CY21 ROKFC IN-KIND A20R210P2, UNACCOMPANIED ENLISTED
PERSONNEL HOUSING (UEPH 100B), USAG HUMPHREYS, KOREA
SECTION TABLE OF CONTENTS
DIVISION 33 - UTILITIES
SECTION 33 61 13.13
PREFABRICATED UNDERGROUND HYDRONIC ENERGY DISTRIBUTION
PART 1 GENERAL
1.1 SUMMARY
1.2 REFERENCES
1.3 SUBMITTALS
1.4 QUALITY ASSURANCE
1.5 DELIVERY, STORAGE, AND HANDLING
PART 2 PRODUCTS
2.1 STANDARD PRODUCTS
2.2 PIPING AND CASING MATERIALS
2.2.1 General
2.2.2 Piping
2.2.2.1 Steel Pipe
2.2.2.2 Copper Tubing
2.2.2.3 Reinforced Thermosetting Resin Pipe (RTRP)
2.2.2.4 Polyvinyl Chloride (PVC) Pipe
2.2.2.5 Joints and Fittings for Copper Tubing
2.2.3 Casings
2.2.3.1 Polyvinyl Chloride (PVC) Casing
2.2.3.2 Polyethylene (PE) Casing
2.2.3.3 Reinforced Thermosetting Resin Pipe (RTRP) Casing
2.3 PIPING CONNECTIONS
2.3.1 Steel Pipe
2.3.2 Copper Pipe
2.4 END SEALS
2.4.1 Types
2.4.2 Casing and End Seal Testing and Certification
2.5 INSULATION
2.5.1 Factory Applied Insulation
2.5.2 Field Applied Insulation
2.6 CONCRETE VALVE MANHOLES
2.7 PIPING AND EQUIPMENT IN VALVE MANHOLES
PART 3 EXECUTION
3.1 EXAMINATION
3.2 INSTALLATION
3.3 PIPING SYSTEMS
3.3.1 Buried Insulated Systems
3.3.2 Buried Un-insulated Systems
3.4 VALVE MANHOLES AND PIPING EQUIPMENT IN VALVE MANHOLES
3.5 THRUST BLOCKS
3.6 INSTALLATION OF PIPING SYSTEMS
3.6.1 Pitching of Horizontal Piping
SECTION 33 61 13.13 Page 1
CY21 ROKFC IN-KIND A20R210P2, UNACCOMPANIED ENLISTED
PERSONNEL HOUSING (UEPH 100B), USAG HUMPHREYS, KOREA
3.6.2 Open Ends
3.6.3 Cutting Prefabricated Piping Sections
3.6.4 Joints
3.6.4.1 Welded Joints
3.6.4.2 Threaded Joints
3.6.4.3 Grooved Mechanical Joints
3.6.4.4 Brazed Joints
3.6.4.5 Nonmetallic Pipe Joints
3.6.5 Anchors
3.6.6 Field Casing Closures
3.6.7 Underground Warning Tape
3.6.8 Markers for Underground Piping
3.7 EARTHWORK
3.8 TESTING
3.8.1 Metallic Pipe Welds
3.8.2 Carrier Pipe Cleaning and Testing
3.8.2.1 Cleaning Carrier Pipe
3.8.2.2 Hydrostatic Pressure Cycling and Tests
3.8.2.3 Operational Test
3.8.2.4 Final Hydrostatic Test
-- End of Section Table of Contents --
SECTION 33 61 13.13 Page 2
CY21 ROKFC IN-KIND A20R210P2, UNACCOMPANIED ENLISTED
PERSONNEL HOUSING (UEPH 100B), USAG HUMPHREYS, KOREA
SECTION 33 61 13.13
PREFABRICATED UNDERGROUND HYDRONIC ENERGY DISTRIBUTION
PART 1 GENERAL
1.1 SUMMARY
The system consists of a buried prefabricated chilled water distribution
system including service connections to a point inside of the building.
