed in sea-worthy solid wall wooden cases in a
manner to avoid damage during transport, handling and storage. They shall also be packed
in such a way that no corrosion occurs on the equipment due to salty moisture when stored
at the port of destination.
Each package shall be marked with the main details of the equipment contained therein,
the type designation or the catalogue number and with the manufacturer's name or
trademark.
Each wooden case shall be clearly marked with the address of EEU and the relevant contact
number and title. All markings shall be legible and durable.
Pole mounted distribution box and its wooden case shall be fitted with an easily readable
nameplate of weatherproof material giving the following details:
✓ Type of pole
✓ Manufacturer's Name
✓ Manufacturer's Serial Number
✓ Year of Manufacture
✓ Rated Frequency
✓ Rated operating voltage
✓ Gross Weight
✓ Purchase order number & date
✓ Property of EEU
QUALITY ASSURANCE
The manufacturer shall submit Manufacturing Quality Assurance Plan (QAP) for approval
& the same shall be followed during manufacture and testing.
The material for final inspection shall be offered by the Supplier only under packed
condition. The owner shall select samples at random from the packed lot for carrying out
acceptance tests.
Guaranteed technical Schedules of Pole mounted distribution box
for 315kVA,
- 2x(3px250A)
- 1x(3px125A) and
- for street light
3x(1px50A)
for 400kVA,
- 1x(3px315A)
- 1x(3px250A)
- 1x(3px125A) and
for street light 3x(1px50A)
4 Rated short time withstand current kA 10
5 Power frequency withstand voltage kV 3
6 Impulse withstand voltage kA 8
7 Protection class IP IP20
No. Item Unit Requirement Offered
8 Outgoing terminal cross section mm2 Up to95
9 Clearance between open contact mm As per IEC standard
10 Clearance between poles (centre to centre) mm As per IEC standard
11 Creepage distance mm As per IEC60947
12 Mechanical endurance kN 80
PRODUCT 19 – MV Auto-Recloser
The Pole Mounted Auto-Recloser for 15 kV and 33 kV Systems shall comply with the
latest editions of and amendments to, the standards/specifications listed below:
IEC 60383 Insulators for Overhead Lines with a Nominal Voltage Above
1000 V;
IEC 60376 Specification of technical grade sulphur hexafluoride (SF6) for use
in electrical equipment;
BS EN ISO 2063 Thermal spraying. Metallic and other inorganic coatings. Zinc,
aluminium and their alloys;
BS EN ISO 1461 Hot dip Galvanised Coatings on Iron and Steel Articles.
Design
This specification covers the design, manufacturing, testing, supply, delivery and
performance characteristics of three-phase, pole mounted automatic recloser, both 15 kV
and 33 kV for use by the Ethiopia Electric Utility.
Performance Characteristics
• The rated continuous current shall be 200 A, 400 A and 630 A for the 15 kV
reclosers, as per specified requirements.
• The rated continuous current shall be 200 A, 400 A and 630 A for the 33 kV
recloser, as per specified requirements.
The short circuit levels given in 1.04 correspond to maximum system short circuit currents
i.e. 31.5 kA at 33 kV and 25 kA at 15 kV.
The recloser is required to operate with two instantaneous trips, followed by two variable
delayed trips.
The recloser shall be capable of performing a sequence of four trips prior to lockout even,
when the line fault is so close to the recloser that the line voltage at the recloser is essentially
zero at the instant of the trip.
If upon the first, second or third reclose normal conditions are restored on the line, the
recloser shall automatically reset after an adjustable time delay of 5, 10, 15 or 20 seconds.
The recloser will now be ready for a whole new sequence of operations.
Means shall be provided to lock out the recloser after one, two, three or four trip operations.
The selection of the reset time and the number of trip operations shall be done by devices
located in a control box.
One overcurrent device shall be provided for fault detection in each phase. The overcurrent
device shall have adjustable minimum phase tripcurrent settings at the values of:
20%, 40%, 50%, 75% and 100% of nominal rated continuous current
For series coil reclosers the highest value of minimum trip current should be equal to 140%
of the continuous coil rating. These coils shall be protected by fuses.
As well as phase overcurrent an earth fault current trip facility shall be provided.
The earth fault tripping levels shall be: 5, 10, 20, 35, 70, 100, 140, 200, 280 and 400 Amps.
Provision shall be made to obtain an individually adjustable time interval between each
opening and reclosing operation.
The range of "Dead Times" shall include the following 0.6, 1, 1.25, 2.5, 5, 10, 20, 30 and
60 seconds.
The selection of each "dead time" shall be independent and settable from devices located
in the control box.
Manual Operation
Means shall be provided to permit manual tripping, closing and lockout of the recloser
locally. These operations shall be done by hand or by operating rods. The automatic
recloser shall be locked out after manual tripping and shall reset after manual close.
Operation Counter
A mechanical operating counter shall be installed on the recloser which can be read by a
person standing at ground level. The counter shall be protected against moisture ingress.
The maximum radio influence voltage shall be 250 micro volts, measured as specified by
IEC 60437.
Tank Fabrication
The tank shall be made of steel of minimum thickness 3 mm and strong enough to support
dynamic short circuit forces and the vibration of the recloser.
The tank and its accessories shall be adequately protected against corrosion and the
Contractor shall include a statement of the method of protection proposed.
Hot dip galvanising is preferred, where this is not practical the tanks shall be shotblasted
and then immediately zinc sprayed to an average weight deposit of not less than 550 g/m2
followed by a zinc chromate based primary paint, and two coats of durable oil and weather
resisting paint. Finish colour shall be Admiralty grey.
The inside of tanks shall be coated with oil resisting varnish or paint so that the oil cannot
come into contact with the tank metal at any time.
The tank shall be perfectly sealed and dielectric fluid tight, with all fittings in place. The
head casting and the tank shall be weatherproof sealed under all operating conditions.
Indicators
All steel work shall comply with the standards outlined in the specifications for "Product –
Galvanized Steel Cross arms " –in Technical Specification of Cross Arms in this document.
Single pole structures or double pole structure with 1.8 m pole centers is used for mounting
the auto-recloser. The maximum pole diameter at the mounting height will be 240 mm.
Lifting Lugs
Lifting lugs shall be provided such that the recloser can be lifted with a single hook without
damage.
Grounding Terminal
Bushings
The terminations shall be brought out through bushings of antifog porcelain. The bushings
shall be rated to carry full line current and shall have spark gaps adjustable over the range
50100 mm.
Bushings shall be fitted with heavily tin- plated terminals and galvanised hardware to take
tin plated aluminium compression lugs.
Creepage Distance
The creepage distance of the bushings shall be 542.5 mm and 1116 mm for 15 kV and
33 kV respectively.
Bushing Labels
The bushings shall be clearly and unambiguously labelled. The labelling of the phases
shall be by raised lettering. Phase identification by adhesive stickers is not acceptable.
Interrupting Medium
The current interrupting medium shall be either vacuum or sulphur hexafluoride (SF6).
The SF6 type reclosers shall conform to IEC 60376.
Additionally all SF6 auto-reclosers shall be fitted with pressure relief vents and low
pressure lockout devices. The pressure relief vent is to avoid explosion by safely venting
any high pressure build-up within the equipment through the pressure relief arrangement.
The low pressure lockout device is to prevent equipment operation in the case of gas
leakage with subsequent loss of pressure.
Recloser Control
The recloser shall be fitted with a separate control box. This control box shall be suitable
for fitting on the pole at a lower level than the recloser. All fittings required for mounting
shall be supplied. All operating parameters of the recloser - minimum trip current, time
current trip characteristics, reclosing and reset times, operating sequences shall be
controlled from the control box. All settings shall be either positive stop selector switches
or plugin components. Ratings shall be clearly marked in relevant units of measure with no
interpretation multipliers or conversion being required.
Each unit shall be equipped with an electronic control capable of operating in the
environmental conditions specified above.
Marking
Each recloser shall be fitted with an easily readable nameplate of weatherproof material
giving the following details:
• Type of recloser
• Manufacturer's Name
• Year of Manufacture
• Rated Frequency
• Rated Voltage
• Rated Continuous Current
• Gross Weight
Type Tests
Type tests shall be carried out in accordance with the practices and tolerances of IEEE
C37.74.
The radio influence voltage test shall be carried out to IEC 60437.
Any item not meeting the type test requirement shall result in rejection of all units on order.
In case of rejection, the Purchaser shall not be liable for cost of type tests.
The Purchaser, at his discretion, may allow the contractor to carry out repeat type tests to
prove his design, but any such repeat tests shall be at the Contractor's expense.
Type/Design Tests may (at the Purchaser's discretion) be dispensed with if the Contractor
furnishes evidence to the Purchaser's satisfaction that the relevant tests have already been
performed on identical equipment. In this case the Supplier/Contractor shall provide
documentary proof in the form of Certified Test Certificates that the assembled equipment
and its component parts been successfully typetested by an independent testing authority
in accordance with the relevant clauses of referenced Standards. Test Certificates as
evidence of successful completion of type tests shall be submitted as part of the Bid.
Acceptable independent testing Authorities include the following: KEMA - Holland, CESI
- Italy, EDF - France and IREQ, - Quebec, Canada. Approval of type tests certificates
supplied by any other authority is subject to the written acceptance of EEU. .
Routine Tests
Routine tests shall be carried out in accordance with the practices and tolerances of IEEE
C37.74.
Any item not meeting the routine test requirements shall be rejected.
Inspection
The Purchaser reserves the right to witness the manufacturing process, any type tests
specifically performed on the equipment to be supplied to EEU and any routine tests
required in the manufacture and supply of such equipment. The Supplier shall provide free
access to the Purchaser to any site where such manufacturing process or tests, either type
or routine tests are taking place. The Supplier shall bear the in-plant costs of such
inspection. The Supplier shall provide the Purchaser of a schedule of manufacture and tests
at least two weeks before the events are to occur.
Technical Schedules
15 kV Auto-Recloser
__________________
Company Stamp
The Bidder is required to provide a list of recommended spares for a 5 year period. All
unit prices quoted shall be valid for any spare parts ordered by the Purchaser in this period.
Details of all special tools and test equipment (including prices where not included in main
offer) required should also be provided. All unit prices quoted shall be valid for tools and
test equipment ordered by the Purchaser during the Contract Period.
Signed __________________
Company __________________
1.2. The transformer shall conform in all respects to the highest standards of
engineering, design, workmanship of this specification and the latest revisions of IEC
standards at the time of offer and the purchaser will have full right to reject any work or
materials which are not in full accordance therewith. The offered equipment shall be
complete with all components necessary for effective and trouble-free operation. Such
components shall be deemed to be within the scope of the bidder’s supply irrespective of
whether those are specifically mentioned or not.
1.3. This Specification may not include all the necessary provisions of the contract
SYSTEM PARAMETERS & SERVICE CONDITIONS
The transformers to be supplied shall be suitable for satisfactory continuous operation
under the following climatic conditions:
S. N Item Parameter
REFERENCE STANDARD
The transformer shall comply in all respects to relevant international standards with the
latest editions or amendments thereof. In the event that no reference to Standard is made
herein, all components and parts shall be fabricated, inspected, tested and preserved, so as
to ensure their fitness for designed use and purpose. The bid shall include typical
dimensional and sectional drawings of the transformers and accessories
Relevant
Standard identifications Title
IEC 60071 Insulation co-ordination
IEC 60076 Power Transformers
Relevant
Standard identifications Title
IEC60137 Insulating bushings for alternating voltages above
1000 V
IEC 60214 On-Load Tap Changers
IEC 60296 Specification for unused mineral insulating oils for
transformers and switchgear
IEC 60317-0-1-2013 Specifications for particular types of winding wires-
Part 0: General Requirements-Section 1: Enameled
round Copper wire
IEC 60354 Loading guide for oil-immersed power transformers
IEC 60542 Application guide for on Load tap Changers
IEC60551 Determination of Transformer and reactor sound
level
IEC 60554-3-1 Specification for cellulosic paper for electrical
purposes-Part 3: Specifications for individual
materials, sheet 1- General purpose electrical paper.
IEC 60567 Guide for sampling of gases and oil from oil filled
electrical equipment and analysis of free and
dissolved gases
IECITR 60616 Terminal and tapping markings for power
transformers
IEC 60722 Guide to the lightning impulse and switching impulse
testing of power transformers and reactors
IEC 60599 Interpretation of the analysis of gases in transformers
and other oil-filled electrical equipment in service
ANSI/IEEE C 57. 12. 90 Test code for liquid immersed distribution, Power
and regulating Transformer
Electrical accessories shall comply with the relevant IEC standards even if not expressly
mentioned. In the event of direct conflict between various order documents, the precedence
of authority of documents shall be as follows –
The transformers shall be capable of withstanding external short circuits for at least
3 seconds following application of loading conditions specified in IEC 60076-7. The
transformer shall have a minimum insulation life of 20.55 years and service life at least 25
years
The ability of the transformer to withstand the dynamic effects of short circuit shall be
demonstrated by tests and complete test reports (including oscillograms and records of the
condition of the transformer before and after the short-circuit test) shall be submitted with
the bid for tender evaluation.
The transformer and its component parts shall be able to carry loading beyond rated power
under permissible loading given in IEC 60076-7, Table and clause 4.3.2 for distribution
transformers.
Neutral points shall be brought out on a bushing to enable LV transformer earthling.
The transformer shall be designed to minimize the risk of accidental short-circuit caused
by animals, birds or vermin. The manufacturer shall consider the safety of operators and
maintenance staff in the design of the transformer in particular the following aspects as per
clause 9.1.2 of IEC 60076-1;2011
All outdoor apparatus, including bushing insulators with their mountings, shall be designed
so as to avoid any accumulation of water.
The maximum noise levels shall be in accordance with BS EN 50464-1 and Table 5. The
sound level shall be measured and tested in accordance with IEC 60076-10 or NEMA TR-
1 and shall not exceed the guaranteed maximum level (without tolerance).
Drawings and documentation for each size of transformer offered shall be submitted with
tender. Clearly detailing importance dimensions, any special features of the offered design,
clearances, accessories, fittings and the features of the offered design that make it
impossible for vandals to siphon oil from the transformer even after forceful breaking of
accessory/fitting.
Design drawings (by the manufacturer) complete with manufacturer’s guaranteed technical
particulars (GTP) shall be submitted to EEU for approval before manufacture. The design
drawings shall be detailed and shall include a minimum of the following:
i.Overall dimensions of the transformer and relevant electrical clearances. This shall include
all perspectives and respective
a) Weight of oil.
d) Core material
f) Insulating materials
iv.Legend for all technical engineering drawings with manufacturer name, logo, model
number, revision/drawing number and key
The transformers of ratings 25kVA, 50kVA, 100kVA, 200kVA, 315kVA and 400KVA
shall be pole-mounted type.
Note: All design drawings must be stamped and signed by the manufacturer’s authorized
personnel
Sealing and cooling
The transformers shall be hermetically sealed oil transformers and shall be manufactured
with a sealed tank equipped with fins that allow the expansion at the temperature
variations. The tightness of the tank should be 0.5 Bar. The transformer should be designed
in such a way that oil does not come into contact with the air.
Leakage found shall be corrected by the supplier
Design of Cores
Core material
Only Prime and New core materials M3 Grade or better shall be used for the core
construction. The manufacturer shall provide all necessary proof and type test report. The
bidder should offer every batch of core lamination received from its sub vendors along with
Invoice of sub vendor, Mill test certificate, packaging list, Bill of lading, custom clearance
towards proof of prime core materials for verification by the purchaser without any cost to
the purchaser.
The design of the magnetic circuit shall be of non-ageing, Cold Rolled Grain Oriented
(CRGO) Silicon steel of minimum of M3 Grade (Nominal thickness of 0.23mm and
maximum total loss at 1.7T to be 0.85w/Kg or better as per IEC 60404-8-7) high
permeability without burrs and such as to avoid static discharges, development of short
circuit paths within itself or to the earthed clamping structure and production of flux
components at right angles to the plane of laminations which may cause local heating.
Each lamination shall be insulated with high quality insulation coating. The core and its
Clamping plates shall form a rigid unit structure, which shall maintain its form and position
under the severe stresses encountered during shipment, installation and short circuits
b) All parts of the cores shall be of robust design capable of withstanding any
shocks to which they may be subjected during lifting, transport installation and service.
c) All structural members of the assembled cores shall be of steel. All castings
shall be fitted and structural steel adequately cleaned and painted before being built into
the structure any non-magnetic or high resistance alloy used shall be subject to approval.
d) Adequate fitments shall be provided to enable the core and windings to be lifted
out of the transformer tank.
g) The framework and core bolts shall be effectively insulated from the core so as
to reduce circulating currents to a minimum.
Windings
General
a) The HV and LV windings shall be made of continuous smooth high-grade
electrolytic copper as per IEC 60317. The characteristics of copper required shall be as per
IEC 60076-5. The Purchaser will inspect the quality of copper material used: size of
copper, number of turns, weight of copper and density…etc.
d) Terminals of all windings shall be brought out of the tank through Bushings
for external connections.
e) The windings shall be uniformly insulated and the LV neutral points shall be
insulated for full voltage.
f) The completed core and coil assemble shall be dried in vacuum at not more
than 5mm of mercury absolute pressure and shall be immediately impregnated with oil
after the drying process to ensure the elimination of air and moisture within the insulation.
Vacuum may be applied in either vacuum over or in the transformer tank.
i) The stacks of windings shall receive adequate shrinkage treatment before final
assembly.
j) All leads or bars from the windings shall be brought out of the tank through
bushings for connection shall be rigidly supported. Stresses on coils and connections must
be avoided.
k) The coil clamping arrangement and the finished dimensions of any oil ducts
shall be such that they will not impede the free circulation of oil through the ducts.
Bracing of Windings
The windings and connections of all transformers shall be braced to withstand shocks
which may occur during transport or due to switching and other transient conditions during
service.
Any metal pieces in contact with end rings shall be so designed and secured that they do
not weaken the electrical or the mechanical properties of the rings.
If the transformer winding is built up of sections or disc coils separated by spacers the
clamping arrangements shall be such that equal pressure is applied to all columns of
spacers. All such spacers shall be securely located, shall be of suitable material and shall
receive adequate shrinkage treatment before assembly.
Technical data of the Medium Voltage windings (dimensions, number of turns, thickness
and type of wire, etc.) shall be supplied to Employer for purposes of windings repair, in
Purchaser's workshops.
The data shall be submitted together with the offer, or when submitting documents for
prototype approval.
Insulating Material
a) The HV and LV windings shall be separated so as to allow for cooling and ease
of repair. Insulating sleeves for the transformer tapping’s shall be in crepe paper and inter
layer insulation shall be in Grade K- Diamond dotted press paper.
