Technical Interview Q&A For Planning Engineer
Technical Interview Q&A For Planning Engineer
• Total Float: The amount of time an activity can be delayed without delaying the
project’s completion date.
• Free Float: The amount of time an activity can be delayed without delaying the
early start of its successor activity.
• Total Float affects the project timeline; Free Float affects only the immediate
activity chain.
📅 3. How do you perform a Time Impact Analysis
(TIA)?
Answer:
Formulas:
EVM helps evaluate project health in terms of time and cost performance.
⏳ 5. What is a critical path? How do you identify it in
Primavera P6?
Answer:
The Critical Path is the longest path through the project with zero total float. Any delay
in this path will delay the project.
In Primavera P6:
• Collect actual progress data from site (dates, quantities, resource usage).
• Update activity % complete in Primavera using Physical %, Duration %, or
Units %.
• Enter actual start/finish dates.
• Recalculate the schedule (F9).
• Compare with the baseline to identify slippages.
• Generate reports (S-Curve, lookahead, variance).
Common constraints:
• Start on/after
• Finish on/before
• Mandatory Start/Finish
• As Late As Possible
• Expected Finish
Constraints control activity timing, but excessive use can distort the critical path. Use
them only when contractually or practically required.
Prepared by:
🔍 Types of S-Curves:
📊 Uses:
Example Insight:
If the Actual curve is below the Planned, the project is behind schedule.
It helps in:
In Primavera P6, you can highlight Critical Path by applying the “Critical” filter.
1. Quantity-Based:
Example: If 50m³ of concrete poured out of planned 100m³ → 50% complete.
2. Rule of Credit (Milestone Weighting):
Example for an activity like “Column Casting”:
a. Shuttering: 25%
b. Steel Fixing: 25%
c. Concreting: 50%
3. Physical Observation:
a. Used for lump-sum works like landscaping, plastering, etc.
Choose the method that reflects actual physical completion, not just effort or time
spent.
It helps in preparing EOT claims, internal analysis, and for management escalation.
It includes:
• Activity names
• Start/End dates
• Resources required
• Constraints or prerequisites
• Dependencies (submittals, material deliveries)
Shared with site teams during weekly planning meetings to keep everyone aligned.
Tool/Concept Purpose
Primavera P6 Master scheduling, critical path, resource planning
MS Excel + Power BI Reporting, dashboards, visual analytics
S-Curve Track cumulative progress vs. plan
Gantt Chart Timeline overview of activities
Histogram Resource planning (manpower, equipment)
Critical Path Identify activities impacting project duration
Lookahead Plan Site execution roadmap for short-term control
Delay Register Log and analyze project delays systematically