The contract drawings show the specific arrangement of piping, sizes and
grades of pipe, and other details.
1.2 REFERENCES
The publications listed below form a part of this specification to the
extent referenced. The publications are referred to within the text by the
basic designation only.
AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)
ASME B1.20.2M (2006; R 2011) Pipe Threads, 60 Deg.
General Purpose (Metric)
ASME B16.9 (2018) Factory-Made Wrought Buttwelding
Fittings
ASME B16.11 (2016) Forged Fittings, Socket-Welding and
Threaded
ASME B16.18 (2018) Cast Copper Alloy Solder Joint
Pressure Fittings
ASME B16.22 (2018) Standard for Wrought Copper and
Copper Alloy Solder Joint Pressure Fittings
ASME B16.26 (2018) Standard for Cast Copper Alloy
Fittings for Flared Copper Tubes
ASME B31.1 (2018) Power Piping
ASME BPVC SEC IX (2017; Errata 2018) BPVC Section
IX-Welding, Brazing and Fusing
Qualifications
AMERICAN WATER WORKS ASSOCIATION (AWWA)
AWWA C606 (2015) Grooved and Shouldered Joints
AMERICAN WELDING SOCIETY (AWS)
AWS B2.2/B2.2M (2016) Specification for Brazing Procedure
and Performance Qualification
SECTION 33 61 13.13 Page 3
CY21 ROKFC IN-KIND A20R210P2, UNACCOMPANIED ENLISTED
PERSONNEL HOUSING (UEPH 100B), USAG HUMPHREYS, KOREA
ASTM INTERNATIONAL (ASTM)
ASTM A53/A53M (2018) Standard Specification for Pipe,
Steel, Black and Hot-Dipped, Zinc-Coated,
Welded and Seamless
ASTM A105/A105M (2018) Standard Specification for Carbon
Steel Forgings for Piping Applications
ASTM A106/A106M (2019a) Standard Specification for
Seamless Carbon Steel Pipe for
High-Temperature Service
ASTM A183 (2014; R 2020) Standard Specification for
Carbon Steel Track Bolts and Nuts
ASTM A234/A234M (2019) Standard Specification for Piping
Fittings of Wrought Carbon Steel and Alloy
Steel for Moderate and High Temperature
Service
ASTM A536 (1984; R 2019; E 2019) Standard
Specification for Ductile Iron Castings
ASTM B62 (2017) Standard Specification for
Composition Bronze or Ounce Metal Castings
ASTM B75/B75M (2020) Standard Specification for Seamless
Copper Tube
ASTM B88M (2020) Standard Specification for Seamless
Copper Water Tube (Metric)
ASTM C518 (2017) Standard Test Method for
Steady-State Thermal Transmission
Properties by Means of the Heat Flow Meter
Apparatus
ASTM C591 (2019a) Standard Specification for Unfaced
Preformed Rigid Cellular Polyisocyanurate
Thermal Insulation
ASTM D1784 (2020) Standard Specification for Rigid
Poly(Vinyl Chloride) (PVC) Compounds and
Chlorinated Poly(Vinyl Chloride) (CPVC)
Compounds
ASTM D2000 (2018) Standard Classification System for
Rubber Products in Automotive Applications
ASTM D2241 (2015) Standard Specification for
Poly(Vinyl Chloride) (PVC) Pressure-Rated
Pipe (SDR Series)
ASTM D2996 (2017) Standard Specification for
Filament-Wound "Fiberglass"
(Glass-Fiber-Reinforced
Thermosetting-Resin) Pipe
SECTION 33 61 13.13 Page 4
CY21 ROKFC IN-KIND A20R210P2, UNACCOMPANIED ENLISTED
PERSONNEL HOUSING (UEPH 100B), USAG HUMPHREYS, KOREA
ASTM D2997 (2015) Centrifugally Cast "Fiberglass"
(Glass-Fiber-Reinforced
Thermosetting-Resin) Pipe
ASTM D3350 (2012) Polyethylene Plastics Pipe and
Fittings Materials
COPPER DEVELOPMENT ASSOCIATION (CDA)
CDA A4015 (2016; 14/17) Copper Tube Handbook
KOREAN INDUSTRIAL STANDARDS (KS)
