VOLUME 3 OF 3 : COMMERCIAL
TENDER DOCUMENT
FOR
EMPLOYER
EL
T : 3-8777 7000
0
FAX : 03-8777 7778
MARCH 2025
PROPOSED REPLACEMENT OF JOINT SEALANT AND CONCRETE REPAIR AT APRON AREA
AND ITS ASSOCIATED WORKS AT SULTAN AHMAD SHAH AIRPORT, KUANTAN, PAHANG
TABLE OF CONTENTS
VOLUME 3 OF 3 - COMMERCIAL
reamble/1 of 13 -
P
PREAMBLES TO ALL TRADES
Preamble/13 of 13
BILL NO. 2 : JOINT SEALANT WORKS As per Bill of Quantity section,
(ALL PROVISIONAL) PROCUREHERE
ToC-VOL 3/1
PROPOSED REPLACEMENT OF JOINT SEALANT AND CONCRETE REPAIR AT APRON AREA AND ITS
ASSOCIATED WORKS AT SULTAN AHMAD SHAH AIRPORT, KUANTAN, PAHANG
IMPORTANT:
he Tenderer is advised to complete and provide the required information/documentswhichmaycontributetotheoverall
T
scoring in the tender evaluation.
DATE : ……………………………………………………….
TSC(V3)/1
SECTION A1(C)
BILLS OF QUANTITIES
PREAMBLES TO ALL TRADES
PREAMBLES TO ALL TRADES
1.0 GENERALLY
B. The description stated in the Bills are not comprehensive. Reference should be made to
the ‘Specification of Materials and Workmanship’ for details of types of materials and
quality of workmanship; to Part A : ‘General Conditions and Preliminaries’ for conditions
affecting the whole of the Works; and to these Preambles for methods of measurement
and pricing factors.
C. The Contractor’s rates and prices shall allow for compliance with the above-mentioned
documents.
D. The requirements of all items contained in this section shall apply to the whole of the
works regardless of the Trade Headings under which they have been described and are
to be taken into account when pricing these Bills of Quantities.
E. The prices entered against the items in the Bills of Quantities shall be the full inclusive
values of the finished work shown on the Drawings and/or described or implied in the
specifications and/or Bills of Quantities, and shall cover the costs for supply of materials
including cutting and waste, unloading, storage, packing, carriage and cartage, hoisting,
all labour for plant, supervision, fuel, establishment charges; duties, taxes, profit and
any other expenses and everything else indispensable necessary for the due and
proper completion of each item and fulfillment of all the Contractor’s duties and
obligations under the Contract.
F. When any item is not priced or left blank by the Contractor, the value of work under the
particular item shall be deemed to be included under other items in the Bills of
Quantities, or allowed for in the Contract Sum.
G. The Contractor shall be held to have fully understood all matters concerning the works
to be carried out under this Contract. Any query should be settled with the Architect prior
to submission of the Tender. No consideration shall be given to any query raised by the
Contractor indicating lack of comprehension of the works to be done or material to be
supplied after acceptance of the tender.
H. Unless otherwise specifically stated in the Bills, the following shall be deemed to be
included with all items :-
(b) Materials, goods and all costs in connection therewith, including unloading,
storage, packing, carriage and cartage, duties, taxes and surtaxes.
(c) Plant and all costs in connection therewith, including fuel and lubricating oil.
(d) Assembling, hoisting, fitting and fixing materials and goods in position.
Preamble/1 of 13
PREAMBLES TO ALL TRADES
I. Where items are described as ‘Supply only’, the rates and prices shall be deemed to
include (a), (b), (c) and (g) above.
J. Where items are described as ‘Fix only’, the rates and prices shall be deemed to include
(a) - (g) inclusive above, except (b).
K. Works described as curved or circular shall be deemed to include for all junctions
between straight and curved or circular work.
L. The term “approved” shall mean granting of approval by the Developer or his authorised
representative.
