Ashiro Small Scale Irrigation Project
Ashiro Small Scale Irrigation Project
JUNE 2/ 2017
JIMMA-ETHIOPIA
Group members ID No
SIGNITURE
1.MR.KENENI ELIAS (PHD) ---------------
2.MR.WANA GEYISA(MSC) ---------------
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Acknowledgement
Above all, we would much attribute to the almighty God who gave us a life worth living and the
strength to accomplish this work.
We would like to give special thanks to our advisor Mr.Keneni Elias (Phd Fellow ) and Mr.Wana
Geyisa (Msc Fellow.) who gave us a complete and series comments, suggestion and give the
direction how to do this project
We would like to express our gratitude to all those who help us for the success and
accomplishment of our final project, whose support was either direct or indirect during
our project progress.
Our thanks will still be incomplete if we did not mention the effort of our friends and classmates
for giving us encouragement, valuable discussions throughout the work of this Project.
Page i
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Executive Summary
Water is vital to life and development in all parts of the world. In our country agricultural
sectors play a key role in economic growth; as such the irrigation scheme is an item of high
priority in developmental activities. The implementation of Ashiro small scale Irrigation project
is one of the irrigation projects essential to overcome the adverse effect of erratic rainfall
dependent agricultural activities in Ethiopia.
Ashoro small-scale irrigation project is located in Oromia regional state of Arsi zone, Adaba
woreda.
The hydrologic data processing is determined by rainfall frequency analysis, development of
composite hydrograph by USSCS method has been included, peak design flood is 97.20 m3/s.
Crop water requirements for the proposed crops of cabbage, tomato, and onion, their crop
pattern and scheme is included in the project. The duty is 0.5l/s/ha. The base flow is 10l/s. As the
dry season flow is not sufficient for the crops to be on the safest side, we incorporate night
storage design.
Design of diversion head work structure should consider the possible dangers that can cause
significance and slight collapse of the designed structure. As a result the safety and consistency
of such structure maintains the intended function for the user and for the local community as a
whole. The design of diversion head work for this particular project focuses on vertical broad
crested weir type. The canal alignment, hydraulic design of canal network, design of conveyance
structures and design of furrow irrigation system are elaborated in detail of design of irrigation
system design part.
The project cost estimation and environmental impact assessment, positive and negative impacts
of the project, and mitigation measures are described in the sections seven and eight of this
project. Generally, the cost benefit analysis ratio indicates that the project is feasible.
The conclusions and recommendations for this project work have also be drawn out at the end of
this paper.
P a g e ii
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Table of Contents
Acknowledgement ............................................................................................ i
INTRODUCTION............................................................................................. 1
P a g e iii
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
CHAPTER TWO ............................................................................................. 10
CHAPTER 3 .................................................................................................. 50
P a g e iv
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
4.1 Introduction ......................................................................................................................... 73
4.2 Head work site selection ..................................................................................................... 73
4.3 location of the weir .............................................................................................................. 73
4.4 selection of weir type .......................................................................................................... 74
4.5 Head Work Design .............................................................................................................. 75
4.5.1 Type of head work structure ......................................................................................... 75
4.5.2 Highest Flood Level Determination ............................................................................. 75
4.6 Tail water depth determination ........................................................................................... 75
4.6.1 Manning‟s Roughness coefficient ................................................................................ 78
4.6.2Tail Water Depth Computation corresponding to peak flow ........................................ 78
4.6.3 Discharge of the river ................................................................................................... 79
4.7 Design of Diversion Weir ................................................................................................... 81
4.7.1 Crest length/ water way ................................................................................................ 82
4.7.2 Flow over the Weir Crest.............................................................................................. 82
4.7.3 Top and bottom width................................................................................................... 86
4.8 Water surface profile at the weir site .................................................................................. 87
4.8.1Water Surface Profile at the U/S of the Weir ................................................................ 87
4.8.2Water Surface Profile D/S of the Weir .......................................................................... 88
4.9 Energy dissipation ............................................................................................................... 90
4.10 Dimension of stilling basin ............................................................................................... 92
4.11 Scour Depth Determination............................................................................................... 93
4.12 Cut offs .............................................................................................................................. 93
4.13 Design of under sluice ....................................................................................................... 94
4.14 Head Regulator .................................................................................................................. 95
4.15 Depth of sheet pile............................................................................................................. 96
4.16 Impervious Floor ............................................................................................................... 96
4.17 Thickness of Impervious Floor by Bligh‟s Theory ........................................................... 98
4.18 Check by Khosla, s Theory ............................................................................................... 98
4.19 Structural Design of the Weir.......................................................................................... 101
4.19.1 Stability analysis of the weir .................................................................................... 101
4.20 Design of wing wall ...................................................................................................... 110
4.21 Design of divide wall ...................................................................................................... 118
4.22 Design of an embankment earth fill dyke ....................................................................... 119
Page v
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
CHAPTER 5 ................................................................................................ 120
DRAINAGE................................................................................................. 147
6.1 General .............................................................................................................................. 147
6.2 Requirement of drainage ................................................................................................... 147
6.3 Selections of drainage systems .......................................................................................... 148
6.3.1 Surface drainage systems............................................................................................ 148
6.3.2 Subsurface drainage system........................................................................................ 149
6.4 Alignment of surface drainage .......................................................................................... 149
P a g e vi
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
6.5 Design of surface drainage ................................................................................................ 149
6.6 Selection of Drainage System ........................................................................................... 149
6.6.1 Capacity of drainage ................................................................................................... 150
6.6.2 Permissible velocity .................................................................................................... 150
6.6.3 Side slope.................................................................................................................... 150
6.6.4 Manning coefficient (n) .............................................................................................. 150
6.6.5 Longitudinal (bed) slope ............................................................................................. 151
6.7 Design of Drainage Canals ................................................................................................ 151
6.7.1 Mean Annual Rain fall (MAR) ................................................................................... 151
6.7.2 Drainage coefficient (DC) .......................................................................................... 152
6.7.3 Types of drainage canals ............................................................................................ 152
6.8 Design of Tertiary Drain ................................................................................................... 152
6.8.1 Design of sub collector ............................................................................................... 154
6.8.2 Design collector drain ................................................................................................. 157
P a g e vii
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
8.3.2 specific objectives...................................................................................................... 172
8.4 Assessment of environmental impact ................................................................................ 172
8.4.1 Assessment of positive environmental impact ........................................................... 172
8.4.2. Assessment of negative environmental impact ......................................................... 172
8.5 The Mitigation Measures .................................................................................................. 174
8.5.1. Environmental mitigation plan .................................................................................. 175
8.6 Environmental Management Plan ..................................................................................... 175
8.7 Environmental Monitoring and Auditing .......................................................................... 176
REFERENCES............................................................................................. 180
P a g e viii
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
LIST OF TABLE
Table: 1.1 The major land use types of Adeba Wereda ________________________________________________ 7
Table: 1.2 the major land use types of Lencha washo kebele ____________________________________________ 8
Table: 2.1 Guideline for selecting the return period___________________________________________________ 11
Table: 2.2 24-hours Maximum Daily Rainfall of Adaba Station __________________________________________ 12
Table: 2.3 computation of rainfall frequency analysis _________________________________________________ 13
Table: 2.4 skewness ranges _____________________________________________________________________ 15
Table: 2.5 Determination of threshold value for outliers of daily heaviest rainfall __________________________ 15
Table: 2.6 Rearranged maximum daily rainfall of Adaba station ________________________________________ 17
Table: 2.7 Computation of rain fall frequency analysis ________________________________________________ 17
Table: 2.8 skewness ranges _____________________________________________________________________ 18
Table: 2.9 Determination of threshold value for outliers of daily heaviest rainfall __________________________ 19
Table: 2.10 Rearranged maximum daily rainfall of Adaba station _______________________________________ 20
Table: 2.11 Computation of rainfall frequency analysis _______________________________________________ 20
Table: 2.12 Determination of threshold value for outliers of daily heaviest rainfall _________________________ 21
Table: 2.13 Rearranged maximum daily rainfall of Adaba station _______________________________________ 22
Table: 2.14 Computation of rainfall frequency analysis _______________________________________________ 23
Table: 2.15 Determination of threshold value for outliers of daily heaviest rainfall _________________________ 24
Table: 2.16 Corrected reliable data for computation of rainfall frequency analysis _________________________ 25
Table: 2.17 Summary of result for 50 years return period storm ________________________________________ 30
Table: 2.18 CN adjustment for below and above average moisture condition ______________________________ 34
Table: 2.19 collecting the above values in tabular form _______________________________________________ 36
Table: 2.20 Design Rainfall Arrangement in relation to rain fall profile and areal to point ratio _______________ 38
Table: 2.21 computation of cumulative Rain fall ____________________________________________________ 39
Table: 2.22 Direct run off computation ____________________________________________________________ 39
Table: 2.23 Computation of peak discharge for each incremental run off _________________________________ 39
Table: 2.24 calculation of design discharge ________________________________________________________ 41
Table: 2.25 Peak Discharge Analysis Using Complex Hydrograph Method ________________________________ 48
Table: 3.1 Determination of effective rainfall through different methods in mm ___________________________ 53
Table: 3.2 ETo determination using pen-man montieth method ________________________________________ 59
Table: 3.3 cropping pattern data ___________________________________________________ 61
Table: 3.4 Dry crop data ________________________________________________________________________ 64
Table: 3.5 Field Water Supply ____________________________________________________________________ 66
Table: 3.6 Irrigation interval and application depth __________________________________________________ 70
Table: 4.1 River bed slope computation ___________________________________________________________ 76
Table: 4.2 Sample value of manning’s ____________________________________________________________ 78
Table: 4.3 Tail Water Depth Estimation along River X-Section __________________________________________ 79
Table: 4.4 Computation of the backwater curve at different points U/S of the weir _________________________ 88
Table: 4.5 Stability analysis of dynamic case_______________________________________________________ 104
Table: 4.6 Forces and moments acting on weir at static case _________________________________________ 108
Table: 4.7 the various Forces and their moments about the toe. ______________________________________ 112
Table: 4.8 The Various Forces and their moment about the toe _______________________________________ 116
Table: 5.1 Recommended Side Slope of Canals _____________________________________________________ 124
Table: 5.2 Longitudinal Slopes of Canals __________________________________________________________ 125
P a g e ix
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Table: 5.3 Permissible velocities (unlined canal) ____________________________________________________ 125
Table: 5.4 Permissible velocity (lined canal) _______________________________________________________ 126
Table: 5.5 Roughness coefficients _______________________________________________________________ 126
Table: 5.6 Tabulated result for secondary canal ____________________________________________________ 128
Table: 5.7 Tertiary canal tabulated result _________________________________________________________ 130
Table: 5.8 Drop structure tabulated form _________________________________________________________ 138
Table: 5.9 Furrow infiltration and inflow rate _____________________________________________________ 144
Table: 5.10 Spacing between rows and plants ______________________________________________________ 144
Table: 6.1 Maximum permissible velocity for different soil type _______________________________________ 150
Table: 6.2 Maximum side slope for drain canals for different soil type __________________________________ 150
Table: 6.3 possible values of Manning coefficient for different value of Hydraulic _________________________ 151
Table: 6.4 Yearly total rain fall of Adaba station. ___________________________________________________ 151
Table: 6.5 DC for different ranges MAR value ______________________________________________________ 152
Table: 6.6 Cross-section of tertiary drain__________________________________________________________ 154
Table: 7.1 Take off sheet ______________________________________________________________________ 162
Table: 7.2 bill of quantity (BOQ) ________________________________________________________________ 166
Table: 7.3 required workers and cost paid per day (assume) __________________________________________ 169
Table: 7.4 Estimation of project benefit __________________________________________________________ 170
Page x
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
LIST OF FIGURE
Figure 1.1 Location map of the study area __________________________________________________________ 4
Figure 2.1 Composite hydrograph curves for each excess runoff ________________________________________ 49
Figure 2.2 Composite hydrograph curves for peak runoff _____________________________________________ 49
Figure 4.1 Elevation versus distance curve __________________________________________________________ 77
Figure 4.2 stage discharge curve _________________________________________________________________ 80
Figure 4.3 Tail water rating curve _________________________________________________________________ 80
Figure 4.4 Head over the weir ____________________________________________________________________ 83
Figure 4.5 Weir body schematic Section ___________________________________________________________ 86
Figure 4.6 A typical water profile over the weir _____________________________________________________ 89
Figure 4.7 Energy dissipation ____________________________________________________________________ 91
Figure 4.8 Stability analysis of the weir ___________________________________________________________ 103
Figure 4.9 Forces act on weir ___________________________________________________________________ 107
Figure 4.10 Upstream wing walls _______________________________________________________________ 112
Figure 4.11 Downstream wing wall ______________________________________________________________ 115
Figure 5.1 Rectangular main canal ______________________________________________________________ 128
Figure 5.2 Cross-section of trapezoidal main canal _________________________________________________ 129
Figure 5.3 Plan View of Division Box (sample)______________________________________________________ 132
P a g e xi
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
LIST OF ABBERIVATION
ASSIP Ashiro Small Scale Irrigation project
RH Relative Rumidity
IR Irrigation Requirement
ER Effective Rainfall
NIR Net Irrigation Requirement
GIR Gross Irrigation Requirement
GW Ground Water
CWR Crop Water Requirement
Ea Application Efficiency
FC Field Capacity
WP Welting Point
TAM Total Available Moisture
PWP Permanent Welting Point
ETO Potential evapotranspiration
FAO Food and Agricultural organization
ETC Crop Water Requirement
U/S Upstream
TEL total energy level
HFL high flood level
D/S Downstream
Max.RF maximum rainfall
a.m.s.l, above mean sea level
KC Crop coefficient
MAR Mean Annual Rainfall
USASCS United States American Soil Conservation Services
CN Curve Number
AMC Antecedent Moisture Content
EIA Environmental Impact Assessment
UTM Universal Topographic Map
P a g e xii
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
CHAPTER ONE
1. INTRODUCTION
Water is one of the most valuable resources that must be used or utilized in efficient manner. For
irrigation, with an adequate water supply, suitable soil, suitable design and construction of
irrigation structure and good management should ensure sustained high yields of crop per unit
area of land. The success of an irrigation project in meeting these requirements depends to a
large extent on the proper functioning of its water conveyance and distribution system
(Clemmens and Moden, 2007). Since inherently there is no single type of well managed
irrigation system more or less efficient than one another. Management is the key for efficient,
profitable and good performed irrigation (Claudio, 2009).
Presently the problem of the global warming is becoming the main issue of the world as well as
the country which results increase in temperature and decrease in rainfall both in amount and
distribution. This unreliable rainfall and desertification in turn reduce the production return from
the existing limited natural resource. This problem is beomming the main constraint for
development and increasing agricultural production. Besides increase in population is another
constraint which needs special mechanism to facilitate food availability for the rapid increasing
population.
Irrigation plays an important role in the development of agricultural sector and contributes much
in economy development of the country. It ensures production of high value crop, protection of
crop failures due to drought, cultivation of suitable multi cropping practices in a season;
maximize the value of land and farmers and increase their living standards, create job
opportunity and generate additional income.
Irrigation water is artificial application of water to the land through different structure to assist
the production of crops. The amount of irrigation water applying in the field depends on climatic
data such as, rainfall, both maximum and minimum temperature, sunshine hrs., wind speed and
relative humidity. The above climatic data except rain fall are used to calculate reference
evapotranspiration using CROPWAT 8 computer programme developed by FAO. Then crop
water requirement (CWR), net and gross irrigation water requirement (NIR & GIR) and volume
of water are calculated by considering the amount of rainfall, crop growth stage and different
Page 1
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
losses through the different irrigation structure. Crop water requirement is the daily required of
water for the crops starting from planting till harvesting. Net irrigation requirement is the amount
of irrigation water that applies in the crop root zone without including water losses. Gross
irrigation requirement is the sum of net irrigation requirement and water losses due to
conveyance loss (seepage, infiltration...), application loss (field application loss due to irrigation
crew) and evaporation loss.
The major constraint in any small scale irrigation to produce optimum production per unit of
water is proper water management and efficient operation and management of water distribution
and irrigation canals. In addition incorrect irrigation system design and construction have a
significant contribution for poor performance of irrigation water conveyance (Christopher et al.,
1997). Particularly on surface irrigation system, the limitations are inefficient with large tail
water loss, loss to deep drainage, limited ability to apply small amount of water and poor water
distribution uniformity (Claudio, 2009). The main problems that can be found in an irrigation
canal network which have impacts on poor performance are limited amounts of water available
at the water source, high water consumption in fields close to the water source resulting in water
shortages at the tail end of the scheme, illegal manipulation of canals and structures, siltation,
plant growth, water losses, frequent overtopping and low water levels due to canal erosion
(Bosch and Vanden, 1992).
One possible approach to conserve this precious resource and to get rid of the above problem
may be through improving the performance of the existing small-scale irrigation network and
improving its management and utilization level. As such development of performance indicators
and rigorous evaluation methodology is needed to help managers to improve their system.
Evaluation exercise is useful tool to aid scheme manager to compare the efficiency of alternative
system and operating procedures to improve existing irrigation scheme (Claudio, 2009).
Irrigation plays an important role in the development of agricultural sector and contributes much
in economy development of the country. It ensures production of high value crop, protection of
crop failures due to drought, cultivation of suitable multi cropping practices in a season;
maximize the value of land and farmers and increase their living standards, create job
opportunity and generate additional income.
Page 2
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
For Ashiro Small Scale Irrigation Project area Ashiro stream has been found the only alternative
source to use for the irrigation purpose.
Accordingly, Ashiro stream has an estimated catchment area of 64km2 and catchment length of
about 19.7 km has been selected as potential water source. Based on the preliminary assessment,
there are no potential pollutants along its catchment and there are no known potential users at
upstream site.
Ashiro stream is un-gauged and its minimum and maximum flows are not known, however,
during the preliminary assessment elders leaving nearby the stream has been asked about the
sever drought flow. Their response is that the steam is perennial and they haven‟t seen any
remarkable dry period flow during the recent drought that has occurred in the country.
Ashiro small scale irrigation project area is situated at Geographical UTM of 552553E &
778913N in Adaba Ana/district. The main source of irrigation in the project area is Ashiro
stream. The stream headwork site is located at about 9kms away from Adaba town. It covers a
total drainage area of 64km2. 58% of the catchment is covered with dense forestland, 37% with
cultivated land and the rest 5% with open woodland. The upper reaches of the catchment area is
forest land with rugged mountain terrain slope, while the lower part of the drainage area is flat
and the stream flows to Wabe River. The length of drainage area is about 19.7 km2 and the
overall slope is around 6.8%.