There shall be double layer enamel insulation for the copper winding conductor. The
insulation shall be of class A with temperature class of 105oC as per IEC 60085.
b) Grade K- Diamond dotted Press Paper (thermopox): is a press paper with
qualities to improve the mechanical strength of oil immersed transformer windings without
reducing partial discharge levels in accordance with IEC standards 60641-2 and 60243-1
a) The Primary of transformers (HV side) will have three bushing in porcelain.
b) Bushings shall be outdoor type, easily replaceable and shall be located on the
top. Bushing Material Shall be Porcelain material. Cemented in type bushing shall not be
accepted. The Bushing Shall be manufactured and tested in accordance with IEC
60137/DIN 42530/DIN 42532/DIN 42534/DIN42539 BSEN standard.
d) MV bushings shall be rated to withstand the highest system voltage and the
maximum fault current of the windings when connected to the 15kV network and for the
same period of time.
The bushings shall be equipped with line clamps suitable for the connection of aluminium
(up to 240mm2) or copper (up to 150mm2) conductors of Medium voltage line.
Minimum external clearance values specified in the above table is for an altitude of 3000meter.
Creepage distance for MV bushings
The outer creepage distance for outdoor bushings shall not be less than 30mm/kV. The
insulation levels of the bushings shall conform to the given in the technical schedule.
The Bidders shall submit to the Purchaser the Type tests reports of medium voltage
bushings with their bids. The type tests shall be performed according to the latest published
International Standard IEC 60137 and shall include the following type tests:
✓ Wet power-frequency voltage withstand test
✓ Dry lightning impulse voltage withstand test
✓ Temperature-rise test
✓ Verification of thermal short-time current withstand test
✓ Cantilever load withstand test
✓ Verification of dimensions
LV Bushings
a) The position of each LV bushing shall be permanently and legibly marked on
the tank or lid with a label corresponding to the rating plate designation. The LV neutral
connection shall have a permanent, special marking, different from the phase connections.
The LV rod diameter shall be greater than or equal to M20 depending on the current rating.
Bushing Labels
The HV bushings shall be labeled - 1U, 1V, 1W and the LV bushing 2u, 2v, 2w, 2n. The
labeling of the phases shall be by permanent raised lettering on the transformer tank or
cover. Phase identification by adhesive stickers is not acceptable.
50 45
100 46
200 47
315 48
400 50
Every care shall be taken to ensure that the design and manufacture of all transformers and
auxiliary plant shall be such as to reduce noise and vibration to the level of that obtained
in good modern practice.
DUTY UNDER FAULT CONDITIONS
Any transformer may be directly connected to an underground or overhead distribution line
and switched into and out of service together with its associated distribution circuit.
The Transformer shall be capable of carrying its normal rating continuously at any tap
without undue stress and Overheating.
All transformers shall be capable of withstanding for three seconds without damage any
external short-circuit.
2 Any wiring liable to come in contact with oil shall have suitable oil resisting
insulation. The ends of stranded conductors shall be treated to prevent creepage of oil inside
the wire. There shall be no possibility of oil entering connection boxes for cables or wiring.
1. ELECTRICAL DATA
1.1. SHORT-CIRCUIT CURRENTS
The transformers shall withstand the thermal and mechanical effects of any short-circuit
that can appear at the terminal of any winding. The short-time current (3sec (rms.) shall be
for the specified system fault levels.
1.2. INSULATION LEVEL
The complete transformer arranged for service shall comply fully with the requirements of
IEC 60076-3 including altitude correction factor
All secondary voltage ratings shall be at full load current at nominal tap.
1.4. VECTOR GROUP
The vector group of the three-phase transformers shall be Dyn5.
2.2 the mv windings shall be provided with an off-load tap changer providing 5
positions and each step shall be 2.5%. the tap settings shall be 5%, +2.5%, 0%, -2.5%, -
5%, for three phase transformers.
2.3 the off-load tap changer shall be linear type and mounted on top cover. the tap
changer shall be operated after disconnection of power supply.
3. LOSSES
The bidders’ offers shall be accompanied with Type test reports (as per IEC60076 and
IEC60071) conducted at independent third-party testing Laboratories for the offered that
was conducted within five years from the date of the bid submission. Type tests shall be
conducted on the Transformers of identical design to prove that the offered transformers
satisfy all the design requirements set out in this specification.
In case of any doubts, Ethiopian Electric Utility (EEU) reserves the right to verify the
original type test reports of the independent third-party testing Laboratory or ask the
supplier to conduct the type tests at an independent third-party test laboratory which is
approved by EEU without ADDITIONAL COST to the employer (EEU)
The maximum Load losses and No-Load losses at rated load and conditions shall be as
given below:
The above losses are the maximum allowable and there should not be any positive
tolerance.
Provided that the tested loss is below the required maximum load loss, if, on delivery, the
tested losses exceed the guaranteed losses, the excess of the guaranteed values will be
capitalized, and the amount deducted from the contract price as below:
✓ No Load Loss US$6000 per kilowatt.
✓ Load Loss US$3200 per kilowatt.
There will be no credit for losses less than the guaranteed value.
4. TRANSFORMER TANKS
The smaller parts such as brackets, etc. shall be hot-dip galvanized. Fasteners mounted on
hot-dip galvanized or ready painted part shall be galvanized or made of stainless-steel ISO
class F1 or A2.
All steel surfaces shall be sand blasted in accordance with DIN 55928 Part 4 and shall then
be painted in the following sequences.
If any hot dipped galvanized parts are provided the same painting method shall be applied,
however instead of two primer coats one adhesive coat and one base coat shall be applied.
In this case the mean thickness of galvanizing shall be 70 µm. Mechanical damage shall be
repaired at site with original paint as above.
The overpressure relief device shall be covered with a suitable "cover" to protect persons
in the vicinity of the transformer against the spurting of hot oil in the event of an internal
fault of the transformer. The cover (window of the cover) shall be directed toward high
voltage side of the transformer.
5. TRANSFORMER OIL
a) The transformer shall be filled with oil up to maximum permissible level before
delivery. The complete first filling shall be of new oil free from inhibitors and additives up
to maximum permissible level for the supplied transformer. The oil shall contain at least
0.3% by weight oxidation inhibitor of type (DBPC) according to IEC 60296.The oil shall
be new and satisfied to contain less than 2 mg/Kg (not detectable) of PCB’s.
d) The type of insulating liquid, e.g. “Mineral oil-based insulating oil pursuant to
DIN VDE 0370”/relevant IEC is to be indicated on the rating plate of each transformer.
6. UNDERCARRIAGE
The following undercarriage shall be provided as specified in the technical schedules.
Transformers shall be fitted with an under frame suitable for bolting the transformer to a
pole mounted platform in case of pole mounted transformers.
7. EARTHING TERMINAL
The material shall be copper or brass type earthing flag approximately 63 mm square and
a thickness not less than 6 mm with a center hole of 12 mm diameter shall be welded
externally to the tank, one on the tank cover and one on the base frame.
A grounding sign shall be put next to the grounding screw. The marking shall be stamped
and red color painted on tin plates which shall be fastened with transformer.
a) Rating and diagram plates bearing the data specified in the appropriate
IEC recommendations.
b) Oil filling and drain valves. It shall only be possible to open these
valves with a special key/spanner to discourage tampering.
c) Tank earthing terminal. M12 size screws -2 Nos. one on the tank cover
and another on the base frame suitable for copper earthing wires.
d) Lifting fittings
i) Cable Clamps
l) Arcing Horns
1. Type Tests,
3. Acceptance Tests.
Prior to the tests the supplier shall submit an outline of the procedures and tests in its plans,
to demonstrate fulfilment of the requirements specified in subsequent sections of the
detailed technical specification
Before regular manufacturing commences, samples of the equipment i.e. the transformers
shall be made available for testing to ensure compliance with the design.
The Buyer reserves the right to call for type tests on the equipment at the Supplier’s
expense, on samples selected at random at the Manufacturer's Works and witness these
tests at an approved independent third-party standard Laboratory. Failure to meet the
conditions of test could result in the rejection of a complete batch of equipment’s.
The Buyer will have the authority to delay delivery of any items of equipment, which have
not been tested and approved in accordance with the Contract.
The Supplier shall report on progress and will compare the Supplier’s production program
with actual progress and shall report in a timely manner to the Employer the reason for any
delays.
The inspection and acceptance tests shall be carried out in accordance with the provisions
in the applicable standard, supplemented by the specific requirements indicated in the
technical specifications free of cost to the Employer.
At least 21days’ notice of the date, time and place of all tests shall be given to the Buyer
so that arrangements can be made to have the test witnessed.
In addition to the above requirements, the following requirements shall apply and take
precedence.
1. TYPE TESTS
In addition to the IEC requirements the following type tests shall be conducted on the
Transformers of identical design to prove that the offered transformers satisfy all the design
requirements set out in this specification.
Checking of weights, dimensions, fittings, accessories, tank sheet thickness, oil quality,
material, finish and workmanship as per Guaranteed Technical Particulars and contract
drawings
4. ACCEPTANCE TESTS
All acceptance tests as stipulated in the relevant standards and as given below shall be
carried out by the supplier in the presence of the Employer’s/Buyer’s representative on
10% samples.
1)Visual Inspection
2)Measurement of winding resistance and Megger test.
3)Voltage ratio measurement and check of polarity or vector group symbol at all tap
positions. Bushing positions shall have permanent markings at this stage of production.
7)Dielectric test.
9)Induced over voltage withstand test 30kV and 66kV for 60 seconds on the 15kV and 33kV
windings respectively.
5. SPECIAL TESTS
Other type and routine tests shall also be carried out as per IEC60076-3 clause 7.3.3.2 with
the interest of the employer without additional price.
1)A rating plate bearing the data specified in IEC 76 or other approved standard. Indicating
tfollowing shall be fixed on the same side as LV bushings,
2)Name of manufacturer,
4)Year of manufacture,
5)Rated power,
6)Rated frequency,
7)Rated voltages,
8)Rated currents,
10)short-circuit impedance,
13)Total mass,
16)Insulation level,
17)Type of cooling,
19)Each bushing shall be marked with the name or trademark of the manufacturer,
20)A diagram plate showing the internal connections and also the voltage vector relationship
of the several windings. In addition, a plan view of the transformer giving the correct
physical relationship of the terminals shall be given. When links are provided for changing
the transformer group symbol and/or ratio, then means shall be provided for clearly
indicating in which mode the transformer is connected. The transformer ratio shall be
indicated for each tap,
The above plates shall be of stainless steel or of other material capable of withstanding
continuous outdoor service and shall all be suitably mounted to prevent vibration, rattling
or corrosion.
TRANSPORT
The equipment should be individually packed with plastic pallets in a way suitable for
transport. The packing should be suitable for introducing equipment into standard transport
industry containers. All additional elements of the equipment should be packed into a
single crate.
Transformers should be transported with their complete oil load and accessories in place.
The transformer should be completely secured in its packaging.
A visual inspection of the equipment will be carried out up on receiving it, checking for
possible damage occurred during transport and the ware housing process. In addition, if
there are complementary elements, they should be verified (clamps, grounding bolt, fuses,
etc.) at the store.
PACKAGING
Each Packaging shall be clearly marked in Print (Capital Letters) with the following data
in each transformer:
• Contract No.
• Serial No
• Instructions for unloading with a mobile crane and with a fork-lift truck, checking
of the correctly balanced during the transportation.
QUALITY PLANS
The bidder shall draw up for each section of the work quality plans which shall be
submitted to the Purchaser for approval at least two weeks prior to the commencement of
work on the particular section. Each quality plan shall set out the activities in a logical
sequence and, unless advised otherwise, shall include the following:
I. General
1 Manufacturer’s Name
2 Country of manufacturer
20 HV Windings
No Item Unit Requirement Bid Offer
32 Secondary
32.1 Manufacturer
32.2 Type (DIN type or eqvt.) Yes
32.3 Rated current A
32.4 power frequency test kV 3
32.5 lightning impulse test kV 8
32.6 clearance across insulator mm 80
32.7 Min. creep age distance mm 70
33 Noise level dB(A) <48
34 VI. Materials, Masses, Measures
and Drawings
34 Transformer tank, material Steel
34.1 Transformer total mass kg
34.2 Overall dimensions including
bushings:
34.3 Height mm
34.4 Depth mm
34.5 Width mm 900 to 1400mm
34.6 Thickness of tank plate
34.7 Top mm Minimum 5mm
34.8 Bottom mm Minimum 6mm
No Item Unit Requirement Bid Offer
Company Stamp
Guaranteed Technical Schedules for 33/0.4kV, 315KVA Distribution Transformer
I. General
1 Manufacturer’s Name
2 Country of manufacturer
20 HV Windings
20.1 Material, wire or strip Copper
wire/strip
20.2 Insulation
20.3 Power frequency withstand voltage kV(rms) 95
20.4 Rated lightning, impulse withstand kV(peak) 250
voltage
21 LV Windings
21.1 Material, wire or strip Copper
wire/strip
21.2 Insulation
21.3 Power frequency withstand voltage kV(rms) 3
32 Secondary
32.1 Manufacturer
32.2 Type (DIN type or eqvt.) Yes
32.3 Rated current A
No Item Unit Requirement Bid Offer
Scope of supply
Design, Manufacture, Testing at manufacturers works before dispatch, Packing, Delivery
of material and submission of documents to purchaser
Application: This specification specifies the performance and general requirements for
three phase pole mounted load break switch for outdoor dependent manual operation as
load break switch in 15kV and 33 kV network in given service conditions.
2.5 Insulators pins and conductor fittings for overhead power lines, BS3288
Service Condition
Item Parameter
Altitude Any altitude up to 3000m
Annual Rainfall 1250mm
Period of exceptional Rains June to September
Ambient Air Temperatures:
Average +300c
Minimum -50c
Maximum 500c
Relative Air Humidity 70%
Wind Velocity:
Maximum wind( height above ground level)
0-30m 35m/s
30-50m 45m/s
Isoceraunic Level Upto100 thunderstorm days/year
Seismic Level No records of any activity
Design
The load break switch shall fulfil the following minimum requirements according to
IEC265 and IEC129 under IEC standard conditions
The load break switch shall be suitable for mounting on single concrete/steel pole and shall
be ready for mounting and operation. It shall be complete with all necessary items such as:
• Operating rod and handle for manual control with necessary fixing accessories
and padlock
• Cross arm where insulators strings with clevises can be fixed. Clevises are
according to IEC 60471 or BS 3288 for ball eye of standard coupling size 11
according IEC 60120 and BS 3288 with minimum failing load 70KN.
• Earthing connection for protective earthling conductor of cu 35mm2.
• Clamps for connecting all aluminium conductors of AAC 50 up to 240 mm2 both
for incoming and outgoing side.
• All accessories and structures needed to mount on a single concrete/steel pole
• The length of the load break switch cross arm shall be preferably 2000mm for 15kV
and 2500mm for 33kV. However, alternatives may be quoted. The switch
disconnected cross arm shall be suitable for installing tension insulator strings of
cap and pin type. The load break switch shall be supplied with complete accessories
and structure to mount on a single concrete/steel pole. The purchase should not use
additional material to mount the load break switch on a single pole.
Materials
The insulator material shall be porcelain or toughened or annealed glass or cast resin. The
terminal shall be compatible and ready connecting with aluminium conductor.
Markings
The load break switch shall be marked according to requirements of IEC 60265
Testing
Testing shall be in accordance with IEC 60265 and IEC 60129.
Installation
The load break switch shall be mounted at the top of a single pole. Operation and locking
to both open and closed positions with a padlock shall be possible from the ground level.
The switch shall be suitable for single pole mounting on pole of 11m or 12mt length with
the following top diameter:
REFERENCE STANDARDS
The Fault passage Indicator (FPI) including the operating devices, accessories and
auxiliary equipment forming integral part thereof, shall be designed, manufactured,
assembled and tested in accordance with the relevant standards, specification and codes
of practices, referred to herein and shall be the latest editions including all applicable
official amendments and revisions.
The design, manufacture and performance of the equipment shall comply with all
currently applicable statutes, regulations and safety codes.
Unless otherwise specified, the equipment offered shall conform to the latest applicable
Standards and in particular, to the following:-
IEC 61010 Standard for safety requirements for electrical equipment for
measurement, control, and laboratory use
IEC 60445:2021 Basic and safety principles for man-machine interface, marking and
identification - Identification of equipment terminals, conductor
terminations and conductors
IEC 60445:2021 Direct acting indicating analogue electrical measuring instruments and
their accessories
EN 60-950 Product Safety testing standard for "Information Technology Equipment"
(known as ITE)
IEC 60529 Protection against accidental contact, foreign Objects and water
The Fault detection system shall be designed to operate in the following environmental
conditions.
Description Service Condition
Altitude Altitude 3000m
Annual Rainfall 1250mm
Period of exceptional Rains June to September
Ambient Air Temperatures:
Average +300c
Minimum -50c
Maximum +500c
Relative Air Humidity 70%
Wind Velocity:
Maximum wind (height above ground
level) 0-30m 35m/s
30-50m 45m/s
Isoceraunic Level Up to 100 thunderstorm days/year
Seismic Zone Zone 4
Pollution (IEC 60815) Very Heavy:- Class IV
System parameters
The Fault detection systems shall be designed to operate on a 15kVand 33kV overhead
line network with the following characteristics:
• The OHL fault indicator shall be designed to operate at ambient temperature from
-5oC up to +50oC
• It shall be suitable for mounting on OHL conductors from 5mm up to 35mm
overall diameter with rated operating voltage of 15kV and 33kV.
• The housing of OHL fault indicator shall be made of weather proof, robust, non-
metallic, fire retardant, UV stabilized material.
• The OHL fault indicators shall be suitable for outdoor installation with IP65
degree of protection or better
• The OHL fault indicators shall be suitable for installation and removal on live
overhead lines with the use of insulated hot-stick provided by the manufacturer.
• Hot-stick mounting adapter shall be supplied for every 100 units of OHL fault
indicators
• Clamping tightness of OHL fault indicators shall be able to withstand wind
pressure without slipping or falling out of the conductor.
• The OHL fault indicators shall be equipped with local indications. Local
indication by ultra-bright blinking LEDs (red color). Any additional local
indicating method may be proposed and shall be evaluated by EEU. Local
indications shall have a clear 360° visibility from a distance of 100m at daylight
and 500m at night-time.
• The OHL fault indicators shall be maintenance-free, fully self-contained without
external transformer or connections, and do not require additional source of
supply.
• The battery for driving the local indications shall be high-grade non-rechargeable
(lithium-ion) battery easily replaceable with or without using common hand tools
and shall have a minimum operating life of 10 years in the atmospheric
temperature conditions specified above.