KS B 0222 (2007; R 2017) Taper Pipe Threads
KS B 1543 (2017) Steel Butt-Welding Pipe Fittings
KS B 1544 (2015) Copper Alloy Solder-Joint Fittings
KS D 3562 (2019) Carbon Steel Pipes for Pressure
Service
KS D 5301 (2009; R 2019) Copper and Copper Alloy
Seamless Pipes and Tubes
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When
used, a designation following the "G" designation identifies the office
that will review the submittal for the Government. Submit the following in
accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-03 Product Data
Markers For Underground Piping
SD-07 Certificates
Welding
1.4 QUALITY ASSURANCE
Weld piping in accordance with qualified procedures using performance
qualified welders and welding operators. Qualify procedures and welders in
accordance with ASME BPVC SEC IX. Welding procedures qualified by others,
and welders and welding operators qualified by another employer may be
accepted as permitted by ASME B31.1. Prior to welding operations, submit a
copy of qualified procedures and a list of names and identification symbols
of qualified welders and welding operators. Notify the Contracting Officer
24 hours in advance of tests performed at the work site, if practicable.
Apply welder's personal assigned symbol near each weld made as a permanent
record. Weld structural members in accordance with Section 05 05 23.16
STRUCTURAL WELDING.
1.5 DELIVERY, STORAGE, AND HANDLING
After delivery to the jobsite, protect all materials and equipment from
anything which could cause damage to the material or equipment. Seal
SECTION 33 61 13.13 Page 5
CY21 ROKFC IN-KIND A20R210P2, UNACCOMPANIED ENLISTED
PERSONNEL HOUSING (UEPH 100B), USAG HUMPHREYS, KOREA
piping at each end to keep the interior clean and free of dirt and debris.
Keep fittings together and keep their interior surfaces clean at all
times. Keep insulation dry and clean.
PART 2 PRODUCTS
2.1 STANDARD PRODUCTS
Provide system components which are standard products of a manufacturer
regularly engaged in the manufacture of the product and that essentially
duplicate items that have been in satisfactory use for at least 2 years
prior to bid opening. Provide a service organization that is, in the
opinion of the Contracting Officer, convenient to the site.
2.2 PIPING AND CASING MATERIALS
2.2.1 General
Provide metallic pressure pipe, fittings, and piping accessories that
conform to the requirements of ASME B31.1 and are types suitable for the
temperature and pressure of the water.
2.2.2 Piping
2.2.2.1 Steel Pipe
Provide piping conforming to ASTM A53/A53M, Grade B, standard weight, black
or KS D 3562, Schedule 40 or to ASTM A106/A106M, Grade B, standard weight.
2.2.2.2 Copper Tubing
Provide tubing conforming to ASTM B88M, Type K or L or KS D 5301.
2.2.2.3 Reinforced Thermosetting Resin Pipe (RTRP)
Provide RTRP conforming to ASTM D2996 or ASTM D2997.
2.2.2.4 Polyvinyl Chloride (PVC) Pipe
Provide PVC piping conforming to ASTM D2241 with a Standard Thermoplastic
Pipe Dimension Ratio (SDR) of 26 and PVC 1120 or 1220 as the material.
2.2.2.5 Joints and Fittings for Copper Tubing
Provide wrought copper and bronze solder-joint pressure fittings that
conform to ASME B16.22 and ASTM B75/B75M or KS B 1544. Provide cast copper
alloy solder-joint pressure fittings conforming to ASME B16.18 or KS B 1544.
