Braemar TH3 TH4 TH5 Gas Ducted Heater Installation Manual
Braemar TH3 TH4 TH5 Gas Ducted Heater Installation Manual
This Braemar gas ducted heater must be installed in accordance with these instructions, local gas fitting regulations, municipal
building codes, electrical wiring regulations, Australian Standard AS/NZS 5601 Gas Installations and any other relevant statutory
requirements.
This heater must not be installed downstream from an evaporative cooler, air washer or indoor unit of a refrigerated system. This
heater is not suitable for installation in a marine environment.
For external installations, ensure that the heater is located to maintain the minimum flue clearances as specified below and in
AS/NZS 5601. Measurement is taken from the edges of the flue terminal.
SAFETY INSTRUCTIONS
Employers and Employees Responsibility Some points to consider
The installation and maintenance of gas ducted heating units, Some points to consider when working on or in a roof
particularly at height, has the potential to create Occupational What is the best and safest access to the roof and working
Health and Safety issues for those involved. Installers are areas?
advised to ensure they are familiar with relevant State and What condition is the roof in? Should the roof structure and
Federal legislation, such as Acts, Regulations, approved Codes surface be checked?
of Practice and Australian Standards, which offer practical Does the worker have appropriate footwear?
guidance on these health and safety issues. Compliance with Are all power cables/extension leads safe and appropriately
these regulations will require appropriate work practices, rated?
equipment, training and qualification of workers. Seeley Are all ladders, tools and equipment suitable and in good
International provides the following information condition?
as a guide to contractors and employees to assist in minimising Where ladders are to be used, is there a firm, stable base for
risk. them to stand on? Can they be tied or secured in some
way at the top?
Risk Assessment Is there a roof anchor to attach a harness and lanyard to? If
A risk assessment of all hazardous tasks is required under so, instruction should be issued for the use of an approved
legislation. A risk assessment is an essential element that should harness or only suitably trained people used.
be conducted before the commencement of work, to identify and Are all tools and materials being used, prevented from slipping
eliminate the risk of falls and other risks, or to minimise these and falling onto a person at ground level? Is the area below
risks by implementing control measures. This does not need to the work area suitably protected to prevent people entering
be a complicated process - it is a matter of assessing the job to this area?
be done and considering what actions are necessary so the Does the work schedule take into account weather conditions,
person doing the job does not injure themselves. allowing for work to be suspended in high winds, thunder
storms/lightning or other types of weather giving wet, slippery
This should be considered in terms of: surfaces?
What are the chances of an incident occurring?
Is there an on-going safety check system of harnesses, ropes,
What could the possible consequences be?
ladders and access/lifting equipment, and any anchor points
What can be done to reduce, or better still, eliminate
on roofs before the commencement of work?
the risk? Is there a system which prevents employees from working on
or in roofs if they are unwell or under the influence of drugs or
alcohol?
Are there any special conditions to consider i.e. excessive roof
pitch, limited ground area, fragile roof,electrical power lines?
HEATER LOCATION
All TH series heaters can be split in two (remove fan box) to assist HOSE END OF HEATER
in lifting heaters into ceilings and moving the heater into position: HEAT EXCHANGER
END OF HEATER
centre panel.
END OF HEATER
Remove the two retaining screws near the top of the centre panels
from the room fan end of the heater.
Lift the room fan end of the heater to disengage from the locating HEAT EXCHANGER
1. Remove side panels from combustion fan end of heater. 1. Disconnect flue fan extension from combustion fan. Remove
flue outlet cover from opposite side of heater.
2. Twist combustion fan towards burners, lift fan up to separate 2. Twist combustion fan towards burners, lift fan up to seperate
from heater. from heater.
3. Turn combustion fan 180 degrees. locate fan feet in 4 round 3. Turn combustion fan 180 degrees. locate fan feet in 4 round
holes in flue pan twisting combustion fan towards burners to holes in flue pan twisting combustion fan towards burners to
lock. lock.
4. Fit side panels back to heater. 4. Reconnect flue fan extension using silicon to seal connection.
Secure flue outlet to side panel using screws previously
removed. Fit flue outlet cover to the original outlet hole.
TH Extra Air heaters are designed for use with an add-on refrigerated
cooling system - these models include an “X” in their model numbers,
eg, TH3X20, TH4X30 and TH5X32. The following points must be
Heater
taken into account to ensure correct operation of both the refrigerated
cooler and the heater.