Page 3
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
1.1.3 Location and Accessibility
Ashiro site is located in Ganda washa in Adaba District of West-Arsi Zone. The communities
nearby/around the envisaged irrigation development site are sedentary agricultural people
producing food crops using rain-fed and traditional irrigation method. The geographical
coordinate of the project area is: From 551494.09E to 552617.1280E to and 779797.5426N to
778925.6845N with an average elevation of 2444.53m a.s.l.
Besides, it is accessible by asphalt, all weathered road and dry weathered road up the project site.
The site is 7 km far from Adaba town and which is 3km along the asphalt road, and 4 km along
all-weathered road.
Page 4
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
The following steps have been followed to execute the project work in general.
Raw data are available from the feasibility report
Hydrological analysis to get maximum design flood discharge
Assessment of water demand of the crop
Design of headwork (weir)
Page 5
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Design of irrigation system(canal irrigation system)
Drainage system design
Overall cost and benefit analysis of the project
Assessment of environmental impact assessment
1.4 Topography.
The command area is found mainly at the right side of the river with a general feature having an
average slope of 0%-4% that can be taken as an indication for its suitability for surface irrigation.
Based on the soil study of the area, the dominant type of the soil is clay which is found good for
irrigation for it has good moisture holding capacity. Besides the irrigation drainage duty of the
area is 0.5l/sec/ha.
1.5 Soil
The texture of the soils in the study area is clay. The soils are very dark brown in dry and black
in moist. In general the study area has soil depth of greater than 150cm. This indicates that soil
depth is not a critical limitation for root development and soil moisture storage. Soils of the study
area ranges from imperfectly drained to poor-drained soil condition. Thus, drainage structures
are required to avoid the water logging problems.
1.6 Climate
According to information from Adeba wereda agricultural office Woreda exhibits two agro-
climates (Dega 85% and Weina dega 15%).
Adeba Meteorological station is the nearest station to the project area. Thus, all the
meteorologial data used were collected from Adeba meteorological station.
0
The mean minimum annual temprature is 5.3 C while the mean maximum annual temprature is
o
23.9 C. The annual mean temperature of the Adeba Meteorological station is 14.6 oC. The mean
annual rain fall of the wereda is 845.8 mm.
Page 6
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Other land use categories includes grazing land 8.41%, forest land 35.42%, homestead 3.27%
and others 25.56% which represents degraded, eroded and stony areas. The pattern of land use of
the Woreda is shown in Table3 below.
The Peasant association in which Ahsiro irrigation project located comprises about
2151hectares of land. About 40.55 % of this area of land is currently under cultivation.
Other land use categories includes grazing land 0.78%, forest land 58.43%, and others
0.24% which represents degraded, eroded and stony areas. The pattern of land use of the
kebele is shown in Table4 below.
Page 7
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Table:1. 2 the major land use types of Lencha washo kebele
Page 8
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
1.8.2 Farm Size and Land Tenure
At Woreda level, land holding per farm family ranges from 1 to 5 hectares with an average
holding size of 3 hectares. In the project area, however, land holdings ranges from 1 to 0.25ha
with an average of 0.625. These holdings are fragmented and some farmers cultivate land both
within and outside the scheme area.
Shortage of Oxen: Oxen are the major source of farm power. However, due to scarcity of grazing
land and shortage of other feed sources, about 6 % of the farming population has no oxen and 94
% of the the farmers own oxen in the project area, While in the peasant association in which the
project is located about 7.5 % of the farming population has no oxen and 92.5 % own oxen.
Page 9
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
CHAPTER TWO
2.1 General
Hydrology is used in engineering mainly in connection with the design and operation of
hydraulic structure. For the analysis and design of any water resource project adequate data and
length of records are Necessary. A hydrologist is often challenged with lack of adequate data.
The basic hydrological data required are: Climatologically data, Hydro meteorological data like
(temperature, wind velocity, humidity, etc.), Precipitation records ,Stream-flow records, Seasonal
fluctuation of ground water table or piezometric heads, Evaporation data, Cropping pattern,
crops and their consumptive use, Water quality data of surface streams and ground water,
Geomorphologic studies of the basin, like (area, shape and slope of the basin, mean and median
elevation) mean temperature (as well as highest and lowest temperature recorded). The design of
water resource project like irrigation project, the peak magnitude of the flood are of great
important to design economical as well as structures with less probability of failure.
In the design of hydraulic and irrigation structures, the peak flow that can be expected
within assigned frequency is of primary important. Under estimation of peak flow would
result inadequate capacity of structures and its consequence is failure.
To estimate the magnitude of peak flood, the following methods may be used depending on
the data availability namely: Rational method, Empirical formulas, Unit hydrograph
technique, flood frequency studies, Snyder’s and SCS methods.
P a g e 10
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Though the station has relatively more records, all years are not fully recorded. Therefore,
records of years having no missed data are taken. For this design 10years daily maximum rainfall
data is processed.
2.Barrage and minor dams with storage less than 60Mm3 100
P a g e 11
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
P a g e 12
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Table: 2.3 computation of rainfall frequency analysis
Year of Daily
highestDescendi
recorde ng Ran (Y- (Y- (X-
S.N d RF(mm) (x) k Y=log x Ym)^2 Ym)^3 Xm)^2
1.9614210 0.141266 2542.176
0.053095763
1 1997 32.2 91.5 1 9 7 4
1.6384892 0.002800
2 1998 43.5 43.5 2 6 8 0.000148228 5.8564
1.6190933 0.001124
3.7686E-05
3 1999 41.6 41.6 3 3 1 0.2704
1.6031443
5.43131E-06
4 2000 36.4 40.1 4 7 0.000309 0.9604
1.5634810 0.000487
-1.07724E-05
5 2001 26.1 36.6 5 9 8 20.0704
1.5611013 0.000598
-1.46433E-05
6 2002 40.1 36.4 6 8 5 21.9024
0.000856
-2.50609E-05
7 2003 36.6 36 7 1.5563025 4 25.8064
1.5078558 0.006038
-0.000469289
8 2004 36 32.2 8 7 9 78.8544
1.4281347 0.024784
-0.003901898
9 2005 91.5 26.8 9 9 7 203.9184
1.4166405
-0.004820464
10 2006 26.8 26.1 10 1 0.028536 224.4004
15.855664 0.206802
0.044044981
Sum 410.8 2 9 3124.216
Mea 1.5855664
n 41.08 2
Number of data=10
P a g e 13
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
∑
Standard deviation (Xi), √ , since ∑ 216
=√ ,
= 18.63
∑
Standard deviation (Yi), √
Mean, X=41.08
Before proceeding to the other analysis the adequacy of rainfall data series should be checked
and it should be realized. The data series should be considered and adequate if relative
standard error, ≤10%, where is the relative standard error.
Input data:
∑
Ẋ= = = 41.08mm
∑ = 15.85mm
∑
= = 1.585
∑ = 0.21,∑ = 0.044
=√ =√ = 0.153
P a g e 14
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
∑
Cs = = =1.71
Outliers are data points that depart significantly from the trend of the remaining data. The
detention or retention of these outliers can significantly affect the magnitude of statistical
parameters computed from the data, especially for small samples. As shown from the above
calculations the station skew is greater than +0.4, so based on the following principle the Cs
value falls in the second case. Therefore, it needs checking for higher outlier. -0.4<Cs<+0.
Table: 2.4 skewness ranges
Case1 If skewness(Cs) < -0.4 check for lower outlier
Table: 2.5 Determination of threshold value for outliers of daily heaviest rainfall
Since it is stated that the skewness coefficient is greater than +0.4, our data recorded with respect
to lower outlier is within reasonable range. So, there is no lower outlier. Thus, the data is only
checked for higher outlier.
To detect the outlier the following frequency equations are applied.
P a g e 15
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Lower outlier, Yh=Ym-Kn×Sy Where Ym=mean of data in log unity
Kn=from table for sample size N
From above calculated value for data N=10, Ym=1.59, Sy=0.153, Kn=2.036 and Cs=1.71
Lower outlier Yh =Ym - Kn×Sy =1.59-2.036×0.153= 1.278
Lowest datum RL= 10Yh
=101.278=18.96mm
The lowest record daily heaviest rainfall data is 26.1mm in the 2006 which is greater than the
threshold value of lower outliers. Hence the daily heaviest rainfall data recorded with respect to
lower outlier is within reasonable range. Thus, there is no lower outlier.
Higher outlier determination
P a g e 16
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
FIRST ITERATION:-
Table: 2.6 Rearranged maximum daily rainfall of Adaba station
S.N Year of Daily highest
recorded rainfall
1 1997 32.2
2 1998 43.5
3 1999 41.6
4 2000 36.4
5 2001 26.1
6 2002 40.1
7 2003 36.6
8 2004 36
9 2005 79.71
10 2006 26.8
Outliers are data points that depart significantly from the trend of the remaining data.
The detention or Retention of these outliers can significantly affect the magnitude of statistical
parameters computed from the data, especially for small samples. As shown from the above
P a g e 17
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
calculations the station skew is less than -0.4, so based on the following principle the Cs value
falls in the first case. Therefore, it needs checking for lower outlier. -0.4<Cs<+0.4.
∑
Standard deviation(Y), √ √
∑
Skewness coefficient = 1.43
Before proceeding to the other analysis the adequacy of rainfall data series should be checked
and it should be realized. The data series should be considered and adequate if relative standard
error, ≤10%, where is the relative standard error.
11.99% Where
√ √
11.99% > 10%. Therefore the data is not reliable and adequate.
Tests for Outliers
Outliers are data points that depart significantly from the trend of the remaining data. The
detention or retention of these outliers can significantly affect the magnitude of statistical
parameters computed from the data, especially for small samples. As shown from the above
calculations the station skew is greater than +0.4, so based on the following principle the Cs
value falls in the second case. Therefore, it needs checking for higher outlier. -0.4 < Cs < + 0.4
P a g e 18
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Table: 2.9 Determination of threshold value for outliers of daily heaviest rainfall
Parameters Value log transferred Remark
P a g e 19
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
SECOND ITERATION:-
P a g e 20
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
N=10 ∑ =0.0149
∑
Standard deviation (X), √ =√ =12.799
∑
Standard deviation(Y), √ √
∑
Skewness coefficient = 1.112
Before proceeding to the other analysis the adequacy of rainfall data series should be checked
and it should be realized. The data series should be considered and adequate if relative standard
error, ≤10%, where is the relative standard error.
10.36% Where
√ √
10.36% > 10%. Therefore the data is not reliable and adequate.
Tests for Outliers
Outliers are data points that depart significantly from the trend of the remaining data. The
detention or retention of these outliers can significantly affect the magnitude of statistical
parameters computed from the data, especially for small samples. As shown from the above
calculations the station skew is greater than +0.4, so based on the following principle the Cs
value falls in the second case. Therefore, it needs checking for higher outlier. -0.4<Cs<+0.4.
Determination of threshold value for outliers of daily heaviest rainfall.
Table: 2.12 Determination of threshold value for outliers of daily heaviest rainfall
Parameters Value log transferred Remark
P a g e 21
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Higher outlier determination
From above calculated value for data N=10, Ym=1.575mm, Sy=0.123, Kn =2.036, and
Cs=1.112
Yh =1.575+2.036 × 0.123=1.825
= 101.825 = 66.83mm
The highest record daily heaviest rainfall data is 71.61mm in the 2005 which is greater than the
threshold value of higher outliers. Hence the daily heaviest rainfall data recorded with respect to
higher outlier is out of the range. So, the recorded sample in year 2005 is dropped out but our
data less than 10 in this case difficult to obtain Kn . Therefore the highest rainfall in the second
outlier test is 66.83mm which is less than 71.61mm,so that better to replace 71.61mm by
66.83mm and the frequency analysis has been done for sample of 10 years.
THIRD ITERATION:-
Table:2.13 Rearranged maximum daily rainfall of Adaba station
S.N Year of Daily highest
recorded rainfall
1 1997 32.2
2 1998 43.5
3 1999 41.6
4 2000 36.4
5 2001 26.1
6 2002 40.1
7 2003 36.6
8 2004 36
9 2005 66.83
10 2006 26.8
P a g e 22
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Retest for outliers
Outliers are data points that depart significantly from the trend of the remaining data. The
detention or retention of these outliers can significantly affect the magnitude of statistical
parameters computed from the data, especially for small samples. As shown from the above
calculations the station skew is less than -0.4, so based on the following principle the Cs value
falls in the first case. Therefore, it needs checking for lower outlier. -0.4<Cs<+0.4.
∑
Standard deviation(Y), √ √
P a g e 23
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
∑
Skewness coefficient = 0.858
Before proceeding to the other analysis the adequacy of rainfall data series should be checked
and it should be realized. The data series should be considered and adequate if relative standard
error, ≤10%, where is the relative standard error.
9.4% Where
√ √
Outliers are data points that depart significantly from the trend of the remaining data. The
detention or retention of these outliers can significantly affect the magnitude of statistical
parameters computed from the data, especially for small samples. As shown from the above
calculations the station skew is greater than +0.4, so based on the following principle the Cs
value falls in the second case. Therefore, it needs checking for higher outlier. -0.4<Cs<+0.4.
Table: 2.15 Determination of threshold value for outliers of daily heaviest rainfall
No of data 10 Given
P a g e 24
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
From above calculated value for data N=10, Ym=1.572, Sy=0.116, Kn =2.036, and Cs=0.858
Higher outlier Yh =Ym +Kn × Sy
Yh =1.572+2.036×0.116=1.808
Highest datum, RH=10Yh
= 101.808 = 64.26mm
The highest record daily heaviest rainfall data is 66.83mm in the 2005 which is greater than the
threshold value of higher outliers. Hence the daily heaviest rainfall data recorded with respect to
higher outlier is out of the range. So, the recorded sample in year 2005 is dropped out but our
data less than 10 in this case difficult to obtain Kn . Therefore the highest rainfall in the first
outlier test is 66.83mm which is greater than 64.26mm,so that better to replace 66.83mm by
64.26mm and the frequency analysis has been done for sample of 10 years.
Table: 2.16 Corrected reliable data for computation of rainfall frequency analysis
Daily
Year of highest
Descending
S.N recorded RF(mm) (x) Rank Y=log x (Y-Ym)^2 (Y-Ym)^3 (X-Xm)^2
0.013434144
1 1997 32.2 64.26 1 1.807940721 0.056511911 671.0172
0.000318205
2 1998 43.5 43.5 2 1.638489257 0.004660912 26.46074
0.000116751
3 1999 41.6 41.6 3 1.619093331 0.002388761 10.52354
3.56958E-05
4 2000 36.4 40.1 4 1.603144373 0.001084121 3.041536
-3.05814E-07
5 2001 26.1 36.6 5 1.563481085 4.53912E-05 3.083536
-7.57802E-07
6 2002 40.1 36.4 6 1.561101384 8.31197E-05 3.825936
-2.69483E-06
7 2003 36.6 36 7 1.556302501 0.000193652 5.550736
-0.000242533
8 2004 36 32.2 8 1.507855872 0.003889083 37.89634
-0.002868347
9 2005 64.26 26.8 9 1.428134794 0.020187746 133.5411
-0.003622313
10 2006 26.8 26.1 10 1.416640507 0.023586164 150.2095
0.007167843
Sum 383.56 15.70218382 0.112630859 1045.15
Mean 38.356 1.570218382
P a g e 25
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
As it has been described earlier 10 years 24 hr (daily) heaviest Rainfall data is obtained from Adaba
Meteorological station, that are used for the determination of the maximum probable flood. Based on the
available data, the following methods are used to estimate the design flood.
P a g e 26
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
∑
Standard deviation(Y), √ √
∑
Skewness coefficient = 0.731
XT=Xm +KT×
Where, XT=Annual Maximum rain fall T years return Period.(T=50 Years)
Xm=Mean rain fall data
KT=Frequency factor
=Standard deviations
w =2.797
Therefore, KT=2.054
XT=Xm + KT*
XT =38.356+2.054×10.77
XT=60.47mm
Therefore the maximum probable point rain fall of 50 years return period analyzed in normal
distribution method is 60.47 mm.
2. Gumbel’s Distribution Method
The distribution is applicable to extreme hydrologic events such as maximum daily rain fall, rain
intensity and peak flood flows and expressed by an equation;
XT=Xm+ KT* ------------------------------------------------------ (***)
Where Xm =mean of the annual maximum daily rainfall
T= Annual maximum rainfall of T years return period (design storm)
KT= Frequency factor expressed as;
KT = …………………………………………………(**)
P a g e 27
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Where, Yn= reduced mean in Gumble‟s extreme value, distribution for sample size from table
Sn =reduced standard deviation in Gumble‟s extreme value distribution for sample size
from table.
These equations are used under the following procedure to estimate the peak flood magnitude
corresponding to a given return period based on the mean flow series. Assemble the maximum
daily rainfall data and note the sample size N.
=standard deviation of annual rain fall.
∑
√
To determine the distribution parameters when it is applied to asset of data distribution the
following steps are followed.
1. Assemble the maximum daily rainfalls data and note the sample size N. Here the daily rain
2.fall data is the variety X, find and Xm and .
3. Using table and determine Yn and Sn appropriate to given N.
4. Find Yt for a given T by equation (*)
5. Find KT by equation(**)
6. Determine the required XT by equation (***)
∑
Xm = = 38.356
∑
√ =10.77
P a g e 28
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
3 .Log Pearson Type Three Distribution Method
This distribution is extensively used in USA for project sponsored by U.S government. In this
the variant is first transformed into logarithmic form (base 10) and the transformed data is then
analyzed. If X is the variant of random hydrologic series of Y variants
Y= logX -------------- (*) are first obtained. For this Y series, for any recurrence interval T
YT=Ym + kzSy------------------------------------------------------------------------------------- (**)
Ym= mean of value=1.57mm(from table above)
Where kz = frequency factor which is a function of recurrence interval T and the coefficient of
skew Cs.
Sy=Standard deviation of the Variant sample:-
∑
√
P a g e 29
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
4. Log normal Distribution Method
Log normal distribution method is especial type of log Pearson type three distribution method
with Cs=0, i.e from table for Cs=0 and T50, Kz=(0,50)=2.054
From table (Ven Te Chow) for Cs=0, T50, kz=2.054
Y50=Ym + kz×Sy
YT =1.57+2.054×0.111=1.798
XT=Antilog (YT)= antilog(1.798)=62.81mm
Therefore the minimum probable point rainfall of 50 years return period analyzed in log normal
distribution method is 62.81mm.