2.0 ABBREVIATIONS
2.1 Throughout these Bills of Quantities the following abbreviations have been used:
i) General
(g) NO - Number
Preamble/2 of 13
PREAMBLES TO ALL TRADES
(d) CM - Centimetre
(e) mm - Millimetre
(f) KG - Kilogram
(i) OZ - Ounce
3.1 The costs of providing constructional plant, equipment, vehicles and machinery for
use directly in connection with the construction and completion of the Works are to
be priced in the Preliminary Section of these Bills of Quantities. However, the costs
of operating the same are to be included in the prices and rates of the relevant
items in these Bills of Quantities.
4.1 Work described in these Bills of Quantities as curved or circular shall be deemed to
include all junctions between straight and curved or circular work.
Preamble/3 of 13
PREAMBLES TO ALL TRADES
5.1 Unless otherwise specified the cost of making good at junction between new and
old works shall be included in the prices and rates of the new works.
6.1 Prices and rates for items/works measured as Lump Sum items shall be deemed
to cover for providing everything necessary for the proper execution and
completion of the items/works according to the true intent and meaning of the
Contract Documents taken together whether the same may not be particularly
shown or described provided the same is reasonably inferred to therein.
7.1 All Items in these Bills of Quantities shall be priced by the Contractor. Should
Contractor fail to price any item, the value thereof shall be deemed to be included
in the prices and rates of other items therein.
Preamble/4 of 13
PREAMBLES TO ALL TRADES
EXCAVATOR
Method of Measurement
B. The quantities of excavation shall be measured nett and the Contractor shall allow in his
prices for increase in bulk after excavation.
C. The quantities of filling shall be measured as equal to the void to be filled and no
allowance shall be made for loss in consolidation. Thickness stated is those after
compacting.
Excavating In Rock
E. Excavating in natural rock (other than boulders not exceeding 1 cubic metre in volume
each) as defined in the Specification is measured separately.
F. To qualify for rock excavation rates, the Engineer must certify that material encountered
is to be classified as rock and measurements of the volumes excavated be agreed
between the Contractor and Engineer prior to commencement of work.
G. Rock excavation shall be measured and paid for based on the volume insitu, viz. it its
natural accuring state prior to excavating.
Contrary to SMM
H. For the purposes of site clearance, small trees are defined as not exceeding 600mm
girth at a height of 1 metre above ground.
K. Breaking up and removing buried brickwork, concrete, reinforced concrete or other hard
substances met within in excavations are not measured separately.
L. Keeping excavations free from storm and percolating water are not measured
separately.
Preamble/5 of 13
PREAMBLES TO ALL TRADES
EXCAVATOR (Cont’d )
A Unless otherwise stated, depths of excavation are measured from the general formation
levels to the bottom of the excavations.
C Quantities of each fill are measured nett (i.e. excluding volumes occupied by permanent
parts of the Works to be executed under the Contract).
(a) Excavating in whatever type of material met with excluding rock as defined in
the Specification met with on the surface or in the excavations
(b) Levelling bottoms of the excavations or grading the bottom of the excavations to
falls or cambers, and compacting the same
(c) Trimming sides of the excavations to form vertical, battering or sloping faces
(f) Backfilling of selected excavated materials into the excavations and compacting
the same by methods and in the manners as specified in the Specification.
Disposal of surplus excavated material (the balance after backfilling) shall be
measured separately
(h) Deposit, spread and level in making p levels of surplus excavated materials
within the site.
(i) Keeping the excavations free from storm, percolating or spring water by
pumping or whatever other means necessary
E Prices for trench excavations shall include for surface and basement trenches. No
distinction shall be made between surface and basement trenches.
F Prices for disposal of surplus excavated materials (the balance after backfilling) shall
include for multiple handling of the materials or transporting the material about the site as
may be necessary prior to disposal.
Preamble/6 of 13
PREAMBLES TO ALL TRADES
EXCAVATOR (Cont’d )
G Prices for earth, sand, quarry dust and the like material in filling, beds and blinding etc.
shall include for levelling surfaces of the same or grading surfaces of the same to falls or
cambers, trimming sides of the same to form vertical, battering or sloping surfaces, and
any temporary retaining boards as may be required.