ON/OFF
HOME/AWAY
Gas Connection
All Models
IMPORTANT
ENSURE THAT POLARITY OF
POWER SUPPLY IS CORRECT
Earth
Q
FLUE
M
Q
FLUE
M
CONNECTION
CONNECTION
ELECTRICAL P
ENTRY [1] ELECTRICAL P
ENTRY [1]
E
E
A A F
F
D D
B
B
GAS
C
C
GAS
ENTRY L L
J
L L ENTRY
J
K
Note 1: G
Note 1: G Alternative electrical entry
AIR OUTLET AIR INLET
Alternative electrical entry points can be AIR OUTLET AIR INLET points can be used - knockouts
6
KITS
Installation kits Miscellaneous kits
HEATER MODEL INSTALLATION THERMOSTAT KIT PART No KIT DESCRIPTION KIT PART No
Internal 075945 Spectrolink comfort control (SCC) and cable 077314
TH3/4 External Spectrolink (SCC) 075952 Side wall heat shield kit (TH3/4) 077420
Underfloor 077345 Flue guard kit 079073
Internal 077284 TH5 flashing kit - flush to wall 076010
TH3 External Manual Digital 077291 TH5 Small (TH516/TH523) flashing kit - 150mm 075990
Underfloor 077352
TH5 Small (TH516/TH523) flashing kit - 300mm 076034
TH5 Internal/Underfloor 075983
Spectrolink (SCC) TH5 Large (TH532) flashing kit - 150mm 077260
External 076041
TH5 Large (TH532) flashing kit - 300mm 077277
Notes:
- TH3 & TH4 installation kits are also suitable for TG3 & TG4 model heaters. TH3/4 - 15/20/25 kW - flashing kit - flush to wall 076898
- The Spectrolink Comfort Control thermostat is required to enable maximum
TH3/4 - 15/20/25 kW - flashing kit - 150mm 076331
heater functionality.
Zoning kits - 4 & 5 star heaters only TH3/4 - 15/20/25 kW - flashing kit - 300mm 076348
KIT DESCRIPTION KIT PART No TH3/4 - 30/35 kW - flashing kit - flush to wall 076898
24 Vac zone kit 077215 TH3/4 - 30/35 kW - flashing kit - 150mm 076362
240 Vac zone kit 077208 TH3/4 - 30/35 kW - flashing kit - 300mm 076386
Spectrolink comfort control thermostat (SCC) and cable 077314 TH5 plenum box kit (small units only 16/23 kW) 076287
Note:
- Zone dampers are not supplied by Seeley International and are not included in the
above zone kits.
Attach powder coated die cast flue terminal to heater over flue
Heater base
outlet, fixing in place using screws supplied.
Construct the heater base and prepare wall opening to the
dimensions shown in the table below. TH3/TH4 Heater flue outlet
ENSURE THAT THE BASE IS LEVEL IN BOTH DIRECTIONS.
Heater is approved for installation against a wall.
Refer to above kits tabel for flashing kit part numbers.
Dimension (mm)
Heater Model Concrete slab Wall opening
A B C D
TH3 and TH4 models
TH315, TH415 400 800 460 760
TH320, TH420 400 800 460 760 External flue terminal
TH325, TH425 400 800 460 760 POWDER-COATED DIE CAST VERSION
TH330, TH430 550 900 460 870
TH435 550 900 460 870 USED ON 3 AND 4 STAR HEATERS
TH3X20, TH4X20 400 800 460 760
TH3X25, TH4X25 400 800 460 760 Powder coated die cast flue terminal and starter collars are
TH3X30, TH4X30 550 900 460 870 included in external installation accessories kit.
TH5 models Larger starter collars (400mm) required for the X30,X32 & 35kW
TH516 400 1200 460 1160 units are supplied inside the heater fan inlet.
TH523 400 1200 460 1160 Old style stainless steel external flue terminal is available as an
TH532 550 1200 460 1160
option P/No 628967.
TH5X23 400 1200 460 1160
TH5X32 550 1200 460 1160 A flue guard kit is available for external installations. P/No 079073.
B
A
Plastic vent cowl.
5 STAR ONLY
Check that
upper transit Terminate
plug is secure condensate drain in
a suitable location
Remove &
discard lower
transit plug Condensate drain elbow
7 TH3, TH4, TH5
CEILING INSTALLATION
A
Permanent artificial lighting must be provided at the appliance See page 6. OF HEATER
HEATER
with the switch adjacent to the access opening.