• The total continuous flash indicating time of OHL fault indicator shall be 1500
hours or more.
• Flashing period for permanent faults shall be programmable.
• Soldered battery terminal connections are not acceptable.
• The OHL fault indicators shall be bi-directional and able to detect all line-to-line
and line-to-ground fault conditions with built-in restraints to prevent false
operation due to sudden variations in load current, proximity to other circuits,
inrush currents due to feeder switching or auto-recloser operation.
• The OHL fault indicators shall be equipped with the following selectable and
adjustable local reset options:
✓ Local Automatic Reset: 10 to 30 seconds after recovering the line voltage (re-
energized line) and return of minimum primary current of 3A.
✓ Local Time Reset: selectable to 2, 4, and 8 hours. Local manual reset shall
also be provided such as by using magnet mountable on standard insulated
hot-sticks, or proximity local, or any other method accessible from the ground
level. Magnet and its adapter to hot-sticks, and/or proximity local shall be
supplied for every 100 units of OHL fault indicators.
• The OHL fault indicators shall be provided with manual pre-adjusted trip current
value of the load currents in steps of up to 500 amperes or better, and load
dependent self-adjusted value of trip current.
• The OHL fault indicators shall have a response time not lower than 80ms to
prevent false indication due to disturbances with tolerance of ±10ms.
• One single product shall be proposed to cover the whole range of above
characteristics:- Particularly, the same product should be installed on any network
for 15KV or 33 kV
Marking
Each OHL fault indicators shall have a clear and durable nameplate that will remain
visible throughout the lifetime of the device, and shall bear the following information: -
• Manufacturer Name and Model/type
• OHL Fault Indicator Ratings
• Conformance standard
• Serial Number
• Year of Manufacture
• Property of EEU
PACKING AND SHIPPING
Each OHL fault indicator shall be packed in a box as a complete unit and shall be
delivered ready for use. Accessories like hot-stick mounting adapters, manual reset
(magnet + hot-stick adapter and/or proximity local remote-control) should be supplied in
a separate box with printed marking relating to the box of the OHL fault indicator. A
minimum of one (1) of each accessory should be provided for every 100 units of smart
OHL fault indicator supplied.
Packing shall protect the OHL fault indicators against damage during shipment and site
handling. Suppliers should coordinate with EEU Warehousing Department for additional
packing, handling, and or shipping instructions, as applicable. Each box shall be printed
with the following information:
a. Purchase Order Number / Tender Number
b. OHL Fault Indicator Rating
c. Manufacturer’s Name and Model/Type
d. Year of Manufacture
e. EEU Item Code
Test Requirements
• The OHL fault indicator shall be inspected and tested in accordance of IEC or
Equivalent Standards.
• Copies of previous test/calibration reports issued by third party testing laboratory that
is accredited to ISO/IEC 17025:2005 or 17025:2017 confirming accuracy and
compliance of the overhead line fault indicator offered shall be submitted with the
offer for evaluation.
• Routine test shall include:-
✓ Visual and dimensional inspection
✓ Grip force and deflection
✓ Vibration resistance
✓ Torsion and tension of the adapter
✓ Drop resistance
✓ Shock resistance
✓ Climate dependence
✓ Degree of protection
✓ Durability of markings
✓ Functional tests on the indicator
• The following type test reports shall be submitted:-
✓ Electromagnetic compatibility (EMC)
✓ Impulse overvoltage tests on the equipment – clearances
✓ Dielectric voltage withstands tests on the equipment – controlled
overvoltage
• Functional tests shall include:-
✓ Clear indication
✓ Clear perceptibility of visual indication
✓ Frequency dependence
✓ Response time
✓ Power source dependability
✓ Check of testing element
✓ Non response to d.c voltage
• The following type test report for printed circuit board coating performance shall be
submitted:-
✓ Environmental, humidity and thermal conditioning tests
✓ Dielectric voltage withstand tests
✓ Protection against bridging for indoor/outdoor type
✓ Spark resistance
✓ Comparative tracking index
✓ Resistance to soldering heat test
✓ Flammability test
✓ Coating adhesion test
✓ Insulation resistance between conducting parts
✓
Training
The successful bidder shall give training about installation, Operation & Maintenance.
Training at different site to the personnel as deputed by the awarding authority. The
successful bidder shall submit the training schedule to the site authority for EEU. The
Training should be comprehensive to the satisfaction of the trainees. The Trainer should
cover both theoretical & practical aspects of the modules, operation & maintenance
requirements of the modules etc. The trainer shall also exhibit major components of the
modules separately for visual clarity of the trainees with better understanding. The
successful bidder shall bear every cost required for the Training.
Documentation
Each device shall be supplied with a user manual for installation, maintenance and
commissioning at site.
Quality Assurance
The Bidder shall supply documentary proof that the manufacturer possesses ISO 9001
and ISO 14001 Quality insurance certification, for the design, manufacture and testing of
Fault Indicators for medium voltage lines.
GUARANTED TECHNICAL PARTICULARS for NON
COMMUNICABLE OVERHEAD LINE FAULT PASSAGE
INDICATOR (FPI) / FAULT SENSING INDICATOR (FSI) (TO BE
FILLED UP BY BIDDERS)
To be filled and signed the Manufacture and submitted together with relevant copies of the
Manufacture’s catalogues, drawings, technical data, sales records for previous five years
four customer reference letters, details of suppliers’ capacity and experience; and copies of
complete type test certificates and test reports for tender evaluation, all in English
Language
2 Country of Manufacture
DESIGN
The medium voltage switchgear should be gas insulated and should consist of the following
components.
⮚ Load break switch insulated with SF 6and operated with motor/manual
for incoming lines.
⮚ Vacuum Circuit breakers operated with motor/manual for outgoing
feeder lines.
All individual switches should be lockable in open position with padlock.
The switchgear should be sealed for life. The Spring Mechanisms shall be of long-life
corrosion resistant material and dust proof. Degree of Protection of the housing should be
a minimum amount of IP54.
The Ring Main Units (RMU) are installed on MV feeders for feeder automation to detect
faults on MV lines, isolating the fault through feeder sectionalisation and restore power
supply to the healthy part of feeder, by extending alternate power supply. The RMU should
also facilitate load balancing on the feeders by shifting loads from one feeder to another
feeder.
The RMUs should accommodate Non Extensible RMUs.
Non-Extensible RMU Switch Board
These units shall comprise of a set of stand-alone units of vacuum circuit breakers to be
coupled together to form a switching station or switch board inSF6 insulation enclosure.
The RMU switch board facilitates the transmission of power from substation to load centre
through high capacity express feeders and distribute the power received at load centre to
flow capacity feeders emanating from load centre and feeding Distribution Transformers.
Power supply from 2 or more main MV express feeders emanating from same or different
substations may be accommodated, to extend alternate power supplying the event of outage
of any feeder, after isolating the faulty feeder. The units shall be outdoor ground mounted
type.
Performance Characteristics
I Overall Unit
a) Service Outdoor
b) Type Metal enclosed
c) Number of Phases 3
d) System Voltage 15kV
e) Rated Frequency 50 Hz (±5%)
d Maximum rated voltage 17.5kV
e Maximum equipment rating voltage 24kV
f Insulation SF6 and Vacuum
g SF6Monitoring system Pressure Gauge and Low
pressure alarm.
II Load Break and Fault making(LBFM)Switches
a No. of poles 3
b Switch Type SF6-Single Break, Load
breaking and fault making
switch
c Rated voltage 15 kV
f Rated current 630 Amps
g Load breaking current 630 Amps at 0.7PF
h Short Time Rating 25 kA for 3 Seconds.
i Making capacity 62.5 kA
j Impulse withstands voltage to earth 125kV
between poles.
k Power frequency withstand voltage to 50kV
earth and between poles
III Vacuum Circuit Breakers
a) Type Vacuum
b) No. of poles 3
c) Rated Voltage 15kV
d) Rated Current 630A
e) Breaking current 25kA for 3 Seconds.
f) Making current 62.5kA
g) Impulse flashover withstand voltage 125kV peak
h) Power frequency withstand voltage 50kV
IV Bus bars
a) Material Copper
b) Rated Current 630 Amps
c) Breaking Current. 25 kA for 3 seconds
d) Insulation of bus bars EpoxyorPVC sleeved
insulation to be provided.
e) Bus bar connections Anti-oxide grease
f) Bus bar end Caps Yes
V Current Transformers
a) Three Nos. Cast-resin CTs around bushing on or split core type around
XLPE cables for.
b) Current Transformer ratio For incoming 800/1A and for
outgoing 300/1A. Resin cast
c) Over current factor To correspond to breaking
capacity circuit breaker
d) Class of accuracy 5P10
e) Rated burden, VA 90
Accuracy limit factor, ALF
f) Rated burden As designed to drive the
protective relays
g) Impulse flash over withstand voltage 125kV (peak)
h) Power frequency withstand voltage 50kV
VI Protection
a) Self powered IDMT Protection relays (Numeric/ Micro Processor
based) 2 Nos. over current 1 No. earth fault element shall be of IDMT
relay for feeder control with Display for operator ease for tripping and
closing.
b) It shall be provided with emergency OFF push button
Time delay 50 ms to 20 S
Setting ranges of Earth Fault time delayed (51 N)
PS 1% to 100% of In or better
TMS 0.002 to 2.00
Title:
Issue No. Page 315 of
Technical Specifications for 15KV and 33KV Surge Arrestors. 1
433
1 General Details
2 Manufacturer’s name
3 Switchgear model No
4 Type SF6 gas insulated and
Vacuum
II APPLICABLE STANDARDS
1 Rated voltage kV 15
2 Highest system voltage kV 17.5
3 Highest equipment voltage rating kV 24
4 Rated frequency Hz 50
5 One minute power frequency kV 50
withstand voltage
6 Lightning Impulse withstand voltage kV(pea 125
k)
7 Rated short time current kA 25
8 Rated duration of short circuit Sec 3
9 Rated making current kA 62.5
10 Operating cycle 0-0.3S -CO-3 Min-CO
11 Minimum SF6 gas pressure at 20°C kg/cm² 1.35
IV ENCLOSURE
1 Material (Main Tank) Galvanized steel sheet
2 Thickness of enclosure, partition and mm Not less than 2.5mm
doors
3 Thickness of enclosure base mm not less than 4mm
S.No Description Unit Required by EEU Offere
4 Separate compartments for each of Yes
VCB Disconnector Switch, Bus bar
provided
5 Normal SF6 gas operating pressure kg/cm² 1.35
6 Type of pressure relief device &
location
V VACUUM CIRCUIT BREAKERS
1 Rated normal current A 630
2 Rated short circuit breaking current KA 25
3 Rated short circuit making current KA 62.5
4 Rated Impulse withstand voltage KV 125
5 Rated power frequency recovery KV 50
voltage
6 Small inductive breaking current: A
7 Rated cable charging breaking A 50
current
8 Rated out of phase breaking current A
9 On supply side of circuit breaker kV
(peak)
10 On load side of circuit breaker kV
(peak)
11 Opening Time ms 35
12 Maximum Arching Time ms 6
13 Rated maximum total break time ms 31
14 Maximum Closing time ms 150
15 Length of Each Break Mm
16 Minimum number of operations at ● Mechanical
rated current(as per IEC 62271-100) Endurance-class M2(10,000
operating sequences)
● Electrical
Endurance – E2
VI Load Break and Fault making (LBFM) Switches
S.No Description Unit Required by EEU Offere
1 No. of poles 3
2 Switch Type SF6-Single Break, Load
breaking and fault making
switch
3 Rated voltage kV 15
4 Rated current 630 Amps
5 Load breaking current 630 Amps at 0.7PF
6 Short time Rating 25 kA
7 Fault making capacity (kA peak/
62.5 kA
min.)
8 Impulse withstand voltage to earth
kV 125
between poles.
9 Power frequency withstand voltage to
kV 50
earth and between poles
10 Operating mechanism Motorized LBS Each motor
for close / open shall be provided with
separate MCB and Local-
Remote switch.
11 Manual operation Possible without removal of
motor
12 Addition / removal of Without overhaul of
motor operating mechanism
4 Class of accuracy
(i) Protection core 5P10
(ii) Metering core CT for measurement
purpose shall be provided
5 Rated burden by EEU. Free space shall be
6 Impulse flash over withstand voltage KVp available inside the RMU
for installation of
7 Power frequency withstand voltage KV measurement CTs
CONTROL SUPPLY
The line sectionalizers are provided with a Voltage transformer on one side or either
side as the case may be to sense the powered supply and provide Control supply for
operation of sectionalisers.
FAULT BREAKING CAPACITY
The sectionalisers shall have no rated fault breaking capacity and will sectionalise the faulty section
(which it is to control) only when the power supply to the line is interrupted by the controlling circuit
breaker/auto recloser at the main substation.
OPERATION
Purpose of sectionalizers
The sectionalizers are deployed in Distribution system to improve the reliability of power supply.
The sectionaliser is load breaking and fault making switch with Voltage sensing and timing control
mechanism. The sectionaliser has no fault current interrupting capability and therefore always work
in association with a circuit breaker having auto reclosing facility.
Functions of Sectionalisers
The function of a sectionaliser is to isolate the faulty section and restore power supply to healthy part
of feeder when a permanent fault occurs on the feeder. If the fault is transient in nature, then supply
is restored after momentary interruption on reclosing of feeder circuit breaker
Components of Sectionalisers
The sectionaliser consists of 3 parts
Load breaking and fault making SF6/ Vacuum switch called DM switch
Fault detecting and control relay box called TSR
Voltage Transformer on either side of sectionaliser on loop feeder and on incoming side only for
radial feeder.
Operation of sectionaliser
The principle of operations how the Sectionaliser operates in case of transient fault
and permanent fault on radial feeder and Loop feeder is explained in Appendix A
Advantages of Sectionalisers
The advantages of Sectionaliser are
Any number of Sectionalisers can be deployed on line in series, improving reliability
index to desired level.
The number of interruptions to any customer for any permanent fault is only
two irrespective of location
The sectionalisers facilitates automatic power supply restoration from loop feeder in
case of fault providing supply to all healthy sections other than faulty section.
ELECTRICAL AND MECHANICAL ENDURANCE
The voltage sensing sectionaliser shall be capable of performing not less than 20,000 mechanical
operations and 20,000 electrical operations at rated current without getting damaged.
FAULTY SECTION INDICATOR
An indicator to indicate the faulty section shall be provided on the controlling breaker in the main
sub-station. The indicator shall indicate the particular sectionaliser which has locked out on
permanent fault. The indicator will work on the basis of discrimination of time elapsed between the
first reclosing of the circuit breaker and its next tripping due to permanent fault in a particular
section.
DESIGN AND CONSTRUCTIONAL REQUIREMENTS
The sectionalisers shall be of either vacuum of SF6 type.
The equipment shall be of outdoor type and suitable for mounting on single or double-pole
structures.
Tank
The switching contacts are housed in a steel tank of thickness 3mm. Thickness below the minimum
value will be considered only in exceptional cases where protective finishes are used. The contractor
shall provide full information where any such special finish is used and also provide field experience,
if any.
Each tank shall be provided with an explosion vent on the side (only for SF6 type) which shall safely
release any over pressures developed by excessive internal arcing. A mechanical low gas pressure
interlock which prevents operation of the sectionaliser if the gas pressure falls below certain safe
pressure shall be provided. There shall be a visible indication of low gas pressure through a window
in the tank and also through a flag which could be seen from the ground.
The sectionalisers shall be provided with a mechanically operated contact position indicator. The
provision shall also be made for manual opening and closing of the sectionaliser from ground level
using a hook stick.
A manual lock-out ring which when pulled by the hook-stick prevent operation of the sectionaliser
to take up maintenance work in the downstream of the sectionaliser.
Indicators
Two nos. ON/OFF indicators shall be provided, one on the side of the tank by the operating lever
and one underneath the tank visible to the operator from below.
Sectionaliser bushing terminals shall be designed so as to directly receive AAAC conductor up to 200
mm² size by using bolted clamps so as not to require the use of lugs. The terminal arrangement shall
be such as to avoid bimetallic corrosion.
SF6 Lockout
If the unit is SF6 insulated then a lockout on low pressure should operate and prevent the unit from
closing.
A visual alarm shall be incorporated in case of low gas pressure.
COORDINATION WITH THE SUB-STATION BREAKER
As the sectionalisers installed on a feeder work in coordination with the circuit breaker or an auto-re-
closer at the main sub-station controlling the feeder, this aspect requires proper attention. In the case
of manually operated circuit breaker, the normal interval between the first and subsequent trials is
two minutes or so. In such cases only voltage sensing sectionalisers can be used. However, in the
case of an auto-re-closer, it is possible to use both Voltage and Current Sensing Sectionalisers.
Remote control Operation
Sectionaliser Control
The Sectionaliser shall be fitted with a separate control box.
Protection and timer relays shall be installed in this control box. This control box shall be suitable for
fitting on the pole at a low level than the Sectionaliser to provide inspection maintenance and setting
access to utility personnel. All fittings required for mounting shall be supplied. All operating
parameters of the Sectionaliser shall be controlled from the control box.
All settings shall be either a) through a suitable interface pad/keyboard designed for the harsh
operating environment of the Sectionaliser, b) positive step selector switches or c) plugin
components.
Ratings shall be clearly marked in relevant units of measure with no interpretation multipliers or
conversion being required.
Each unit shall be equipped with an electronic control armoured capable of operating in the
environmental conditions specified in spec. No. TS-GN-01. The cable shall be protected in either a
metallic non rusting tube or a metallic cover that can be fitted over the cable. The cable protection
shall be securely fixed on the pole and appropriate permanent fixings shall be provided. The fixings
shall not be plastic tie wraps. Stainless steel tie wraps are permitted.
Communication System
Remote Terminal Unit / Remote control shall be provided for the Sectionaliser if so specified in the
technical schedule. The remote control shall be achieved through a communication link between
control centre and the Sectionalisers and necessary provision shall be incorporated in the control
box.
GSM/GPRS/ CDMA service is available in 7 towns and is proposed to be deployed for
communication between Control Centre and this device. Alternatively communication may be
provided through a radio link with the Control room.
The Unit shall incorporate the necessary remote terminal interface equipment to enable linkage
between the unit control and the communication system.
The Unit shall incorporate an energy storage system to enable the equipment to operate within one
month of being disconnected/ powered-off from the network.
Full details and rights to use protocols for communication and operation of the device shall be
provided to the client/purchaser to enable the SCADA system to interface with the unit. The cost of
the provision of any protocol look up tables etc. shall be included in the cost of the device. Full
details shall be included with the supply of the device to enable the Unit to be integrated with the
SCADA system.