H Prices for hardcore, crusher run and the like material in filling and beds etc. shall include
for hand packing the same to form vertical, battering or sloping surfaces and any
temporary retaining boards as may be required.
I Prices for hardcore, crusher run and the like material in fillings and beds etc. to receive
concrete or paving shall include for blinding the same with sand or quarry dust, and
levelling surfaces of the same or grading surfaces of the same to falls or cambers.
(k) Upholding and maintaining sides of the filling by whatever means necessary
including the use of bentonite and any special shoring or sheet piling etc. as
may be necessary but which do not form a permanent part of the Work to be
executed, but excluding any planking and strutting to be left in or any sheet
piling etc. which form a permanent part of the Work to be executed.
Excavation
(3) Excavating around and removing boulders not exceeding 1 cubic metre in
volume each.
(5) Multiple handling of excavated material and all transport and handling
charges at loading and unloading ends.
(6) Planking and strutting including any left-in including special shoring and/or
any other means of withholding he sides of the excavation and ensuring the
safety of adjoining structures.
(7) Additional excavation and backfilling for planking and strutting or to batter the
face of the excavation.
(9) Keeping all excavations free from water, mud, etc. by pumping or baling if
required, and for providing any temporary drains required.
Preamble/7 of 13
PREAMBLES TO ALL TRADES
EXCAVATOR (Cont’d )
(11) Complying with the Architect’s instructions issued from time to time to ensure
the safety of excavation and adjoining structures.
(2) Loss of materials in compaction and due to the soft nature of the ground,
sinking or erosion.
(1) All laps, joints including bonding adhesives, reinforcing or batten strips, etc.
(3) Fitting and sealing around inlets, outlets, projections and the like.
Preamble/8 of 13
PREAMBLES TO ALL TRADES
Definitions
A. In respect of demolitions and alterations the following words or expressions shall have
the meanings hereunder assigned to them :-
Making good - Making good in its fullest sense to match existing work
and through, around, into, over and up to new items,
openings and the like and the proper jointing to
existing.
Preamble/9 of 13
PREAMBLES TO ALL TRADES
Definitions (Cont’d)
A. In respect of demolitions and alterations the following words or expressions shall have
the meanings hereunder assigned to them :- (Cont’d)
Overhauling And Repairing - Piecing out and repairing damaged portions of door
Door And Frame frame and lining; repairing and refixing frame
architraves including renewing as necessary;
refixing frame and lining; hacking out broken glass
and reglazing; raking out and repainting frames;
overhauling, oiling and adjusting ironmongery;
easing and adjusting door; taking out door and
shooting bottom to clear new floor finish and
rehanging.
Taking Out Door And Frame - Taking off door; taking out frame, lining, architraves
and all associated joinery; taking out threshold and
any steps; taking out pelmet and curtain rails; taking
up floor springs; preparing opening to receive new
work.
Taking Out Window And - Taking out window; taking out frame, lining,
Frame architraves, shutter boxes and all architraves
joinery; taking out internal and external sills; taking
out pelmet and curtain rails; rails preparing opening
to receive new work.
Taking Out Sanitary Fittings - Taking out sanitary fittings complete with brackets,
bearers, backboards, drainers and the like;
disconnecting wastes and services; stopping off
pipes out of sight and making good.
Materials
B. Unless otherwise described in the Bills of Quantities, all materials arising out of
demolitions and alteration work shall become the property of the Contractor who shall
allow credit for the full value to him of all materials salvage.
C. Where provision is made in the Bills of Quantities for the value of credits to be shown
separately, the Employer shall be entitled to purchase salvaged materials from the
Contractor upon payment to the Contractor of the credit value (if any) shown in the Bills.
Preamble/10 of 13
PREAMBLES TO ALL TRADES
Workmanship
D. Demolitions are to be carried out in such a manner and sequence as to cause the least
possible disturbance to those parts of the work which are to remain.