Check that the section of the roof in which the heater is to be
installed is capable of supporting the additional load of the HEATER LOCATION
heater. Where possible, the heater should be mounted over a E
AVOID QUIET AREAS:
load-bearing wall so that it is not being supported by the ceiling - Above bedrooms, living room, E = 770, 880,1160
750 Min
joists alone. lounge room, dining room etc Depends on model - see
Check that the heater does not cause deformation of any part of PREFERRED LOCATIONS:
“Heater Dimensions” page
the building structure. - Above laundry, bathroom,
kitchen, garage etc’
Flue connection - TH3 & TH4 Ensure 200mm minimum clearance above heater
This heater must be flued using AGA approved 100 mm metal Service/maintenance platform - 19mm particle board or equivalent
flue pipe.
External joins - socket must face downwards. Internal joins - 100 mm flue cowl
socket must face upwards. TH3/TH4 500 mm to nearest
part of roof AGA approved
Socket joins must be adequately sealed - eg, Silastic 747 silicone
sealant. 100 mm flue pipe
Twin-wall metal flue must be used for any part of the flue that is 200 mm minimum Single or twin skin
not readily accessible. for servicing AGA approved
Twin-wall metal flue is recommended for flue exceeding 2m in
length.
Permanent Platform
Flue lengths: Flue bends: 19 mm particle board
- Maximum vertical: 4.8m - Maximum 2 x 90o elbows or equivalent 100 mm 90o
o
- Maximum horizontal: 4m - 2 x 45o bends = 1 x 90 elbow bend
- Maximum total: 6m Fire resistant base NOT REQUIRED
o
90 bend and starter collars are included in internal installation Fitting the flue
accessories kit. Fit flue socket Fit flue elbow Fit flue pipe
Larger starter collars (400mm) required for the X30,X32 & 35kW to heater inside socket inside socket
units are supplied inside the heater fan inlet. on heater on flue elbow
TH5 SEAL CONNECTIONS: Seal flue and condensate drain connections using silicone sealant or PVC primer and solvent cement.
INSULATE DRAIN LINE: Fit insulation (eg, Armaflex) over full length of condensate drain line in sub-zero climates
Condensate drain tee assembly:
The flexible tube supplied as part of the condensate drain tee assembly is intended to prevent excessive strain of the condensate drain fittings when fitting and
securing the rigid PVC drain line. It is not designed to take the place of a 90o bend.
Minimum 500mm to
nearest part of roof 100mm plastic
Flue drain elbow
DWV pipe
Seal remaining drain transit plug located on the opposite side of the heater to
condensate drain using silicone sealant or PVC primer and solvent cement.
Light switch must Fix flue pipe in Vent cowl, condensate drain tee
place with screw assembly, flue drain elbow and flue
200mm minimum be adjacent to
drain hose are supplied in 5 star
for servicing access opening internal installation accessories kit.
Attach flue terminal to
flue, fixing in place with P/No 075983
screw. Vent cowl
External Wall
FLUE
Flue drain elbow
Flue system
Braemar TH5 heaters must be flued using 100mm DWV plastic pipe and components complying with AS1260.
The flue terminal on the side of the heater is designed to accept either the male end of a 100mm DWV M-F elbow, or 100mm DWV pipe.
Connections
The connection to the heater, and all other joins in the flue and condensate drain system must be sealed to prevent leakage of
condensate.
USE SILICONE SEALENT OR PVC SOLVENT CEMENT AND PRIMER FOR ALL CONNECTIONS.
Flue treminal
The flue system must be terminated to outside with a 100mm DWV vent cowl as shown in the installation diagrams.
This is supplied in both internal and external installation accessories kits.
Maximum flue length
Maximum vertical rise : 5 metres,
Maximum total flue length 12 metres,
Maximum number of bends 4 x 90° (2 x 45° bends = 1 x 90°).
Condensate drain
Use either 15mm rigid PVC pressure pipe or 20mm rigid PVC electrical conduit.
Do not allow condensate to be discharged over electrical connections, earth stakes, concrete paths, copper pipes or metallic roofs.
Do not discharge directly into guttering.
Condensate can be discharged into a vent pipe via a tundish and self-sealing device, or into a vertical section of a downpipe via a tundish.
Condensate drain must run down hill from connection point on heater to point of discharge - do not allow any part to run up-hill.
Condensate drain must be well supported.
Do not allow condensate to be discharged into any potable water system or potable water system collection point.
Fit insulation (eg, Armaflex)over full length of condensate drain line in sub-zero climates.
Set zone fan speeds (SCC thermostat, 4 & 5 star heaters only)
4 & 5 STAR HEATERS
Run heater on HIGH and check pressure at outlet test point, adjust if necessary: With the SCC in OFF mode, press and hold FAN and press ZONE 1
- All natural gas models: 875 +/- 50 Pa Use the UP/DOWN arrows to adjust the fan speed for the common
- Propane models: or flashing zone.