As we can see from the above four methods the maximum rainfall obtained by Gumbel
Distribution Method is the highest (76.98mm). The lowest rainfall is given by Normal
Distribution Method (60.47mm) .We adopted the design storm ( maximum daily rainfall )
obtained by Gumbel Distribution Method ( 76.98mm), because it gives a bit larger amount
rainfall value than other distribution. Taking the conservative value of flood for the design of
structure will make the structure safe and stable. Here adopting the higher storm magnitude will
not affect the economy of the structure as the difference very less when compared.
Hence, Design Point Rainfall pd=76.98mm.
P a g e 30
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Where:-
QP -is peak discharge /peak flow rate in( m3/sec).
C -Runoff coefficient
I=I (tc,p)- The mean rainfall intensity in (mm/hr) for a given duration of „tc‟ and for a given
probability of excedance ( chance of occurring(p)).
A= Area of watershed in „km2‟.A=64km2>50km2(no need to calculate the peak discharge).
Time of concentration (tc) is calculated by using Kirpitch equation
P a g e 31
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Tc= )0.77
√
Where:-
L= Basin length in „m‟.
The use of this method to compute Qp requires parameters; Tc, I (tc ,p) and Limitation:
Calculation of mean run off coefficient is difficult if the catchments covered by different land
features with different area coverage (but in our cases run off coefficients of different land
feature is not given.)
Is only applicable to small-size (<50 km2) catchments.
Estimation of I (tc ,p) requires some other regional constants based on catchments characteristics.
Because of the above limitations, rational method is not applicable for the determination of peak
flood for Ashiro irrigation project.
2. Empirical Formula
The empirical formulae used for the estimation of the flood peak are essentially regional
formulae based on statistical correlation of the observed peak and important catchment
properties. To simplify the form of the, only a few of the flood peaks are used. For example,
almost all the formula use the catchmentʾs area as a parameter affecting the peak flood and most
of them neglect the flood frequency as a parameter. By far the simplest of the empirical
relationships are those which relate the flood peak to the drainage area. The maximum flood
discharge Qp from a catchment area A is given by these formulae as:
Qp = f (A)
Dr. Admassu Gebeyehu developed an empirical formula similar to be used in some catchments
of Ethiopia based on regional statistical correlation of climatologically and hydrological data.
However, it can only be used for rough estimation of mean annual flood peaks. His equation is:
QP=Q (1+Kt×CV)………….general formula
Q=0.87×A^0.7 (Dr.Admassu‟s relation)
Where:- A-Catchments area (km2) = 64km2
Kt-frequency factor
√
Kt = [ 0.57721 + ln (ln[ )]
= 2.59
P a g e 32
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
T= return period = 50yrs
Cv = the average Coefficient of variation (0.38 for most cases)
Q = 0.87×640.7 = 15.98m3/sec
QP = 15.98(1+2.59×0.38) = 31.71m3/sec.
The empirical formula method is not convenient for the determination of peak flood of Ashiro
stream.
3. Synthetic Unit Hydrographe Technique (SNYDER’S METHOD)
Snyder (1938) developed a set of empirical equation for synthetic unit hydrographs in USA. This
equation used with some modifications in many other countries and so called Snyder‟s Synthetic
Unit Hydrograph. For our case Snyder‟s method is not applicable because, it works for
derivation of unit hydrograph for catchment, where rain fall & run off data not available.
4. SCS Curve Number method.
4.1 Peak flood analysis by SCS unit hydrograph method
Design flood is calculated by using SCS (The United States Soil Conservation Service) method.
This method is widely adopted and more reliable method for flood estimation. The approach
considers, watershed parameters, like Area, Curve number, and time of concentration.
4.1.1 Determination of curve numbers for the study area
Curve number (CN) is achieved based on USSCS method by watershed characterization in terms
of land cover, treatment, hydrologic condition and soil group. From the watershed analysis curve
number at condition II =74.74 since peak rainfall is found at an antecedent moisture condition II
state, this value has to be changed to antecedent moisture condition III.
The SCS method has an index, which is called curve numbers (CN) to represent the
combined hydrologic effect of soil, land use; agricultural land treatment class hydrologic
conditions and antecedent soil moisture. The SCS method has also developed a soil
classification system that consists of four hydrologic groups according to their minimum
infiltration rate which is obtained for a bare soil after prolonged wetting. The groups are
identified by the letters A, B, C, and D.
Group A: deep sand, deep loess, aggregated silts, high infiltration
rate,>7.6mm/hr;
Group B: shallow loess, sandy loam, moderate infiltration rate (3.8 to 7.6mm/hr);
P a g e 33
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Group C: clay loams, shallow sandy loams, soils low in organic content and soils high in clay,
low infiltration rate (1.3 to 3.8 mm/hr)
Group D: soils that swells significantly when wet, heavy plastic clay, and certain saline soils,
very low infiltration rate (<1.3mm/hr)
The soil characteristics associated with each group have been determined. The SCS uses an
antecedent rainfall index to estimate three antecedent moisture conditions (I-dry, II-normal, III-
wet). The relationship between rainfall and runoff for these three conditions is experienced as
curve numbers, CN. Each storm in a rainfall series is assigned one of the three curve numbers
according to antecedent rainfall.
Curve number adjustments for water shade moisture states are made according to three classes of
antecedent moisture condition (AMC), which is the index of the watershed wetness on the day of
the storm and determined by the total rainfall in the 5 day period preceding storm.
Three levels of AMC are used for different soil groups:
AMC I: Lowest runoff potential, the watershed soils for satisfactory placing or cultivation.
AMC II: The average condition
AMC III: The highest runoff potential, the watershed is practically saturated from antecedent
rains.
Table: 2.18 CN adjustment for below and above average moisture condition
II 12<28 36-53
III >28 >53
CN (I) = = AMC I
AND
P a g e 34
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
AMC (I) =
AMC ( ) = 40.6+30.34+3.38=74.74= CN ( )
guide line).
Si =
P a g e 35
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
D if………Tc>3hr.
m3/sec.
peak flow:
P a g e 36
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Where:- Tp=
Rain fall profile is the distribution of design rain fall with respect to time in the in the whole
watershed area. It needs developed models for the selected drainage area. I f there is no
sufficient modelling data in the vicinity, standard curves may be adopted. Similarly, as the area
of watershed gets larger, coincidence of all hydrological incidences become less and less. This
can be optimized by changing the calculated point rainfall to areal rain fall. The conversion
factor is taken from standard table that relate directly with the size of watershed area and type
of gauging station.
P a g e 37
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Table: 2.20 Design Rainfall Arrangement in relation to rain fall profile and areal to point ratio
Duration Design RF Areal Areal Incremental Descending Descending
point profile point RF RF order order
RF RF number
ratio
Hr Mm % % Mm Mm mm
P a g e 38
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Table: 2.20 computation of cumulative Rain fall
2.06 0
Q= Mm 6.52 0
11.43 0.3796
24.09 5.1181
29.4 8.1127
33.83 10.9064
Table: 2.23 Computation of peak discharge for each incremental run off
P a g e 39
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
P a g e 40
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
based on the assumption that the greatest hourly increment of the rain occurs during the first hour
of a storm and a smaller flood than that computed by assuming the greatest hourly increment of
rain occurs during the 6th hour of storm.
Hr Mm % % Mm mm Number
P a g e 41
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
13 Determine the magnitude of the daily rain fall with the
given recurrence interval by applying statistical
method
20 21 22 23 2 2
4 5
P a g e 42
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
ental rainfall
rain fall
24 Fill in the time peak as Tp, D+Tp, 2D+Tp… 5D+Tp or add Tp in every
value of 23 and mention in24.
P a g e 43
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
25 Fill in the time of end as Te,D+Tb,2D+Tb,…5D+Tb
26 27 28 29 30
Land use cover Area ratio (%) “CN” Weighted ”CN” “CN”
Hydrologic AMC CN
al soil
Group “C”
P a g e 44
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Group C: moderate high run off
31 Find the maximum potential deference b/n rainfall (P) and S M CN=8
direct run off (Q), which is given by the following formula. 7.18
25400 S=37.
254
S= CN 35
32 Substituting the value of “S” in the following formula, giving the relation b/n direct run
off (Q) and rainfall (P).
( P 0.2S ) 2
Q=
( P 0.8S )
33
P a g e 45
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Substituting the value of P1 as mentioned 22 23
in col. 20, in the above formula and fined
P(mm) Q(mm Remark
find the corresponding value of Q (33)
)
enter; Enter the value of Q in col. 35.
2.06 0.00 P < 0.2s ( Q = 0 )
34 35 36 37 38 39
Hr Mm Mm M3 Hr Hr Hr
/s
P a g e 46
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
0.32-0.64 000 0.00 0.0 0.32 1.622 3.79
35 There are the value of Qas found out in col.33 corresponding to the value of P
37 Multiply col. 36 and peak rate of runoff corresponding to 1mm run off excess as
found incol.11
38 Plot triangular hydrograph with time of beginning, peak time and time to end as
mentioned in 23,24,25 and peak run off as mentioned in col.37
39 Plot composite hydrograph by adding all the triangular hydrographs .The resultant
hydrograph will be composite hydrograph of desired return period. The coordinate
of the peak of hydrograph will give the peak run off with desired return period.
P a g e 47
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Table: 2.25 Peak Discharge Analysis Using Complex Hydrograph Method
Base
Q1 Q2 Q4 Flow Q total
TIME (m³/sec) (m³/sec) Q3 (m³/sec) (m³/sec) Q5 (m³/sec) Q6(m³/sec) (m³/sec) (m³/sec)
0 0 0.01 0.01
0.32 0 0 0.01 0.01
0.64 0 0 0 0.01 0.01
0.96 0 0 0.963686636 0 0.01 0.973686636
1.28 0 0 1.927373272 12.0309677 0 0.01 13.96834101
1.301 0 0 1.990615207 12.8205 0.498967742 0.01 15.32008295
1.6 0 0 2.891059908 24.0619355 7.603317972 0 0.01 34.56631336
1.622 0 0 2.957313364 24.8890645 8.126046083 0.48764977 0.01 36.47007373
1.942 0 0 3.921 36.9200323 15.72936406 7.580737327 0.01 64.16113364
2.262 0 0 3.342254613 48.951 23.33268203 14.67382488 0.01 90.30976152
2.582 0 0 2.763509225 41.7257601 30.936 21.76691244 0.01 97.20218182
2.902 0 0 2.184763838 34.5005203 26.36980074 28.86 0.01 91.92508487
3.47 0 0 1.157490775 21.6757196 18.26479705 21.29889299 0.01 62.40690037
3.79 0 0.578745387 14.4504797 13.69859779 17.03911439 0.01 45.77693727
4.11 0 7.22523985 9.132398524 12.77933579 0.01 29.14697417
4.43 0 4.566199262 8.519557196 0.01 13.09575646
4.75 0 4.259778598 0.01 4.269778598
5.07 0 0.01 0.01
From the analysis, the 50 year return period design run off is 97.20m 3
/s( flood peak at the
P a g e 48
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Composite Hydrograph
120
97.202
100
UH-1
80 UH-2
Discharge (m³/sec)
UH-3
60 UH-4
UH-5
40
UH-6
Base Flow
20
Q total
0
0 1 2 3 4 5 6
-20 Time(hr)
Composite Hydrography
120
Discharge(m³/sec)
100
80
60
Q total
40
20
0
0 1 2 3 4 5 6
-20
Time (hr)
P a g e 49
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
CHAPTER 3
3. WATER DEMAND, AGRONOMY AND WATER DELIVERY
ASPECTS
3.1 General
Every crop requires a certain quantity of water after a certain field interval throughout its period
growth .If the natural rain is sufficient and timely so as satisfy both those requirement no
irrigation water is required for raising that crop.
To design properly an irrigation scheme it is necessary to know the crop water requirements.
The function of water with respect of growth of plant and its yield are:
1. Solvent for gaseous, minerals and other soluble food.
2. Conduct and translocation of solutions in cell and tissues.
3. as an active reagent in photosynthesis and hydrolysis.
The factors that affect the water requirement of plants are: type of soil, type of plant,
metrological variables like sunshine, temperature, humidity, rainfall and wind etc.
3.2 Duty and Delta of the crop
3.2.1 Delta
Each crop requries a certain amount of water after a certain fixed interval of time,throughout its
period of grouth. The depth of water require every time,generally varies from 5 to 10cm depend
up on the type of crop,climet and soil.with the interval of time(frequncy of irrigation). The
summation of total water depth supplied during the base period of a crop, for its full grouth, will
evidently represent the total quantity of water required by the crop for its full-fledged
nourishment. This total quantity of water requred by a crop for its full growth,(maturity) or total
8+7\depth of water (in cm) is called its delta(∆)
The average values ofb deltas for a certain crops are represent the total water requrment of the
crops. The actual requrment of irrigation water may be less, depending upon the useful rainfall.
Moreover, these values represent the value on the field, i.e.‟delta on field‟ which includes the
evaporation and percolation losses.
P a g e 50
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
3.2.2 Duty of water
The „duty‟ of water is the relationship between the volume of water and the area of the crop it
matures. It may be define as the number of hectares of land irrigated for full growth of a given
crop by supply of 1m3/s of water continuously during the entire base period (B) of the crop.
Thus, if water flowing at a rate of one cubic meter per second, runs continuously for B days, and
matyres 200 hectares, then the duty of water for that particular crop will be define as 200hectares
per cumec to the base of B days. The duty generally represented by the letter D.
By defination of duty (D), one cubic meter supplied for B dayes matures D hectares of land
Therefore,this qu(V) matures D hectares of land or 104D sq.m of area.
P a g e 51
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
B.Effective rainfall
It is defined as the rainfall that is stored in the root zone and can be utilized by crops. All the
rainfall that falls is not useful or effective. The different methods used to calculate ER from
monthly total rainfall data are as follows;
Fixed percentage effective rainfall
The effective rainfall is taken as a fixed percentage of the monthly rainfall
ER=% of total rainfall
Dependable rainfall
An empirical formula developed by FAO/AGLW based on analysis for different arid and sub-
humid climates. This formula is3 as follows
ER=0.6×total rainfall -10 ----------------for total rainfall<70mm
ER=0.8×total rainfall-24 ----------------for total rainfall>70mm
Empirical formula for effective rainfall
This formula is similar to FAO/AGLW formula (see dependable rainfall method above) with
some parameters left to the user to define. The formula is as follows;
ER= a ×total rainfall-b ----------------total rainfall<Z mm
ER= c ×total rainfall-d ----------------total rainfall>Z mm
Where a, b, c, d and Z are variables to be defined by the user.
Method of USDA soil conservation service
The effective rainfall is calculated according to the formula developed by USDA soil
conservation service which is as follows.
ER=total rainfall×(125-0.2×total rain fall)/125 for total rainfall<250mm
ER=125+0.1×total rainfall for total rainfall>250mm
P a g e 52
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
From the table we adopt USDA soil conservation Service method, since it estimates more
effective rainfall for minimum total rainfall. (I.e. for high total rainfall much of the rain is
percolated to root zone). The effective rainfall has been calculated by USDA soil conservation
method which relates monthly effective rainfall to monthly total rainfall for different values of
monthly ETcrop. Generally the lower the rainfall the higher the percentage efficiency since less
water is lost to runoff and deep percolation.
C. Carry over soil moisture
This is the moisture retained in the root zone between cropping seasons or before the crop is
planted. The source of this moisture is either from rainfall that means according before sowing or
it may be the moisture that remained in the soil from past irrigation.
P a g e 53
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
D. Net irrigation requirement
After the exact evapotranspiration of crops have been determined, the NIR should be determined.
This is the net amount of water applied to the crop by irrigation exclusive of ER, S, and GW.
NIR=CWR-ER-S-GW
NIR is determined during different stages of crop by dividing the whole growing season in to
suitable intervals. The growing season is more preferably divided in two decades. The ETcrop
during each decade is determined by subtracting those contributions from the ETcrop.
E. Gross irrigation requirement
Usually more amount of water than the NIR is applied during irrigation to compensate for the
unavoidable losses. The total water applied to satisfy ET and losses is known as gross irrigation
requirement (GIR).
GIR= where, Ea=application efficiency
The effect of local condition and agricultural practices on crop water requirement: includes the
local effect of variations in climate over time, distance and altitude, size of fields, water
availability, irrigation water quality, etc
P a g e 54
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
3.4.1Reference Evapotranspiration (ETo)
Reference evapotranspiration (ETO):- is the rate of evapotranspiration from an extensive
surface of 8mm to 15mm tall, green grass cover of uniform height, actively growing, completely
shading the ground and not shortage of water (FAO 24,1983 ).
There are different methods, which are adopted to estimate the ETo values which need specific
data. The most widely used methods are as follows:
FAO Blaney-Criddle Method
Radiation Method
Hargrave‟s Class A Pan Evaporation Method
FAOPan evaporation Method
Penman Method
Penman-montheith Method
Thornthwaite Method
1. Blaney-criddle method
This method is suggested where only temperature data are available and is given by;
ETo=c[p(0.46T+8)]
o
T=mean daily temperature in c over the month
p=mean daily percentage of total annual daytime hours obtained from table for a given
month and latitude
c=adjustment factor which depends on minimum relative humidity, sunshine hours and
daytime wind estimates
2. Thornthwaite method
ETo=1.6×b×(
P a g e 55
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Where ETo=potential evapotranspiration in cm/month
0
Tm=mean monthly temperature in c
I=actual heat index, obtained from monthly heat index I of the year
a=b= ( )
Ep=pan evaporation
Ep=0.459R×Ct×Cw×Ch×Cs×Ce
2 o
=0.393+0.02796Tc+0.0001189Tc , Tc=mean temperature in c
2
=0.708+0.0034V-0.0000038V , V=mean wind velocity at 0.5m above the
ground, km/day
Humidity at noon
P a g e 56
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Cs=coefficient for percentage of possible sunshine
Ce=coefficient of elevation
For areas where measured data‟s on temperature, humidity, and sunshine durations or radiation
are available, the penman method is adopted.
The method uses mean daily climatic data, since day and night time weather conditions
considerably affect level ET; an adjustment for this is included.