Provide cast copper alloy fittings for flared copper tube conforming to
ASME B16.26 and ASTM B62. Brass or bronze adapters for brazed tubing may
be used for connecting tubing to flanges and to threaded ends of valves and
equipment. Extracted brazed tee joints produced with an acceptable tool
and installed as recommended by the manufacturer may be used. Design
grooved mechanical joints and fittings for not less than 862 kPa service.
Provide grooved mechanical joints and fittings that are the product of the
same manufacturer. Provide grooved fitting and mechanical coupling housing
of ductile iron conforming to ASTM A536, with molded synthetic polymer of
pressure responsive design conforming to ASTM D2000 for circulating medium
up to 110 degrees C and grooved joints conforming to AWWA C606. Provide
steel nuts and bolts conforming to ASTM A183 for coupling for use in
SECTION 33 61 13.13 Page 6
CY21 ROKFC IN-KIND A20R210P2, UNACCOMPANIED ENLISTED
PERSONNEL HOUSING (UEPH 100B), USAG HUMPHREYS, KOREA
grooved joints.
2.2.3 Casings
2.2.3.1 Polyvinyl Chloride (PVC) Casing
Provide PVC casings that conform to ASTM D1784, Class 12454-B with a
minimum thickness equal to the greater of 1/100 the diameter of the casing
or 1.50 mm.
2.2.3.2 Polyethylene (PE) Casing
Provide polyethylene casings conforming to ASTM D3350, Type III, Class C,
Category 3 or 4, Grade P 34 with thickness as follows:
Casing Diameter (mm) Minimum Thickness (mm)
250 and smaller 3
250 to 450 4
450 through 600 5
over 600 6
2.2.3.3 Reinforced Thermosetting Resin Pipe (RTRP) Casing
Provide RTRP casing of the same material as the pipe, with casing thickness
as follows:
Casing Diameter (mm) Minimum Thickness (mm)
200 and smaller 1.2
250 2
300 2.7
350 2.9
400 to 450 3
500 3.2
600 3.9
2.3 PIPING CONNECTIONS
2.3.1 Steel Pipe
For pipe smaller than 19 mm, provide Schedule 80 steel pipe with threaded
end connections conforming to ASME B1.20.2M or KS B 0222. Weld all steel
pipe 19 mm and larger. Provide steel welding fittings conforming to the
requirements of ASTM A105/A105M or ASTM A234/A234M. Provide welding
fittings conforming to ASME B16.9 or KS B 1543 for buttweld fittings and
ASME B16.11 for socket-weld fittings. Use long radius buttwelding elbows
SECTION 33 61 13.13 Page 7
CY21 ROKFC IN-KIND A20R210P2, UNACCOMPANIED ENLISTED
PERSONNEL HOUSING (UEPH 100B), USAG HUMPHREYS, KOREA
conforming to ASME B16.9 or KS B 1543 whenever space permits.
2.3.2 Copper Pipe
Braze or provide insulated pipe couplings for copper pipe connections with
wrought copper or cast copper alloy solder joint pressure fittings
conforming to AWS B2.2/B2.2M and CDA A4015. Provide cast bronze containing
an O-ring seal on each end, jacketed and sealed, to act as an expansion
joint for insulated pipe couplings for copper pipe.
2.4 END SEALS
Provide pre-insulated sections of pipe with complete sealing of the
insulation to provide a permanent water and vapor seal at each end of the
pre-insulated section of piping. Provide field modified pre-insulated
sections of piping with an end seal which is equivalent to the end seals
furnished with the pre-insulated section of piping. Test and certify end
seals in accordance with paragraph Casing and End Seal Testing and
Certification.