- TH415/20/25 2500 +/- 200 Pa
- TH430 1900 +/- 200 Pa Press SET to accept fan speed selected
-TH516 2500 +/- 200 Pa Repeat for all enabled zones
-TH23/32 1700 +/- 200 Pa
Reduce fan speed and allow heater to switch to LOW and check pressure at
Balance the air flows
outlet test point:
- All natural gas models: 400 +/- 20 Pa With the heater running and all outlets open, adjust balancing
- Propane models:
- TH415/20/25 1100 +/- 100 Pa
dampers to achieve a suitable air flow from each outlet.
- TH430 1000 +/- 100 Pa
-TH516 1100 +/- 100 Pa Programming the thermostat (SCC thermostat)
-TH523/32 800 +/- 100 Pa
OUTLET PRESSURE HIGH PRESSURE
Discuss auto program requirements with the customer
TEST POINT ADJUSTMENT To enter programming mode press and hold SET with the SCC in
AUTO mode.
Gas Out
Use the UP/DOWN arrows to adjust the day or group of days to be
LOW PRESSURE programmed then press SET - system goes to WAKE time period
ADJUSTMENT Adjust time, temperature, zones and fan speeds:
- Use UP/DOWN arrows to adjust start time then press SET
- Use UP/DOWN arrows to adjust required temperature then press
SYSTEM SETUP SET
Set the time and day (SCC thermostat) - Use UP/DOWN arrows to select zones to be heated for time period
then press SET
With the SCC in OFF mode, press and hold SET - Use UP/DOWN arrows to adjust fan speed then press SET (this
Use the UP/DOWN arrows to adjust the time, press SET when step is not required in multiple thermostat systems)
satisfied - System will go to next time period
Use the UP/DOWN arrows to adjust the day, press SET when Repeat setting procedure for AWAY, HOME and SLEEP time
satisfied periods
Set the heater and cooler type (SCC thermostat) Explain system operation to customer
With the SCC in OFF mode, press SET & AC MODE Explain the operation of the system to the customer/home owner
simultaneously Hand the operating instructions and warranty card to the
Use the UP/DOWN arrows to adjust to heater type to HEAT 3 customer/home owner.
(factory default), press SET when satisfied
Use the UP/DOWN arrows to adjust the cooler type, press SET
when satisfied
- COOL 1 = evaporative (factory default)
- COOL 2 = refrigerated
Note that the above settings can only be adjusted within the 1st hour
of powering the SCC. After that, disconnect the SCC loom, discharge
the SCC capacitor then re-connect the loom.
Thermostat not connected *SSD Shut down type dependent on current operating status.
Safety shut down: Reset not required.
Connect "manual/2-wire" thermostat to "MAN L1 Lockout 1: User reset from SCC (press RESET twice), or
T/STAT" terminals on circuit board Manual t/stat off-on-off-on - wait 5 seconds at each
Connect Braemar Spectrolink CC to "CC" terminals state, or
on circuit board Power off - power on.
L2 Lockout 2: Reset from SCC service mode only
No thermostat communication. 4 & 5 STAR HEATERS
Check for "YES" on SCC display when first powered Code Shut down
Description SCC display
No type
Thermostat not calling for heat 1 P-55 closed at start L1 Reset, 1
Adjust set point above current room temperature. 2 P-55 failed to close L1 Reset, 2
Check LED's - centre LED (red) on steady
3 P-55 open during run SSD Normal
*
o
Combustion fan does not start 4 Thermistor > 70 C during run SSD Normal
Check that the fan is not blocked or jammed 5 Thermistor not connected or short circuit L1 Reset, 5
7 Ignition failure L1 Reset, 7
No spark
# 8 P-cond closed at start L1 Reset, 8
Check flue cowl is installed correctly
Check wiring to pressure switch is not dislodged 9 Internal memory failure L2 Reset, 9
Heater shuts down after 60 seconds # 17 Condensate detected in run SSD Normal
Check that thermistor is in duct and located # 18 Condensate detected at start L1 Reset, 18
approximately 3m from heated air outlet (4/5 star 19 HX OT2 open at start L2 Reset, 19
only).
Warranty Service
Australia 1-300-650-644
seeleyinternational.com
It is the policy of Seeley International to introduce continual product improvement. Accordingly, specifications are subject to change
without notice. Please consult with your dealer to confirm the specifications of the model selected.
623467w www.braemar.com.au