The modified penman equation is,
ETo= [W×Rn +(1-W) ×f(u )×( )
Where W×Rn=radiation term
(1-W) ×f (u) × ( ) = aerodynamic ter
ETo=reference crop evapotranspiration, mm/day
W=temperature-related weighting factor
Rn=net radiation in equivalent evaporation, mm/day
=wind-related function
difference between the saturation vapor pressure at mean air
temperature and the mean actual vapor pressure of the air, mbar
c=adjustment factor to compensate for the effect of day and night weather conditions.
5. Penman-monteith method (direct estimation of ETo)
ETo = ×
2
C=constant to convert units from kg/m /s to mm/day
P a g e 57
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
n actualhour sofsunshine
N possiblehoursofsunshine
6
L=latent heat of vaporization=2.45×10 J/kg
S=
and = × RH/100
P a g e 58
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
From the above five methods of determination of ETo,the pen-man monteith method is proposed
because of Blaney-criddle and Thornthwaite methods use temperature data only so that the other
climatic conditions are ignored. And also Hardgrave‟s method is not considering all climate data.
The pen-man monteith method is done using the computer software Cropwat 8.0 windows as
follows for the available climatic data‟s.
P a g e 59
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
7
August 13.1 27.9 85 99 6.8 18.5 186.5
Septem
12.7 28.7 86 99 7.8 20.2 78.1
ber
Octobe 10
11.7 29 79 8.2 20.3 40.6
r 7
Novem 12
9.8 29.5 75 9.7 21.5 4.4
ber 5
Decem 12 10.
8.8 30.2 69 21.6 5.2
ber 5 2
Averag 11 8.5
11.33 29.85 76.4 20.7 59.6
e 8.9 9
Crop selection
During the final study of the proposed project, selection of potential crops has been given due to
the focus of the following situations.
Climatic conditions of the particular area
Availability of water
Type of soil
The economic importance of the crop
Stable food for the local people
Method of irrigation
Yield response factor and water utilization efficiency
Labor requirements
Markets among others
These proposed crops includes Onion,Potato and Head Cabbage.
3.5 Cropping Pattern
Cropping pattern indicates that the area under crops in different crop season. The cropping patter
depends on;
P a g e 60
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Availability of water- the cropping pattern should be planned such that the crops can be
irrigated during the critical irrigation demand.
Type of soil-Detail soil survey should be conducted to determine the suitable type of crop for a
particular land.
Climatic conditions-Crops requiring more water should be grown in the when rainfall is
available.
Value of crop- As far as possible, the crops which have high market value should be grown.
Socio-economic aspects- While deciding the cropping pattern, the socio-economic aspects and
specific requirements of the region should be considered.
Those cropping pattern is for the two season of crop by adjusting planting and harvesting date at
the given period.
P a g e 61
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
optimum soil water and fertility condition and achieving full production potential under the
given growth environment.
P a g e 62
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
∑
+[ ](
Where:
i day number within the growing season [1.. length of the growing season],
The steps needed to arrive the kc value for different growing stages are as follows:
1. Establish planting or sowing date from local information or from practice in climatic
zones.
Determine total growing seasons and length of crop development stages from local
information or from literature.
2. Kc for initial stage: predict irrigation and/or rainfall frequency for predetermined ETo
values and obtain Kc value from table for known humidity and wind speed values (FAO 33)
3. Kc for mid season: for given climate (humidity and wind) select Kc values from table
and/or plot a straight line
4. Late season stage: for time of full maturing (harvest with in few days) select Kc values
from tables as above. Assume a straight line between Kc values at the end of mid season
period and at the end of growing season.
Development stage: assume straight line between Kc values at end of initial to start of mid
season stage.
P a g e 63
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Table: 3.4 Dry crop data
Crop Name: Onion Planting date: 01/10 Harvest: 23/01
L
Initi M at tot
Stage al Develop id e al
Length (days) 25 30 10 5 70
0. 0.
Rooting depth (m) 0.3 --> 3 3
0. 0.
Critical depletion 0.3 --> 3 33
0. 0.
Yield response f. 0.45 0.45 8 3 2
L
Initi M at tot
Stage al Develop id e al
11
Length (days) 25 30 45 15 5
1. 06
Kc. Values 0.5 --> 15 5
P a g e 64
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
0. 0.
Rooting depth (m) 0.4 --> 4 4
0. 0.
Critical depletion 0.35 --> 35 35
0. 0.
Yield response f. 0.45 0.45 7 2 1.8
L
Initi M at tot
Stage al Develop id e al
16
Length (days) 40 60 50 15 5
1. 0.
Kc. Values 0.7 --> 05 95
0. 0.
Rooting depth (m) 0.4 --> 4 4
0. 0.
Critical depletion 0.45 --> 45 45
0. 0. 1.4
Yield response f. 0.2 0.2 45 6 5
P a g e 65
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
(source :-FAO DRAINAGE PAPER NO-56)
The “*” in the specified months indicates that, there is enough effective rainfall in the
command area so that water is not diverted.
The peak crop water requirement period from the above table is during January=0.5 l/s/ha.
P a g e 66
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Therefore, 0.5 l/s/ha amount of water diverted in the field satisfy water requirement of the
crop.
P a g e 67
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Blocks up to 20ha
Unlined= 0.7
lined or piped=0.8
Field application efficiency
light soil =0.55
medium soil=0.7
heavy soil=0.6
Source (siyrce FAO, 1978) ICID/ILRI
Therefore , project efficiency is the product of conveyance and field canal and field application.
For Ashiro Small scale irrigation project:
Conveyance Efficiency (Ec) =0.65 for command area 15ha
Field Canal Efficiency (Eb) = 0.7 for blocks up to 20ha
Field application efficiency (Ea) = 0.6 for clay soil
Ep = Ec × Eb × Ea
= 0.65×0.7×0.6= 0.273 thus, for this the proposed irrigation efficiency is 27.3%.
3.8 Irrigation scheduling
Irrigation scheduling is the schedule in which water is applied to the field. The scheduling of
irrigation can be field irrigation scheduling and filed irrigation supply scheduling.
Field irrigation scheduling
It is done at the field level. The two field irrigation scheduling parameters;
A.Depth of irrigation (d)
It is the depth of water that can be retained in the crop root zone between the field capacity
and the given depletion of the available moisture content.
Where
P a g e 68
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
D=effective root zone depth, m
P=depletion factor
Because of the application losses such as deep percolation and runoff losses, the total depth
of water to be applied will be greater than the net depth of water
I(days) =
Where, =the peak rate of crop evapotranspiration, m/day and others are as defined
above.
P a g e 69
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Table: 3.6 Irrigation interval and application depth
D ETc.
( peak
A m FC- E (m/day dnet(m dgross( I(day
Crop S ) PWP P a ) m) mm) s)
2 0 0
. 0. . . 0.0046
Onion 7 3 0.15 3 6 4 36.45 60.75 7
0
2 . 0
Potat . 0. 3 . 0.0053 42.52 70.87
o 7 3 0.15 5 6 5 5 5 8
0
Head 2 . 0
Cabb . 0. 4 . 0.0053
age 7 4 0.15 5 6 1 72.9 121.5 14
It is expressed as q×t =
Where,
q=stream size or application rate, lit/sec
t=application time, sec
Ea=application efficiency
p=depletion factor
As=application specific gravity
P a g e 70
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
A=area of the command (field) in ha
D=effective root zone depth, m
In the above equation q×t indicates the total volume of water applied to the field during irrigation
at the head of the field. But the total volume of water diverted at the headwork will obviously be
greater than this value, because there is loss of water during conveyance and distribution canals.
The volume of water to be diverted is given by;
Q×t =
Design discharge =
P a g e 71
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
=54.94 l/s
=0.0549m3/s
Irrigation Duty (D) = 0.5 l/s/ha.
P a g e 72
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
CHAPTER FOUR
4. HEAD WORK DESIGN
4.1 Introduction
This section comprises of design of structures that deals with the provision of water from the
water source point as well as protection of topographic nature of land at headwork. The selection
of structures type to be used for the water diversion & retaining works will be
Executed.Their proper dimensions of these structures also will be designed taking into
consideration their stability, practicality & economically achievable.
4.2 Head work site selection
Head work site of this project was selected based on design and construction suitability of
foundation nature, river bank, and proximity to command area. In addition to these guiding
principles, the following points are considered;
nearly straight, well defined River X-section
Impervious and strong foundation condition
It includes the maximum irrigable area with minimum possible diversion height.
The site is relatively accessible.
The site is selected in such a way that the backwater effect does not cause any damage to
the adjoining areas
4.3 location of the weir
Initially, it is difficult to decide on the location of the proposed structure without having
topographic maps of the project area and layout of the river course. However, by walking along
the river up and downstream of the location where the existing intake is or where the farmers
believe it is an appropriate location; it is possible to identify a few places for the proposed
structure. In our cases we did not get the chance to visit river up and down stream of the river but
the topographic map of the catchment area had been given to us in addition to the topographic
map of the catchment area ,geologic set up of the river bank has been discussed in the
introduction parts of this project.
P a g e 73
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
The following factors have to be considered when selecting the site for diversion weirs.
Location of the Irrigated Area.
Stability of the river bank.
Construction materials and resources available.
Topographic survey.
Soil investigation.
Hydrological data.
4.4 selection of weir type
When a weir is designed, the designer should consider the skill of the people who are expected to
implement the structure. There are weirs of different types and shapes and most of them are
constructed to serve the same purpose. The designer should not impose a weir with a shape
which cannot be constructed easily by the local builders.
The followings are common types of weir:
1. Ogee shaped weir: it is known for best hydraulic efficiency (can accommodate large
amount of flow with small depth).Hence it is preferable for high discharge bearing rivers.
However, it needs skilled manpower for construction.
2. Broad crested weir: it is the most simply type weir both for design and construction, but
has low hydraulic efficiency as compared to ogee weir. This type of weir is recommended for
low discharging rivers and where skill of implementing bodies is in doubt.
3. Vertical drop weir: this one has vertical downstream face, just like the natural Tisa bay
fall. The downstream face of the weir is not acting to smoothening and energy dissipation of
the coming flood and boulder effects. However, energy is expected to be dissipated at the bed
of the rivers. Hence, the river bed should be sound rock.
In deciding the type of the weir, the following conditions should be considered.
Economy of construction
Physical feasibility
Foundation condition
Size of the project
P a g e 74
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
P a g e 75
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
P a g e 76
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
A. Area-End method
Individual are, An =0.5×(cumulative 2nd+cumulative 1st)×Distance 2nd.
Average height, Havg =
Havg =
Average slope , I=
I=
Therefore, average river bed slope at the diversion site is 0.012 (1.2%). OR by using the second
method:-
P a g e 77
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
P a g e 78
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
4.6.3 Discharge of the river
Input data:
Manning's roughness coefficient, n =0.035
Average river bed slope, S = 0.0121
V= × ×√
Q=V*A
m =1
Elevation Bed W.Depth Water Wett.Perm. Hydraulic Slope Roughness Velocity Discharge
Top Width Rad. R I avg
El.(m) d (m) Area A(m2) P (m) Coeff. N V (m/Sec) Q (m3/Sec)
(m) (m) (m/m)
2453.54 12 0 0 12 0 0.0121 0.035 0 0
2453.79 12 0.5 5.834 12.54 0.465231 0.0121 0.035 1.88651294 11.0059165
2454.29 12 1 11.333 13.07 0.8671 0.0121 0.035 2.85770151 32.3863312
2455.04 12 1.5 16.5 13.61 1.212344 0.0121 0.035 3.57357632 58.9640093
2455.84 12 2 21.334 14.14 1.508769 0.0121 0.035 4.13491039 88.2141784
2456.8 12 2.3 24.07 14.46 1.664592 0.0121 0.035 4.41506337 106.270575
2457.8 12 2.4 24.96 14.568 1.713344 0.0121 0.035 4.50089645 112.342375
2458.85 12 2.5 25.833 14.68 1.759741 0.0121 0.035 4.58183012 118.362417
P a g e 79
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Stage-Discharge Relation
2460
2459
2458
2457
Stage(m)
2456 Stage-Discharge
Relation
2455
2454
2453
0 50 100 150
Discharge(m3/sec)
2.5
1.5
Stage(m)
0.5
0
0 50 100 150
Discharge(m3/sec)
P a g e 80
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
From the above table ,used to compute the highest flood level(HFL) and tail water depth by
using interpolation based on the peak flood discharge (Q peak= 97.2021m3/sec).
Discharge Elevation
88.2142 2455.84
97.2021 x (HFL)
106.27058 2456.8
X=HFL=2456.82m
Tail water depth
Discharge Depth
88.2142 2
97.2021 X (TWD)
106.27058 2.3
Tail water depth=2.15m
Tail water level= River bed level +corresponding discharge height from d/s rating curve.
TWL=2453.5m +2.15m=2455.65m .a.s.l.
4.7 Design of Diversion Weir
Maximum river flow/Flood, Qmax= 97.2021m3/sec
Longitudinal slope of the river, S=0.0121
Water depth in main canal = 0.27m
River bed level = 2453.5m
Average elevation of the highest point in the field= 2454.03m
Length of main canal= 600m
Head loss at turnout loss=0.05m
Head loss a cross head regulator=0.1m
Average particle size (from laboratory analysis), d mean=3.0mm
Tail water depth (from tail water curve), D3= 2.15m
11. Head loss a cross the filed=0.00m
12. Silt height = 0.5m
Slope= = =0.0008
Drop due to main canal (head loss in the main canal) =600m×0.0008=0.48m.
P a g e 81
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Therefore, the crest level of the weir=2454.03m+0.27m+0.05m+0.1m+0m+0.48m=2455.16m
Therefore, Weir height = Crest Level of the Weir – River Bed Level
=2455.16m-2453.5m
H=1.66m, take 1.7m for design.
4.7.1 Crest length/ water way
It is the width provided at the site for the river water to flow. In other word, it is the length of the
weir. Approximate water way to provide between the abutments may be calculated from lacey‟s
regime perimeter formula. The length of waterway is usually determined from Lacey‟s wetted
perimeter. Lacey developed the equations based on the analysis of large amount of data collected
on several river gullies.
The wetted perimeter, p is given by
P=4.75*√ Where Q=design discharge=97.2021m3/sec (obtained from hydrological analysis)
p=wetted perimeter
P=4.75*√ =4.75*√ =46.83m Using looseness factor it can be reduced to be more
Economical.Looseness factor is the ratio of overall length of weir to lacey perimeter for design
discharge.
P a g e 82
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Discharge over the weir is generally expressed by the following equation Q=CdLHe3/2
Where, Q = design discharge (m3/s).
He = Height of energy line above the crest (m)
L = length of the weir.
Cd = discharge coefficient. The coefficient Cd is not constant but depends on many factors such
as head above sill, shape and width of sill, upstream slope and downstream slope of the
sill, height above the upstream floor (P) and roughness of the surface. For roughly
estimation of river flow over the weir crest, most designers use Cd = 1.7 for broad created weir
and 2.1 for ogee shaped weirs. Effective waterway length is part of the weir crest at which free
over flow is fully observed.
P a g e 83
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
He= ) 2/3=1.89m
2. Design head, Hd
The approach velocity
Va=
The values of Hd can be obtained from equation 3 by trial and error method.
Hence, the value of Hd= 1.81m.
Computation of Ha, and Approach velocity, Va
√ √ /sec.
P a g e 84
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Tail water depth- Discharge rating curve, tail water depth equivalent to the flood discharge (i.e.
Q =97.2021 m3/sec) is found to be 2.15m
Tail water depth =River bed level +Corresponding discharge height from d/s rating curve.
Tail water level = 2453.54m a.s.l + 2.15m = 2455.69m a.s.l.
River bed level = 2453.54m a.s.l
Weir top level, = 2453.54m+1.7m=2455.24m
D/S T.E.L
High flood level before construction of the weir (D/S HFL) is = river bed level+ tail water depth
(From tail water curve)
Where HFL before construction, D/S HFL
= tail water depth corresponding to design discharge =2455.69 m a.s.l
D/S HFL=2455.69m a.s.l
Ha = Va2/2g= He –h = 1.89 m – 1.81 m = 0.08m
D/s TEL =Tail water level (D/S HFL) +ha=2455.69m a.s.l + 0.08m =2455.77m
U/S HFL =U/S TEL –velocity head
Where U/S TEL = RL of weir crest + He
= 2455.16m a.s.l + 1.89m
= 2457.05m a.s.l
Velocity head = 0.08m
U/S HFL =2457.05m a.s.l – 0.08m =2456.97m a.s.l
Afflux
Afflux = U/S HFL- D/S HFL
= 2457.05m a.s.l –2455.69m a.s.l = 1.36m > [1m-1.2m] the allowable afflux
which is 1m.
The calculated afflux is greater than the allowable afflux, but the river bed is steep slope so that
this elevation can be attained a little distance on the upstream. In addition to this, protection
walls are provided on one hand and, there is no area needed to be secured from flood damage in
the vicinity on the other hand. Therefore, the afflux could be 1m.
P a g e 85
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
P a g e 86
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
The level of the back water curve is needed to determine the safe level of the embankment and
super structures so as to know the length of the wing wall and to know whether the embankment
needs some treatment measures to protect the overtopping of water over the river bank due to the
construction of the weir. Therefore it is important to know where the effect of backwater curve
will cease.
Water profile U/S of the weirs needs to be known for two purposes:
A. To determine the height of the river banks u/s of the weir and,
B.To find out whether the water surface is height enough to deliver the required discharge to the
off take canal.
There are several methods to determine the water profile upstream of the weirs. Out of these for
our particular scheme; the profile by approximate method is selected, which is given as;.
Y=
Where, y = Water rise at a distance X U/S of the weir above the normal water depth
X = distance from the crest to the point where y is required to be determined
S= slope of the river bed(s = 0.012)
o = rise of water above the normal water depth at the weir site. (x = 0)
First let‟s determine the end point where y becomes zero. At this point the effect of the
backwater curve disappears. It is computed as follows.
Y=
=XS-2 0=0
P a g e 87
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
X=
Therefore the effect of construction of weir on the water profile during peak flood ceases at
226.67m away from the axis.
Table: 4.4 Computation of the backwater curve at different points U/S of the weir
Y=
Assumed
interval(x)
0 1.36
20 1.130588235
40 0.922352941
60 0.735294118
80 0.569411765
100 0.424705882
120 0.301176471
140 0.198823529
160 0.117647059
180 0.057647059
200 0.018823529
220 0.001176471
226.67 2.94118E-10
The effect of constructing a barrier (weir) on u/s water surface diminished and disappears at
226.67m u/s of the weir and this indicates that no infrastructure is to be laid in this gap without
considering this rise of water.
