0% found this document useful (0 votes)
40 views17 pages

Bill of Quantities for Community Centre

The document is a Bill of Quantities for the proposed Community and Worship Centre for Family Covenant Church in Epworth, detailing labor and material costs for various construction tasks. It includes sections for site clearance, foundation work, brickwork, roofing, joinery, plastering, flooring, and painting, with a grand total estimated at $100,724.13. Specialist works such as plumbing, electrical, and steel structure framework are excluded and require consultation before commencement.

Uploaded by

Prince
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
40 views17 pages

Bill of Quantities for Community Centre

The document is a Bill of Quantities for the proposed Community and Worship Centre for Family Covenant Church in Epworth, detailing labor and material costs for various construction tasks. It includes sections for site clearance, foundation work, brickwork, roofing, joinery, plastering, flooring, and painting, with a grand total estimated at $100,724.13. Specialist works such as plumbing, electrical, and steel structure framework are excluded and require consultation before commencement.

Uploaded by

Prince
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 17

BILL OF QUANTITIES

FOR
PROPOSED COMMUNITY &
WORSHIP CENTRE
FOR FAMILY COVENANT CHURCH
ON STAND NUMBER 17000,
EPWORTH
25 JULY 2024
STAND 17000
CLIENT: FCC 25 JULY 2024
EPWORTH

LABOUR ONLY BILL OF QUANTITIES


ITEMDESCRIPTION
UNIT QUANTITY RATE
BILL NO. 1

SITE CLEARANCE

A Clear site of all vegetation, including removal


and disposal of bushes, shrubs, undergrowths,
hedges, trees and stumps not exceeding
0.50metres girth and grubbing up roots and m2 650 $ 0.50
filling in holes

Setting Out m2 540 $ 0.50

FOUNDATION TRENCHES

B
Excavate for surface trenches (1.5 metres depth
x 1 metre width as standard). Engineer to
confirm depth on site and advise the contractor
on which one to use. m3 300 $ 7.00

FOOTING/ FOUNDATION CONCRETE

C In strip footings / Foundation Concrete


(350mm depth) m3 70 $ 25.00

FOUNDATION BRICKWORK

Approved Looad Bearing bricks ( minimum


compressive strength 15 Mpa) in 1:4 cement
mortar in English bond

D Half brick walls m2 35 $ 7.00

E One brick walls m2 120 $ 12.00

F Allow for Back Filling and Compaction item

SLAB / OVERSITE CONCRETE (GRADE 30MPA)

F In surface bed slab / Oversite Concrete


(200mm) m3 107 $ 25.00

FOUNDATION WORKS SUB TOTAL


STAND 17000
CLIENT: FCC 25 JULY 2024
EPWORTH

ES

AMOUNT

$ 325.00

$ 270.00

$ 2,100.00

$ 1,750.00

$ 245.00

$ 1,440.00

$ 800.00

$ 2,675.00

$ 9,605.00
BILL NO. 2

BRICKWORK TO WALL PLATE

Approved Load Bearing Bricks laid in 1:4


Cement Mortar.

A Half brick walls m2 215 $ 7.00 $ 1,505.00

B One brick wall m2 710 $ 12.00 $ 8,520.00

C Provision for Scaffolding Hire Item $ 400.00

RING BEAM & LINTEL

C Reinforced beams and Lintels m3 5 $ 25.00 $ 125.00

Total $ 10,550.00
BILL NO. 3

ROOF COVERING AND CAPENTRY

On site made roofing trusses complete with IBR


Roofing sheets with safe top nails laying & making
A goodThe trusses are to be “Gangnail” m2 555 $ 9.00 $ 4,995.00
Total $ 4,995.00
BILL NO. 4

JOINERY & IRONMONGERY

A INTERNAL & EXTERNAL SOLID CORE DOORS

Door installation by specialist and hung to pressed


steel frames.