2.4.1 Types
Provide end seals of one of the following types:
a. Carrying the outer casing over tapered pipe insulation ends and
extending it to the carrier pipe. Provide sufficient surface bonding
area between the casing and the carrier pipe.
b. Using specially designed molded caps made of polyethylene or rubber of
standard manufactured thickness. Provide a minimum of 40 mm surface
bonding area between the cap and both the casing and carrier pipe.
c. Using elastomeric-ring end seals designed and dimensioned to fit in the
annular space between the casing and the carrier pipe.
d. Using a waterproof mastic seal vapor barrier over the exposed
insulation ends.
e. Shrink sleeves.
2.4.2 Casing and End Seal Testing and Certification
Demonstrate that testing and certification procedures by an independent
testing laboratory, for casings and end seals, are capable of resisting
penetration of water into the casing and insulation. Perform the test on
each type of prefabricated system to be furnished. Provide hot and cold
cycle testing followed by immersion in a water filled chamber with a head
pressure, consisting of 14 days of temperature cycling. Circulate a fluid
with a temperature of 5 degrees C through the carrier pipe alternating
every 24-hours with a fluid with a temperature of 95 degrees C circulating
through the carrier pipe for a low temperature hot water or dual
temperature service or 24 degrees C for a chilled water service. While the
hot and cold cycle test is being performed, the test sample is either
buried or encased in dry bedding sand with a minimum of 300 mm of sand all
around the test sample. Restrain the 80 mm diameter carrier pipe of the
test sample during the test period. Provide an insulation thickness not to
exceed the maximum thickness provided for the piping in the project. Do
not exceed transition times for temperature cycle testing of 15 minutes in
going from cold to hot and 30 minutes in going from hot to cold. The fluid
SECTION 33 61 13.13 Page 8
CY21 ROKFC IN-KIND A20R210P2, UNACCOMPANIED ENLISTED
PERSONNEL HOUSING (UEPH 100B), USAG HUMPHREYS, KOREA
in the carrier pipe may be water, oil or heat transfer fluid. Immerse the
test sample in a water filled chamber following the hot and cold cycling
test. Provide a pressure of not less than 60 kPa at the highest point over
the entire length of the 2.4 m test sample for a minimum of the 48 hour
test period. Provide water containing a dye penetrant to check for end
seal leakage. Upon completion of the pressure test, cut the test sample
open using a light that will readily show the presence of the dye that was
in the water, inspect the test sample. Evidence of the dye inside the test
sample indicates that the end seal is not acceptable and cannot be
certified.
2.5 INSULATION
2.5.1 Factory Applied Insulation
Provide factory insulated pre-fabricated pipe and fittings with
polyurethane (polyisocyanurate) foam meeting the requirements of ASTM C591
having a density not less than 32 kg per cubic meter. Provide the
polyurethane (polyisocyanurate) foam completely filling the annular space
between the carrier pipe and the casing with an insulation thickness of a
minimum of 20 mm. Provide an insulation thermal conductivity factor not
exceeding the numerical value of 0.02 W/mK at 24 degrees C, when tested in
accordance with ASTM C518. Provide a manufacturer's certification that the
insulated pipe is free of insulation voids.
2.5.2 Field Applied Insulation
Provide polyurethane (polyisocyanurate) field applied insulation for
fittings, and field casing closures and other piping system accessories, as
required, with thickness matching adjacent piping insulation thickness.
For buried fittings and accessories, provide field applied polyurethane
(polyisocyanurate) insulation to match adjacent piping with a protective
covering matching the pipe casing. Provide shrink sleeves with a minimum
thickness of 1.3 mm over casing connection joints.
2.6 CONCRETE VALVE MANHOLES
Provide concrete valve manholes in accordance with Section 33 61 13.19
VALVES, PIPING AND EQUIPMENT IN VALVE MANHOLES.
2.7 PIPING AND EQUIPMENT IN VALVE MANHOLES
Provide piping and equipment in valve manholes in accordance with Section
33 61 13.19 VALVES, PIPING, AND EQUIPMENT IN VALVE MANHOLES.
PART 3 EXECUTION
3.1 EXAMINATION
After becoming familiar with all details of the project, verify all
dimensions in the field and advise the Contracting Officer of any
discrepancy before performing the project.