4.8.2Water Surface Profile D/S of the Weir
Once the crest level is decided, it is required to draw the water profile for Q max. (For 50 year
return period) discharge. The water profile is required to:
Carry out the stability analysis of the weir
Design the weir structurally
Design the downstream wing wall, and protection works downstream of the apron.
P a g e 88
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Construction of weir elevates the total energy line U/S of the structures. The difference b/n the
U/S and D/S energy grade line becomes high. Therefore, the energy must be dissipated before it
reaches the natural river course; otherwise it causes damage to the banks and D/S apron. The
flow over the weir is super critical. Therefore the energy tends to dissipate by a hydraulic jump
d/s of the weir. Thus we need to compute the conjugate depths y1 and y2 and compare the value
of y2 with the tail water depth y3. Depending on the condition of the tail water with respect to the
y2, the downstream apron/impervious floor/stilling basin level should be adjusted.
The water profile D/S of the weir is required to carry out the stability analysis of the weir as well
as to design the D/S wing wall and other river bank protection D/S of the weir
(0)
Ha
Hd
D/S
HFL
p
P+ Hd = Y1 +
P a g e 89
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
V1= Velocity at the points of initial jump
V1=
q =Discharge intensity
q= /sec/m.
V1=
1.7+1.89 = y1+
3.59= y1 +
jump.
Critical depth yc is equal to
Yc =( ) =( )
Y1<yc , implies that the flow takes place from supercritical to subcritical flow .The post /
sequent jump .y2.
The post jump depth or conjugate depth, y2 calculated from Upstream is known
y1=0.5746m.The downstream depth y2 will be:-
= √ -1)
Y2=2.35m
The difference between y2 and y3 must be zero for best hydraulic condition. In general case the
difference can be increased up to the range of 0.2m to o.4m. In this case y2 is nearly equal to y3 ,
implies no need to depress the bed of the river. Y2=Y3 hydraulic jump occur at the toe of the
weir.
4.9 Energy dissipation
Construction of weirs elevates the total energy line upstream of the structure. The difference
between the upstream and downstream energy grade line become very high. Therefore, the
energy must be dissipated before it reaches the natural river course, otherwise it causes damage
P a g e 90
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
to the banks and downstream of the apron. The flow over the weir is in a supercritical state.
Therefore, the energy tends to dissipate through a hydraulic jump downstream of the weir. To
control location of the jump, the apron and stilling basin are designed to suit a range of river
discharges.
U/S TEL
y3
1.7m
y1 y2
V1=
1.7+1.89 = y1+
3.59= y1 +
3.59= y1 +
P a g e 91
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
V1= = 7.69m/sec.
jump.
Critical depth yc is equal to
Yc=( ) =( )
Y1<yc , implies that the flow takes place from supercritical to subcritical flow .The post /
sequent jump .y2.
The post jump depth or conjugate depth, y2 calculated from Upstream is known
y1=0.5746m.The downstream depth y2 will be:-
= √ -1)
Y2=2.35m
As y3=y2 the jump occurs on horizontal apron there is need to construct stilling basin in order to
mitigate erosion of horizontal apron.
4.10 Dimension of stilling basin
Length of basin =4.2 y2=4.2*2.35=9.87m
Height of chute block H=y1=0.5746m
Width of chute block b=y1=0.5746m
Space between chute blocks, S=2.5*y1=2.5*0.5746=1.4365m
Length of chute block l=2*y1=2*0.5746=1.1492m
Height of end sill h=0.2*y2=0.2*2.35= 0.47m
Width of the end sill = 0.15y2=0.1*2.35=0.235m
Slope of end sill is 2:1
ES= = =1.036m
Hj(height of jump)=y2-y1=2.35m-0.5746m=1.7754m
Li(length of jump)=5(y2-y1)=5(2.35-0.5746)=8.877m.So,the minimum length of the d/s
impervious length is about 8.877m from the toe of the weir.
P a g e 92
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
R = 1.35( ……………………………….……equ3.1.
R = 1.35 * ( = 2.512m
The weir foundation will be laid on relatively fresh rock after removing the top most weathered
rock with a depth 0.2m from the minimum river bed level and an average depth of 0.5m from the
remaining weir axis accordingly the longitudinal and cross-sectional dimension of the weir.
Therefore only nominal anchorage (cut off) depth 1.0m is provided for u/s and 1m depth for d/s
after the removal of weathered rock. This cut of depth is to anchor the weir body with the fresh
rock, thereby blocking seepage in b/n the bed rock and the weir. The weathered rock is exposed
at the center of the river but overlain by silt clay soil at the banks, so removal the specified
thickness of weathered rock is done after excavating the overlain silt clay soil deposit. Cut off
dimensions are fixed based on the geological study conducted along the river cross section at the
weir site.
P a g e 93
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
For a 1m length of the scouring sluice, one layer 1 m by 1m sheet metal is used.
The critical case in the case of under sluice is during non-flow condition. The high flood
condition is expected during summer. In this condition, water is not required for irrigation. If so,
the under sluice should be fully opened/Taken away/.
P a g e 94
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
P a g e 95
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Deriving head =0.3
Cd = 0.62
The area of the intake = 0.4m*0.4m=0.16m2
Using the above formula for Qd, the value of Cd=0.62, Also take the value of h L (driving head),
0.3m
Qd=Cd*A*(2ghL) 0.5 = 0.62*0.16m2*(2*9.81*0.3)0.5=0.241m3/s/ha
Since this value, 0.241m3/s/ha is greater than the amount of discharge wanted to pass through the
canal, 0.0075m3/s/ha thus, the canal head regulator dimension is enough to deliver the flow
(0.0075m3/s) to the canal.
The gate for head regulator is to be vertical sheet metal of size 0.5m x 0.5m for the closure of the
opening space providing some extra dimensions for the groove insertion, gross area of sheet
metal for the gate will be 0.55m x 0.6m (allowing 5cm insertion for grooves).
(0.5m+5cm) × (5cm+0.5m + 5cm)= 0.55m×0.6m.
4.15 Depth of sheet pile
Depth of D/S sheet pile below the river bed ,d2
d2= 1.75R – T.W .D
d2 = 1.75*2.512-2.15=2.246m, Adopt d2 =2.0m
The thickness of d/s cut off t=0.5m
Depth of U/S sheet pile below the river bed,d1
d1= 1.5R – (h +Hd)
d1= 1.5*2.512-(1.7+1.81)=0.258m
Adopt d1 =1.0m
The thickness of u/s cut off t=0.5m
4.16 Impervious Floor
Seepage head, Hs= Pond level – Bed Level
=2455.16-2453.5
By Bligh ' s theory, the total creep length (L) is given by:
P a g e 96
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Where, C=Bligh ' s Creep coefficient taken as (5-9) for gravel foundation
LD=2.21*C √
=2.21*9 √
Ld =8.2m
Length of upstream impervious floor, L
u
Lu=L- (Ld+B+2d 1 +2d2)
Lu =15.3-(8.2 +3.3+2*1+2*2)
Lu = -2.2m
The analysis shows, there is no need of providing U/s impervious floor, hence, the u/s cutoff
should be located at the heel of the weir, but for allowance provide a nominal floor length
3m.
For the u/s impervious floor let us take nominal value of Lu= 3m
P a g e 97
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Provided 1m*1m*1m concrete block cover 0.6m thick gravel
Minimum length u/s lunch apron=2d1=2*1=2 m
Thickness of downstream floor after 4m from the function of the weir wall.
H=Hs-
H=1.7-
( ) and ( )
√
Where, 𝞴= and
d is upstream depth below upstream floor thickness and b is total length of the floor .
b=14.5m and d=1m
Thus,
√ √
From the above formula, and 𝞴= and
finally:
( )=
P a g e 98
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
( )=
= 100-28.41 = 71.59%
c=19*√ * +
c=19*√ * +
since the point c1 is in the rear or back water in the direction of flow , the correction is positive.
C1=1.51% (+ve)
b. Correction at C1 due to the thickness of floor
Pressure at C1 shall be more than at C‟1 as the direction of flow is from C1 to C‟1 and hence the
correction will be +ve .
C1t=* +
( ) and ( )
P a g e 99
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
√
Where, 𝞴= and
d is downstream depth below upstream floor thickness and b is total length of the floor .
b=14.5m and d=2m
√
And, 𝞴=
( )
( )
c=19*√ * +
c=19*√ * +
since the point c1 is in the rear or back water in the direction of flow , the correction is positive.
C1=1.51% (-ve). The point E2 is affected by pile No 1 and since E2 is the forward direction of
flow from pile No 2.
b. Correction at E2 due to the thickness of floor
Pressure at E2 shall be less than at E‟2 as the direction of flow is from E‟2 to E2 and hence the
correction will be -ve.
E2t=* +
P a g e 100
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Total length of the impervious floor, b=14.5m
Depth of downstream pile, d2=2453.04-2450.54=2.5m
√
,
GE= =
√ √
Besides satisfying the hydraulic requirements, the designed structure has to be safe against
Overturning, sliding, tension and such related structural parameters. Hence the designed section
is checked for stability requirement.
The external forces acting on weir varies from region to region and hence considering the
geology of the area and behavior of the river foundation condition, the stability analysis is
carried out on the effect of the following forces.
Water pressure
Weight of the over flow weir section
Silt pressure
Water pressure: -The resultant force due to external water
= ½ γwh2, a citing at h/3 from base, where γwis the unit
Weight of water (i.e. 10 KN/m3) and h is the depth of water
Weight of the over flow weir section: - the weight of the weir body is the major resisting force
and a unit length of the weir is considered.
P a g e 101
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Unit weight of sound masonry =23kN/m3
Silt pressure:- the force due to silt is considered up to canal outlet level and given by,
Psilt = ½ ka γsub h2 and it acts at h‟/3 from base
Where ka = coefficient of active earth pressure
γsub = submerged unit weight of silt material
h‟ = height of silt deposited (i.e. from the river bed up to crest)
The weir section developed under the hydraulic design has checked for structural safety as
follows:
Structural analysis deals with checking the stability of the weir against.
i. - Over turning
ii. - Sliding
iii. Tension
Analysis of the weir stability for two conditions should be taken such as:
A).Dynamic case
B). Static case
A) Dynamic case -Conditions:
Dynamic case
Uplift pressure was considered for the general weir section.
Water wedge weight was considered for the weir crest only (critical depth)
Downstream water pressure was considered
Unit weight of water is 10KN/m3 and that of sound masonry work is 23KN/m3
Unit weight of silt = 19kN/m3
Moment is taken about the toe per meter width
Angle of internal friction=350(Assumption)
P a g e 102
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
HF
L
Hd W
H
=He-
w d
W W
Pw H1
2
1 1.7
y1=0 P
1 w
Pw
2
W (H+Hd) = wHt
Pu
3.3m
P2 P1
P a g e 103
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
=168.912
W2= Self =Ap* =0.5*1.7*23 = *1.5=1 =29.325*1=29.
Ps=0.5*0.271*
9*0.52=0.3049
Pw1=15.385
P a g e 104
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Ww2=10*0.5
*1.5*1.7=12.7
5
P a g e 105
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
+ve=284.7 ve=106.032
438
e=| -X|<
∑
x= ∑
= =1.69
0.04<0.55, hence the weir is safe against over stress (no tension).
The weir is stable in all cases.
∑
max= *(1+ )=34.30KN/m2
∑
min= *(1- )=29.65KN/m2
P a g e 106
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
B) Static Case
Force acting on the weir includes:
Self-weight of weir is considered at all section of the weir.
Up lift pressure was considered for the weir section (zero at the toe).
Water weight was considered at the upstream face of the weir on the height of the weir.
W
W2
H
1.7
Pw1
P a g e 107
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Table: 4.6 Forces and moments acting on weir at static case
=168.912
W2= Self =Ap* =0.5*1.7*2 = *1.5=1 =29.325*1=29.
Pw1=14.45
P a g e 108
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Ps=0.5*0.271*
9*0.52=0.3049
0.14<0.55, hence the weir is safe against over stress (no tension).
P a g e 109
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
The weir is stable in all cases.
4. Factor of safety against contact pressure
The contact pressure (stress) on the foundation at the toe or heel of the weir body should be less
than the allowable bearing capacity of the foundation material .Maximum and minimum
compressive stress developed at the toe of the weir is given by:
∑
max= *(1+ )=27.24KN/m2
∑
min= *(1- )=16.187KN/m2
Stability analysis shows that the designed weir section (i.e. 1.8m top width and 3.3 m bottom
width) is safe structurally and also it is economical.
4.20 Design of wing wall
sufficient free board should be provided for u/s and d/s using wall in order to protect the wall and
embankments from being over topped by surges,splesh& sprey,and wave action setup the
turbulence of hydraulic jump and not to allow high flood water to bypass the structure. The
common practice in the design of well is adopted for this project, assign tentative dimensions and
check for the overall stability of the structures.
To control the spillage of flood in to the irrigation canal and to protect the scouring of banks due
to the incoming high velocity wing wells are provided.
Therefore the maximum footing depth or height that should be provided in this situation can be
determined as shown below.
Lw=5√ =7.84m
Lw=8m
P a g e 110
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Ka= = =0.271
P a g e 111
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Wm=
Weight Wm1 = ×Ap
of =
= 23×1m×4.09×1
masonr 94.07×0.5=4
y =94.07 = = 0.5 7.035
=1.77 =168.06
P a g e 112
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
=94.95
Wm3 = m×Ap =
Ws
Ws = s×As×b
=Weig
=1= (2. =74.313×2.5
ht for
=18× ×2.3×3.59 3) 3
backfill
soil =74.313 =2.53 =188.011
Ps
= kaŶs
= ×0.2
Ps =
71×18×
Active
=1.55×5
soil
= ×4.59 1.385
pressur =51.38
e 5 =1.53 =78.619
∑ ∑ ∑
Sum ∑
P a g e 113
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
e=/ -x/<
x= = =1.325
e=/ -x/<
e =0.325<0.55,it is safe(tension)
4) Factor of safety against contact pressure
The contact pressure (stress) on the foundation should be less than the allowable bearing capacity
of the foundation material. Maximum and minimum. Compressive stress developed toe of the
weir given by
δmax = *(1+ ) =163.542KN/
The foundation condition should be checked with respect to this value construction.
From stability analysis, the desired wall section (i.e 1m top width and 3.3m bottom width is safe)
(B) Dimension of the D/S Wing wall
D/s wing wall Height = TWD + Fb
Where, TWD is Tail water depth = 2.15m
Fb = Free board = 0.5m (Assumed)
Therefore, D/S Height of wing wall = TWD + Fb = 2.15+0.5 =2.65m (Above River Bed
level)
Top width Of wall, B= = = 1.726m
√ √
P a g e 114
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Ps = Force due to soil pressure
US = Weight of soil
P a g e 115
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Table: 4.8 The Various Forces and their moment about the toe
Horizont Moment
Vertical al Lever Moment KN.m
Load(K Load(KN arm Anticlock clockwise (-
Code Nm) m) R(m) wise (+ve) ve)
Wm1
= m×A
p
=23×1
m×2.65 =0.5×60.95
=
Wm2
= m×A
p
=23×1×
×2.3×2
=3.3-
.15 56.8675×1.7
×2.3 7
=56.867
5 =1.77 =100.655
Wm3=
s×AS×b
=23×1×
Wm=Wei
3.3×1 =1.65×75.9
ght of = =
Ws = Ws = 1+ (2 =44.505×2.5
P a g e 116
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Weight of s×s×b .3) 3
back fill
=18× × =2.53 =112.5976
2.3×2.1
5
=44.505
Ps
= kaŶs
=
Ps = = ×0.271
×3.15 =1.05×24.20
Active soil ×18×
pressure =1.05 =25.41
∑ ∑ ∑ = ∑
Sum 386.9626
-Ka = = =0.271
P a g e 117
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
e=/ -X/<
X= = = =1.44
The foundation condition should be checked with respect to this value construction.
-From stability analysis the desired wall section (i.e 1m top width and 3.3m bottom width is safe)
4.21 Design of divide wall
The divide wall separates the under sluice from the main weir portion and allows a silt free water
flow to the head regulator by depositing the silt in the under sluice pocket. It is a wall
constructed parallel to the direction of flow of river to separate the weir proper section & the silt
excluder section there by facilitates scouring operations. If there are head regulator on both sides,
silt excluders & there by divide walls have to be provided on both sides. Without divide walls
currents approach the scouring sluices from all directions and their effectiveness is reduced. With
the provision of divide walls flow can be concentrated along the regulator face.
The second objective of the wall is to separate the floor of the scouring sluices which is generally
at lower level than of the remaining portion and thus prevent turbulent action.
The third reason is to prevent cross currents and flow parallel to the weir which will cause
scouring.
The length of the divide wall on the upstream side extends a little bit the head regulator;
Sometimes may extend up to the end of the upstream impervious floor. On the downstream side,
thought is common to extend the wall to the end of the downstream impervious floor; it can be
extended till the toe of the weir wall.
Design consideration
While designing the wall the following forces has to be taken into consideration:
(a) Silt pressure up to the full tank level on the pocket side when the river level is low. At this
time there is no water on the river side or the pocket side.
P a g e 118
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
(b) Difference of water pressure of about 0.25 to 2.0m on both sides depending on the height of
the wall.
Wall height fixation
The existing topographical condition at the weir axis and HFL are considered to be most
governing parameters for fixing the wall height and freeboard (0.35m-0.4m).
U/S wall height = U/s HFL - foundation level + free board
U/S wall height=2457.05m-2454m +0.4m=3.45m
D/S wall height = D/s HFL - foundation level + free board
D/S wall height=2455.69m-2454m+0.4m=2.09m
The downstream wall height can be made as steps to reduce the wall height.
P a g e 119
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
CHAPTER 5
5. IRRIGATION CANAL SYSTEM DESIGN
5.1General
Canals are designed to distribute water properly in the system that will make irrigation possible
and efficient. The purpose of the design of main and secondary canal lines is to distribute water
just as evenly from the intake to the command area. Whereas drains are designed to dispose of
the water from the field which may create water logging in the field. Soil and crop characteristics
represent basic quantities in the compatibility of the canal hydraulic parameters.
The layout of the network distribution depends on the slope and Shape of the land, which is
suitable to irrigation practices. The network system or main canal, secondary canals and tertiary
canals are to be designed properly by providing sufficient canal area. Based on the topography of
the command area, the main canal, secondary, and field canals run along the contour; while
tertiary canals are aligned across the contour. The type and method of irrigation is surface and
furrow irrigation respectively.
