DOCUMENTS & DRAWINGS REVIEW REPORT
VIVO ENERGY TANZANIA
REPLACEMENT OF PMS & AGO PIPELINES - SUPERVISION OF WORKS
Our Reference No. 21288710-A05-LOT00-CO-008-Rev 2.0
Review Date: 15.12.2021 DDR Revision No. 2.0
_A05 EXECUTION AND COMMISSIONING
The documents/drawings listed hereunder have been reviewed. Review statuses, along with comments (where applicable) below.
Discipline: LOT00_PROJECT
Document Type: TP - GTP
Doc./Dwg. Ref. No.: WCL/0002/2021‐MP 01
Doc./Dwg. Revision No: 01
Description:
Review of KOJ PRODUCT PIPELINES REPLACEMENT PROJECT – MOBILIZATION PLAN submitted by WCL ltd. on 14.12.2021 by email
Review Status:
Reviewed (no comment)
Reviewed with Comments (works may proceed subject to incorporation of comments)
Incorporate Comments & Re-submit for Review (works may not proceed)
For information only, review not required
Review:
Reviewed with Comments (works may proceed subject to incorporation of comments)
> Where are the toilet/sanitary facilities for WCL workers located?
> Indicate where the material laydown area will be located
> indicate where blasting & painting (if any) will be carried out on site
> Machinery/Cranes fitness certificate & operators licenses to be provided for review prior to use
> Indicate where the Diesel Generator set will be installed
> Ensure the site is fully secured and no risk of stealing.
> To ensure proper traffic management will be carried out (inside & outside of depot)
> Atleast 2 first aiders required based on manpower. Ensure site is equipped with adequate first aid kits
> Ensure all workers are equipped with mandatory PPEs & inducted with appropriate HSSE training by VET
> No mention of any mess room for workers.
Attachmments:
1
2
NOTE:
Review of any Drawings or Documents by the Employer or Employer's Personnel in accordance with the Contract is solely to monitor the
performance of the Contractor. Any comment on or absence of comment on a Drawing or Document (including proposed changes to any
Drawings or Documents) shall not relieve the Contractor of any of its undertakings, warranties, obligations or liabilities under or in
connection with the Contract. The Contractor is totally responsible for designing the Works in accordance with the Contract.
Reviewed by: Released by:
Initials: KAA KAA
Remarks:
Date: 15.12.2021 15.12.2021
Transmittal Ref. 21288710-A02-TRA-LI-013
FOR-30-01-02 Rev 02 - This document is the property of EKIUM AMIO. Any communication or reproduction is prohibited without prior authorisation. ©EKIUM AMIO February 2019
Page 1 of 1