Protection
E. The Contractor shall be responsible for the full protection of those parts of the buildings
which are to remain including the provision of temporary dust-proof screens, tarpaulins,
dust sheets and the like.
Dimensions
Rates to include
(1) Any temporary shoring, needling, strutting, scaffolding, screens and the like
and other temporary works.
(2) Cleaning and stacking materials which the Contractor may require for making
good.
(4) Executing the whole of the demolitions and alterations in phases as may be
directed by the Architect.
Preamble/11 of 13
PREAMBLES TO ALL TRADES
Method of Measurement
A. All structural steelwork, whether in structures which are mainly steel framed or not is
measured in accordance with the Alternative Method of Measurement expressed at
Clauses 38, 39 and 40 of the SMM except that all cutting, holes and openings required
for other Trades, whether made at the Shop or Site, have not been measured
separately and shall be deemed to be included with the items, of structural steelwork.
B. No allowance has been made in measurement for the weight of weld metal or for rolling
margin.
Rates to Include
(2) All straight, raking, bevel and splay cutting and notching.
(3) All shop and site drilling, holes and openings (no deduction in weight being
made for same) and in the case of structural steelwork, including those for
other trades.
(4) Marking, hoisting and erecting including temporary braces and supports.
D. Rates for gratings, ladders, stair balustrade, railings and gates are to include for all
labour, materials and appliances in welding.
E. Rates for all welded work exposed to view shall include for filling the welds smooth.
Preamble/12 of 13
PREAMBLES TO ALL TRADES
EXTERNAL WORK
ROADS
(3) Laying, rolling and consolidating sub-base, base course, binder and wearing
course in layers or sequence as required.
(5) Making joints, working around manhole covers and other like projections.
Preamble/13 of 13
BILLS OF QUANTITIES
AMOUNT
ITEM DESCRIPTION
(RM)
A Preliminary Items
The Preliminary items as set out hereunder are deemed to apply to the Information Only
whole of the Works as described in this document and/or as shown on the
drawings and the Contractor shall allow for complying with the same for
any cost in connection therewith.
The Contractor is required to insert the cost amounts in the monetary Information Only
columns against items and clauses of the preliminaries where such items
and clauses are of monetary significant to the Contractor.
Where items and clauses are left unpriced, it shall be deemed that the cost Information Only
of such items and clauses have been allowed for elsewhere within the
Tender and no subsequent claims arising out of expenses and/or loss
incurred against such unpriced items and clauses shall be entertained.
B Definitions
BQ.1 / 1 of 18
PROPOSED REPLACEMENT OF JOINT SEALANT AND CONCRETE REPAIR AT APRON AREA AND ITS
ASSOCIATED WORKS AT SULTAN AHMAD SHAH AIRPORT, KUANTAN, PAHANG
AMOUNT
ITEM DESCRIPTION
(RM)
Definitions (Cont'd)
A Description of Works
The scope of works for this contract includes the construction, completion, Information Only
testing and commissioning of all requirements as stated in the Drawings
and Specifications including but not limited to all the necessary temporary
works, demolition works, mechanical & electrical works.
The scope of works shall be the Proposed Replacement of Joint Sealant Information Only
and Concrete Repair at Apron Area and Its Associated Works at Sultan
Ahmad Shah Airport, Kuantan, Pahang
The contractor is required to visit the site and study comprehensively the Information Only
Tender documents in determining the detail scope of works
BQ.1 / 2 of 18
PROPOSED REPLACEMENT OF JOINT SEALANT AND CONCRETE REPAIR AT APRON AREA AND ITS
ASSOCIATED WORKS AT SULTAN AHMAD SHAH AIRPORT, KUANTAN, PAHANG
AMOUNT
ITEM DESCRIPTION
(RM)
A Contractor's Responsibility
The Contractor shall be entirely responsible for ensuring that all operations
and methods of construction, materials and workmanship are safe,
sufficient and in accordance with the Contract Documents. No inspection
by the Superintending Officer (S.O.) and no instruction given or certificate
issued by the Superintending Officer (S.O.) shall be deemed to imply that
the Superintending Officer (S.O.) has assumed or taken over any part of
the Contractor's responsibility as defined above.