Canal alignment is straight as for as possible.
The average slope of a main canal is flatter than the average slope of a branch canals.
The command area of the project is beyond Ashiro River between 2415m and 2459m amsl,
contour elevations. Contour canals are suitable for hilly terrains to avoid excessive slope, cutting
and filling.
The main canal starts from the diversion weir. All field canals are supplied by tertiary canals;
which are generally governed by the orientation and direction of field, and the method of
irrigation.
5.2 Canal capacity
The aim of this study is the determination of the quantity of water required for the growth of
plant, which serve as the basic for the design of irrigation canal and stuctures.The determination
of irrigation water requirement therefore need the study and analysis of cropping pattern ,
estimation of crop water requirement , estimation of effective rainfall and estimation of
irrigation efficiency.
P a g e 120
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
P a g e 121
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
the easiness of operation and management
the slope of cultivable land
minimum number of tertiary canals
the irrigation of more area in gross command
minimum drainage and canal infrastructures
And a canal should be aligned on a watershed or ridge as far as possible because it
ensures irrigation on both sides of the canal and avoids cross drainage works.
5.4 Canal design
5.4.1 General
To take away water from the canal headwork such as weir, barrage, storage reservoir or storage
dam to the field; a well-designed distribution system consisting of a network of canals is
required.
Based on the water requirements of crops on the area to be irrigated, the entire system of main
canal, secondary canal, tertiary canal and field distributaries should be designed properly. The
canals are designed for a certain realistic value of peak discharge that must pass through them, to
provide sufficient irrigation water to the command area. Therefore, the design of canal is based
on the irrigation water requirement. The designed canal is unlined; because in Ashiro irrigation
project area, there is an impermeable soil and has hard foundation. The canals passing through
such area have no tendency to shift their courses and they do not cause much problem for
designing irrigation structure.
5.4.2 Design parameters
5.4.2.1. Duty
Duty is the capacity of water to irrigate the land. It is the ratio of the area of the land to be
irrigated to the quantity of water required. The field water supply of the project estimated by
using “crop Wat 8”. The duty of canal is 0.5l/s/ha.
5.4.2.2 Time factor
Time factor is the ratio of the number of days the canal actually runs during a watering period to
the total number of days of the watering. Take 12hr working time out of the 24 hr of the day.
P a g e 122
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
5.4.2.3 Slope
Slope is fixed by the design discharge and silt factor or velocity. A steeper slope with maximum
permissible velocity will be more economical, but the FSL will be lower. Additionally the design
slope is flatter than the natural available slope. Fall is provided to adjust the slope, but the
number of falls must be of minimum.
5.4.2.4 Side slope selection
Canal side slope depends on the material in which it is constructed and banks are made. Based on
whether the canal is in cut or in fill, and as per the soil types, the canals are designed as steep as
possible in order to limit excavation volumes and reduce excavation and disposal costs as well as
simplicity of construction. For erodible soils, the slopes are checked against the criterion of
maximum allowable velocity, or by the principle of attractive force. Other factors considered in
canal slope selection include, inter alignment, method of construction, depth of canal and level of
ground water table. Side slopes through cuts in rock and lined canals can be vertical.
The slope to be given to the sides depends on the angle of the internal friction for a particular soil
.in other word the slope adopted should also be remembered that the side slopes adopted in
cutting and filling are not the same.
P a g e 123
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Table: 5.1 Recommended Side Slope of Canals
Soil type Side slope (Horizontal : vertical )
Cut Fill
The recommended slop for main & secondary canal is 1V: 1.5H or 1V: 2H.
For our case use side slope 1V: 1.5H (clay soil)
5.4.2.5 Side slope for lined canal
Based on soil type that is found in the irrigable area i.e. Clay soil the permissible velocity lies
from 0.41m/s to 1.67m/s.
The canal can be made fairly water tight by limiting the canal section with various materials. In
ordinary lined canal, the steepest satisfactory side slope from construction point of view is
ranging from 1.25:1 to 1.5:1
5.4.2.6. Longitudinal slope
Canal bed slope depends up on the slope of the natural ground for economy in the earth work and
bed slope should be the same as the ground slope as in the case of contour canal because it
affects the velocity of flow.
P a g e 124
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Take longitudinal slope from below table between the ranges. But for lined main canal
1/800 to 1/1000.
S=0.0035 for unlined canal and 0.00125 for lined canal.
[Arora 2003]
P a g e 125
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Table: 5.5 Permissible velocity (lined canal)
S.no Type of lining Maximum permissible velocity (m/sec)
1 Boulder lining 1.5
2 Brick tile lining 1.8
3 Cement concrete lining 2.7
4 Masonry 2.0
Wood 0.013-0.165
Steel 0.0125-0.018
Concrete 0.013-0.018
Masonry 0.02-0.036
Earth 0.0225-0.035
P a g e 126
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Comparison is made with USBR recommendation. Freeboard for main, secondary and tertiary
canals is varying from 0.2 to 0.35m.
5.5 Main canal design
One main canal off takes from the intake point of the head works. The Ashiro Main canal is
designed to supply water to sc1 and sc2 canals simultaneously.
Design of lined rectangular canal
Economical lined Rectangular section criteria;
Available data efficient section
Q=0.0549m3/sec R=
n=0.028 (masonry) B = 2y
S=0.00125 (lined canal)
Side slop 1:1.5
Using manning equation
⁄ ⁄
⁄
⁄
( )
⁄ ⁄
= 0.33m/s<2 m/s , ok !
Fb=0.2+0.15Q1/3
Fb=0.25m
P a g e 127
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
FB
D Y
Sample calculation:-
V= =
Where:
B = the bottom width of the main canal
D = the depth of water in the main canal
m = the side slope of the drainage canal
R = the mean hydraulic radius of main canal
A = the area of main canal section.
P = the wetted perimeter of the canal section
P a g e 128
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
S = the bed slope of the canal
Q=9ha×0.0005 m3/s/ha =0.0045m3/s
Fb = 0.2 + 0.15 = 0.36m
Ss = 1V:1.5H
V Permissible = (0.41-1.67)m/sec
S =0.0035 (Unlined canal) (0.0225 -0.035)
For most Economic Section R =
A = By + m , Assume B = 0.4m
A = 0.4y + 1.5
n = earthen canal (0.0225 – 0.035) = 0.035
0.0045 × 0.035 = (0.4y +1.5 ) ( )^2/3 × (0.0035)^1/2
= (0.4y + 1.5 )
P = 0.609m, R= = = 0.0435m
B
Figure 5.2 Cross-section of trapezoidal main canal
P a g e 129
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Duty
V
Area (m3/s/ha R= Fb(m
3 2
Canal (ha) ) Q (m /s) A(m ) P(m) A/P (m/sec) Y(m) B(m) )
TC1-
1 3.5 0.0005 0.00175 0.0144 0.444 0.03 0.42 0.040 0.30 0.22
TC1-
2 3 0.0005 0.0015 0.0124 0.419 0.0295 0.45 0.036 0.29 0.20
C1-3 2.5 0.0005 0.00125 0.0112 0.403 0.028 0.45 0.034 0.28 0.22
TC2-
1 3.5 0.0005 0.00175 0.0134 0.399 0.034 0.45 0.044 0.24 0.22
TC2-
2 2.5 0.0005 0.00125 0.0102 0.353 0.0288 0.45 0.037 0.22 0.22
Sample calculation
TC1-1:- Trapezoidal earthen canal
A = B×y+ m×y2
P = B + 2y√
V= =
Where:
B = the bottom width of the main canal
D = the depth of water in the main canal
m = the side slope of the drainage canal
P a g e 130
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
R = the mean hydraulic radius of main canal
A = the area of main canal section.
P = the wetted perimeter of the canal section
S = the bed slope of the canal
Q=3.5ha×0.0005 m3/s/ha =0.00175m3/s
Fb = 0.2 + 0.15 = 0.22
Ss = 1V:1.5H
V Permissible = (0.41-1.67)m/sec
S =0.0035 (Unlined canal) ( 0.0225 -0.035)
For most Economic Section R =
A = By + m , Assume B = 0.3m
A = 0.3y + 1.5
n = earthen canal (0.0225 – 0.035) = 0.035
0.00175 × 0.035 = (0.3y +1.5 ) ( )^2/3 × (0.0035)^1/2
= (0.3y + 1.5 )
P = 0.444m, R= = = 0.03m
V = ×A = × 0.0144 × (0.03)^2/3
P a g e 131
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
box. For this irrigation project division box is proposed to divide water from the secondary canal
to tertiary canals.
Using broad crested weir formula, Q= CLH3/2
C = coefficient of discharge, C= 1.7
Q1=1.71×L1×H1^3/2 and Q2=1.71×L2×H2^3/2
Since = H1 = H2
= , L1 = Lo ( )
= , L2 =L1 ( )
Qd Lo L1 Q1
L2
Q2
Lo =
L1 = Lo × )
L2 =Lo×( )
P a g e 132
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
D = Depth of Division Box
Bo = Width of the incoming canal
Ho = Depth of the incoming canal
Q = discharge of incoming canal,
P a g e 133
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Q = C×L×
Where Q=discharge over rectangular sill
C=coefficient discharge=1.7
L=effective length
Lo = = = 0.187m
L2= ×0.162=0.01m
F1 = where f =
, where
P a g e 134
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
n= roughness coefficient = 0.014
(Dp)=0.50m
Hence, using 100% full pipe of diameter 0.50m,
The intake loss, h is calculated as follows.
Therefore, h =
= = 0.0041m
P a g e 135
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
A steel bar mesh is used at the in let of the pipe to protect debris and other foreign materials.
5.10 Design of drop structure
Drops are provided at places where the ground slope is steeper than the canal bed slopes. For
easy of construction and operation all drop heights with in the scheme are made standard. They
are all vertical drops with standard dimensions. In some cases they are designed with raised crest
level so as to minimize the effect of the approaching velocities.
Drop structures are flow control structures that are installed in canals when the natural land slope
is too steep. The drops allow reducing the canal bed slopes to convey water without causing
erosive velocities. For this, the canal is divided into different reaches over its length; each reach
follows the design canal gradient. When the bottom level of the canal becomes too high
compared to the natural ground level, drop structures are installed. Vertical drops are used for the
dissipation of up to 1.5 m head for unlined canals and up to 2 m head for lined canals. If it‟s
greater than 1.5m for earthen canal chute is design.
An important aspect of a drop is the stilling basin, required to avoid downstream erosion.
A drop of 0.75m, 0.5m, and 0.25m, designed for Ashiro SSIP. Drops are also used for off take
position adjustment.
a. Critical hydraulic
1. Design discharge, Q (m3/s)
2. Height of drop, h (m)
3. Width of drop, bc =
Where
d = water depth of the canal, m
4. Critical discharge, q = Q/bc
Sample design 0.75m high drop on Sc1, at a station 0+030m is then made as a sample.
P a g e 136
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Only vertical type drop is selected throughout the whole canals length.
Sample Design of Drops
Canal: Sc1 (0+030m), Drop height, h = 0.75m
Hydraulic elements of the canal
Q= 0.0045m3/s, V= 0.42m/s, b= 0.40m, d=0.058m
√ √
Basin Width, B = = =0.12m
P a g e 137
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Table: 5.8 Drop structure tabulated form
Can Chain Drop Q(m3/s B(Can d(flo V(m/se Basin Basin L1and a dc Q bc
al age ec) al) w) c) width( length( L2
Heig
B) L)
ht
30.00 0.75 0.0045 0.4 0.058 0.42 0.12 2.51 1.3 0.15 0.0 0.0 0.2
32 18 4
40.00 0.75 0.0045 0.4 0.058 0.42 0.12 2.51 1.3 0.15 0.0 0.0 0.2
Sc1 32 18 4
70.00 0.75 0.0045 0.4 0.058 0.42 0.12 2.51 1.3 0.15 0.0 0.0 0.2
32 18 4
140.00 0.75 0.0045 0.4 0.058 0.42 0.12 2.51 1.3 0.15 0.0 0.0 0.2
32 18 4
150.00 0.75 0.0045 0.4 0.058 0.42 0.12 2.502 1.3 0.15 0.0 0.0 0.2
32 18 4
170.00 0.25 0.0045 0.4 0.058 0.42 0.12 2.501 1.3 0.15 0.0 0.0 0.2
32 18 4
10.00 0.5 0.003 0.32 0.051 0.41 0.1 2.5 1.28 0.15 0.0 0.0 0.1
3 16 9
Sc2 20.00 0.5 0.003 0.32 0.051 0.41 0.1 2.5 1.28 0.15 0.0 0.0 0.1
3 16 9
P a g e 138
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
will be 10L/sec-2L/sec=8L/sec.
Qdesign=54.94L/sec.
Therefore, Qdesign>Qbaseflow in this case better to provide pond (night storage reservoir).
Irrigation hour = 12hr=24hr-12hr=12hr the water will be stored in the night storage.
5.11.1 Determination of pond capacity
Irrigable land for Ashiro = 15 ha
Water duty = 0.5l/s/ha
Irrigation hour = 12 hrs
Capacity per 12 hrs = 15hax0.5lit/s/ha x12hrx3600 s/hr x 1m3/1000 lit
= 324m3
Adding 35% for dead storage (seepage & siltation)
Total demand per 12 hrs = 1.35x324 m3 = 437.4m3
Inflow capacity per 12 hrs = 0.0549m3/s x12 hrs x3600 s/hrs
= 2373.4m3.
The total water depth in the pond is taken to be 1.75m (assume)
Inner slope 1V:2H
Outer slope 1V:1.5H
A=1.3125+1.75+1.75B
A=3.063+1.75B
V=A*D= (2.3+3.063+1.75B)* 1.75
324= (2.3+3.063+1.75)*1.75
B=bottom width=26m
T=top width=26+1.5+2=29.5=30m
P a g e 139
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
= 0.5V2 +
0.0075 = 0.8.A √
A = 0.0095m2
D = 0.109m (pipe diameter)
Secondary canal (T0-2),
Q=9ha*0.5l/sec/ha=4.5l/sec=0.0045m3/sec.
h=driving head=0.05m
Q = Cd* A √
0.0045 = 0.8.A √
A = 0.00568m2
D = 0.085m (pipe diameter)
Tertiary canal (T0-3),
Q=3.5ha*0.5l/sec/ha=1.75l/sec=0.00175m3/sec.
h=driving head=0.05m
Q = Cd* A √
0.00175 = 0.8.A √
P a g e 140
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
A = 0.0022m2
D = 0.053m (pipe diameter)
5.13 IRRIGATION SYSTEM
5.13.1 General
Irrigation water can be conveyed, distributed and applied to the fields by either or a combination
of the two methods:
Gravity system
Pressurized system
Gravity conveyance and distribution systems comprise of open canal systems and canal
structures for controlling and regulating the flow. Water flows by gravity from the headwork to
the required off-take point and be distributed again by gravity. Even the field application of
water to the crops is by gravity in which the water flows on the surface of the soil where it
infiltrates.
In pressurized irrigation systems, water is conveyed and distributed either on the whole or part of
the system by closed conduit (pipelines) under pressure. In several irrigation systems around the
world, a combination of gravity and pressurized conveyance and distribution system can be used.
The water might be conveyed in some convenient part of the system by gravity and when it is
required to lift it to a higher canal, a pump can be used to pump it to the higher elevation.
Similarly, the field application of the water to the crops can also be done under pressure with
pressurized system such as sprinkler and drip systems or a combination of surface and
pressurized systems.
5.13.2 Selection of Irrigation Methods
The selection of irrigation methods depends on a number of factors such as:-
topography
soil type
water quality and water availability
Affordability etc.
The choice of irrigation method for ASSIP is surface irrigation method due to many reasons in
its favor; the more important ones are summarized as below:-
P a g e 141
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Capital cost than other methods which can manage with locally available materials, but for
pressurized irrigation technique, the materials are to be imported from the five main surface
irrigation methods, furrow and basin irrigation method is proposed under Samira irrigation
project.
Surface irrigation suitable for an area under study, being within the Margin of slop for any of
surface irrigation methods
It is a proven technique currently used in Ethiopia and also in the Study area.
The proposed crop such as onion, potato, Head cabbage, are used to be cultivated in the project
area also suitable for surface irrigation
5.13.3 Surface irrigation method
In a surface irrigation event has four distinct hydraulic phases can be discerned:
Advance phase: the time interval between the start of irrigation and arrival of the advancing
(wetting) front at the lower end of the field.
Ponding (wetting storage or continuing) phase: the irrigation time extending between the
end of advance and inflow cut-off. The term “Wetting” phase is usually used for furrow and
border where tail water runoff can occur, whereas ponding is the preferred term for basin
irrigation (no tail water runoff)
Depletion (vertical recession) phase: is the time interval between supply cut- off and the time
that water dries up at the inlet boundary.
Recession (horizontal recession) phase: the time required for the water to recede from all
points in the channel, starting from the end of the depletion phase. The time difference at each
measuring station between the clock time or cumulative time for advance and recession is the
opportunity time, Infiltration to occur.
Surface irrigation methods applied in the forms of:-
Furrow irrigation
Basin irrigation
Border irrigation
Furrow irrigation
Furrows are narrow ditches dug on the field between the rows of crops. The water runs along
them as it moves down the slope of the field.
P a g e 142
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
The water flows from the field ditch into the furrows by opening up the bank or dyke of the ditch
or by means of siphons.
Border irrigation
In border irrigation, the field to be irrigated is divided into strips (also called borders or
Border strips) by parallel dykes or border ridges. The water is released from the field ditch onto
the border through gate structures called outlets.
Basin irrigation
Basins are horizontal, flat plots of land, surrounded by small dykes or bunds. The banks prevent
the water from flowing to the surrounding fields. Basin irrigation is commonly used for rice
grown on flat lands or in terraces on hillsides. Trees can also be grown in basins, where one tree
usually is located in the center of a small basin.
In case of Ashiro irrigation project farrow irrigation is used because of the following reasons:-
Furrow irrigation is suitable for many crops
The method reduces labor requirements in land preparation and irrigation so it is economical.
Uniform flat or gentle slopes are preferred for furrow irrigation which should not exceed
0.5%.
Soils that crust easily are especially suited to furrow irrigation because the water does not
flow over the ridge, and so the soil in which the plants grow remains friable.
In clay soils, the infiltration rate is much lower than in sandy soils, so Furrows can be
recommended for clayey than for sandy soils.