Remote terminal unit (RTU) and modem is included in the standard equipment for the automated
switch.
Information on load break switch and sectionaliser states and fault values shall be transmitted to the
SCADA system
Data to be TRANSMITTED to SCADA
The following data shall be transmitted / enable interface with the SCADA system
Status information of sectionaliser
Lockout status of sectionaliser.
Voltage
Remote lockout reset.
No of operation of the unit.
Low SF6 if SF6 insulted
MARKING
The sectionalisers shall be provided with a name plate legibly and indelibly marked with the
following:-
Name of the manufacturer,
Type, designation and serial number,
Rated voltage and current,
Rated frequency,
Number of poles,
Rated normal current,
Rated breaking capacity,
Rated short-time current,
Rated making current.
Schedule for pole mounted 15kv line sectionalisers
No Item Unit
Requirement Bid Offer
1 Nominal system voltage kV 15
2 Highest Equipment Voltage for gas kV 17.5
insulateded equipment
3 Highest Equipment Voltage for air kV 24
insulateded equipment such as
bushings
4 Rated acive load breaking capacity A 400
5 Transformer off-load breaking A 10
capacity
6 Line charging breaking capacity A 10
7 Rated short time symmetrical current kA 10
8 Rated making current kA 20
9 Rated basic impulse level kV 125
10 Rated one minute power frequency kV 50
withstand voltage between phases
11 Rated one minute power frequency kV 2
withstand voltage between control
circuit to earth
12 Voltage sensing relay Yes/No Yes
13 TSR timer settings sec 0-10 sec
14 Lockout timer settings sec 0-10 sec
No Item Unit
Requirement Bid Offer
15 Directional facility of voltage sensing Yes/No Yes
- load source
16 Interruption medium Vacuum or SF6 Vacuum
17 SF6 low pressure lock-out of SF6 Yes
insulated
18 Electrical endurance operations 3000
19 Mechanical endurance operations 3000
20 No. of ON/OFF indicators provided Nos. 2Nos.each
21 Radio interference voltage µV 250
Lines in General
The following section describes the basic characteristics of the overhead distribution system design
of 33kV and 15kV networks.
Overhead Medium Voltage (MV) power distribution lines shall be routed along the roads and
straight as far as possible.
Private land and/or vegetation should be avoided as far as possible in construction of MV lines.
Poles and stays shall be positioned so as to cause least obstruction to the general public.
Ensure that poles and stays are not at high risk of being damaged by vehicles.
Overhead power lines shall be routed to avoid crossing of other power and telecommunication
lines as far as is practicable.
The following points shall also be considered when locating the pole positions along the lines.
The maximum span for MV lines shall be maintained as close as possible to basic spans. If the
actual planned span significantly exceeds the basic span, the calculation of loads applied to pole
shall be done for specific span, conductor and pole and on pole clearance must be checked for mid-
span clashing.
Using the covered conductors or insulated cable in areas with difficult vegetation control might be
the right solution provided that the designer has the assurance that the area does not suffer from
bush fire.
The areas prone to common bushfire shall be constructed on steel or concrete poles, bare conductors
and porcelain or glass insulators to avoid unnecessary destruction and costly replacement.
Supports
The medium voltage lines shall be normally designed as single circuit, three phase three-wire on
concrete (earthed) with steel cross arms.
General standardization
Concrete poles for medium voltage lines are standardized in the following load classes:
Class 1 2 3 4 5 6 7
Fmax (kN) 20.0 16.5 13.4 10.7 8.5 6.7 5.3
Concrete poles for medium voltage lines are standardized in the following lengths:
For medium voltage lines the lengths 11m to 14m shall be used as standard.
Foundations
General
This chapter applies for foundations for concrete or tubular steel poles.
Foundations shall be designed, for any type of soil to be found, both in dry and fully submerged
conditions and for rock.
Foundations shall normally be of the simple earth type employing bearing plates with foundation
baulks and kicking blocks as necessary.
The poles shall be placed in the ground to the planting depths dictated by foundation design but not
less than the following:
All foundations shall be designed to withstand uplift, settlement, overturning and sliding when
subjected to the specified conditions of loading. Allowance shall be made in foundation design for
hydrostatic pressure effects of seasonal rain drying out cyclic loading and wind induced vibration.
Foundation and stay and anchor baulks shall be of reinforced concrete or steel fabrication,
compatible with the material of the pole.
Foundations on places where the loads are high (dead end, heavy angle, transformer on pole etc.)
or the soil conditions are poor shall be of reinforced or mass concrete type.
All concrete types of foundation shall be designed with two different heights above ground.
In flood prone areas, the height of foundations for above ground shall be about 50 cm to ensure
protection against aggressive water.
At pole or tower positions where occasional flooding may cause damage to towers or foundations,
protective embankments shall be erected or alternative measures shall be proposed by the
Contractor.
For the final foundation design the Contractor has to perform the required soil investigation, and
has to base his choice of appropriate foundation design on the detailed information obtained therein.
The Contractor shall perform a comprehensive soil investigation to ascertain the soil conditions
and characteristics using approved methods to determine the type of foundation applicable. The
soil investigation shall provide the Employer engineer with sufficient information on the subsoil
conditions. Soil investigations are to be performed in accordance with relevant BS or DIN Standard.
The possible deterioration of the consistency of cohesive soils and the resulting reduction there
from of the bearing capacity shall be considered. If ground water exists, the corresponding decrease
of weight of soil due to uplift conditions shall be considered in the calculations.
• Overturning moment
• Bearing pressure
Stays
General
Stays shall normally consist of stranded galvanized steel stay wires complying with the
requirements of BS or other approved standard. The attachment of the stays to the supports and
foundation shall consist of a factory-formed helical termination clamp with shackle to match the
pole face landing plate at one end and a similar termination to match the stirrup of the stay rod.
Stay rods, stirrups and stay foundations shall be of approved dimensions and types. Stay assembly
shall be fabricated in steel and galvanized to the requirements of ISO 1461 or other approved
standards. The stay rod shall be locked into the stay plate or stay log to prevent rotation of the rod.
Each stay assembly shall be equipped by stay insulator of an approved design. Approved devices
shall be provided in each stay wire for adjusting the tension in the stay wires after erection and
during maintenance.
Load to Stay
Load to stay/stays is actually the difference between transversal and longitudinal loads imposed to
the pole and the maximum working load of pole.
Final contribution of all stays in vertical plane must be considered and checked during the pole
foundation design.
Soil conditions assessment of stay is not necessary as the distance from pole foundation (where the
soil investigation report exists) is short.
When assessing the stay slope and stay depth the maximum length of available stay rod must be
considered.
Medium voltage line stays and bare conductor low voltage line stays shall be equipped by stay
insulator which shall be mounted not less than 3 from pole top for MV lines and 1m from pole top
for bare conductor LV lines. Tubular steel poles shall not use the stay insulator.
Cross linked polyethylene (XLPE) covered aerial bundled catenaries cable – for urban areas and
narrow corridor environment.
Medium voltage overhead cable system is relatively expensive and its use shall be limited.
calculations only; unlikely to happen in normal situation; maximum tension 20% of UTS of the
conductor is to be read as the ceiling, not the optimum
HW፡ high wind; usual case of part loaded conductor; used as case for calculation of maximum
ERR፡ erection; normal case applicable during the stringing; actually only temporary initial case for
MT፡ maximum temperature; steady state of the conductor used for maximum sag calculation and
clearance check.
Other Definitions
Wind Span
Wind Span is the maximum possible half span lengths (total) on either side of the pole, which can
withstand the design wind speed.
The Basic Span of a line section between two tension points can be calculated by using following
formula.
L=Span Length
Weight span
The Weight Span is the representation of dead weight load of the conductors on pole expressed in
length of the specific conductor and its unit weight.
Recommendation:
As the tension of the conductor depends on conductor temperature and the formula calculating
these effects is cubic; even after simplifying, it is advisable to use professional software for
calculation of the sag and tension of the conductor.
MV fittings
Tension clamps
Conductor attachment to the insulator string at tension and dead end towers shall be of the
preformed dead end tie or bolted type tension clamp.
Suspension clamps
Conductor attachment to the suspended insulator string (on towers) shall be of the trunnion bolted
suspension clamp.
Preformed ties
Performed ties shall be made of aluminium coated steel or aluminium alloy wire and will be
furnished with neoprene protective sleeve for conductor.
Wrap-lock attachment of the conductor by prefabricated side ties or top ties shall be used for line
post insulators.
The conductors shall, except at angle positions, be bound into the top groove of pin insulators by
means of a pre-formed helical binding (top-tie): at small angle positions and where double insulator
arrangement is required (crossings) they shall be bound into the side groove so that the insulator is
inside the angle included by the conductor.
As a replacement of preformed ties the preformed stirrup together with aluminium tape and
aluminium binding wire can be used.
Where the PVC covered conductor is used the conductor shall be covered by semi conductive
polyvinyl tape in between ±20cm from the ends of bind.
Joints
Joints for line conductors shall be of approved pre-formed helical or compression types and shall
comply with the requirements of IEC 61284. The electrical conductivity and current carrying
capacity of each joint shall not be less than those of the line conductor.
Non-tension joints and tap off connectors shall be preferably compression type or approved type
of parallel clamp and shall not permit any slip or damage of the connection at a load of 25 per cent
of the ultimate strength of the conductor, and shall be designed so that no loosening of the
connections can occur in service.
Where the PVC covered conductor is used the joint or tap off joint shall be covered by petrolatum
whether proofing tape in between ±5cm from the ends of joint.
Joints
Joints for line conductors shall be of compression types and shall comply with the requirements of
IEC 61284. The electrical conductivity and current carrying capacity of each joint under the test
conditions shall not be less than those of the line conductor. The joints shall be equipped with black,
weather resistant polyethylene sleeve insulation with high resistance to solar radiation.
Earthing
Metal poles and poles having installed equipment such as surge arresters, cable sealing ends,
autorecloser, load break switch or transformer as well as line ends shall have installed a protection
earthing. All metal poles/towers must have protection earthing.
The pole ground lead shall extend above the top of the pole and shall be bonded to the surge
arresters, plate bolts, tension insulator bolts, and in general all metallic supports installed on the
structure according to that specification.
Auto-reclosers
Auto-reclosers shall be designed for three-pole operation and outdoor installation.
The auto-recloser shall be supplied with brackets for pole mounting. All three poles shall be able
to operate simultaneously from ground level. The position of the auto-recloser shall be clearly
marked on the operating device. The autorecloser shall be equipped by surge arresters built-in or
attached to bushing cover.
The MV Pole-Mounted Dropout Fuse Set can be installed on common cross-arms or on two pole
on top of Overhead mounted transformer .
Dropout Fuse Sets shall be hand-operated from ground level using a glass fibre pole (Operating rod
provided as tool), which shall also be designed to facilitate replacement of the fuse links. Dropout
Fuse Sets shall be of single-phase type.
Contacts of the fuse cut-out shall be suitable to terminate the line conductors.
The equipment in the MV Pole-Mounted Dropout Fuse Sets shall be installed with necessary
clearances, easy access to the fuses for testing, maintenance, removal and normal operation and to
provide safety measures against all possible hazards.
The MV Dropout Fuse Sets shall be of the type equipped with fuse holder latches and designed to
prevent falling out of fuse holder.
The single-vent distribution MV Dropout Fuse shall be open type dropout, single insulator with
attachment hooks for load break tool.
The terminals of the MV Dropout Fuse Sets shall be plated clamp type connector.
The MV Dropout Fuse Sets shall have built in feature for delayed release so that dropout takes
place at or after the fault duration. The time delay should be approximately about 0.1 sec.
The fuse holder insulators shall be made of the composite type or porcelain type.
After operation, the fuse shall be capable of withstanding the power frequency, recovery voltage
across its terminal.
Fuse links shall be of robust construction to ensure that no damage results from normal handling
and operation of the associated equipment. Fuse link material shall effectively resists deterioration
under the prevailing climatic conditions.
The fuse holder shall have a provision for earthing. All metal parts not meant to carry current shall
be connected to a double earthing system and suitable earthing terminals shall be provided with all
equipment.
The MV Pole-Mounted Dropout Fuse Set shall be capable of withstanding the electrical and
mechanical stresses as specified in the relevant IEC/IEEE/ANSI Standards.
Where fuses are used for disconnecting and protection of transformers they shall be co-ordinated
with the rating of the related distribution transformer.
MV Surge Arresters
The surge arresters shall be designed and erected on every distribution transformer as well as on
any T-off or dead end connection, where the overhead line is connected to underground cable.
The surge arresters shall be of the hermetically sealed plug-in type (metal encapsulated) with metal
oxide material having non-linear resistance. The enclosure shall be silicone copolymer. The surge
arrester shall be preferably equipped with a disconnector.
The surge arresters shall be maintenance free and shall have a pressure relief device for failure
protection in case of overloading .The surge arrester shall be preferably the “bracket type”
(insulated bracket).
Connection to the grounding system shall be by stranded copper wires of adequate cross-section
(min.35sqmm).
15/33kV Feeder Added to Existing Network Mesh, Space Constraint Route with Houses Too Close
to Route or Partially Blocking the Route
Where a new distribution single circuit from primary substation to the existing network mesh is to
be designed in fully congested area where the horizontal clearance to existing houses is not
achievable, an armless single pole line shall be designed. Line shall be strung with catenary
suspended XLPE fully insulated MV aerial bundled cable shall be used. In places where the route
is blocked by houses the adjacent wall of the house, landlord consent required, can be used for
cantilever support installation in straight line. Walls cannot be in any case used as a support if the
line deviation exceeds 2°.
Basic span on lines with MV aerial bundled cable shall be reduced by at least 40% and the poles
shall be designed as effectively and fully earthed system.
15kV or 33kV Single Long Overloaded Feeder in Existing 33/15kV Network Mesh; Capacity
Needs Massive Improvement
Transformation using existing poles and conductors of the line shall be arranged in the following
manner:
Support poles - suspension of the 15kV/33kV cross arm by 60cm from normal position and pole
top standoff cross arm shall be used to form the triangular configuration suitable for 33kV
clearances. Pin/post insulators shall be changed to ones suitable for 33kV.
Tension poles – for both used configuration (vertical single pole and horizontal H pole) new double
sided cross arm suitable for 33kV shall be used. Tension strings for 33kV shall be used, conductors
adequately shortened using preformed dead end ties and stays shall be repositioned.
Line shall be than checked and all attached transformers shall be replaced by 33/0,4kV type. Than
the feeder shall be reconnected to 33kV side of the primary substation
Overall costs of that transformation are approximately 15% of the price of the new feeder
improving the capacity by 200% and reducing the losses by 400%.
Basics
The Contractor is responsible for the true and proper setting out of the erection work in relation to
the survey lines and reference benchmarks and for the correctness of the position, levels, dimension
and alignment of all parts of the lines.
All erection work shall be done under the supervision of the Employer. All erection drawings,
setting diagrams and other relevant information shall be approved. Erection work shall not
commence before all such drawings, etc., are approved by the Employer. Five copies of such
drawings shall be given to the Employer for use by his supervisors in the field. The Contractor shall
also provide, when required, reasonable use of his facilities and equipment to enable inspection,
measurement and testing of erection work by the Employer.
The Contractor shall keep damage within the right-of-way to a minimum consistent with the
successful execution of the erection work. The Contractor shall exercise all precautions to avoid
damage to crops and other property. Damage repair works shall be borne by the Contractor only
when the damages are due to negligence on their part.
No continuous track for maintenance within the right of way, along the entire line route is foreseen
for MV lines.
No separate payment other than foreseen in the price sheets shall be made to the Contractor on
account of building or repairing access roads and tracks.
Soil Investigations
The Contractor shall be responsible at his own cost for ascertaining that the foundations to be
employed are suitable for the sub-surface conditions encountered at each pole/tower site. For this
purpose he will be responsible for classifying these conditions at each pole/tower site at an early
stage of the Contract. The Contractor shall be responsible for any subsidence or failure due, in the
opinion of the Employer, to insufficient care having been taken in his examination of ground
conditions or in installation of the foundations. Prior to construction the Contractor shall submit
for approval his proposals for correlating the results of the soil tests with the parameters employed
for the foundation design. These proposals shall also consider visual and manual checks and tests
to be made after excavation and will be to the Employer’s approval.
The Contractor shall prepare a Schedule for construction purposes which clearly indicates the class
of foundation to be installed at each site and records the soil investigation data on which the choice
has been made. The Schedule will be subject to approval of the Employer prior to commencement
of foundation construction.
When required by the Employer the Contractor will be required to make arrangements for a
comprehensive soils investigation to be carried out at any specified pole/tower site, including deep
borings and laboratory analysis of undisturbed soil samples and for a report and recommendation
to be submitted.
Pole Locations
General route sketch shall be provided by the Employer to the Contractor in the SW form (GIS,
DWF or KMZ).
The Contractor shall be prepared to amend the route, according to detailed requirements of the
authorities, until final approval is obtained. No additional costs will be considered for such minor
work. Amendments required after receipt of route approval by the authorities shall be remunerated
as per the relevant Contractual rate for survey works.
The initial survey profile for the MV line may be provided by the Employer.
The Contractor shall perform detailed full scale survey for MV line, determine the pole/tower
locations in the map and longitudinal profiles and prepare pole/tower lists with main data for each
pole/tower including wind span and weight span.
The topographical line survey shall be carried out along the approved line route.
The theodolites used and measuring techniques applied shall have the ability of digital recording
technique. The survey shall be carried out to a minimum accuracy of 1 in 2.000 for distance- and 1
minute for angular measurements.
The Contractor shall prepare longitudinal profile drawings of the distribution line, in scales of:
They shall display the bottom conductor catenaries, at maximum temperature, together with the
ground- or special clearance curves, as well as the minimum temperature catenaries. Pole/tower
Nos., pole/tower types, weight spans, wind spans, equivalent spans, section length, continuous
chain age, elevations, level differences, UTM co-ordinates (for angles and dead ends), etc. shall be
shown. Along the bottom of the profile plan, a strip plan of the line route, extending 20 m beyond
the corridor limits, to either side of the centre line, shall be shown. The strip plan shall detail all
relevant information regarding obstructions, services, vegetation, terrain type, land use, etc...
Horizontal and vertical co-ordinates of all features affecting the line construction shall be indicated
on the profile plan. Crossings of existing overhead lines shall be documented with measured
elevations and locations of their top and bottom conductors, at centre line and side profile limits,
together with the air temperature at the time of measurement. All qualified crossings and
approximations shall be covered by individual clearance calculations, to be shown on the profile
plan. Pole/tower centre co-ordinates of angle pole/towers and end pole/towers shall be reduced to
UTM, WGS84 datum, and indicated on the profile plans.
