Monthly Progress Report - 17 Dec 24

This biweekly report details the progress on the construction of Angel's Head Office in Kinshasa, covering the period until December 16, 2024. Key updates include the status of engineering works, technical submittals, and milestones for the project, with significant fabrication and delivery timelines outlined. Overall progress is tracked against a baseline schedule, indicating the project's advancement towards completion by March 2026.

Uploaded by

Imran Khan Niazi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
21 views15 pages

Monthly Progress Report - 17 Dec 24

This biweekly report details the progress on the construction of Angel's Head Office in Kinshasa, covering the period until December 16, 2024. Key updates include the status of engineering works, technical submittals, and milestones for the project, with significant fabrication and delivery timelines outlined. Overall progress is tracked against a baseline schedule, indicating the project's advancement towards completion by March 2026.

Uploaded by

Imran Khan Niazi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 15

Structure, Finishing & MEP Works on a Head Office

Building
Biweekly Report No.01

Bi-Weekly Progress Report – Dec 2024


CONSTRUCTION OF ANGEL’S HEAD OFFICE - PLOT
NO. 21.977 C / LIMETE - KINSHASA
Client

Principal Architect

Structure Engineer – Complete Project

Main Contractor

Foundation Structure Engineer

Client Nominated Sub-Contractor (PEB Works)

Client Nominated Sub-Contractor (Aluminum / Glazing Works)

Submission Date Reporting Period

17 /12 /2024 Start Till 16-Dec-24

This report may contain information that is privileged or confidential. It is intended for the sole use of the individuals to whom it is addressed.
You must not, directly or indirectly, use, disclose, distribute, print, or copy any part of this report if you are not the intended recipient.

1|Page
Structure, Finishing & MEP Works on a Head Office
Building
Biweekly Report No.01

TABLE OF CONTENTS

Page

1. PROGRAM OVERVIEW........................................................................................................................... 3

2. SUMMARY UPDATE ............................................................................................................................... 4

3. PROGRESS S-CURVE ANALYSIS ......................................................................................................... 6

4. CONSTRUCTION REPORT..................................................................................................................... 8

4.1 KEY MILESTONES ..................................................................................................................... 8

4.2 PROGRESS AND STATUS ........................................................................................................ 8

5. PROGRESS DEPICTION ...................................................................................................................... 11

6. ANNEXURES……………………………………………………………………………………………………..13

2|Page
Structure, Finishing & MEP Works on a Head Office
Building
Biweekly Report No.01

1. PROGRAM OVERVIEW

The sequence of works is built up after having much correspondence among all stake holders and
incorporating all the design changes till date. The construction sequence is being derived by the “delivery at
site dates” of Steel Structure Building supplied by Parissis and consequently drive the whole project.

Master Program (Baseline):

The baseline schedule (Master Program) is prepared based on the below milestones governing the completion
timeline of the project;

A- Remaining Engineering Works (Coordination of all Parties)

3|Page
Structure, Finishing & MEP Works on a Head Office
Building
Biweekly Report No.01

B- PEB Fabrication & Delivery Timelines (Parissis Updated Timelines)

C- Aluminum Fabrication & Delivery Timelines (Bifem’s Updated Timelines)

D- Procurement of other Civil & MEP Items (Parkland SA)

E- Mobilization & RCC Building Works (Parkland SA)

F- PEB Building Erection Works (Parissis)

4|Page
Structure, Finishing & MEP Works on a Head Office
Building
Biweekly Report No.01

G- Façade / Glazing Works (Bifem)

H- Fit-out & MEP Works (Parkland SA)

2. SUMMARY UPDATE – Till 16-Dec-24

2.1. Engineering Works Status

Engineering Works Status

Description Status Update 16/12/24 Remarks

Submitted on 10/12/24, Parissis is


Concrete Drawing Awaiting comments if any from BTA and Parissis
reviewing

Steel to Concrete Parissis is finalizing after receiving


To be submitted by Parissis
Connection of Final Concrete Drawing
Steel to Façade Parissis to finalize fabrication drawing for Hold
Bifem submitted on 11/12/24
connections Members
Atrium's façades Parissis to finalize fabrication drawing for Hold
Bifem submitted on 11/12/24
Connection Members
Parkland to finalize with Schindler and submit final
Lifts Glass Details Bifem submitted on 11/12/24
drawing

Stair ST-01 Parissis submitted to BTA Response awaited from BTA

Parissis submitted to BTA-


Stair ST-02 Response awaited from BTA
Response awaited
To be Submitted by Parissis by
Stair ST-03 Parissis to submit
today.