Design consideration of Furrow
Furrow spacing
Furrow slope
Furrow length
Furrow stream
Furrow spacing
Furrow can be spaced to fit the crops grown and the type of machines used for planting
and cultivation. Crop like potatoes, maize, cotton and sugarcane are planted 60 - 90cm apart
spacing between all furrows. Furrows should be spaced close enough to ensure that water
spreads to sides into ridge and the root zone of the crop to replenish the soil moisture uniformly.
P a g e 143
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Table: 5.9 Furrow infiltration and inflow rate
Soil Infiltration Furrow inflow (l/s/1000m
texture rate(mm/hr) length)
Clay 1-5 0.03-0.15
Clay 5-10 0.15-0.3
loam
Sources
Furrow slope
The slope or grade of the furrow is important because it controls the speed at which water flows
down the furrow.
A minimum furrow grade of 0.05% is needed to ensure surface drainage. For Clay to clay loam
soil the recommended slope is 0.05%-0.2%. (A.M.Michael, 1978) slope recommended for border
apply to furrow)
In our case we adopted that the furrow slope 0.2% for Ashiro irrigation project.
As the furrow grade increases, the range of infiltration slows down and the side spread of
water into the crop ridge decreases, so that wastage may occur at the end of the furrow.
Furrow Length
The furrows length also depends on the gradients of different farms15ha irrigated land is divided
by 32m, 48m,and 64m length of furrow and 55 furrow is equal to 1ha.
The optimum length of the furrow is usually the longest furrow that can be safely and efficiently
be irrigated. Long furrow are an advantage inter cultivation.
The optimum length of the furrows is usually the longest furrow that can be efficiently
irrigated. It may be as short as 45m on soils which take up water rapidly or as much as 300m or
longer on the soils with low infiltration rate. The length of the furrow may often be limited by
the size and shape of the field.
P a g e 144
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Furrow Stream
The size of the furrow stream is the one factor which can be varied after the furrow irrigation
system has been installed. The size of the stream usually varies from 0.5 to 2.5lit/se.
To obtain the most uniform irrigation, the largest stream of water that will not cause erosion
is used in each furrow at the beginning of irrigation. Its purpose is to wet the entire length of
each furrow as quickly as possible, thus enabling the soil to absorb water evenly through the
entire furrow length.
The maximum size of irrigation stream that can be used at the start of the irrigation limited by
consideration of erosion in furrows, over topping of furrows and prevention of run- off at the
down steam end.
The maximum non-erosive flow rate is estimated by the following empirical equation.
Qm = (Michael, 1997)
P a g e 145
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Time of cut off (Tco): Tco reflects an irrigation management decision made by the former and
designer. It should be an adequate length of time to infiltrate a satisfactory depth of water over
the length of the furrow without causing excessive deep percolation
P a g e 146
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
CHAPTER 6
6. DRAINAGE
6.1 General
Drainage is the term applied to systems for dealing with excess water that describe all the
processes where by surplus water is removed from the land. It includes both internal drainage of
soil and the collection and dispersal of surface runoff.
By its nature, irrigation creates periodically saturation condition of upper layers of soil formation
over a long period where intensive irrigation is practiced; even deep soil layers tend to become
saturated and consequently underground water table rises in absence of adequate drainage
facilities. The knowledge of drainage engineering is very essential to solve this problem.
Waterlogged land is of little use; however, it can be utilized after providing proper drainage
arrangement. Usually in undulating country, the surface slopes are sufficient to carry off this
surplus water into the ditches and stream without any engineering construction. Low lying flat
areas are usually invariably near or below the flood level of the river. In order to prevent the area
from flooding the river must be trained; it is usually done by constructing of embankments
6.2 Requirement of drainage
Irrigation system design without drainage is incomplete. Soil has the capacity of holding water,
which enables plant to grow by drawing water and nutrient in solution in the water from the soils
through their root system. The structure of the soil consists of framework of solid materials
enclosed by complex system of pore and channel that provide a space within the soil for air and
water.
When all this space is filled with water, the soil is termed as saturated. A soil can only remain in
a saturated condition, if it is below water table and cannot drain truly. It may be temporarily
saturated during and immediately after irrigation or heavy rainfall. Saturation capacity is
maximum amount of water or moisture that a soil can hold at saturation, it depends on the
volume of its pore space.
In order for plant to grow, apart from availability of water, air also is needed, and hence soil
should be permanently saturated with water. A good soil, therefore, has internal drainage
characteristic, which means water must be able to move fairly and easily through the soil, that
excess water can remove when required.
P a g e 147
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
So far irrigated lands are concerned the following benefits may be achieved from adequate
drainage scheme.
Those are:
1. It facilitates early ploughing and in turn early sowing crop
2. It actually extends the crop root zone. Thus, more soil moisture is made available crop
growth
3. It maintains higher soil temperature. Soils that are water logged take more time for
warming up. The reason is, water logged soil require more heat to raise the temperature of a
given of water by 1°c than to raise the temperature of value of air by 1°c.
4. It helps in maintaining proper area of upper soil. The aeration and higher temperature
increased the bacteriological activities in the soil.
5. In the processes of draining the land, harmful salts are leached out
6. It also improves the sanitary conditions and makes surrounding clean
6.3 Selections of drainage systems
Drainage may be artificial or natural. Drains are termed artificial when they are constructed after
proper consideration of existing conditions and function to be served. Artificial drains are
generally constructed to dispose of surplus water quickly, before it gets absorbed deep into the
soil. Drainage can be classified into two main systems. Those are Surface drainage system and
subsurface drainage system
6.3.1 Surface drainage systems
Surface drainage problem occur in nearly flat area, uneven land surface with depression or ridges
preventing natural runoff and in areas without outlet. Soils with low infiltration rates are
susceptible to surface drainage problem. Surface drainage is intended for safe removal of excess
water from the land surface through land shaping and canal construction. Function of the system
may be considered as:
Collection systems
conveying systems
Outlet system
Water from the individual field is collected and is then removed through a system to the outlet.
Generally, surface drainage is required for
P a g e 148
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
1. The removal of storm rainfall where the subsurface drainage is not economically feasible
2. The collection and disposal of surface irrigation runoff
3. The collection and disposal of drainage in deltaic area
6.3.2 Subsurface drainage system
Subsurface drainages are required for soils with poor internal drainage and a high water table.
This type of drain does not hinder movement in the field but they have high initial investment
cost.
However, here in our case we have recommended to use the surface drainage system because of
the fact that our project is small scale and low cost of installation.
P a g e 149
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
It maintained in good condition easily
6.6.1 Capacity of drainage
Drainage should be designed to carry the maximum anticipated flood efficiently.
6.6.2 Permissible velocity
The velocity of the drain water should be such that the ditch is kept clean by the flow. In other
words, ditch should be self-cleaning for the design velocity. It should also be seen that no
scouring of bed and side scour. The maximum value of mean velocity must be safe against
erosion. Based on soil type, which found in the irrigable area for clay permissible velocity
1.22m/sec.
Table: 6.2 Maximum side slope for drain canals for different soil type
Soil type Side slope (H:V)
Sand, silt clay 3:1
Sand, clay, silt loam 1.5:1
Fine clay, clay loam 1:2
P a g e 150
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Table: 6.3 possible values of Manning coefficient for different value of Hydraulic
Hydraulic Radius N
<2.5 0.04-0.045
2.5-4 0.035-0.04
4-5 0.03-0.35
>5 0.025-0.03
P a g e 151
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
For Ashiro irrigable area, MAR = 463.356mm/year.
6.7.2 Drainage coefficient (DC)
The drainage coefficient uses to get the amount of water that must be removed from soil surface
in order to have sustainable agriculture. It depends, on depth of irrigations, method of irrigation,
leaching requirement and soil characteristics. There are different methods for estimating drainage
coefficient. Those are:
The value of Dc can be obtained by different empirical method.
1.Hudson(1975)
He suggested that:
I.For MAR 1000mm; Dc=MAR/100 mm/day
II.For MAR 1000mm; Dc=10 mm/day
Therefore in our case MAR=463.356mm/yr which is less than 1000mm
So use the formula DC=10 mm/day
2. 1% of MAR
DC=0.01×463.356, DC=4.63
P a g e 152
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
They are designed with trapezoidal cross-section with 1.5:1 (H:V) side slopes. The hydraulic
designs of the drainage channels are normally designed using the Manning equation.
Sample calculation DC1 (Drain canal).
Available data
Area to be drained A=3.5ha
Drainage coefficient, DC = 10mm/day
Bed slope, S=0.001 (assume)
Capacity of the drain, Qd= Dc*A= 10mm/day*3.5ha
For the most efficient cross section and for minimum volume of excavation the bottom width is
determined by:-
B= 2Dtan (ϴ/2)
B = bottom width, m
D = depth of flow of water
ϴ = Angle between the side and the horizontal
= tan-1(1/1.5) = 33.69ᴼ
In this case, D= 0.04m
Therefore, v = vp =1.22m/sec.
P a g e 153
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
The discharge of flow, Manning:
Q=A×V
Q=0.0034m2×1.22m/sec
Q=0.0043m3/sec˃0.0041m3/sec, (ok!)
Free board of tertiary drain
The top of canal banks has to be maintained higher than the level to allow for waves and possible
fluctuation in supply. The vertical distance between the top of drainage canal banks and the full
supply level of drainage canal, known as free board. FB= 0.15m (FB= 10 to 20cm)
For the trapezoidal drainage canal
B = 0.0241m
D = 0.04m
DT = D + FB = 0.04m + 0.15m = 0.19m
Where: DT = the total depth of canal including free board.
Area
Drainage (ha) Q V (m/s) D B A P R FB
DC1-1 3.5 0.00175 1.22 0.04 0.0241 0.00340 0.168 0.02 0.15
DC1-2 3 0.0015 1.22 0.036 0.0238 0.00273 0.154 0.0177 0.15
DC1-3 2.5 0.00125 1.22 0.034 0.0225 0.00245 0.145 0.0168 0.15
DC2-1 3.5 0.00175 1.22 0.044 0.0292 0.00418 0.188 0.0222 0.15
DC2-2 2.5 0.00125 1.22 0.037 0.0245 0.00296 0.158 0.0187 0.15
P a g e 154
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
For the most efficient cross section and for minimum volume of excavation the bottom width is
determined by:-
B= 2Dtan (ϴ/2)
B = bottom width, m
D = depth of flow of water
ϴ = Angle between the side and the horizontal
= tan-1(1/1.5) = 33.69ᴼ
In this case, D= 0.058m
P a g e 155
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
DT = D + FB = 0.058m + 0.15m = 0.208m
Where: DT=the total depth of canal including free board.
DC-2 (Drain canal).
Available data
Area to be drained A=6ha
Drainage coefficient, DC = 10mm/day
Bed slope, S=0.001 (assume)
Capacity of the drain, Qd= Dc×A= 10mm/day×3.5ha
For the most efficient cross section and for minimum volume of excavation the bottom width is
determined by:-
B= 2Dtan (ϴ/2)
B = bottom width, m
D = depth of flow of water
ϴ = Angle between the side and the horizontal
= tan-1(1/1.5) = 33.69ᴼ
In this case, D= 0.051m
Therefore, v=vp=1.22m/sec.
The discharge of flow, Manning:
Q=A×V
P a g e 156
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Q=0.0055m2×1.22m/sec
Free board of tertiary drain
The top of canal banks has to be maintained higher than the level to allow for waves and possible
fluctuation in supply. The vertical distance between the top of drainage canal banks and the full
supply level of drainage canal, known as free board. FB= 0.15m (FB= 10 to 20cm)
For the trapezoidal drainage canal
B = 0.035m
D = 0.058m
DT = D + FB = 0.058m + 0.15m = 0.208m
Where: DT=the total depth of canal including free board.
Since, Q = 0.0174m3/sec
S =0.001
For trapezoidal drainage canal:
-The area of the drain section is given by
A = BD + m --------------------------- (2)
-Wetted perimeter of the drain section
P a g e 157
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
R= = √
----------------------------- (4)
However, for efficient and economical design of trapezoidal drainage canal the following
equation is true.
R= -------------------------------------------- (5)
Equating eq. (4) and (5) we get the following relation between D & B.
Then, R = = √
=
= ,Since m =1.5
R= = √
= = 0.5D
P a g e 158
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
The top of canal banks has to be maintained higher than the level to allow for waves and possible
fluctuation in supply. The vertical distance between the top of drainage canal banks and the full
supply level of drainage canal, known as free board. For our case, take a free board of 0.2m.
For the trapezoidal drainage canal
B = 0.14m
D = 0.23m
DT = D + FB = 0.23m + 0.2m = 0.43m
Where: DT=the total depth of canal including free board
P a g e 159
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
CHAPTER SEVEN
7. Economic Analysis
7.1 General
A project is economically feasible, if the total benefit which results from the project exceeds the
total cost spent to implement the project. That mean benefit-cost ratio at the project should be
greater than unity.
A widely accepted method is the construction of a ratio of expected project benefit to expected
project costs on a common time basis. Costs include these necessary to implement a project, such
as investment costs operation and maintenance expenses, other direct cost and any associated
costs that are needed to make the products or service of the project available for use or sale.
7.2 Cost Evaluation
Before economies of an engineering project can be evaluated, it is necessary to reasonably
estimate the various cost and revenue components that describe the project .So, the costs of all
civil works have been determined from the quantities of each and every component of structures.
7.3. Material
7.3.1. Site clearance-
Prior to starting earth work on by pass canal& weir, main canal etc the area under consideration
shall be free from trees, bushes, insitu stones.Cost for site excavation for 1m2 of site excavation
the cost will be 12 birr.
7.3.2. Excavation
This includes reworked sediments and Fractured and jointed biotitic and boulders. It can be
excavated by means of sledgehammers, wedges and miners bars.
- Weir – before earth work (foundation excavation) of weir is started, it is better to finish the
weir before rain coming.
The cost of excavation for foundation will be 40birr/m3.
7.3.3. Concrete
Assume C-15 grade concrete used for Ashiro small scale irrigation project
Cement=140birr/bag
Sand =563birr/m3
P a g e 160
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Aggregate=500birr/m3
Water=0.27birr/m3
Assume
Sand= m3=0.465m3
3
Aggregate= =0.93m3
P a g e 161
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
P a g e 162
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
The actual volume of the stone in the
foundation wall will be =28.8-1.08=27.72m3
P a g e 163
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
conveyance of all materials,
labour charges, curing etc
Mix 20mm thick complete for 9
exposed faces of masonary
walls including racking of
joints and curing etc
Selected material fill in 10km 1.3
borrow area, spread &
compact 20cm
300mm thick cemented 1.2
stone pitching
Simple Handpicked steel 5
gates
1.6 Head work
Site clearance 400
Foundation excavation 72
Carting away excavated 50
materials
Hard rock excavation 130
Back fill with local soil 80
Masonary work for weir 133.593
proper and side walls
Concrete (1:2:4) for stiling 84.3
basin and up stream floor
Pointing (all guide wall) 16.06
Intake pipe (RCC) Installation 18
1.7 u/s flood protection
works/dyke of 2m top width
,1.5;1 slope and 100m length.
P a g e 164
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
1.11 Drop structure
Clearing up to 15 cm 8m2
Foundation excavation 6m3
Masonary work with 1:3 3m3
mortar
Plastering with 1;3 mix , 3 6m2
coats
Back fill 2m2
1.12 u/s retaining wall
Normal soil excavation 170m3
Masonary work with 1:3 200m3
mortar
Plastering with 1;3 mix , 3 180m2
coats
Concrete c-15 (1;3;6) 6.5m3
1.13 D/s retaining wall
Normal soil excavation 63m3
P a g e 165
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Table: 7.2 BILL OF QUANTITY (BOQ)
P a g e 166
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
faces of the weir &
stilling basin with
cement mortar 1:3
2.4 Gate Work
2.4.1 Simple intake gate NO 1 8,000.00 8,000,00
fixing as per drawing
2.4.2 Simple sluice gate NO 1 10,000.00 10,000.00
fixing as per drawing
2.5 U/s and D/s stone for M2 1.5 575.83 863.75
protection
SUBTOTAL 565051.69
3 CANAL
Lined Canals
3.1.1 Site clearance M2 940.00 12 11280.00
3.1.2 Trench Excavation M3 14000 40 560000.00
3.1.3 Back fill with local soil M3 823.76 111,22 91,618.59
3.14 Masonary M3 729.80 1,548.10 1,129,803.38
3.1.5 Concrete M3 92.67 150.00 13,900.50
SUBTOTAL 1806601.97
4 Teritary drain
excavation & shaping
4.1 Site clearance M2 860 24 20640.00
4.2 Trench Excavation M3 2496 60 149760.00
4.3 Back fill with local soil M3 860 60 51600.00
SUBTOTAL 222000.00
5 Pond structure
5.1 Excavation of ordinary M3 3574 92.40 330,237.60
soil
5.2 Fill and compction with M3 73 124.88 9,115.88
red clay or equivalent
material
SUBTOTAL 475,508.26
6 Access road
6.1 Site clearance M2 11244 16.80 188,899.20
6.2 Cutting and filling with Km 2 7,000 14000.00
select material to an
average depth of
0.5m,width 4 to
SUBTOTAL 202899.20
7 DIVISION BOX
P a g e 167
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
7.1 Of soil including 3 92.40 292.91
deposting the
excavated stuff as and
where directed
7.2 Including cost and 4 1,458.84 6,083.36
conveyance of all
materials, labour
charges, curing etc
7.3 Mix 20mm thick 9 143.98 1,251.19
complete for exposed
faces of masonary walls
including racking of
joints and curing etc
7.4 Selected material fill in M3 1.3 111.20 144.56
10km borrow area,
spread & compact
20cm
7.5 300mm thick cemented 1.2 281.00 328.77
stone pitching
7.6 Simple Handpicked 5 500.00 2,500.00
steel gates
SUBTOTAL 10,600.79
TOTAL 3,513,156.51
VAT(15%) 526973.47
GRAND TOTAL 4040129.98
COST PER HECTARE 269,341.99
P a g e 168
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Table: 7.3 required workers and cost paid per day (assume)
TOTAL 941,520.00
PROJECT COST = over all construction cost + human resources cost
= 3,513,156.51+ 941,520.00 = 4454676.51
Estimation of Project benefit the Purpose of Irrigation Project is to increase the crop production
in this case all the Agricultural out puts are sold for the assumed life time of the project which is
10 yrs.
Present project cost= birr
Assume that the annual operation and maintenance cost of the project cost is 15%, contingency
cost is 10% of the initial investment. i.e.