The Contractor shall locate and indicate benchmarks and reference points already existing in the
project area. Where these do not exist, the Contractor shall provide such reference points in
consultation with e.g. the Town Planning Department, Public Works Department, etc.
Marking of the line route and pegging of pole/tower positions shall be as per Contractor's Method
Statement.
To facilitate approval of profile plans, the Contractor shall provide the Employer either with two
licensed copies of software inclusive of all relevant survey- and other data in digital form, or with
two complete sets of transparent sag templates in Perspex or similar material, 4 to 5 mm thick,
based on the range of equivalent spans required, staggered at 50 m, and for the conductor types and
scales to be used. The templates shall be cut precisely along the conductor catenaries in still air, at
maximum temperature (hot curve). The sag curve in still air, at minimum temperature (cold curve),
the span grid, the ground clearance line, and all relevant details like design loading conditions,
particulars of conductors, equivalent span applicable, scales, etc. shall be engraved.
The Contractor shall consider any condition of uplift on poles/towers as result of conductor loading
and shall provide the appropriate measures in his design and supply to handle the effect thereof.
At pole locations with additional loading due to span lengths exceeding the stipulated maximum
spans for conductor weight loading and in case of uplift which cannot be handled by tangent pole,
tension pole shall be used.
The Contractor shall investigate and prove that the type of tension pole/towers proposed for such
locations can withstand such increased loading.
According to technical data of the utilized conductor, the maximum and minimum temperature and
the possible spans, the Contractor will prepare a sag template for the distribution of poles/towers.
The curve will be plotted using the Contractor's computer program and subsequently cut in durable
material.
Clearing of Right-of-Way
The Contractor shall clear the right-of-way, fell any vegetation and dispose of waste material along
the entire length of a distribution line.
The distribution line right-of-way is 10 meters wide for the 15/33 kV lines on poles symmetrical
about the centre line.
All trees, snags, stumps, shrubbery, ant hills and undergrowth exceeding 2 meters in height as
measured on the downhill site shall be cut to a maximum stump of 20 cm along the right-of-way.
All trees adjacent to the right-of-way which could fall across the conductors or against the
pole/towers shall be cut, this criterion shall apply with the conductors displaced 53° from the
vertical in either direction.
In addition to the clearing required on the right-of-way all trees, bush stumps and snags to each
pole/tower location shall be cut, regardless of height and clearance to conductor to a maximum
stump of 25 cm, in an area of 8 by 8 meters around a pole/tower.
The Employer will make the necessary arrangements with landowners so as to permit the
Contractor the cutting or trimming of trees located both inside and outside the right-of-way where
such cutting or trimming is necessary. The Contractor shall notify the Employer 14 days in advance
of commencement of any proposed clearing operation. No clearing shall be undertaken until the
Employer has made the arrangements with the landowner and/or unless in the presence of the
Employer. The removal of some huts and cottages, which are situated along the right-of-way, is
the responsibility of the Employer.
The Contractor shall remove and dispose of any felled trees and waste material such as useless
packaging material to the satisfaction of the Employer.
Design of Foundations
The Contractor shall stake out the pole locations and submit to the Employer the foundation
conditions, including permissible bearing pressures expected at each pole/tower, together with the
type of foundation proposed. The Employer may require the Contractor to make additional
investigations at pole sites to verify the foundation conditions.
In excavating foundations for supports with foundation baulks and for stay and anchor baulks where
used, the holes shall be undercut so that the baulks have above them solid and undisturbed earth on
their principal bearing surface wherever possible.
Blinding concrete shall be provided under all concrete foundations at the base of the excavation for
a thickness of at least 75 mm and shall be deemed to be included in the price of the foundations.
Foundations on places where the loads are high (Tensions, dead end, angle, heavy angle,
transformer on pole etc.) or the soil conditions are poor shall be of concrete type and reinforcement
bar shall also be used as required.
For the final foundation design the Contractor has to perform the required soil investigation, and
has to base his choice of appropriate foundation design on the detailed information obtained therein.
The distribution of poles will be carried out according to the following constraints and rules:
Poles in tangent positions shall be oriented with the transverse faces at right angles to the
distribution line centre line, and poles in angle positions shall be oriented with the transverse face
or right angles to the bisector of the deviation angle.
Poles shall be assembled in accordance with the approved Contractor's drawings and erected by
any suitable method which will not overstrain structural members or their foundations. The method
of erection shall not interfere with adjacent as intersecting line and/or other improvements. Tension
structures (except those used in straight line for anchoring purposes only) shall have the appropriate
deflection towards the load applied by conductors and equipment. It should be noted that permanent
maximum negative pole deflection of 5° (towards the resulting load) is acceptable. Any positive
pole deflection (in direction of resulting load) is not acceptable and shall be rectified.
If the stays are to be used, the stay wires should be engaged before stringing giving the pole
appropriate “backload”.
If the above requirements are not found possible in particular cases, the Contractor shall bring the
attention of the Employer to the conditions and propose means to improve the condition.
Stringing
The Contractor shall submit in writing for approval a complete and detailed description of the
stringing equipment, stringing and sagging procedure intended for use.
The Contractor shall supply all necessary tools and stringing equipment which shall be subject to
the approval of the Employer. Under no circumstances shall the conductors be allowed to contact
the ground or any other obstacle.
The stringing equipment and operation shall be such as to avoid overstressing pole structures or
foundations. Any damage to Concrete poles or foundations occurring in such an operation shall be
made good at the expense of the Contractor. Non-metallic lagging shall be used to protect any part
of any structure which may be subject to abrasion by the pulling line or which may damage
conductors passing over it.
Conductors shall be strung carefully to avoid kinking, loosening of strands, scraping, nicks or other
damage. Bends of less than the minimum-bending radius of 18 times the cable diameter will not be
permitted. Jumper loops shall be made up between terminal fittings and formed into such a shape
as will afford the minimum clearance specified on the pole outline drawings and so that the jumper
insulator string, if any supplied, is not deflected from plumb alignment. Any damage to conductors
shall be reported immediately to the Employer who will decide whether or not the conductor is
damaged enough to warrant repair or replacement at the Contractor's expense.
Appropriate stringing sheaves or travelers shall be used which will not damage the conductor. The
stringing sheaves shall be of low friction design. They shall be carefully cleaned and oiled so as to
remain free running and any sheaves that in the opinion of the Employer are not suitable shall be
removed from the line and replaced. Stringing sheaves shall have a minimum diameter measured
at the bottom of the groove of 18 conductor diameters.
Stringing sheaves for horizontal arrangement cross arms on poles shall be fitted upright on the
cross arm and designed to properly distribute loads to the cross arm. They shall be installed at such
a height as to support the conductor at its permanent elevation when clipped-in.
Stringing sheaves for the suspended cable system (i.e. tower, MV ABC cable or LV ABC cable)
shall be suspended from the cross arm/pole attachment bolt.
Sheaf surfaces in contact with the conductor shall be lined with neoprene or rubber. Sheaves for a
conductor shall be so designed and so used that the pulling line does not damage or deposit foreign
matter in the neoprene or rubber lining, which might cause damage to the conductor. Splices shall
not travel through the sheaves.
If it becomes necessary to leave the conductor in the sheaves during the stringing operation due to
inclement weather or equipment breakdowns, the conductor shall be left at a minimum of twice the
normal sag. Conductors which have been in the sheaves for more than 60 hours or during
exceedingly windy weather shall be inspected for damage. The Contractor shall repair or replace
any damaged conductor.
The stringing operation shall be executed with due regard to the safety of erection personnel and
the public. While conductors are being run out, and when being tensioned and finally clipped-in,
all conductors shall be earthed by the Contractor at points approved by the Employer. The
Contractor shall record the position of each earth connection and before he reports that a line may
be energized, he shall deliver to the Employer a written statement certifying that all earth
connections placed by the Contractor on conductors have been removed and that every member of
the Contractor's staff has been informed that he shall not work on the line again unless in possession
of a written authorization by the Employer.
The Contractor shall supply and install all guard structures required for crossings over electric
supply and communication lines, railroads, roads, highways, obstructions and for the protection of
the conductor. All guard structures shall be of adequate strength to withstand the stresses to which
they may be subjected. Stringing sheaves shall be used on guard structures. Immediately after
completing sagging of a section of lines, the Contractor shall remove and dispose of all guard
structures.
The Contractor shall use a portable and/or mobile short-wave radio communication system to
control the stringing operation. The Contractor shall obtain the necessary licences for this system
from the concerned authorities.
Sagging
The Contractor shall sag the conductors in accordance with the initial sag and tension tables to be
prepared by him based on the final sag and tension tables approved by the Employer.
The length of the conductors sagged in one operation shall be limited to the length that can be
sagged satisfactorily.
The tension prescribed in the sag and tension tables shall not be exceeded by more than 10% at any
time during stringing and sagging operations.
The tension/sag shall be measured by digital dynamometer allowing to download and print the final
values. Subject to the approval of the Employer, the Contractor may employ other methods of
checking sag.
As soon as possible after completion of clipping-in the Contractor shall re-check the sags for
correctness and shall then turn over his initial and check sagging results to the Employer.
Final approval of the sagging of an entire section between permanent or temporary dead-ends will
be given when the completed sagging has been checked and found to be within the specified
tolerances. All clearance shall conform to the drawings.
Splices
Full tension splices shall be compression joints.
Full tension splices for covered conductor shall be covered by weather resistant heat shrink
insulation sleeve.
Splices for MV ABC cable are not supposed to be on tension and in reality are similar to MV
underground cable joints. The utmost care shall be taken to ensure that during jointing the sleeve
remains well centred on the conductor core after compression.
A maximum of one splice per conductor cable will be allowed in any phase in any span. No splices
shall be located in any span crossing main roads, major rivers, major communication or power
lines.
No joints shall be applied at less than 10 meters from attachment point at pole or tower.
The finished splices shall be straight, free from cracks, and shall not deviate from straightness more
than 0.5 % of its length. Straightening of a bent splice by means of sledgehammer blows or a similar
manner will not be permitted. Unsatisfactory joints shall be cut out and replaced at the Contractor's
expense.
The making of compression joints and any application of repair sleeves shall be done only in the
presence of the Employer and shall be stamped with an approved stamp. Records of all splicing
and application of repair sleeves shall be kept and handed-over to the Employer.
When damage to a bare conductor does not exceed three aluminium strands, either broken or nicked
deeper than one-third of their diameter a repair splice or sleeve shall be installed and where this
limit is exceeded the damaged section of the conductor shall be cut out and spliced with the above-
mentioned preformed line splice or compression joint.
Insulator strings shall be handled so as to avoid bent pins or chipped glaze. Chipped, cracked or
score insulators of the Contractor's supply shall not be installed.
Hardware and accessories shall be handled to prevent contact with the ground. All items shall be
clean and inspected for missing parts or visual defects before installation. All connections shall be
made in accordance with the drawings or as recommended by the manufacture, bolts firmly
tightened, split pins inserted where required, all in a good workman-like manner according to the
best practice of distribution line construction.
All split pins in each insulator string shall be carefully checked to ensure that they are properly
seated to avoid accidental uncoupling of insulator units. All split pins shall be faced toward the
stepped leg of the pole to facilitate inspection.
The Contractor shall supply all necessary accessories, i.e. special tools, compressors, draw benches,
etc. required for making dead-ends for conductors.
All pins used in clevises and other line hardware shall be installed in such a manner that the head
of the pin is in the highest position so that the pin will not drop out if the split pin is lost.
All sockets shall be turned so that the open side faces the ground on all insulator assemblies which
are to be installed in a substantially horizontal position in order to facilitate drainage of water.
Imperfectly or poorly galvanized hardware as determined by the Employer shall not be used. Such
pieces shall be replaced with new hardware.
Properly tight dead-end tie assemblies made of aluminium coated steel or aluminium alloy wire
shall be installed in accordance with manufacturer's recommendations.
Wrap-lock attachment of the conductor by prefabricated side ties or top ties shall be used for line
post or pin insulators.
The conductors shall, except at angle positions, be bound into the top groove of insulators by means
of a pre-formed helical binding (top-tie): at small angle positions and where double insulator
arrangement is required (crossings) they shall be bound into the side groove so that the insulator is
inside the angle included by the conductor.
Medium voltage lines with bare conductors and horizontal construction should have the centre
phase post/pin insulator mounted in zig-zag positions to keep the phase to phase clearance equal in
horizontal plane.
Subject to approval of the Employer it is possible to use the bolted or compression dead end clamps
for conductor termination.
Subject to approval of the Employer it is possible to use the preformed alloy stirrups, aluminium
tape and aluminium binding wire for binding the conductor to the side groove of the post/pin
insulator. For top groove binding the double bow tie lock without the stirrup shall be used.
Jumpers and other leads connected to line conductors shall have sufficient slack to allow free
movement of the conductors. Where slack is not shown on the construction drawings it will be
provided by at least two bends in a vertical plane, or one in a horizontal plane, or the equivalent.
Line Accessories
Danger Plates and Number Plates
A danger plate shall normally be on the transverse face of a the poles with the exception of those
poles located not further than 40 meters from roads in which case the signs shall be affixed facing
the road. The mounting height shall be about 2.5 meters above ground level.
Number plates of approved design and material shall be attached to each pole and positioned under
the danger plate.
The mounting shall be made with inox or galvanized bolts, nuts and galvanized washers.
LV Surge Arresters
Surge arresters are foreseen to protect the low voltage networks and shall be of the metal-oxide or
valve type.
For pole mounted transformers the surge arrester shall be connected to ABC cable in between
transformer LV bushing and fuse switch (or inside the multiway distribution box on incoming bus
bars). Arresters connected to ABC overhead lines shall be stud mounted and with insulated
connecting cable on the other side (to be used with piercing connector).
For ground mounted transformers the surge arrester shall be connected inside the multiway
distribution box on incoming bus bars.
Connections
All weather exposed connections (including earth) shall be protected with adequate penetrox grease
and denso tape in not less than 2 layers.
The MV/LV substation shall consist of, but is not limited to, the following facilities:
Maximum height : top of MV bushing level 80cm below MV fuses cross arm
MV Surge Arresters
These must be used on all three-phase transformers. The arrester shall be fitted as near as possible
to the equipment being protected i.e. use the facility for fitting the lightning arresters directly to the
tank.
Jumpers from cut-out fuses shall pass the arrester on its way to MV bushing.
Ensure the maximum length of unsupported jumpers is 1500mm and obtain a minimum spacing of
700mm between phases, phase/earth, and phase/pole for all jumpers.
LV Distribution Boxes
The boxes shall be of a weather-proof design made of robust sheet satisfying protection class IP549
as minimum. The boxes shall be of epoxy type glass fibre reinforced, resistant to UV radiation,
fabricated according to DIN. Their last coat of paint shall be of RAL 7035, light grey. Bolts and
nuts exposed to the atmosphere shall be of the anticorrosive type (stainless steel).
• In the LV side / secondary side of the transformer, connection should be done by 2x240+1
x 120 mm2 CU conductor.
It shall accommodate the items specified with all relevant auxiliary components including cable
gland plates, terminal blocks.
MV Cable data
Type Construction Ampacity (A)
Al240mm2 AL 403
Al400mm2 AL 518
Al500mm2 AL 585
Cu95mm2 3xCU 290
Cu120mm2 3xCU 330
Cu185mm2 3xCU 417
Cu240mm2 CU 505
Cu400mm2 CU 630
Cu500mm2 CU 689
LV Cable data
Type Construction Ampacity (A)
LV25mm2 4xCu 143
LV35mm2 4xCu 173
LV50mm2 4xCu 205
LV70mm2 4xCu 265
LV95mm2 4xCu 303
LV120mm2 4xCu 346
LV185mm2 4xCu 457
LV240mm2 4xCu 527
LV300mm2 4xCu 590
No metal sheath, no armour and jacket made of PVC or HDPE is the standard system of materials
for LV cables.
Cable Formation
MV single core cables shall be laid in triplex formation as standard.
MV single core cables may be factory assembled in a triplex formation for ease of installation in
the field. Factory assembled cables commonly employ a length of lay within a range of 25 and 60
times the cable diameter of the largest cable in the bundle.
MV three core cables and LV cables shall be laid in single formation as standard.
Conflicts with obstructions such as building foundations, electrical circuits, telephone circuits, and
water and sewerage mains shall be avoided wherever possible.
Detailed survey of the streets or other areas in which it is proposed to make an underground
installation shall be performed to obtain accurate data on the location of existing services e.g. gutter
drains, manholes for sewers and other utilities, fire hydrants, shut off values for water and gas lines,
utility poles, trees and any other obstructions which may be visible on the surface. This data shall
be supplemented by other information as available from municipal and public utility records on
construction and routing, depth, size and description of all underground installations.
Detailed route design shall be prepared for each proposed cable route showing trench cross-section
and location of utility lines if known. This design shall be submitted for approval prior to the
commencement of any works.
It is then often necessary to dig trial holes to establish the trench route in detail. The trial holes will
indicate the position of other services so that smooth bends can be provided to reduce the pulling
loads when long lengths of cable are being installed.
The trial holes also provide information on the nature of the ground for excavating and timbering
purposes and on whether there is any chemical activity which would necessitate a special
anticorrosion finish for the cable. Any unusual soil characteristic which might affect the thermal
resistivity, and hence cable rating, would also be noted. Reference is made later to special
precautions necessary if possible ground subsidence is suspected.
Cables are usually laid in trefoil formation. At regular intervals adequate non-corrodible clad or
rope is wrapped around the cables to keep the trefoil formation during the backfilling of the trench.
Another type of installation generally used within or on entry to substations is with the cable buried
in concrete trough (unfilled or filled). In such installations the cables are generally placed with a
relatively small separation between the phases in concrete troughs which have reinforced and
sometimes interlocked lids for mechanical protection.
Direct Buried Conduits
In a direct buried conduits or duct manhole system, instead of installing the cables directly in a
trench, conduits (ducts) are installed in the trench, through which the cables can be pulled and
installed at a later date, as required. Sufficient spare ducts are installed for future use. Conduits
made of many different materials, in different diameters and wall thicknesses are available for use
for different applications. Plastic ducts made of polyvinyl chloride (PVC) with 100 mm or 125 mm
diameter are most commonly employed. The ducts can be either directly buried in ground or
encased in concrete. The ducts begin and terminate in underground chambers, known as manholes.
The exact installation location and distance between the manholes is selected to allow convenient
pulling and splicing of the cables.