Door size 900mm x 2100mm high no 20 $ 30.00 $ 600.00

Purposemade Double Doors Hard wood no 5 $ 80.00 $ 400.00

Total $ 1,000.00
BILL NO. 5

PLASTERING & WALL FINISHES

A INTERNAL & EXTERNAL WALL PLASTERING

12mm One coat cement/sand plaster with woodfloat


finish on to the following surfaces m2 1,850 $ 2.00 $ 3,700.00

B INTERNAL WALL SKIMMING

Render in Rhinobond and set in rhinoset, steel


trowel finish to internal m2 1,140 $ 1.50 $ 1,710.00

C Provision for Scaffolding Hire Item $ 200.00

Total $ 5,610.00
BILL NO. 7

FLOOR COVERINGS & FINISHES

FLOOR SCREEDS/ ROUGH FLOOR

A 40m Screed on floors to receive porcelain floor tiles m2 536 $ 2.00 $ 1,072.00

PORCELAIN FLOOR TILES

B
600mm x 600mmx10mm matt double loaded
Porcelain tiles with non-slip surface, or similar
approved, colour from manufacturer's standard
colour range, on adhesive to manufacturer's
recommendation

C Tiles laid on floors m2 536 $ 3.00 $ 1,608.00

Total $ 2,680.00
BILL NO. 8

PAINTING

INTERNALLY & EXTERNALLY

Prepare, stop and apply one undercoat and two


finishing coats washable external quality PVA paint
(colour from manufacturer's standard colour
range) on the following surfaces

A On External and Internal Walls m2 1,850 $ 2.00 $ 3,700.00

C Provision for Scaffolding Hire Item $ 200.00

Total $ 3,900.00
PROPOSED MATERIALS LIST

Amount
Item Description Quantity Unit Rate $ Suppliers List
$USD

1 Foundation Concrete

1.1 Supa-Set Cement 350 Bags $ 11.00 $ 3,850.00 Century Steel

River sand to SAZ J.Masedza


1.2 60 m³ $ 15.00 $ 900.00
standards approval Holdings

¾ Quarry Stones/19- J.Masedza


1.3 60 m³ $ 35.00 $ 2,100.00
25mm aggregate Holdings

Trenching Walls
2 Brickwork (mortar
mix 1:4)
Load Bricks
2.1 minimum strength 15500 No. $ 0.12 $ 1,860.00 S & M Bricks
28Mpa

230mm Rod
2.2 Reinforcement Brick 24 No. $ 2.14 $ 51.36 Halsted
force

115mm Rod
2.3 Reinforcement Brick 7 No. $ 1.99 $ 13.93 Halsted
force

2.4 Supa - Set Cement 52 Bags $ 11.00 $ 572.00 Century Steel

J.Masedza
2.5 Pit Sand 10 m3 $ 25.00 $ 250.00
Holdings
Hardcore & Sand
3
Blinding
J.Masedza
3.1 Gravel 80 m3 $ 15.00 $ 1,200.00
Holdings
250-micron black
3.2 polythene sheet (2.4m 3 rolls $ 144.00 $ 432.00 Halsted
x 100m)

Termite Poison Oil


3.3 15 5 ltrs $ 2.80 $ 42.00 Halsted
Based
PROPOSED MATERIALS LIST

J.Masedza
3.4 Riversand 30 m3 $ 15.00 $ 450.00
Holdings

4 Slab / Oversite
J.Masedza
4.1 River Sand 85 m3 $ 15.00 $ 1,275.00
Holdings
4.2 Supa-Set Cement 535 Bags $ 11.00 $ 5,885.00 Century Steel

¾ Quarry Stones/19- J.Masedza


4.3 85 m3 $ 35.00 $ 2,975.00
25mm aggregates Holdings

S193 Reinforcing
4.3 40 m3 $ 26.00 $ 1,040.00 Century Steel
Mesh (2.4 x 6m)

5 20mm Screed Floors

Supa-Set Cement
5.1 185 Bags $ 11.00 $ 2,035.00 Century Steel
PC15
J.Masedza
5.2 River Sand 35 m3 $ 15.00 $ 525.00
Holdings
6 Floor & Wall Tiling
600 x 600 Porcelain Bathroom
6.1 372 Boxes $ 15.00 $ 5,580.00
Floor Tiles @ 4 Botique