3.2 INSTALLATION
For all pre-insulated, prefabricated systems, obtain the services of a
trained representative of the pipe system manufacturer to instruct the
Contractor's work forces in the installation procedures to ensure that the
system is installed in accordance with the manufacturer's published
SECTION 33 61 13.13 Page 9
CY21 ROKFC IN-KIND A20R210P2, UNACCOMPANIED ENLISTED
PERSONNEL HOUSING (UEPH 100B), USAG HUMPHREYS, KOREA
instructions and the plans and specifications. Provide a manufacturer's
representative who regularly performs such duties for the manufacturer.
Furnish the Contracting Officer a list of names of personnel trained and
certified by the pipe system manufacturer in the installation of this
system. Only personnel whose names appear on a less than one year old list
will be allowed to install the system.
3.3 PIPING SYSTEMS
3.3.1 Buried Insulated Systems
Provide carrier pipe, insulation, casing, end seals, fittings and
accessories for buried insulated systems.
3.3.2 Buried Un-insulated Systems
Provide carrier pipe, fittings and accessories for buried un-insulated
systems.
3.4 VALVE MANHOLES AND PIPING EQUIPMENT IN VALVE MANHOLES
Install valve manholes and piping and equipment in valve manholes in
accordance with Section 33 61 13.19 VALVES, PIPING, AND EQUIPMENT IN VALVE
MANHOLES.
3.5 THRUST BLOCKS
Install thrust blocks at the locations shown or recommended by the pipe
system manufacturer. Provide thrust blocks in accordance with
manufacturer's recommendations. For systems requiring thrust blocks, at a
minimum, provide thrust blocks at all changes in direction, changes in
size, valves and terminal ends, such as plugs, caps and tees with concrete
having a compressive strength of not less than 14 MPa after 28 days in
accordance with Section 03 30 00 CAST-IN-PLACE CONCRETE. Place thrust
blocks between solid ground and the fitting to be anchored. Unless
otherwise indicated or directed, pour the base and the thrust bearing sides
of the thrust blocks directly against undisturbed earth. The sides of the
thrust blocks not subject to thrust may be poured against forms. Locate
thrust blocks so that the joints for all fittings will be accessible for
repair wherever possible. Do not embed joints in concrete unless the
assembly has previously been hydrostatically tested. Provide thrust
blocks resisted by piles or tie rods to solid foundations in muck or peat,
or replace peat or muck with ballast of sufficient stability to resist the
thrust blocks.
3.6 INSTALLATION OF PIPING SYSTEMS
Prepare pipe ends to match factory coated ends and install the piping
system in accordance with the manufacturer's instructions without springing
or forcing other than what has been calculated for cold spring allowing
free expansion and contraction without damage to joints or hangers. Do not
install copper tubing in a trench with ferrous piping materials. Maintain
a minimum vertical separation of 300 mm between pipes when nonferrous
metallic pipe (e.g., copper tubing) crosses any ferrous piping material.
Provide transition fittings approved by the manufacturer of the piping
system for connections between different types of pipe and system
components.
SECTION 33 61 13.13 Page 10
CY21 ROKFC IN-KIND A20R210P2, UNACCOMPANIED ENLISTED
PERSONNEL HOUSING (UEPH 100B), USAG HUMPHREYS, KOREA
3.6.1 Pitching of Horizontal Piping
Pitch horizontal pipe at a grade of not less than 40 mm in 1 m toward the
drain points unless otherwise indicated.
3.6.2 Open Ends
Provide an approved cap or plug for open ends of pipelines and equipment
during installation.
3.6.3 Cutting Prefabricated Piping Sections
Provide new end seals similar to factory applied end seal for field cut
prefabricated pipe sections in accordance with the manufacturer's
instructions.
3.6.4 Joints
3.6.4.1 Welded Joints
Provide welded joints between sections of pipe and between pipe and
fittings where specified or indicated.