The ducts may be installed by either direct trench excavation or horizontal thrust boring under the
route. Where direct trenching is used, ducts shall be installed in a concrete duct bank of approved
dimensions. Where horizontal thrust boring is employed the bore hole shall be lined with a tight
fitting continuous steel pipe sleeve(s) into which the required PVC/PE duct(s) is inserted.
The duct internal diameter shall be at least 1.5 times the maximum cable outer diameter, where one
cable is installed per duct. Where more than one cable is installed per duct (e.g. 3 X single core
cables) the duct internal diameter shall be at least 2 times the maximum diameter of a circle
circumscribing the cables.
Ducts under roads or railways shall be installed at a minimum depth of 1m and shall extend beyond
the extremities of the road carriageway or railway bed by a minimum distance of 1m. Where it is
necessary for a cable route to parallel a railway line, the cable trench shall be excavated at such a
distance from the railway edge as to avoid any possible structural or mechanical damage to the
railway. However, under no circumstances shall the near edge of the cable trench be within 1m of
the railway bed. The railway authorities shall be contacted with the approved designs for clearance
before the start of any construction activities on the cable to be laid.
At least one spare duct shall be installed at each ducting location. All conditions and restrictions
stipulated by the responsible authorities shall be complied with.
Service and Utility Conflict’s
Where conflict with other services is unavoidable, paralleling with existing installations shall be
avoided wherever possible. It must further be ensured that the minimum clearances tabulated below
are attained in all situations and that any cable ratings are not decreased by paralleling.
EXISTING CABLE/SERVICE
NEW
33KV 15KV LV TELEPHONE WATER or
CABLE
SEWERAGE
Employer and all utilities (stakeholders) concerned are contacted and their written approval
received.
The cable to be installed is adequately protected by a duct of approved type over the critical length.
Installation of cables at depths greater than standard shall only be permitted at road and railway
crossings or at conflict locations, subject to the general approval of the Employer. Necessary steps
shall be taken to ensure that under such situations the current rating of the cable is not seriously
affected by variation in installation depth.
Cable Accessories
It is essential to select the design of accessory to be compatible with the particular cable type and
the particular service application. Compatibility should be validated.
Accessory Types
Joints: A joint is the insulated and fully protected connection between two or sometimes more
cables. It is also termed “splice”. The following types exist for distribution cables:
• Straight joint,
• Transition joint
• T branch joint.
Terminations: A termination is the connection between a cable and other electrical equipment.
It is also termed pothead. The following types exist for distribution cables:
• transformer termination,
• Outdoor termination,
• Indoor termination
Cable Installation
Preliminary Power Cable Installation Requirements
Before any civil works are undertaken, due notice in writing shall be given to all utilities whose
services may be in conflict with the proposed cable route, e.g. telephone, water, sewage, road and
railway, etc. It may be advisable to contact the Engineering Coordinating Committee located at the
offices of the Urban Roads for assistance. Where cables are to be installed in roads, footpaths or
streets, it is advisable to liaise closely with the roads authority and police to ensure that all necessary
measures are taken to minimize the hazards and disruptive effects of installation works.
Drums shall be handled carefully during loading and unloading. Adequate lifting and handling
facilities shall be provided to avoid damage to the cable drum or cable during lifting operations.
Good lifting practices shall be employed during all drum handling activities.
Drums shall not be dropped on the ground. Drums shall be unloaded as near as possible to the
location where they will be supported during cable pulling. Drum rolling distances shall be kept
to a minimum. Drums shall only be rolled in the direction of the arrows inscribed on the drum
flange.
During cable pulling the drum shall be so arranged as to reel the cable from top of the drum
wherever possible.
Excavation of Trenches
Trenches shall be kept as straight as possible and shall be excavated to approved formations and
dimensions. Trenches shall have vertical sides and shall be timbered and sheered where necessary
to prevent subsidence when they are excavated below 1.2m.
At bends in the cable route, the trench shall be dug with a radius not less than the minimum bending
radius for the cable. However, it is recommended that the trench be dug with a lower radius if the
cable is to be laid by pulling over rollers in the trench.
Asphalt, concrete or other surfacing materials shall be cut by motor driven saws. Manual digging
shall be used where existing underground facilities are encountered. Existing facilities uncovered
during excavation shall be protected, shored, braced, and supported, as necessary. All protective
coverings, warning tapes, position markers, etc., pertaining to existing underground facilities shall
be preserved during excavation and restored during backfilling.
At intersections with other utility lines, the trench may be sloped on both sides of the crossing point
to maintain required clearance. However, minimum burial depths for the cable must be maintained.
The slope of the trench shall not exceed 1:10 to avoid sharp bends in the cable.
All excavations exceeding 1.2 meter depths shall be properly sheered and braced. Excavations
shall not be extended below the elevation of adjacent existing foundations unless the foundations
are properly underpinned and shored. The trench bottom shall be smooth and free from stones and
rubble. The trench shall be dewatered before laying the cable.
Cable jointing pits shall be excavated to such dimensions as may be required to provide adequate
room for cable jointing to be completed without excessively stressing the cable, its components or
inhibiting ease of operation by jointers.
Spoil Handling
Excavated surface materials (including base foundations for roadways) should be stacked
separately from sub soils so that correct compaction and reinstatement can be obtained when
backfilling. All excavated materials shall be cleared from the edge of the trench so that rolling back
into the trench does not occur and to avoid the possibility of trench collapse. In general, excavated
materials may not be stacked within a distance equivalent to the trench depth of the trench edge.
Where excavated materials are deemed to represent a hazard, to the public or the operatives, it shall
be removed to an appropriate storage location for future use.
Trench Preparation
Before any cables are laid, the bottom of the trench shall be lined with unwashed river sand, of
favorable grain distribution, and well compacted to a minimum depth of 100mm. Ducts shall be
cleaned and fitted with a bell mouth at entry points and at exit points. Where the end of a duct is
level with the trench bed, a depression shall be made immediately before the duct entry to prevent
stones or coarse soil from entering the duct during cable pulling.
Adequate number of cable rollers and skids shall be provided to ensure that the cable is adequately
supported, does not touch the trench surface and does not exceed its minimum bending radius
during pulling. Cable rollers shall not be installed more than 2 meters apart under any
circumstances. All cable rollers shall be smooth surfaced and free rolling. All cable skids shall be
smooth surfaced. Defective cable rollers or skids shall not be used.
Cable Installation
Cable shall be installed in maximum possible lengths and straight through jointing between shorter
lengths will not be permitted without the prior written authority of the Design Engineer.
Care must be taken to ensure that the cable is not abraded by the trench surface, duct end, cable
rollers or cable skids during installation.
Under no circumstances shall the cable be subjected to a pulling tension in excess of the
manufacturer's maximum permitted cable pulling tension. Cable lubricants may be employed
where pulling is difficult at bends or ducts. Cable lubricants shall be applied in accordance with
cable manufacturer recommendation.
In general, a suitable lubricant should be used when pulling cable into ducts. Underground power
cables have an extruded serving of PVC or polyethylene to which a graphite coating is normally
applied in the factory. A cream of powdered graphite and water, if liberally applied is an ideal
lubricant for these cables. In addition, powdered graphite can be blown through the duct or drawn
through in a bag. Alternatively soap powder has been successfully used as a lubricant.
The cable shall be removed from the cable rollers and placed on the trench bed in such a way as to
form a slightly wavy line in order that its length is approximately 1% greater than the true route
length. This length is necessary to avoid longitudinal stress due to soil settlement and thermal
cycling.
Following completion of each cable pull, the section of cable damaged by the cable pulling
mechanisms shall be cut from the cable and scrapped. The damaged section shall be deemed to
extend beyond the actual pulling mechanism bearing area and shall be at least 1.5m long.
Where cable joints or splices are to be made, the ends of the cables shall be overlapped by 1.5m to
2m to provide adequate slack for jointing.
Where equipment terminations are to be made a 1.5 to 2 meter loop of spare cable shall be provided
for terminating purposes.
Wherever a cable is cut, the ends shall be sealed from moisture entry with an approved cable end
cap unless a joint or termination is to be undertaken immediately.
Cable ends shall remain properly sealed until splices or terminations are to be made.
The required minimum clearances from other underground facilities shall be maintained at all
conflict situations.
The cable route shall be inspected by a representative of Employer and the route length of the cable
shall be measured and recorded (to be nearest 0.5m) for payment and recording purposes. Details
regarding the number and type of joints and repairs, their location and the name of the jointer shall
be recorded and marked on a copy of the construction drawings. These drawings shall be certified
by a representative of Employer.
The cables shall be covered by a layer of unwashed river sand, of favourable grain distribution,
compacted manually to a depth of 100mm. The sand shall be applied by hand tools, spreading the
sand along the length of the cable route to avoid dislodging the cable(s).
Cable tile covers for LV and HV Cables shall be installed. The tile shall be made in such a way to
give a clear visual warning to contractors and utilities of the presence of underground cables or
ducts during excavation.
The tile shall be manufactured from reconstituted low or medium density polythene or a similar
material which shall be rot-proof and resistant to a wide variety of virgin and tipped soil conditions.
The ends of the tile shall be cleanly cut, square with its longitudinal axis and shall have not sharp
edges. The tiles shall be laminated with suitable marker tape identification complying with
Employer specifications.
Backfilling
After all cables and protective covers have been laid, the trench shall be refilled in 150mm layers
of well-compacted material.
Backfilling shall generally be in the reverse order from excavation, i.e. subsoils first followed by
top soils. However, where the backfill material is not of suitable composition, e.g. gravel, wet clay,
etc., a suitable volume of appropriate material shall be imported as necessary to provide adequate
backfill.
Warning Tape
Cable warning tape of an approved type shall be laid above the cable in the backfill material.
Reinstatement
Roads and pathways shall be reinstated or be provided with temporary reinstatement in compliance
with the stipulation of the relevant authority. In any event during temporary or permanent
reinstatement of roads, it shall be ensured that:
Water from any source shall be drained from the excavated site.
While reinstating, longitudinal and transversal slopes of the street shall be taken into consideration.
Road markings which are obliterated as a result of the removal of the surface shall be restored in
the same manner as they were marked before excavation.
The newly reinstated portion should match very well with the old surface. The level of the new
surface after compaction should not deviate from that of the old surface by more than 10mm or as
required by the concerned authority.
Material and layer compaction testing shall be carried out in accordance with the specification of
the concerned authority.
Reinstatement of grass areas shall be completed to provide a profile matching the existing surface
following consolidation. The surface shall be of soil quality similar to that of the surrounding area.
Uprooted shrubs, trees etc. shall be replanted.
Splices and terminations shall be made in accordance with the instructions provided by the
manufacturer. These instructions shall be included with each splice and termination kit.
Terminations shall be so constructed as to provide a complete moisture seal, including the crotch
area of multi-core cables and complete re-jacketing of the individual cores.
LV. Cable terminations shall be so constructed as to provide adequate loops of cable to ensure the
necessary flexibility at joint and to prevent moisture ingress to the cable cores. Each joint shall be
moisture sealed by tape or other approved method.
Care shall be taken in every step from start to finish keeping the cable splice or termination free
from moisture, dirt, particles of metal and air pockets. To accomplish this, hands, tools, containers
and supplies shall be kept clean, dry and free from foreign matter at all times. After the cable
insulation has been exposed by removal of any section of the outer covering, operations shall be
continued without interruption until the cable termination or splice is completed.
Care must be taken that no sharp bends or twists are made in the cable or cores, even temporarily,
while installing a splice or termination. Bending of cable at a short radius may permanently damage
the insulation, shielding or jacket.
The section of cable between the protective pipe and the termination shall be so fixed as to restrict
free movement. The minimum bending radius of the cable shall in no case be exceeded.
and 15kV/33kV lines, cable terminations shall be protected by surge arresters, mounted between
them and the overhead line.
The cable(s) shall not be allowed to bend sharply or kink where it emerges from the protective pipe.
The cable protective pipe shall be of such material as to be non-injurious to the cable and shall
provide a preformed bend in the ground and a bell mouth at the pole where the cable(s) emerges.
Terminating to Equipment
Only terminations of an approved nature may be used. Terminations shall be made to substations
equipment in accordance with the instructions provided by the manufacturer. These instructions
shall be included in each termination kit.
Cable Testing
Required tests to prove the electrical integrity of the installed cables shall be carried out.
All cables to be tested shall be dressed and terminated and prepared for final connection to overhead
network or other plant as appropriate.
It shall be ensured that access to the cable ends or test area is not inhibited by the provision of
barricades, bollards, warning tapes, signs etc.
• Phase Identification
The above tests shall be conducted using an approved insulation resistance measuring device.
All new cables shall be subject to high voltage AC test after installation. This technical information
applies to XLPE insulated cables with voltage ratings from 1.9/3.3 kV to 19/33 kV.
After installation AC test levels shall be in accordance with the cable manufacturer’s
recommendations. The DC testing of the primary insulation is not recommended due to resulting
high electrical stresses.
All tests shall be recorded and certified. Test results shall be tabulated in an approved format and
submitted with the commissioning documents on the handover completion.
Employer shall identify to the Contractor at the commencement of the Construction works all
“Hold” activities where specification issues or specific requirements need addressing to ensure
compliance and acceptability prior to activity or work starting or an inspection is required prior to
the item or process being completed.
Witness testing of specific items of completed work or sections of work shall also be identified by
Employer.
• Before Dismantling safety caution should be done by proper procedure of line discontinued
from substation and grounded on both sides.
• The poles may be very poor and old, therefore cranes are recommended for line men for
removing the pole top items and conductor.
• If required temporary power supply options should be provided for the community partially
disconnected or affected due to LV disconnection during transformer dismantling.
1. Poles: Poles shall be removed from the foundation and all hardware dismounted and packed
separately. Contractor shall prepare a list of all material and send it to the warehouse of EEU. After
dismantling Pole pits should be backfilled to avoid accidents.
2. Transformers: Distribution transformers shall be dismounted and lay to ground. All
equipment like surge arresters, cut-outs, insulators shall be carefully dismounted. Contractor shall
prepare a list of all material and send it to the warehouse of EEU
3. Conductors: Conductors shall be removed and brought to ground and measured. Then it
shall be coiled with indication of length removed. Contractor shall prepare a list of all material and
send it to the warehouse of EEU.
4. Pole line equipment’s – Shall be dismantled with care to avoid damage due to aging.
Section X - Contract Forms 377
3 Route Drawings
The Contractor must provide and maintain, a practicable working environment for its
employees and members of the public. The Contractor must itself, and must ensure that any
subcontractors of the Contractor, at all times identify and take all necessary
precautions/measures/ for the health and safety of all project staff and the community as well
who may be affected by the execution of the project activities.
The Contractor shall, throughout the design, execution, and completion of the Works and
Services, take all reasonable precautions to preserve the condition of the environment, consider
public and occupational safety and addressing any non-compliance to resolving of any defects
therein.
The contractor shall periodically report the project environment, social ,health and safety
performance report to the client. The above ES requirements are general ,the detailed in
presented in number 10 below under the title of ESHS requiremnts.
Section X - Contract Forms 378
✓ The Contractor shall not employ “forced or compulsory labor” in any form.
“Forced or compulsory labor” consists of all work or service, not voluntarily
performed, that is extracted from an individual under threat of force or penalty.
7. Prohibition of Harmful Child Labor
✓ The Contractor shall not employ any child to perform any work that is
economically exploitative, or is likely to be hazardous to, or to interfere with, the
child's education, or to be harmful to the child's health or physical, mental,
spiritual, moral, or social development.
8. Health and Safety
✓ The Contractor shall at all times take all reasonable precautions to maintain the health
and safety of the Contractor’s Personnel. In collaboration with local health authorities,
the Contractor shall ensure that medical staff, first aid facilities, sick bay and ambulance
service are available at all times at the Site and at any accommodation for Contractor’s
and Employer’s Personnel, and that suitable arrangements are made for all necessary
welfare and hygiene requirements and for the prevention of epidemics.
✓ The Contractor shall contract or make an agreement with the nearby hospital for cases
requiring further treatment.
✓ The Contractor shall provide such first aid facilities and ensure that his staffs abide by
such first aid procedures as shall be required by the Public Body
✓ The Contractor shall appoint an accident prevention officer at the Site, responsible for
maintaining safety and protection against accidents. This person shall be qualified for
this responsibility, and shall have the authority to issue instructions and take protective
measures to prevent accidents. Throughout the performance of the Contract, the
Contractor shall provide whatever is required by this person to exercise this
responsibility and authority.
✓ The Contractor shall ensure the safety on sites during the whole period of execution
and shall be responsible for taking the necessary steps, in the interests of his employees,
agents of the Public Body and third parties, to prevent any loss or accident which may
result from carrying out the works.
✓ The Contractor shall take all essential steps, on his own responsibility and at his
expense, to ensure that existing structures and installations are protected, preserved,
and maintained. He shall be responsible for providing and maintaining at his expense
Section X - Contract Forms 381
all lighting, protection, fencing, and security equipment which proves necessary for the
proper implementation of the tasks or which may reasonably be required by the
Engineer.
✓ If, during the implementation of the tasks, urgent measures are necessary to obviate
any risk of accident or damage or to ensure security following any accident or damage,
the Engineer shall give formal notice to the Contractor to do what is necessary. If the
Contractor is unwilling or unable to undertake the necessary measures, the Engineer
may carry out the work at the expense of the Contractor to the extent that the Contractor
is liable.
✓ While carrying out the Works, the Contractor shall comply, and shall ensure that its
employees comply with, the requirements of relevant Health and Safety and other
relevant legislation,
✓ The Contractor shall ensure the co-operation of its personnel in all prevention measures
designed against fire, or any other hazards, and shall notify the Public Body of any
change in the Contractor's working practices or other occurrences likely to increase
such risks or to cause new hazards.
✓ The Contractor shall conduct regular awareness for the public and passerby on safety
precautions and management
✓ Information, Education, Consultation and Communication
✓ The Contractor shall throughout the contract, conduct information sharing and
continuous stakeholder/public consultations in and around work sites, concerning the
risks and impacts, and appropriate mitigation measures and safety precautions with
respect to the contract works and services.
✓ The Contractor shall throughout the contract (including the Defects Notification
Period): (i) conduct Information, Education and Consultation Communication (IEC)
campaigns, at least every other month, addressed to all the Site staff and labor
(including all the Contractor's employees, all Sub-Contractors and Employer’s and
Project Manager’s' employees, and all truck drivers and crew making deliveries to Site
for construction activities) and to the immediate local communities, concerning the
risks, dangers and impact, and appropriate avoidance behavior with respect to of
Sexually Transmitted Diseases (STD)—or Sexually Transmitted Infections (STI) in
general and HIV/AIDS in particular; (ii) provide male or female condoms for all Site
Section X - Contract Forms 382
staff and labor as appropriate; and (iii) provide for STI and HIV/AIDS screening,
diagnosis, counseling and referral to a dedicated national STI and HIV/AIDS program,
(unless otherwise agreed) of all Site staff and labor.