= (0.15*4454676.51+ 0.1*4454676.51)
= 1113669.13Birr
Total project cost= 4454676.51+ 3,562,183= 5568345.64 Birr
Project Benefit
Since irrigation schemes are implemented for the purpose of producing agricultural products
through the year the benefit of the project is obtained by assuming as if all the agricultural out
puts obtained are sold for the proposed project life time.
P a g e 169
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Table: 7.4 Estimation of project benefit
No crop Are yield price price inp no of labour OM total profit total
type a (qt/h (birr/ (price/ ut cost C cost (birr/h profit
(ha a) qt) ha) cost labour/ (birr/h (birr/h a) birr
) ha a) a)
1 2 3 4 5 6 7 8 9 10 11 12 13
onion 6 240 500 120000 150 30 1800 200 3500 11650 6990
0 0 00
Potato 5 120 260 31200 130 20 1600 200 3100 28100 1405
0 00
Cabba 4 160 150 24000 100 15 1200 200 2400 21600 8640
ge 0 0
SU 9259
M 00
Assume that the annual operation and maintenance cost of the project cost is 15%, contingency
cost is 10% of the initial investment. i.e.
= (0.15*925900+ 0.1*925900)
= 231475 Birr
Net benefit =925900- 231475 = 694425 Birr
P a g e 170
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
CHAPTER EIGHT
8. ENVIRONMENTAL IMPACT ASSESSMENT
8.1 INTRODUCTION
Environmental impact assessment (EIA) is one of the environmental management tools that
enable to identify and predict both positive and negative environmental impacts of a proposed
project. And EIA found ways to increase the positive impacts and avoid, minimize or put
mitigation method for the adverse impacts prior to decision-making.
Irrigation is a technology that uses the surface water to supply for crops, where there is soil
moisture stress for crop growth. It is a labour-intensive technology, which can absorb much
labour in agriculture.
Therefore, the EIA report uses the results of the environmental impact assessment like significant
impacts, project alternatives, and mitigation measures. Finally, the environmental management
plan will be formulated as a base line for environmental protection of the irrigated agriculture
that is going to be established in small scale irrigation project.
The environmental impact assessment should be an integral part of the Project detail study and
design phase of proposed irrigation project.
The construction of some infrastructures can cause negative impact to the construction areas on
natural resources, livestock and human directly or indirectly. It also can have positive impact to
the above things therefore before construction activities are under taken environmental impact
assessment should to be done.
8.2 Back Ground information
The Ashiro SSIP is found in Arsi Zone, Ganda washa in Adaba district at about 7-kms of Adaba
town.
This study is meant to ensure the protection of the environment and sustainability of the
development projects. This would help to mitigate the negative impacts that may be caused by
the newly developed irrigation project.
P a g e 171
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
P a g e 172
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Pollution of water quality
Outbreak of disease
Water logging
Loss of land
Soil erosion,
Impacts on hydrology
A. Pollution of water quality
Irrigation may contribute in various ways to the problem of water pollution. One of these is
seepage into the ground water of the nitrates that have been applied to the soil as fertilizers
sometimes up to 50%, sinks into the underground reservoir. The underground water may thus get
polluted; and if consumed by people through wells, etc it is likely to cause such as anemia, will it
ultimately affect the fishing existing in the surrounding water body.
B. Outbreak of diseases
Due to excessive application of water & due to leakage from canals the pits and depressions get
filled up with water. This stagnant pool of water act as breeding places for mosquitoes and the
region becomes malarial prone.
C. Water logging
Soil is said to be water logged when the ground water table gets connected to soil water in the
crop root zone and remains therefore the major period in the year. Negative impacts of water
logging include Reduction crop yield because of the stoppage of air circulation, Difficulty in
Ploughing, other tilling practices, Salt efflorescence, Growth aquatic weeds increase and causing
more tilling expenses.
C. Loss of land
Since the method is surface or overhead irrigation the great area is lost by aligning canal
&furrows. The main impact for the surrounding local community will be losses of grazing land,
bush land and wood land areas that comprise bushes and grasses which used to build houses.
Moreover, the communication network and social infrastructure will be affecting.
D. Soil erosion
During the clearance of trees and vegetation, capacity which consequences light surface flow
&soil erosion. At the heavy rain fall the flood flow easily facilitate soil erosion since there are no
enough trees to mitigate and reduce the flow. During the practice of the land leveling the soil is
P a g e 173
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
disaggregated and is comes structurally weak. Earth work activities for roads, civil works,
construction camps, etc. will remove and district the natural vegetation and top soil particularly
on the steeper slopes increasing the potential for erosion. Roads are important contributor to soil
erosion, primarily because they concentrate and distribute runoff as channel flow rather than a
uniform over land or subsurface flow.
E. Impacts on Hydrology
The irrigation structures have little impact on the total available water but some detrimental
effect on the distribution of water in terms of space and time. This has a significant effect on
aquatic resource, recession agriculture wild life movements and other human activities
downstream of the scheme. All these and other effects are brought about through the reduction
and flood modification.
F.Impact of the project on Human Health.
Impact rose from the concentration of people and animals associated with irrigation schemes.
Risk arises from water related diseases encouraged by the pressure of large amount of surface
water.
8.5 The Mitigation Measures
Pollution of water quality
Establishment of biological, physical & chemical water quality criteria for agricultural
water use
Improve the awareness of the community about use of fertilizers & chemical on water
quality
Proper design of sewages for agricultural water
Outbreak of diseases
Avoidance of stagnant water or slowly moving water
Filling of draining of borrow pits along canals
Water logging
Reducing inflow
Lining of the canal
Reducing of intensity of irrigation
Designing canals with lower depth to reduce seepage
P a g e 174
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Water logging
Burying pipe drains installed at low depth to reduce the water table depth.
Soil erosion
For any road construction side drains longitudes drains, culverts and appropriate angle of wet
and fill should be incorporated to combat soil erosion.
Loss of land
Allocation of financial compensation on the basses of lost income from the land and use.
P a g e 175
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Control of water pollution;
Livestock development;
Canal bank plantation;
Infrastructure for agricultural development;
Control of water logging and soil Salinization;
Establishment of environmental management unit.
8.7 Environmental Monitoring and Auditing
The environmental management unit of the project will undertake regular monitoring of the
expected impacts and the extent of mitigation activities. Moreover, the project will be open for
environmental authority to undertake its own inspection. From the monitoring point of view, the
important parameter is water quality in the project area. An attempt has been made to establish
early warning of indicators of stress on the environment. Suggested monitoring details are
outlined as follows:-
The surface water quality in surrounding water bodies needs to be monitored.
Identification of water-related diseases, sites, adequacy of local vector control and
curative measures, status of public health are some of the parameters which should be closely
monitored for fixed times in a year with the help of data maintained in the local dispensaries
or hospitals.
In order to improve Environmental impact assessment process auditing program is a must.
Auditing comes after monitoring which the predicted out comes and can be used to assess the
quality of predictions and effectiveness of mitigation measures take in the process of
mitigation impact assessment.
P a g e 176
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
CHAPTER NINE
CONCLUSIONS AND RECOMMENDATIONS
9.1 Conclusions
Based on the results of this project design the following conclusions can be drawn:
From feasibility study result the type of soils and geology characteristics of the project area is
suitable for irrigation.
For hydrological analysis of the project site, the nearby station metrological data of 10 years
of maximum annual daily rainfall of Adaba station was taken and analyzed to get maximum
or peak design flood by United States Soil Conservation Service method (USSCS).
According the agro industrial input demand of the country, Ashiro small scale Irrigation Project
is meant to enhance crop production. Therefore, head cabbage, tomato, onion are selected. Its
crop water requirement is worked out by penman monteith method using CPOPWAT VERSION
8.0 software. The duty is 0.5l/s/ha.
USDA soil conservation service method is used to calculate the effective rainfall, because it
estimates more effective rainfall for minimum total rainfall. (I.e. for high total rainfall much
of the rain is percolated to root zone).
The design of any irrigation and hydraulic structures is based on the capacity and property of
the soil and foundation.
Based on the peak discharge broad crested weir and components of head work structure were
designed and relevant dimensions provided. The critical condition has been considered for
stability analysis.
Suitable canal alignment was done and rectangular lined canal (600m start from head work) and
trapezoidal unlined canal for the remaining section is selected based on soil criteria and flow
velocity. Different components of canal structures such as drops, diversion box, etc. Were
designed.
In order to create a favorable condition for plant growth, apart from availability of water to
avoid saturation of the command face system in area, surface drainage system is designed.
The design contains lateral drain (collect irrigation water from furrow), sub collector drain
and collector drain.
P a g e 177
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
The project is expected to be best profitable for the beneficiaries since its benefit to cost ratio
is much attractive.
The environmental impact assessment for the project area is also well through-out. With the
extension of negative impacts, valuable remedial measures are proposed for each effect.
P a g e 178
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
9.2 Recommendations
To make efficient use of the project, farmers need to be supported through training and provision
of other services like inputs (fertilizers, agrochemical), extensions, credit, market etc.
To have efficient use of water and to keep the structure operational, establishment of water user‟s
association is important
For the project to give the expected services all the concerned bodies such as farmers, farmer
associations and government agencies need to manage, follow and monitor the whole activities
of the project.
Since most of the canals in the project command area are unlined, frequent maintenance or silt
removal is needed as to make the canals durable.
Design of any irrigation project need technical skills to operate. To have skilled and efficient
workers it is better to give periodical training for easily adoption of new technology systems.
P a g e 179
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
REFERENCES
1. K. SUBRAMANYA, Professor of Civil Engineering Indian Institute of Technology, Kanpur,
2004.
2. Chow V. T., Maidment D.R., and Mays L.W., 1988. Applied Hydrology. McGraw-Hill, New
York. (R., 1995)
3. Manual on study and design of irrigation structures by Debebe Lijalem and Sisay Chanie.
4. Baba R.Design of diversion weir, small scale irrigation in hot climate,weily & soon 1995
5. Garg, SK, Irrigation (Chow V.T., 1995)& hydraulics structure 12th edition, New Delhi 1995
6. FAO, Guide line for predication of crop water requirement, irrigation &drainage paper 24 and
56FAO, Rome, Italy.
7. Asawa G.L, 2005 irrigation and water resources engineering
8.Sharsrabudhe, S. (1994). Irrigation Engineering and Hydraulic structure, 6th edition. S.k.
KATARIL.
9.R.Maidment, D. (1992). Hand Book of Hydrology. McGraw Hill international book company
USA.
10. Guideline, manuals and standard Designs of small and medium scale irrigation projects in
Ethiopia (Ministry of Water Resources, July, 2002)
11. Ragunath, (1996). Hydrology: Principles, analysis, design. New Delhi: New Age
Publishers.
12. Clemmens, A. and Moden, D. 2007, Water use and productivity of irrigation systems.
Springer-Irrig Sci 25:247-261.
14. Claudio, D. J. 2009. Performance assessment of water distribution in small scale irrigation,
the case study of chokwe irrigation system in Mozambique. An MSc Thesis Presented at the
UNESCO-IHE Institute for Water Education, Delft, the Netherlands
15. Bosch, B.E., and Vaden, N. 1992. Irrigation water management training manual no 7. A joint
work of International Institute for Land Reclamation and Improvement and FAO Land and
Water Development Division. FAO, Rome.
P a g e 180
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
APPENDICES
Table.1 kn value for different sample size (Chow, 1983)
10 2.036 37 2.65
11 2.088 38 2.661
12 2.134 39 2.671
13 2.175 40 2.682
14 2.213 41 2.692
15 2.247 42 2.7
16 2.279 43 2.71
17 2.309 44 2.719
18 2.335 45 2.727
19 2.361 46 2.736
20 2.385 47 2.744
21 2.408 48 2.753
22 2.429 49 2.76
23 2.448 50 2.768
24 2.467 55 2.804
25 2.486 60 2.837
26 2.502 65 2.866
27 2.519 70 2.893
28 2.534 75 2.917
29 2.549 80 2.94
30 2.563 85 2.961
31 2.577 90 2.981
32 2.591 95 3
33 2.604 100 3.017
34 2.616 110 3.049
35 2.628 120 3.078
36 2.639 130 3.104
140 3.129
P a g e 181
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Table 3. Reduced standard deviation Sn in Gumbel's extreme value distribution, N = sample size
N 0 1 2 3 4 5 6 7 8 9
10 0.9496 0.9676 0.9833 0.9971 1.0095 1.0206 1.0316 1.0411 1.0493 1.0565
20 1.0628 1.0696 1.0754 1.0811 1.0864 1.0915 1.0961 1.1004 1.1047 1.1086
30 1.1124 1.1159 1.1193 1.1226 1.1255 1.1285 1.1313 1.1339 1.1363 1.1388
40 1.1413 1.1436 1.1458 1.1480 1.1499 1.1519 1.1538 1.1557 1.1574 1.1590
50 1.1607 1.1623 1.1638 1.1658 1.1667 1.1681 1.1696 1.1708 1.1721 1.1734
60 1.1747 1.1759 1.1770 1.1782 1.1793 1.1803 1.1814 1.1824 1.1834 1.1844
70 1.1854 1.1863 1.1873 1.1881 1.1890 1.1898 1.1906 1.1915 1.1923 1.1930
80 1.1938 1.1945 1.1953 1.1959 1.1967 1.1973 1.1980 1.1987 1.1994 1.2001
90 1.2007 1.2013 1.2020 1.2026 1.2032 1.2038 1.2044 1.2049 1.2055 1.2060
100 1.2065
P a g e 182
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
P a g e 183
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Table.4 Frequency factor for the Pearson type III distribution with negative skew coefficient
Skew Coefficient (Cs)
recurrence interval (year)
1.0101 1.0526 2 5 10 25 50 100 200 1000
percent chance(z)
99 95 50 20 10 4 2 1 0.5 0.1
0 -2.326 -1.645 0 0.842 1.282 1.751 2.054 2.326 2.576 3.09
-0.1 -2.4 -1.673 0.017 0.846 1.27 1.716 2 2.252 2.482 2.95
-0.2 -2.472 -1.7 0.033 0.85 1.258 1.68 1.945 2.178 2.388 2.81
-0.3 -2.544 -1.726 0.05 0.853 1.245 1.643 1.89 2.104 2.294 2.675
-0.4 -2.615 -1.75 0.066 0.855 1.231 1.606 1.834 2.019 2.201 2.54
-0.5 -2.686 -1.774 0.083 0.856 1.216 1.567 1.777 1.955 2.108 2.4
-0.6 -2.755 -1.797 0.099 0.857 1.2 1.528 1.72 1.88 2.016 2.275
-0.7 -2.824 -1.819 0.116 0.857 1.183 1.488 1.663 1.806 1.926 2.15
-0.8 -2.891 -1.839 0.132 0.856 1.166 1.448 1.606 1.733 1.937 2.035
-0.9 -2.957 -1.858 0.148 0.854 1.147 1.407 1.549 1.66 1.749 1.91
-1 -3.022 -1.877 0.164 0.852 1.121 1.366 1.492 1.588 1.664 1.88
-1.1 -3.087 -1.894 0.18 0.848 1.107 1.324 1.435 1.518 1.581 -
-1.2 -3.149 -1.91 0.195 0.844 1.086 1.282 1.379 1.449 1.501 -
-1.3 -3.211 -1.925 0.21 0.838 1.064 1.24 1.324 1.383 1.424 -
-1.4 -3.271 -1.938 0.225 0.832 1.041 1.198 1.27 1.318 1.351 1.465
-1.5 -3.33 -1.951 0.24 0.825 1.018 1.157 1.217 1.256 1.282 -
-1.6 -3.388 -1.962 0.254 0.817 0.994 1.116 1.66 1.197 1.216 -
-1.7 -3.444 -1.972 0.268 0.808 0.97 1.075 1.116 1.14 1.155 -
-1.8 -3.499 -1.981 0.282 0.799 0.945 1.035 1.069 1.187 1.097 1.13
-1.9 -3.553 -1.989 0.294 0.788 0.92 0.996 1.023 1.037 1.044 -
-2 -3.605 -1.996 0.307 0.777 0.895 0.959 0.98 0.99 0.995 -
-2.1 -3.656 -2.001 0.319 0.765 0.869 0.923 0.939 0.946 0.949 -
-2.2 -3.705 -2.006 0.33 0.752 0.844 0.8888 0.9 0.905 0.907 0.91
-2.3 -3.753 -2.009 0.341 0.739 0.819 0.855 0.864 0.867 0.869 -
-2.4 -3.8 -2.011 0.351 0.725 0.795 0.823 0.83 0.832 0.833 -
-2.5 -3.845 -2.012 0.36 0.711 0.771 0.793 0.798 0.799 0.8 -
-2.6 -3.889 -2.013 0.368 0.696 0.747 0.764 0.7968 0.769 0.769 -
-2.7 -3.932 -2.012 0.376 0.681 0.724 0.738 0.74 0.74 0.741 -
P a g e 184
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
Table 5. Runoff curve number for selected agricultural, suburban number for selected
agricultural, suburban (AMC II, Ia=0.2 S)
Land Description Hydrologic soil group
A B C D
Cultivated land: with out conservation 72 81 88 91
treatment 62 71 78 81
Cultivated land: with conservation treatment
Pasture or range land: poor condition 68 79 86 89
Pasture or range land: good condition 39 61 74 80
Meadow: good condition 30 58 71 78
Wood or forest land: thin stand, poor cover, 45 66 77 83
no mulch 25 55 70 77
Wood or forest land: good cover
Open space, lawn, parks, golf courses,
commentaries, etc 39 61 74 80
Good condition: grass cover on 75 % or more 49 69 79 84
of the area
Fair condition: grass cover on 50% to 75% of
the area
Commercial and business area (85 % 89 92 94 95
impervious)
Industrial districts (72 % impervious) 81 88 91 93
Residential
Average lot size Average %
impervious 77 85 90 92
1/8 acre or less 65 61 75 83 87
¼ acre 38 57 72 81 86
1/3 acre 30 54 70 80 85
½ acre 25 51 68 79 84
1 acre 20
Paved parking lots, roofs, driveways, etc 98 98 98 98
Streets and roads:
Paved with kerbs and storm sewers 98 98 98 98
Gravel 76 85 89 91
Dirt 72 82 87 89
P a g e 185
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
P a g e 186
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
P a g e 187
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
P a g e 188
ASHIRO SMALL SCALE IRRIGATION PROJECT 2017 [Year]
P a g e 189