B Location of Site
The Contractor is to refer to the site plan for the location, dimension and
area of the site and he must accept the site as found, on the date of The amount
possession. needs to be filled
into the Bill of
Quantity section in
C Overall Site PROCUREHERE
under BILL NO. 1:
The Contractor shall note that the Site is an operational airport i.e. "Live PRELIMINARIES
Airport".As such, the Contractor shall take all necessary care, precaution
and measures including those that may be imposed or required by the
Local Authorities and/or Superintending Officer (S.O.) to ensure safety of
the passengers, occupants/residents, public and road users and that the
services, provisions and facilities enjoyed by the occupants/residents are
not disrupted.
The Contractor shall been full resposible for any damages, nuisance or
littering of the airport surrounding caused and/or disruptions to services,
provisions and facilities arising from the execution of the Works and shall
address and rectify immediately to the satisfaction of the aforesaid parties
and the costs in connection therewith or compensation(s) imposed shall be
borne by the Contractor at his own cost and expense for which such shall
be deemed to have been allowed for in the Tender/Contract Sum.
BQ.1 / 3 of 18
PROPOSED REPLACEMENT OF JOINT SEALANT AND CONCRETE REPAIR AT APRON AREA AND ITS
ASSOCIATED WORKS AT SULTAN AHMAD SHAH AIRPORT, KUANTAN, PAHANG
AMOUNT
ITEM DESCRIPTION
(RM)
A Visit To Site
The Contractor will be deemed to have examined and visited the Site, and
have to ascertained the nature, character and extent of the Works, local
conditions, accessibility of Site, the supply of and conditions affecting
labour, materials and goods, and any other matter affecting this Contract.
The Contractor shall ascertain and comply with all regulations and
requirements of the airport authorities. The Contractor shall be responsible
for full security of the Works and equipment notwithstanding the provision
of normal security of the airport authority i.e. airside vehicle, permit
charges, escort permit charges (by Airport Security Regulations and
Airside Safety Unit) etc.
As stipulated on Part (viii) of the CIDB Act 1994 and the Construction
Industry Regulation 1996, the successful tenderer will be required to pay
the CIDB a levy equal to 0.125% of the Contract Value for projects / works
RM 500,000.00 and above
BQ.1 / 4 of 18
PROPOSED REPLACEMENT OF JOINT SEALANT AND CONCRETE REPAIR AT APRON AREA AND ITS
ASSOCIATED WORKS AT SULTAN AHMAD SHAH AIRPORT, KUANTAN, PAHANG
AMOUNT
ITEM DESCRIPTION
(RM)
(i) Contractor’s/Erection all risks for a sum insured not less than total Contract The amount
Sum and Third Party Liability not less than RM 5,000,000.00 for any one needs to be filled
claim and unlimited during the period of insurance with extension to into the Bill of
include Principle Existing Property Quantity section in
PROCUREHERE
(ii) Registration number under Employee’s Social Security (SOCSO) Scheme under BILL NO. 1:
and/or Workmen’s Compensation (for employee not covered under PRELIMINARIES
SOCSO scheme) as required by law and/or any other relevant Insurance
Policy
*All the insurance policies referred shall be obtained through the insurance
broker appointed by the Employer (Willis (Malaysia) Sdn Bhd as follows.