✓ The Contractor shall include in the program to be submitted for the execution of the
required facilities, an alleviation program for Site staff and labor and their families in
respect of Sexually Transmitted Infections (STI) and Sexually Transmitted Diseases
(STD) including HIV/AIDS. The STI, STD and HIV/AIDS alleviation program shall
indicate when, how and at what cost the Contractor plans to satisfy the requirements of
this Sub-Clause and the related specification. For each component, the program shall
detail the resources to be provided or utilized and any related sub-contracting proposed.
The program shall also include provision of a detailed cost estimate with supporting
documentation. Payment to the Contractor for preparation and implementation this
program shall not exceed the Provisional Sum dedicated for this purpose.
9. ESHS Requirements
The following Environment, Social, Health and Safety requirements shall be considered by the
Contractor and his subcontractor, if available:
Prohibitions
The following activities are prohibited on or near the project site:
✓ Cutting of trees for any reason outside the approved construction area.
✓ Hunting, fishing, wildlife capture, or plant collection.
✓ Use of unapproved toxic materials, including lead-based paints, asbestos, etc.
✓ Disturbance to anything with architectural or historical value.
✓ Building of fires;
✓ Use of firearms (except authorized security guards).
✓ Use of alcohol by workers.
✓ No unauthorized or indiscriminate felling of trees shall be permitted;
✓ No open or uncontrolled fires shall be permitted;
✓ No pollutants shall be allowed to enter any watercourse.
✓ The Contractor shall not cause areas of stagnant water to form, on the surface or
in open containers;
✓ The contractor shall collect, segregate and dispose or cause to be collected,
recycled or disposed of hazardous waste by authorized body;
Section X - Contract Forms 383
✓ Dispose in authorized areas all of garbage, metals, used oils, and excess material
generated during construction, incorporating recycling systems and the
separation of materials.
✓ No trench shall be left open for more than 7 days, unless duly authorized by the
supervisor upon Contractor’s request. Trenches and other excavation works shall
be established, demarcated/fenced and/or signposted sufficient to prevent
accident or injury to workers or the public, including during hours of darkness.
✓ The Contractor shall prepare and implement Site Management plan (Contractor
Environmental and Social Management Plan) comprises of all sub plans to address each
environmental, social and safety matter; These include: safety management plan, Waste
management plan (both hazardous and non-hazardous), emergency preparedness plan,
Quarry restoration plan, spoil disposal management plan, Physical cultural resource
plan with chance find procedures; Camp site management plan, spontaneous settlement
management plan, labor influx management plan, dust management plan, etc.;
✓ The Contractor shall assign qualified environmental, social and safety management
experts for regular implementation, follow up and reporting of Environmental, Social,
Health and Safety activities as identified in the management plan.
✓ Specific Protection Measures: Quarries and Borrow Areas and deposit sites
✓ The Contractor shall obtain appropriate licenses/permits from relevant authorities to
operate quarries or borrow areas prior to their first use. The location of quarries and
borrow areas shall be subject to review and approval by relevant local and national
authorities.
✓ New sites:
✓ Shall be located 1km or more from settlement areas, archaeological areas, and cultural
sites -including churches and cemeteries, wetlands or any other valued ecosystem
component, or on high or steep ground.
✓ Shall not be located in water bodies, or adjacent to them, as well as to springs, wells,
well fields
✓ Shall not be located in or near forest reserves, natural habitats or national parks.
✓ Shall be designed and operated in the perspective of an easy and effective rehabilitation.
Areas with minimal vegetation cover such as flat and bare ground, or areas covered
with grass only or covered with shrubs less than 1.5m in height, are preferred.
✓ Shall have clearly demarcated and marked boundaries to minimize vegetation clearing
and safety hazards for third parties.
✓ Shall be operated in accordance with the General Environmental Protection
Requirements, the Construction ESMP for the project and in accordance with any
consent / permit conditions.
Section X - Contract Forms 385
✓ Maintenance:
✓ Identify and demarcate equipment maintenance areas (>15m from rivers, streams, lakes
or wetlands).
✓ Ensure that all equipment maintenance activities, including oil changes, are conducted
within demarcated maintenance areas; never dispose spent oils on the ground, in water
courses, drainage canals or in sewer systems.
✓ Identify, demarcate and enforce the use of within site access routes to limit impact to
site vegetation.
✓ Install and maintain an adequate drainage system to prevent erosion on the site during
and after construction.
Specific Protection Measures: Electrical Installation ,Commissioning, Maintenance and
Operation
• All site activities should be implemented as per procedures and proper safety measures
as indicated in :
• EEU Safety and Procedure Manual for Distribution System (O&M)
• EEU Safety and Procedure Manual for Transmission System
• Furthermore implementing recommended international practices for safety of electrical
operation and maintenance works.
Community Relations
✓ To enhance adequate community relations the Contractor should:
✓ Following the WB & country ES safeguard requirements, inform the population about
construction and work schedules, interruption of services, traffic detour routes as
appropriate.
✓ Limit construction activities at night. When necessary, ensure that night work is
carefully scheduled and the community is properly informed so they can take necessary
measures.
✓ At least five days in advance of any service interruption (including water, electricity,
telephone, and transportation routes) the community must be advised through postings
at the project site, at bus stops, and in affected homes/businesses.
✓ The Contractor shall keep accurate records of the Contractor’s personnel, including the
number of each class of Contractor’s Personnel on the Site and the names, ages,
genders, hours worked and wages paid to all workers. These records shall be
summarized on a monthly basis in a form approved by the Project Manager and shall
be available for inspection by the Project Manager until the Contractor has completed
all work.
✓ The Contractor shall prepare and implement Site Management plan (Contractor
Environmental and Social Management Plan) comprises of all sub plans to
address each environmental, social and safety matter; These include: safety
management plan, Waste management plan , Quarry restoration plan, spoil
disposal management plan, chance find procedures; Camp site management plan,
labor influx management plan, dust management plan, etc.
The following is a non-exhaustive list of Sub-Clauses of the Conditions of Contract that make
reference to ES matters stated in the Specification.
20 Design and Engineering The contractor will design, construct, operate, and decommission
the structural elements of the project in accordance with national
legal requirements, the EHSGs and other Good International
Industry Practice (GIIP), taking into consideration safety risks to
third parties and affected communities.
The contractor assign competent professionals to design the
structural elements of a project and the structural design will take
in to account climate change considerations.
Where the project includes new buildings and structures that will
be accessed by members of the public, the Borrower will consider
the incremental risks of the public’s potential exposure to
operational accidents or natural hazards, including extreme
weather events. Where technically and financially feasible, the
Borrower will also apply the concept of universal access (The
concept of universal access means unimpeded access for people
of all ages and abilities in different situations and under various
Section X - Contract Forms 388
22.2.4 Rates of wages and “The Contractor shall inform the Contractor’s Personnel about
conditions of labor their liability to pay personal income taxes in the Country in
respect of such of their salaries, wages, allowances and any
benefits as are subject to tax under the Laws of the Country for
the time being in force, and the Contractor shall perform such
duties in regard to such deductions thereof as may be imposed on
him by such Laws.
22.2.6 Facilities for Staff and Indicate if access to or provision of services that accommodate
Labor physical, social and cultural needs of Contractor’s Personnel is
required.
22.8 Security of the Site Thecontractorit will assess risks posed by these security
arrangements to those within and outside the project site. In
making such arrangements, the Borrower will be guided by the
principles of proportionality and GIIP, and by applicable law, in
relation to hiring, rules of conduct, training, equipping, and
monitoring of such security workers.
The Contractor shall be responsible for the security of the Site,
and:
22.11 Cultural Heritage The Contractor will avoid impacts on cultural heritage.
Findings When avoidance of impacts is not possible, the contractor
will identify and implement measures to address impacts
on cultural heritage.
The contractor follow the following mitigation measures:-
relocating or modifying the physical footprint of the
project; conservation and rehabilitation in situ; relocation
of cultural heritage; documentation;
Strengthening the capacity of national and sub national
institutions responsible for managing cultural heritage
Section X - Contract Forms 390
Loan/Credit No:
RFB No:
To: _________________________________
(were) complete on the date specified below, and that, in accordance with the terms of the
Contract, the Employer hereby takes over the said part(s) of the Facilities, together with the
responsibility for care and custody and the risk of loss thereof on the date mentioned below.
This letter does not relieve you of your obligation to complete the execution of the Facilities
in accordance with the Contract nor of your obligations during the Defect Liability Period.
Title
(Project Manager)
Section X - Contract Forms 394
Date:
Loan/Credit No:
RFB No:
To: ________________________________________
Pursuant to GCC Sub-Clause 25.3 (Operational Acceptance) of the General Conditions of the
Contract entered into between yourselves and the Employer dated _______________, relating to
the ___________________________________, we hereby notify you that the Functional Guarantees
of the following part(s) of the Facilities were satisfactorily attained on the date specified below.
This letter does not relieve you of your obligation to complete the execution of the Facilities
in accordance with the Contract nor of your obligations during the Defect Liability Period.
Title
(Project Manager)
Section X - Contract Forms 395
CONTENTS
1. General
2. Change Order Log
3. References for Changes
ANNEXES
Attention: ______________________________________
With reference to the captioned Contract, you are requested to prepare and submit a Change
Proposal for the Change noted below in accordance with the following instructions within
_______________ days of the date of this letter____________________.
(b) Your estimate shall include your claim for the additional time, if any, for completion
of the requested Change.
(c) If you have any opinion negative to the adoption of the requested Change in connection
with the conformability to the other provisions of the Contract or the safety of the Plant or
Facilities, please inform us of your opinion in your proposal of revised provisions.
(d) Any increase or decrease in the work of the Contractor relating to the services of its
personnel shall be calculated.
(e) You shall not proceed with the execution of the work for the requested Change until
we have accepted and confirmed the amount and nature in writing.
(Employer’s Name)
(Signature)
(Name of signatory)
(Title of signatory)
Section X - Contract Forms 399
Attention: _______________________________
Sub-total hrs
Total Engineering Cost
(b) Other Cost
2
Section X - Contract Forms 400
(Contractor’s Name)
(Signature)
(Name of signatory)
(Title of signatory)
Section X - Contract Forms 401
(Employer’s Letterhead)
Attention: ________________________________
We hereby accept your Estimate for Change Proposal and agree that you should proceed with
the preparation of the Change Proposal.
6. Other Terms and Conditions: In the event that we decide not to order the Change
accepted, you shall be entitled to compensation for the cost of preparation of Change Proposal
described in your Estimate for Change Proposal mentioned in para. 3 above in accordance with
GCC Clause 39 of the General Conditions.
(Employer’s Name)
Section X - Contract Forms 402
(Signature)
Attention: _______________________________
(Amount)
3
Section X - Contract Forms 404
(d) Subcontracts
(a) You are requested to notify us of your acceptance, comments or rejection of this
detailed Change Proposal within ______________ days from your receipt of this Proposal.
(b) The amount of any increase and/or decrease shall be taken into account in the
adjustment of the Contract Price.
(c) Contractor’s cost for preparation of this Change Proposal:42
(Contractor’s Name)
(Signature)
(Name of signatory)
(Title of signatory)
4
Section X - Contract Forms 406
Attention: _______________________________
Attention: _______________________________
We instruct you to carry out the work in the Change Order detailed below in accordance with
GCC Clause 39 of the General Conditions.
(Employer’s Name)
(Signature)
(Name of signatory)
(Title of signatory)
(Contractor’s Letterhead)
(Contractor’s Name)
(Signature)
(Name of signatory)
(Title of signatory)
Signed: __________________
Date: ___________________
Company: __________________
tools
Company Stamp
Appendix A Towns Information 410
Holeta is a vibrant city in which many socio-economic activities are taking place that make it
play major roles in the development of the country. As the center of attraction, the city is
growing fast physically, in economic importance and population size which poses many
challenges that put the city administration under pressure. The other critical issue is the
environmental problem of the lakes themselves which is becoming very sensitive and crucial
issue. These growing challenges need appropriate and timely planning and management
response to exploit the opportunities and curb the undesirable effects of the ongoing
developments on the area. On the other hand, the institutional capacity and absence of
necessary regulation are the critical issues to be addressed in protecting the lakes and their
environs from current and potential damages.
Asset management is a term used to describe a way of managing assets across their entire life
cycle cost and provide for the replacement of the assets at the appropriate point in time. It is a
specific approach to the management of physical assets; be it infrastructure networks, buildings
or moveable assets which bring together good technical management practice with sound
financial principles. It also provides an integrative approach that links project based capital
investment planning with long term operation and maintenance needs to provide sustainable
management system. In general, Asset Management Update is expected to provide a much
more effective system for Holeta City Administration to plan its future budget with an informed
decision.
The City administration lacks the necessary information about their own capital assets for
detailed costing of individual assets and for improvement planning due to absence of strategic
approach to asset management techniques. Hence, the intended Asset Management Plan
supposed to enable the city administration to build knowledge and database of its infrastructure
asset base.
The Geospatial of Holeta City
Astronomically, Holeta is located with geographic coordinates of 90300Latitude and 380
300Longitude. The average Temperature of the city is max. 17.5 oc and min. 12.6oc average
14.6oc .which is the most favorable weather condition throughout the Year.
North Shewa Zone is one of among The Zones found in Oromia National Regional State
and it is located in the northern portion of Oromia National Regional state. The zone
comprises 14 districts including Fitche Town Administration and its total area is
accounted for 8989k2.Fitche town is the administrative center of the zone and it is found
112 km away north of Finfinne. The zone has a total population projected for 1, 594, and
720 in 2010 E.C as of population census of 2007 G.C.
Administratively Fiche town is part of Oromia National Regional State and seat of Girar
Jarso District zone. It is located at a distance of 112-kilo meters from Regional and
National capital_ Finfinne/Addis Ababa towards the north direction.
The structure plan of Fiche town was prepared in 2004. The rationales for the revision of
the structure plan for the town include the completion of the ten years’ planning period
and the fast growth of the town that requires new expansion areas for different urban
land use functions.
Appendix A Towns Information 413
The highway that runs to the northern parts of the country crosses the town. The peasant
associations of Addisge in the north, Torban Ashe in the southwest, Dire Doyyo and
Koticha Gobola (Sefane) and Wertu Silase in the East, surround it. Astronomically, Fiche
town has a grid coordinate that extends from 1077026 to 1084623 Northing and from
467848 to 476274 Easting on Military Grid Reference System (MGRS) of the Universal
Transverse Mercator (UTM) Projection (refer to the location map of the town).
Topography
The structural plan of the town describes the topography of landform of Fiche town and
its environ comprising vast plain areas, swampy and water bodies, soft, rounded hips and
hilly mountains, steep and rounded hills and associated undulating dissected areas. The
southern portion of the town is largely associated and characterized by undulating and
rugged terrains whereas the Northern is to a large extent plain area. The northern and
northwestern part of the town has attractive ridges and includes Torban Ashe up and
pockets of uplands in the southwest all of which have attractive viewpoints. The town has
flat topography in the southwest which is an important place for traditional horse race
(hurufa fardaa). This traditional horse race, which is a common cultural practice in north
Shewa, and this can enhance the tourism potential of the town and its hinterland
Soil types
According to FAO classification, the soil of the project area is classified into two
categories; Vertisols sand Luvisols as shown in the figure 4.7. Mostly this classification is
used for agricultural purpose. For engineering purpose the classification gives some hint
about the properties of the soil in the study area.
Climate
As per the Ethiopian customary climate classification, the town is classified as “Woina-
Dega”; the average annual temperature and rainfall of the town are 19.320C and 860mm
respectively. The presence of Fiche town at the rim of the Abay drainage basin makes the
town to have cool climate related to the scorching heat of the lowlands located towards
the east of the town within the Abay drainage basin. The highway crossing the town to
the northern parts of the country can be turned to an important commercial corridor by
Appendix A Towns Information 414
proposing land uses that can serve both the nearby residents and the passengers crossing
the town.
The monthly mean maximum temperature ranges from 24.190C (August) to 29.40C
(May). The monthly mean minimum temperature ranges from 90C (December) to 13.90C
(August). Whereas, the minimum and maximum annual temperature ranges from
11.960C to 26.860C that make an average of 19.320C
May and December are the warmest and coldest months; March and April are also
warmer months next to May, where the highest maximum mean temperatures are
observed during these three months. On the other hand, the lowest minimum mean
temperatures mostly occur from November to February each year.
Rainfall
The town has five rainy months; from March to April and from June to September that
make two rainy seasons of spring and summer respectively. Summer rain accounts for 50
to 90% of the annual rainfall in the area and is relatively stable when compared with
other rainfall season. Winter is a dry season in Fiche town. The mean annual rainfall
recorded over the ten years (1998-2007) has shown that the month of July is the highest
rainy month with a mean annual rainfall of 244.5mm and in November lNorth (4.5mm)
recorded as per the master plan report. The mean annual rainfall is about 860.6mm.
Drainage
Fiche town is drained by perennial and seasonal streams like Zerefet, Mentera and Lege
Werabessa. All of the streams flow either from northwest direction to southeast or east
directions. This implies that the altitude of the town declines from northwest to southeast
or
south direction.
There are different streams flowing within the boundary of Fiche town. This includes
Lege
Werabessa, Zerefet and Mentera. The volume of these seasonal streams increases during
the rainy season due to an increase for rainfall. Because of this, most of the seasonal
Appendix A Towns Information 415
streams have flood risks especially adjacent to their middle courses and in areas that are
encroached by settlement and cultivation of eucalyptus trees by the sides of the streams
Therefore, there should be a plan of appropriate diversion channels in flood hazard areas
of the town. Besides, those areas of the town encroached by residents should be intervened
by proposing a 30 meter buffer zone after which it is possible to practice urban
agriculture that Includes the cultivation of vegetables and related activities.
Water surface
The surrounding of the study area has the potential of surface water. The surface water
which passes crossing the town was starts from the within and in periphery of the project
area. The project area has rivers or streams potential flowing through the town. These
streams and rivers have low discharge during dry season. In the dry season the discharge
of these streams/rivers become decrease while in the rainy season the discharge increase.
From ground surveyed surface water (figure 4.4) and surface watershed (figure 4.5)
generated from DEM by GIS software, there were potential of surface water in the study
area. But, most of the streams dry in the dry season. Due to this the area has low surface
water catchments and potential for the reason of urban expansion and deforestation in
the study area and in upper catchments. Even if there is surface water, there were
problem in how to use and how to manage effectively the resource in the town.