Larfage Supa fix Tile


6.2 90 Bags $ 4.80 $ 432.00 Tile and Carpet
Adhesives 20kg
6.3 Tile Grout 5kg 50 bags $ 5.00 $ 250.00 Tile and Carpet
Super Structure
7 Walls Brickwork
(mortar mix 1:4)
Common Bricks
7.1 minimum strength 91000 No. $ 0.10 $ 9,100.00 S & M Bricks
28Mpa
Damp Proof Course
7.2 8 No. $ 2.30 $ 18.40 Halsted
230mm
Damp Proof Course
7.3 3 No. $ 1.23 $ 3.69 Halsted
115mm

7.4 230mm Brick force 115 No. $ 2.14 $ 246.10 Halsted

7.5 115mm Brick force 35 No. $ 1.99 $ 69.65 Halsted

7.6 Supa-Set Cement 310 Bags $ 11.00 $ 3,410.00 Century Steel


PROPOSED MATERIALS LIST

J.Masedza
7.7 Pit Sand 55 m3 $ 25.00 $ 1,375.00
Holdings
RC Beams & Lintels
7.8
concrete
J.Masedza
7.9 River Sand 5 m3 $ 15.00 $ 75.00
Holdings
7.1 Supa-Set Cement 25 Bags $ 11.00 $ 275.00 Century Steel
¾ Quarry Stones/19- J.Masedza
7.11 5 m3 $ 35.00 $ 175.00
25mm aggregate Holdings

Deformed Bars (Y12)


7.12 65 No. $ 3.80 $ 247.00 Century Steel
x 6m per Length

Deformed Bars (Y10)


7.13 70 No. $ 2.80 $ 196.00 Century Steel
x 6m per Length

7.14 Tying Wire item $ 150.00 Century Steel

Doors and Door


8
Frames
Solid Core Flush
8.1 20 No. $ 150.00 $ 3,000.00 Halsted
Doors and Frames

8.2 Purposemade Double 5 No.


Doors Hard wood
Wall
9
Rendering/Finishes
9.1 Supa-Set Cement 320 Bags $ 11.00 $ 3,520.00 Century Steel
J.Masedza
9.2 Pit Sand 55 m3 $ 25.00 $ 1,375.00
Holdings
9.3 Rhino set 25kg 80 Bags $ 19.00 $ 1,520.00 Halsted
Dulux Rock grip
9.4 Int/Ext PVA Universal 30 No. $ 45.00 $ 1,350.00 Halsted
paint 20L
Roofing Cover (0.4mm
11
IBR)
0.4mm IBR Roofing
12.1 sheets (80 sheets @ 11 880 m $ 5.00 $ 4,400.00 DA Roof
metres each)
Turnall Holdings
12.2 Safe Top Nails 40 kg $ 4.00 $ 160.00
PROPOSED MATERIALS LIST

GRAND TOTAL $ 62,384.13


BOQ SUMMARY

LABOUR ONLY BILL OF QUANTITIES


SUMMARY

1 Foundations

2 Brickwork to wall plate

3 Roofing Installations

4 Joinery and Ironmongery

5 Aluminium Works

6 Plastering and Wall Linings

7 Pavings and floor coverings

8 Painting

9 Plumbing Works and Drain Laying

10 Electrical Installation

11 Materials cost estimated total

GRAND TOTAL (LABOUR &


MATERIALS)

*NB: BILL EXCLUDES THE FOLLOWING SPECIALIST WORKS - STEEL STRUCTURE FRAMEWORK , ROOF PORTAL
PLUMBING WORKS, ELECTRICAL WORKS AND ALUMINIUM WORKS. PRIOR TO COMMENCEMENT OF WORK
SPECIALIST SHOULD BE CONSULTED.
BOQ SUMMARY

TOTALS

US$9,605.00

US$10,550.00

US$4,995.00

US$1,000.00

US$5,610.00

US$2,680.00

US$3,900.00

US$62,384.13

US$100,724.13

XCLUDES THE FOLLOWING SPECIALIST WORKS - STEEL STRUCTURE FRAMEWORK , ROOF PORTAL FRAMES,
G WORKS, ELECTRICAL WORKS AND ALUMINIUM WORKS. PRIOR TO COMMENCEMENT OF WORK THESE
SPECIALIST SHOULD BE CONSULTED.