3.6.4.2 Threaded Joints
No threaded joints are allowed to be used belowground. Make joints tight
with polytetrafluoroethylene tape applied to the male threads only with no
more than 3 threads showing after the joint is made up.
3.6.4.3 Grooved Mechanical Joints
Provide grooved fittings, couplings, and grooving tools with products of
the same manufacturer. Prepare grooves complying with the tolerances
specified by the coupling manufacturer in accordance with the coupling
manufacturer's instructions. Measure field made groove diameters using a
"go/no-go" gauge, vernier or dial caliper, narrow-land micrometer, or other
method specifically approved by the coupling manufacturer for the intended
application. Measure and record each groove width and dimension from end
of pipe for each change in grooving tool setup to verify compliance with
coupling manufacturer's tolerances. Grooved joints are not allowed in
concealed locations.
3.6.4.4 Brazed Joints
Brazed joints for copper pipe and fittings must conform to CDA A4015.
Utilize brazing alloys melting above 593.3 degrees C.
3.6.4.5 Nonmetallic Pipe Joints
Install nonmetallic pipe joints in accordance with the written instructions
of the manufacturer.
3.6.5 Anchors
Provide factory fabricated, by the prefabricated system manufacturer,
anchor design in accordance with the published data of the manufacturer and
for prefabricated systems. Prevent water penetration, condensation, or
vapor transmission from wetting/contacting the insulation.
SECTION 33 61 13.13 Page 11
CY21 ROKFC IN-KIND A20R210P2, UNACCOMPANIED ENLISTED
PERSONNEL HOUSING (UEPH 100B), USAG HUMPHREYS, KOREA
3.6.6 Field Casing Closures
Execution of field insulation and encasement of joints are to be
accomplished after the visual and pressure tests specified are completed
and in accordance with the manufacturer's written instructions. Provide
foamed in place polyurethane insulation with thickness dimensions and
casing materials not less than those of the adjoining prefabricated
section. Install a standard polyethylene heat shrink sleeve with a 150 mm
minimum overlap at each end of the casing.
3.6.7 Underground Warning Tape
Provide underground 0.1 mm thick, 150 mm wide, printed with repetitive
caution warnings along its length, polyethylene tape with metallic core
warning tape buried above the piping during the trench backfilling
approximately 300 mm deep. Provide tapes, yellow in color with black
letters; color and lettering must not be affected by moisture or other
substances contained in the backfill material.
3.6.8 Markers for Underground Piping
Submit catalog cuts, brochures, circulars, specifications and product data,
and printed information in sufficient detail and scope to verify compliance
with the requirements of the contract documents. Place markers for
underground piping approximately 600 mm to the right of the distribution
system in reference to the fluid flow direction.
Provide concrete markers 150 mm square or round section 600 mm long with
the top edge of the marker chamfered at a minimum of 13 mm all around.
Impress of cast letters on the top of the marker with letters CHW to
indicate the type of system that is being identified. Form each letter
with a V-shaped groove with a width of stroke at least 6 mm at the top and
depth of 6 mm. Provide elevation of markers no more than 25 mm above
finished grade.
3.7 EARTHWORK
Perform earthwork in accordance with Section 31 00 00 EARTHWORK.
3.8 TESTING
Conduct tests before, during, and after installation of the system.
Provide all instruments, equipment, facilities, and labor required to
properly conduct the tests. Provide test pressure gauges for a specific
test with dials indicating not less than 1.5 times nor more than 2 times
the test pressure.
3.8.1 Metallic Pipe Welds
Perform radiographic testing in accordance with ASME B31.1. Perform
radiographic examination of field welds by an approved independent testing
firm or firms regularly engaged in radiographic testing, and interpreted by
a Certified Level III Radiographer employed by the testing firm. Review
and interpretation of all radiographs must be by a Certified Level III
Radiographer employed by the testing firm. Remove, reweld and
radiographically examine any welds found to be unacceptable in accordance
with the above criteria.