Lege Tafo Lega Dadi town Administration is located in the Oromia National Regional state
within the Zone of Oromia special Zone surrounding Finfinne (OSZSF). The social and
economic development of a society is closely related to the availability and dissemination
of adequate information .Today information could now be considered as the basic
infrastructure facility to bring about social change and sustainable economic development.
Being aware of this fact, the Municipality office for collecting, analyzing, storing and
disseminating town development information on natural resource and socio-economic
conditions that are the bases for enable the information of development planning and related
activities.
The objective of preparing this profile is to create scientifically organized physical and socio-
economic data base of Lege Tafo-Lege Dadi Town Administration that reflects the existing
situation, development problems and potentials of the town to be used by the government,
donors and given attention for the major problems of the town. The data used to organize this
document was collected from the Office Sectors and census result report and other related
document available in our office.
Waliso town has seven administrative Kebeles. Dej. Geresu Duki Comprehensive Secondary
School, Oromia Institute of Water Technology, Ambo University – Faculty of Social Science
(Waliso Campus) and other private institutes and colleges are located in Woliso. In Waliso,
there is a natural hot-spring, which makes the town one of the leading tourism heritages in
Ethiopia.
The town allows a round view of 360 degrees from Meja hill – a volcanic mountain (Tulluu
Majaa in Afaan Oromoo), situated in the middle of the town. There is also a natural hot-spring,
which makes the town a tourism heritage in Ethiopia. In addition, Wonchi volcano (Wancii in
Afaan Oromoo), the highest volcano Ethiopias, is 32 kilometers away from Waliso. This
volcano contains a crater lake which became a tourist destination
in 1955 a 40 kW hydro-electric power station was built; by 1965 the installed electrical capacity
was 32 kVA and the annual production 64,500 kWh. In 1958, Waliso was one of 27 places in
Ethiopia ranked as First Class Township. The Multipurpose Community Telecentre was
opened in February 2000, with assistance from the British Council. It was the first of its kind
in Ethiopia, and the next one was opened in Debre Berhan almost two years later. That same
year, construction of a 200-bed hospital was completed, the Wolisso Hospital (officially the
St. Luke Catholic Hospital), which was then opened on 27 April 2001. Construction was
launched in 1997 by an Italian organization (CUAMM Doctors with Africa), equipment
included surgical, X-ray and laboratory equipment, at a cost of 72 million Birr.[1]
Appendix A Towns Information 418
The second largest flower farm in Ethiopia, owned by the Indian company Surya Blossoms,
had its official opening in Woliso on 22 June 2009. Present at the opening was Trade and
Industry Minister Girma Biru, Indian Ambassador to Ethiopia, Gurjit Sing, Oromia Regional
president Abadula Gemeda, and Chairman of Karuturi Global Limited, the parent corporation
of Surya Blossoms, Surya Rao
Demography
The 2009 national census reported a total population for Waliso of 59,685, of whom 18,880
were men and 18,998 were women. The majority of the inhabitants said they practised
Ethiopian Orthodox Christianity, with 23.29% of the population reporting they observed this
belief, while 59.06% of the population were Protestant, and 16.36% were Muslim.The 1994
national census reported this town had a total population of 25,491 of whom 11,899 were males
and 13,592 were females. It is the largest town in Waliso and Goro woreda.
climate
Waliso, the wet season is comfortable and mostly cloudy and the dry season is warm and partly
cloudy. Over the course of the year, the temperature typically varies from 50°F to 81°F and is
rarely below 44°F or above 86°F.
Shamboo climate
Coldest months of Shambu October and September are the coldest months with temperature at
around 13°c. Which months receive most rainfall in Shambu? September and August receive
most rainfall with precipitation count of 1061.86mm.
Schools
In the 1930s a schooling system was introduced to Shambu and the surrounding residents, an
area where 99.9% of the population lives in a rural-agriculture area and most youths walked to
Naqamte for schooling. Primary schools in Shambu include:
Shambu Junior and Elementary School (Est. 1938),Shambu Model Primary and Secondary
School (Est. 1977),Sombo Dedde Primary School (Est. 1989),Shambu Bikiltu Primary School
:Shambu Catholic Primary School,Mati Boru Primary School (private),Abishe Garba primary
School (private),Harbu Lisha primary school,Laga Warqe primary school,Shambu Catholic
kindergarten School Secondary schools
Shambu Preparatory and senior Secondary School establishe The operational Technical and
Vocational Education (TVET) colleges are:
Location Accessibility
Located at an elevation of None meters (0 feet) above sea level, Agaro has a Tropical wet and
dry or savanna climate (Classification: Aw). The district’s yearly temperature is 14.91ºC
(58.84ºF) and it is -7.32% lower than Ethiopia’s averages. Agaro typically receives about 89.51
millimeters (3.52 inches) of precipitation and has 190.26 rainy days (52.13% of the time)
Appendix A Towns Information 421
annually Annual high temperature 18.61ºC (65.5ºF), Annual low temperature 8.64ºC (47.55ºF)
Warmest month February (20.37ºC / 68.67ºF), Coldest Month December (6.97ºC / 44.55ºF)
Wettest Month April (191.44mm / 7.54in), Driest Month December (18.5mm / 0.73in)
Historical Significance: Agaro was once the capital of the former Kingdom of Gomma until
it was conquered by Dejazmach Besha Abuye in 1886. The settlement gained prominence and
was ranked as a First Class Township in Ethiopia by 19581.
Coffee Trading Hub: Agaro plays a vital role as one of the most important trading centers for
coffee in Ethiopia. The aroma of freshly roasted coffee beans fills the air, making it a hub for
coffee enthusiasts and traders alike.
Population and Beliefs: As of the 2007 national census, Agaro had a total population of
25,458. The majority of inhabitants follow the Muslim faith (60.7%), while others practice
Ethiopian Orthodox Christianity (33.76%) and Protestantism (5.04%)
Its coordinates are 9°33'0" N and 40°24'0" E in DMS (Degrees Minutes Seconds) or 9.55 and
40.4 (in decimal degrees). Its UTM position is FL55 and its Joint Operation Graphics reference
is NC37-11.
Location
Harta shek town is located at a distance of about 75 km from the regional capital Jigjiga and
25 km from the capital of woreda, Kebribayah city town. The map of the roads to the project
town form the regional capital is as indicated in the figure here below.
The geographical boundary of Hartashek Town with the current land use and settlement pattern
is as indicated in the map here below.
Climate
Its landscape includes Gamo Zone is elevated between 500 – 4207 meter above sea level
amazing landforms of mountians, valleys, cliff, undulated, rugged and some parts of the area
are flat topography. The highest elevation is located in Daramaloworeda which is known as
Gughe Mountain with peak point of 4207 m above sea level. Mount Gughe is also the highest
peak point of the region. The physiographic division of the country, Gamo Zone belongs to
south western highlands. Some of the rugged highlands such as Mt. Sura /3233m/ of chencha,
Mt. Gina /3000m/ of Dita, Mt. Adigore /3280m/ of Bonke and Mt. Bola Hera /2900m/ in Mirab
Abaya woreda are major mountain peaks of the Zone. This highlands and mountains belong to
the Gamo - konso mountain massif system of the south western highland division of the
country. Mt.Gughe is the highest mountain Peak point of the south west highlands of Ethiopia.
The lowest elevation is located in Gerese woreda-Adowoshebaye with altitude of about less
than 500m above sea level. Hartashek is located in tectonically destructive region of South
Western margin of the East African Rift system (EAR). The geomorphology of the Hartashek
Appendix A Towns Information 424
is highly variable and it is generally the result of repeated volcanic and tectonic events and it
has an overall tilted towards east direction.
Soil Type
The major soil types in Hartashek Residual soil commonly observed on the aphanitic basalt
formation due to high degree of weathering variations. The residual soils are formed by the
mechanical disintegration and chemical decomposition of the underlying rock units of
Rhyolite, the rock unit has a fresh and weathered color of reddish and dark respectively.
More over geographically limited area coverage of colluviums soils are preserved on the foot
of Gurba Mountain. These formations are unconsolidated, randomly oriented and loose
accumulation of different sizes of rock fragments and soil debris. These are occupied the foot
of Gurba Mountain due to down ward movement of debris by gravitational forces.
Project Area
KebriBeyah town is found in Somali Regional State of Fafen Zone, KebriBeyah district located
at a distance of 50 km Jigjiga town capital of the region. The town is situated in the Eastern
part of Ethiopia and covers about 554.31hectares and got legal entity as a town in 2008 E.C.
The town consists of for kebele and rapidly expand in all direction as the land is plain suitable
for construction. The city’s geographical/astronomical/ location is 42039to43038East
Appendix A Towns Information 425
longitude and 8045to9030 North latitude. It is found in Somalia Region, Fafen zone of
Kebribeya Woreda.The city 678 km far from Addis Ababa and also 50km far from jigjig the
capital city Somalia. The kebribeya is bordered on the south by the Degehabur zone, on the
southwest by the fiq zone, on the northwest by gursum, on the north by jijiga and awbare, on
the northeast by Somaliland, and on the east by Harshin, the city administrative center is
kebribeyah town.
Project Area
The town located in the Somali region of eastern part of Ethiopia ,approximately 9km the north
east of city of Dire Dawa .Shinile is situated at coordinates 9.688060N 41.844720E at elevation
of 1028 meters (3,373 feet) above sea level. The town is a part of the shinile woreda (district)
in site zone of the Somali region; it is bordered by Dire Dawa to the south, erer to the west,
Ayesha to the east, and dembel and jijiga zone to the south east. The Addis Ababa – Djibouti
railways and the Ethio- Djibouti railways both have stations in shinilie, making it an important
transportation hub in the region.
According to the climate data shinile town has an average minimum temperature of 15.1
0
C(59.20F)and an average maximum temperature of 35.00C(95.00F),with annual rain fall of
557mm(29.9in),The town of dwale has an average minimum temperature of 15.9 0C(60.60F)
Appendix A Towns Information 426
So in summary, shinile has a very hot semi-arid climate, with average annual temperatures
around 27.60C (81.7 0F) and extremes highs reaching over 350C(95 0F), specially during the
warmest month of the year.
The average annual temperature in shinile town, located in somail region Ethiopia, is 27.620C
(81,720F) which is 5.39%higher than Ethiopia’s averages. The warmest months march with an
average high of 33.95. The coldest moth is January with an average low of 19.670C. (67.410F).
Rainfall
The rainfall of shinile town receives an average of 557mm (21.7inches) of rainfall per year.
The wettest month are august (113mm/4.4 in).and April (90mm/3.5in). the driest month are
January (18mm /0.7in) and December (5mm/0.2in ).the region experiences a long rain season
called the Gu from February to May and short rain season called the Deyr from October to
November . Most of the Somali region including shinile, lies below 1000m in elevation and is
comprised of semi-arid pastoral land with dense shrub land, bush, grass land and bare hills. So
in summary, shinile has avery hot, dry climate with bimodal rain fall pattern and vegetation
typical of semi-arid regions. The town experiences some of the warmest temperature in
Ethiopia.
Previously Togo-Wajale was found under Awberre woreda as part of Keble but now, one
among the newly established city council under Fafen Zone of Somali regional state. The town
lays the border between Ethiopia and Somaliland. The council is located 250Km from the port
of Barbara and 70Km from the capital city of Somali regional state. The council is totally
composed of thirteen Kebeles. Of which, six are main Kebeles and the rest seven are rural
Keble. The council is bounded with different neighbouring wheredas. In the Northern part
bordering with Somaliland, in the Eastern, southern, and western part bordering with Awberre.
The council has three main roads one connected with asphalt road to Jigjiga which is
constructed by Federal Government for the purpose of dry port; the other is road to Somaliland
on northern part which is connected with Barbara port and road to Awberre which is junction
from Jigjiga road. In addition, the latitudinal and longitudinal GPS coordinate location of Togo-
Wajale town is 1061504 North and 316816.6 East with an elevation of 1563m a.m.s.l.
The Togo-Wajale characterized by a rolling topography of gentle hills and broad valleys along
which small cultivation is carried out. A chain of east-west aligned hills are prominent in this
area.The plain area is known by flat topography up to 1372m altitude and the mountain rises
dramatically to the chercher massif extension.
The catchment has an elevation that ranges from 1,870 meters in the northern Somali plateau
near Dire Dawa, falling to about 1372 meters above sea level along the southern limits towards
Somaliland border and receiving annual rainfall of 583mm on the upper catchment526mm on
the middle catchment and at the outlet 383mm.Typical average annual rainfall of the Ogaden
basin is 350 mm and less.
The main land use in Togo-Wajale city council is settlement, farming and mixed farming.
Previously the major types of land cover in the study area were shrub land but now clearing of
shrub land replacing with farm land, open bare land and grass land.Particularly the investigated
Togo-Wajale catchment (Part of Ogaden Basin) is characterized by small variation in
landscape. Considering the surrounding area as a whole, the Basin Slopes and Plain is dipping
less than 0.324%.
Appendix A Towns Information 428
13. Aleta wendo - Geography & Socio-Economic Background of the Project Area
Aleta Wendo (also known as Wendo) Aleta wondo which is part of the newly founded Sidama
Region is located in South Central Plateau at the approximate distance of 340 km for Capital
Addis Ababa city is a town in southern Ethiopia. Located in a fertile and forested area near
Lake Abaya in the upper Gidabo River basin, not far from the sources of the Ganale Dorya and
Dawa Rivers in the Aleta Wendo Zone of the Sidama Regional State, this town has a longitude
and latitude of 6°36′N 38°25′E with an elevation of 2037 meters above sea level. It is the
administrative center of Aleta Wendo woreda.
Climate
Aleta Wondo is characterized by highl,and weather condition with elevation rages from 1700-
2500masl The climate of the town is classified as a mid-land climate. It has a mean Annual
Temperature of 18ºC; Mean Annual Rainfall of 1201-1670mm. January and February are the
hottest months while July and August are the coldest months, Wendo, the wet season is
comfortable and overcast and the dry season is warm and partly cloudy. Over the course of the
year, the temperature typically varies from 52°F to 84°F and is rarely below 48°F or above
88°F.Based on the tourism score, the best time of year to visit Wendo for warm-weather
activities is from early November to early March.
Yirgalem (Amharic: ይርጋለም, Yïrgaläm) locally known as Diko Dalle [1] alternate names
include Yirgalem, Abosto, Dalle) is a town in southern Ethiopia. Surrounded by Lakes Woyima
and Gidawo, it is located 260 kilometers south of Addis Ababa and 40 kilometers south of
Awasa in the Sidama Zone of the Sidama Region. The town has a latitude and longitude of
6°45′N 38°25′E and an elevation of 1776 meters. It is the largest settlement in Dale woreda.
Climate
In Yirga ‘Alem, the wet season is overcast, the dry season is partly cloudy, and it is warm year
round. Over the course of the year, the temperature typically varies from 54°F to 86°F and is
rarely below 49°F or above 91°F.
Location
Sawula towns are found 525km from Addis Ababa. Astronomically, the town Administration
is located at 6° 17' 59" N and 36° 52' 48" E longitudes. Relative geographical location:- The
new Sawla Town plan boundary is fully included the former Sawla town and partially Gurade,
Suka, Turga,Yalla,Sezega,Tsila-Tsimba kebeles. Generally, Sawla town is administrative
centre of Gofa Zone and also serve as a centre for Demba_Gofa wereda and its relative position
makes it an important administrative, commercial and transportation and educational centre for
the Gofa zone wereda and there are four major entrance and out let namely Dema-Gofa, Geze-
Gofa, Zala wereda,Oyida wereda.
Climate
From topographical point of views, the general elevation of the Sawula town Administration
is ranges between 1250m, above sea level. In the south east 1570m above sea level in the North
West the average elevation is about 1410m, above sea level. When we see the landform of the
City Administration it is surrounded by mountain ranges in the North West and steep slope and
plain surface in the south and south east. The steepness of the land severely exposes the land
to be affected by flood. Climatically, the City Administration is classified in to kola/tropical
zone. As a result the annual temperature of the City Administration lies between 23.5c° and
15.4c° whereas the mean annual rainfall is 1309 mm which is orthographic in its type.
Appendix A Towns Information 431
Temperature
The Meteorological data of the past ten years indicate that the mean annual maximum
temperature is 37oc and the mean annual minimum temperature is 25oc. The mean annual
temperature of Sawula Town for the last ten years it has 30. oc. The city located at relatively
lower elevation which surrounded by mountain.As a result, the town enjoys Kolla type of
climate. The temperatures are generally high in little variations among seasons. The climate
of the town has Kolla type of climate in order to make conducive environment for living and
work area by the plan sufficient area for greenery and parks has to be allocate by the plan.
The Sawula Town is found between 600 – 3489 meter above sea level amazing landforms of
mountains, valleys, cliff, undulated, rugged and some parts of the area are flat topography. The
1000 m altitude above sea level is mostly taken as the boundary between highland and
lowlands. The geomorphology of the area is highly variable and it is generally the result of
repeated volcanic and tectonic events and it has an overall tilted towards east direction.
Soil Type
Soil or geomorphologic map for the overall catchment area lying within 0-50 km stretch (Lot
I) produced from 1,000,000 scaled Geomorphologic map of Ethiopia using GIS software
(Arcview).Dysntric Cambisols and Orthicacrisols are the major soil types covering the
catchment area under hydrologic soil grouping.
Figure Bnga`location
Bonga is a town, woreda and one of the multicapital of the South West Ethiopia Peoples'
Region in Ethiopia. Located in the Keffa Zone upon a hill in the upper Barta valley, it has a
latitude and longitude of 7°16′N 36°14′E with an elevation of 1,714 meters above sea level.
Not confused with another town named "Bonga", near Gambela Region.
Climate
Bonga has a tropical monsoon climate (Köppen Am) with a short dry season in December and
January and a lengthy though not intense wet season covering the remainder of the year.
Although afternoons are very warm to hot throughout the year, mornings are cool enough to
be close to a subtropical highland climate (Cwb).
Tepi (also transliterated Teppi and Tippi) is a town in southern Ethiopia. The vowels in the
name are pronounced as in the English words tape and pea. Located in the Sheka Zone of the
South West Ethiopia Region, this town has a latitude and longitude of 7°12′N 35°27′E with a
mean elevation of 1,097 meters above sea level. The town is said to be named after a Majangir
man who once had a bee hive in the large tree that stood in the marketplace
Located at an elevation of 1206.91 meters (3959.68 feet) above sea level, Tepi has a Tropical
wet and dry or savanna climate (Classification: Aw). The district's yearly temperature is
21.49ºC (70.68ºF) and it is -0.74% lower than Ethiopia's averages.