Email: [email protected]; Contact: Kok Weng:
+603-27230659, Nina: +603-27230611; and effected with an insurance
company approved by the Employer. The contractor shall at its sole cost
and expenses maintain and take affect the insurance coverage at all time
during the terms of this agreement/Contract
BQ.1 / 5 of 18
PROPOSED REPLACEMENT OF JOINT SEALANT AND CONCRETE REPAIR AT APRON AREA AND ITS
ASSOCIATED WORKS AT SULTAN AHMAD SHAH AIRPORT, KUANTAN, PAHANG
AMOUNT
ITEM DESCRIPTION
(RM)
A Performance Bond
Notes :
The cost to be priced in under this item shall limit only for opportunity cost
i.e. loss of interest, related cost incurred during BG application and other
incidential cost
Basic calculation:
(i) Estimated Tender Sum below RM500,000.00 = 0.5% (0.005) x Estimated
Tender Sum (Exclude Performance Bond)
The tender is to be firm tender for constructing and executing the whole of
the works and is NOT subject to adjustments in respect of fluctuations in
cost of wages, and/or emoluments and expenses of any kind payable to
work people, or from fluctuations in cost of materials and goods, import
duty or any other duty, nor in expenditure arising out of any changes due to
legislations etc., irrespective of such increases or additional expenditure
coming into effect after the submission of tender or during the progress of
the works.
D Signages
BQ.1 / 6 of 18
PROPOSED REPLACEMENT OF JOINT SEALANT AND CONCRETE REPAIR AT APRON AREA AND ITS
ASSOCIATED WORKS AT SULTAN AHMAD SHAH AIRPORT, KUANTAN, PAHANG
AMOUNT
ITEM DESCRIPTION
(RM)
B Security Clearance
Warning :
Worker's Accommodation is not allowed to be constructed within Airport's
Boundary
D Programme of Work
The Contractor shall submit to the S.O a detail programme using the
Critical Path Method (CPM) inclusive copies of all date on computer
medium and printed hard copies. The programme shall be presented ni bar
chart form and network diagrams indicating the critical activities and
interface dates critical to complete the work on time. The Contractor shall
be required to update all information and maintain the planned programme
using the CPM weekly/monthly or as when instructed by the S.O. by
trained and qualified personnel
BQ.1 / 7 of 18
PROPOSED REPLACEMENT OF JOINT SEALANT AND CONCRETE REPAIR AT APRON AREA AND ITS
ASSOCIATED WORKS AT SULTAN AHMAD SHAH AIRPORT, KUANTAN, PAHANG
AMOUNT
ITEM DESCRIPTION
(RM)
A Hoarding
On completion of the Contract and within one (1) week of the S.O. so
instructing, the entire hoarding, fencing, warning lights and other
precautionary measures are to be removed from the site. All salvage
materials shall become the property of the Contractor and shall be stored
away.
The Contractor shall provide at his own cost a complete first aid kit which
shall be kept and properly maintained in the Contractor's site
representative or some other responsible person who shall on the Site
during all working hours to ensure that the first aid facilities are available
without delay at all times when work is in progress. One responsible
member of the Contractor's staff shall be trained in simple first aid duties. The amount
needs to be filled
into the Bill of
Quantity section in
C Site Meeting PROCUREHERE
under BILL NO. 1:
The Contractor or his representatives shall arrange and attend the site PRELIMINARIES
meetings arranged at fortnightly or at intervals as directed by the S.O. The
S.O. shall record the proceeding of these meetings and arrange for the
making and distribution of copies of the minutes to all interested parties.
The Contractor shall prepare and submit to the S.O monthly reports on the
progress of the works by sections and elements or by Trades: the number
of workmen employed, materials delivered, weather conditions and the
work taken from suitable angle.
BQ.1 / 8 of 18
PROPOSED REPLACEMENT OF JOINT SEALANT AND CONCRETE REPAIR AT APRON AREA AND ITS
ASSOCIATED WORKS AT SULTAN AHMAD SHAH AIRPORT, KUANTAN, PAHANG
AMOUNT
ITEM DESCRIPTION
(RM)
The Contractor shall provide, maintain, alter, adapt as required and move
as necessary, all temporary works and services and clear away (unless
otherswise stated) when no longer required and make good thereafter.
The Contractor shall also ensure that any person and/ or workmen
entering and/or working on site and in the Services/Works shall be
provided with approved Personal Protective Equipment (PPE) including but The amount
not limited to safety harness, safety vest, safety helmet, hearing protection needs to be filled
gear, safety boots, etc where appropriate in relation to the nature and into the Bill of
location of the services/works. Quantity section in
PROCUREHERE
The Contractor shall also ensure that any person and/or workmen entering under BILL NO. 1:
and/or working on Site and in the Works shall be provided with approved PRELIMINARIES
safety harness where appropriate in relation to the nature and location of
the Works.