SECTION 33 61 13.13 Page 12
CY21 ROKFC IN-KIND A20R210P2, UNACCOMPANIED ENLISTED
PERSONNEL HOUSING (UEPH 100B), USAG HUMPHREYS, KOREA
3.8.2 Carrier Pipe Cleaning and Testing
Test distribution piping as required before backfilling, with all joints
exposed. The area between joints may be backfilled as necessary to prevent
pipe movement.
3.8.2.1 Cleaning Carrier Pipe
Prior to testing, clean the interior of the carrier pipe of foreign
materials by thorough flushing with clean water with a circulating water
velocity between 2 and 3 m/s (7 and 10 feet per second) for a minimum of 4
hours. Provide temporary and/or supplementary pumps if required to ensure
that required velocity is achieved. Clean system strainers after the
flushing operation is complete. Temporary strainers must be installed as
required. Leave water in the system after flushing for testing of the
system to ensure the pipe will maintain pressure and is not leaking.
3.8.2.2 Hydrostatic Pressure Cycling and Tests
Hydrostatic pressure tests consist of 4 cycles; .each cycle consisting of a
10 minute period with the first cycle at 1000 kPa followed by a 5 minute
period at a pressure less than 350 kPa. Begin the next cycle immediately
following the completion of the previous cycle with the pressure rise and
drop no more than 690 kPa per minute. Locate the pressure gauge and take
the pressure measurement at the opposite end of the system from where the
pressure is applied. After completion of the hydrostatic pressure cycling,
perform the first hydrostatic pressure test proving the system tight at a
pressure of 1.5 times the working pressure up to 1000 kPa and held for a
minimum of 1 hour. Disconnect the pressurizing apparatus from the system
before starting the 1 hour pressure holding period. Correct any test
failures and repeat the hydrostatic pressure cycling and first hydrostatic
pressure test until the system can hold the required pressure for at least
1 hour. After successful completion of the first hydrostatic pressure
test, drain piping system and fill the piping system as defined in
paragraph TREATED WATER for the remaining tests and for permanent operation
of the system. Repeat the hydrostatic pressure cycling and tests for the
system after the system has been filled with treated water, using the same
test conditions and criteria.
3.8.2.3 Operational Test
Perform operational test on the complete system or testable portions
thereof and conduct with full design flows and operating temperatures in
all runs of piping as if in service, to demonstrate satisfactory function
and operating effectiveness. The operational test will have two cycles.
Each cycle must consist of a 6-hour period with treated water in the system
at the maximum operating temperature of 7.2 degrees C and maximum flow
rate, and a period of at least 6-hours with no flow. Supply temporary
pumps, piping connections, chillers and the gauges required to circulate
the water at the desired temperatures and flow rates. Re-circulate water
through supply lines and return through the return piping to demonstrate
that the pressure drop is compatible with the flow rate and size of pipe
and to show that obstructions do not exist in the piping system. Any
unusual indicated pressure drop will be investigated and any obstructions
removed. Repair any leaks found. After any obstructions have been removed
and any leaks repaired, repeat the operational test until successfully
passed.
SECTION 33 61 13.13 Page 13
CY21 ROKFC IN-KIND A20R210P2, UNACCOMPANIED ENLISTED
PERSONNEL HOUSING (UEPH 100B), USAG HUMPHREYS, KOREA
3.8.2.4 Final Hydrostatic Test
After successful completion of the operational test, pressurize system to
1.5 times the working pressure up to 1000 kPa and hold for a minimum of 4
hours. Disconnect pressurizing apparatus prior to the start of the 4-hour
pressure holding period. Upon test failure, determine the cause of the
failure, correct and repeat all of the hydrostatic pressure cycling and
pressure tests.
-- End of Section --
SECTION 33 61 13.13 Page 14