5|Page
Structure, Finishing & MEP Works on a Head Office
Building
Biweekly Report No.01

2.2. Technical Submittals & Approvals Status

Technical Submittals Status

Total Submitted P=Pending W=Waiting for A2=Approved A 2=Revise and AD=Additional G= Manu.
A1=Approved R=Rejected H=On Hold
Submittals To Date Submissions Approval As Noted Resubmit Detail Required Guarantee Req.
Disciplines

Nos Nos Nos Nos Nos Nos Nos Nos Nos Nos Nos

Plumbing 2
18 16 2 1 0 13 0 0 0 0

Fire Fighting 0
9 9 0 0 0 9 0 0 0 0

HVAC 0
11 11 0 0 1 10 0 0 0 0

Electrical 0
21 21 0 2 0 9 0 0 10 0

ELV 8 8 0 2 0 4 0 0 0 2 0

MEP - Total 67 65 2 5 1 45 0 2 0 12 0

CIVIL - Total 28 22 6 7 9 1 2 3 0 0 0

Over all 95 87 8 12 10 46 2 5 0 12 0

3. COMPLETION PROGRAM S CURVE – Till MAR 26

Plan %age Actual %age


100.0%
100.0%
87.8%
90.0%
80.0% 75.6%
68.1%
70.0%
60.0% 55.6%

50.0% 43.3%
40.0% 33.6%
28.5%
30.0% 24.0%
17.9%
20.0%
10.6%
10.0% 4.7%
0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.1% 0.7% 1.1%
0.0%
J-24 J-24 A-24 S-24 O-24 N-24 D-24 J-25 F-25 M-25 A-25 M-25 J-25 J-25 A-25 S-25 O-25 N-25 D-25 J-26 F-26 M-26 A-26

6|Page
Structure, Finishing & MEP Works on a Head Office
Building
Biweekly Report No.01

4. CONSTRUCTION REPORT

4.1. Key Milestones

A- PEB Fabrication and Delivery Milestones

Final approval of PEB Fabrication Drawings - 24-Dec-24

Batch 1 PEB Material Delivery at Site - 21-Mar-25

Batch 2- PEB Material Delivery at Site - 21-Apr-25

Batch 3- PEB Material Delivery at Site - 31-May-25

B- Project Execution /Interim Milestones Dates


Start of PEB Erection 21-Mar-25
Completion of PEB Erection 14-Aug-25
Start of Concrete Floorings / Fit-out Works 15-Aug-25
Start of Façade Works 20-Aug-25
Start of MEP Works 20-Aug-25
Project Completion 27-Mar-26

7|Page
Structure, Finishing & MEP Works on a Head Office
Building
Biweekly Report No.01

4.2. Progress Status

The Over all Progress based on the 3-D model is as follows;

a- Fabrication works are completed for the below highlighted sections;

PROGRESS DEPICTION
1st Building – first Floor Material Fabrication

8|Page
Structure, Finishing & MEP Works on a Head Office
Building
Biweekly Report No.01

1st Building – Second Floor Material Fabrication

9|Page
Structure, Finishing & MEP Works on a Head Office
Building
Biweekly Report No.01

1st Building – Third Floor Material Fabrication

2nd Building – first Floor Material Fabrication

10 | P a g e
Structure, Finishing & MEP Works on a Head Office
Building
Biweekly Report No.01

2nd Building – Second Floor Material Fabrication

2nd Building – Third Floor Material Fabrication

11 | P a g e
Structure, Finishing & MEP Works on a Head Office
Building
Biweekly Report No.01

2nd Building – Fourth Floor Material Fabrication

Façade Samples – Diabolo Connections with weep holes

12 | P a g e
Structure, Finishing & MEP Works on a Head Office
Building
Biweekly Report No.01

Palisade – Site Mobilization & Preparedness

13 | P a g e
Structure, Finishing & MEP Works on a Head Office
Building
Biweekly Report No.01

14 | P a g e
Structure, Finishing & MEP Works on a Head Office
Building
Biweekly Report No.01

15 | P a g e