Allow for the lighting, marking, watching and safety devices including
during closed hours of the airport (at night).
The Contractor shall at all times take full and sufficient precautions to
ensure the safety of all traffic through, around and diverted by the Works.
To ensure compliance, temporary signage shall be erected and maintained
during the period of need on all approaches to the Works in compliance
with the Contract, the signage scheme being to the approval of the S.O
and the relevant Local Authority
BQ.1 / 9 of 18
PROPOSED REPLACEMENT OF JOINT SEALANT AND CONCRETE REPAIR AT APRON AREA AND ITS
ASSOCIATED WORKS AT SULTAN AHMAD SHAH AIRPORT, KUANTAN, PAHANG
AMOUNT
ITEM DESCRIPTION
(RM)
The Contractor shall arrange for the conveyance of his materials, plant,
carrying out of the works etc. so as to cause a minimum of damage to
existing structures, buildings, roads, culverts, drains, footpath, steps,
retaining wall etc. He shall be held responsible for any damage caused by
his carriers or workmen to any of these from whatsoever cause arising and
shall maintain repair and reinstate same to their original conditions to the
satisfaction of the S.O. or alternatively shall bear the cost if such
maintenance and reinstatement as a deduction from monies due or to
become due to the Contractor under this Contract.
B Submission of Sample
The S.O reserves the right to reject the samples and/or the finished
installation on site, if in his opinion the material and installation on site do
not conform to the approved/submitted samples, brochures and required The amount
method. needs to be filled
into the Bill of
Quantity section in
(i) Manufacturer's Data
PROCUREHERE
Submit for approval as requested by the Superintending Officer, under BILL NO. 1:
manufacturer's specifications, installation instruction, general PRELIMINARIES
recommendation for the work, including certified laboratory test reports and
other data required to show in compliance with these Specifications.
C Hot Works
Hot working includes all types of welding, works involving the use of
bitumen heaters, thermal lance equipment and operations which generate
heat or sparks. The Contractors must ensure satisfactory fire precautions
and safe working conditions whilst carrying out any form of hot working. A
permit to work is required.
BQ.1 / 10 of 18
PROPOSED REPLACEMENT OF JOINT SEALANT AND CONCRETE REPAIR AT APRON AREA AND ITS
ASSOCIATED WORKS AT SULTAN AHMAD SHAH AIRPORT, KUANTAN, PAHANG
AMOUNT
ITEM DESCRIPTION
(RM)
A Electrical Equipment
Contractors are expressly forbidden to use 240v tools and equipment. All
small power tools, equipment and lighting must be rated to a maximum 110
v (55v to earth) and the site supllies must be in accordance with section
604 of the 16th Edition of the IEE Wiring Regulations and the Electricity
Regulations Acts. Contractors are to provide all the necessary tranformers,
switch gear, plugs, sockets, cabling etc. and any extension leads must be
fitted on the 100v supply side.
Contractors must comply with all roads Traffic Legislation. Drivers must
observe all speed limits, road markings and signs. In the Airside, vehicles
are only allowed to be parked within the confine of the Contractors' working
areas and drivers must passes on Airside Driving license and comply with
the current Operational Safety Instruction for Airside Driving.
If any vehicle or plant taller than normal vehicle height is to be used, the
working height of the plant or vehicle must be notified to the S.O. / S.O.R.
BQ.1 / 11 of 18
PROPOSED REPLACEMENT OF JOINT SEALANT AND CONCRETE REPAIR AT APRON AREA AND ITS
ASSOCIATED WORKS AT SULTAN AHMAD SHAH AIRPORT, KUANTAN, PAHANG
AMOUNT
ITEM DESCRIPTION
(RM)
A Working at Height
B Working Space
The S.O. / S.O.R in consultation with the Contractor will specify which
areas are to be designated as the "hard hat" areas. The Contractor must
comply with the rulings in accordance with the Construction (Head
Protection) Regulation.
E Site Diary
The Contractor shall provide a site daily diary in which shall comply with
the standard S.O. / S.O.R format at each site office. It shall be kept at up to
date at all times and shall be regularly certified by the head of the
Contractor's site supervisory team. The site diary shall contain records of
daily weather conditions, labour strength at site, plan on site work done
during each day, etc., and shall be made available at the site to the S.O. /
S.O.R and his representative whenever required. All site diaries shall be
kept in a reasonable tidy condition and shall be handed over to the S.O. /
S.O.R upon completion of the Works
BQ.1 / 12 of 18
PROPOSED REPLACEMENT OF JOINT SEALANT AND CONCRETE REPAIR AT APRON AREA AND ITS
ASSOCIATED WORKS AT SULTAN AHMAD SHAH AIRPORT, KUANTAN, PAHANG
AMOUNT
ITEM DESCRIPTION
(RM)
The Contractor shall provide all labour, plant, tools and equipment for the
proper and efficient execution of the Works. Provide transport for labour
and for the movement of plant and equipment to and from the site.
The Contractor shall submit with his Tender a schedule of plant and
equipment he proposes to use for the Works. Any items listed must be
available for inspection by the Superintending Officer (S.O), either prior to
or after acceptance of the Tender.
No plant or machinery shall be removed from site without the prior written The amount
approval of the Superintending Officer (S.O). needs to be filled
into the Bill of
The Contractor is required to provide standby machinery for paver Quantity section in
and pneumatic tire roller equipped with sprinkle system during PROCUREHERE
window working hours to avoid the working machineries breakdown under BILL NO. 1:
and fail to complete the rehabilitation works within the working PRELIMINARIES
window hours.
The contractor shall carried out detection and mapping all existing
underground utilities such as electrical and telephone cables, water
reticulation pipe, sewerage pipe and all other utilities within the site before
commencement of work including preparation and submission of two (2)
sets of drawing and one (1) soft copy endorse by specialist for S.O.
approval.
BQ.1 / 13 of 18
PROPOSED REPLACEMENT OF JOINT SEALANT AND CONCRETE REPAIR AT APRON AREA AND ITS
ASSOCIATED WORKS AT SULTAN AHMAD SHAH AIRPORT, KUANTAN, PAHANG
AMOUNT
ITEM DESCRIPTION
(RM)
A Working Hours
The Contractor shall take note that on award, he shall submit means of
increasing the hours of working such as to tapping power supply from the
existing system or to existing TNB substation or from the nearest tapping
source, etc.
Note :
The amount
needs to be filled
Contractor must inform MASB KUA to apply the Notice to Air Men
into the Bill of
(NOTAM) at least three (3) working days in advance. Contractor is
Quantity section in
allowed to commence the physical works upon approval of NOTAM by the
PROCUREHERE
Air Traffic Control (ATC) and / or DCA.
under BILL NO. 1:
PRELIMINARIES
B Manufacturer's Warranty or Maintenance Manual
BQ.1 / 14 of 18
PROPOSED REPLACEMENT OF JOINT SEALANT AND CONCRETE REPAIR AT APRON AREA AND ITS
ASSOCIATED WORKS AT SULTAN AHMAD SHAH AIRPORT, KUANTAN, PAHANG
AMOUNT
ITEM DESCRIPTION
(RM)
A As-Built /Completed/Installed
Two (2) sets of CD in PDF & AutoCAD (latest version) and 2 sets hardcopy
of as-built drawing (Endorsed by the Professional Engineer) in A1 sizes
and properly bound, labelled and tagged and shall be submitted to the S.O
within one (1) month after the issuance of Certificate of Practical
Completion (CPC).
The Contractor shall ensure the working areas are clean and tidy all times,
free from debris, waste materials, etc. and that all construction debris and
the like shall not be allowed to accumulate on the Site or anywhere within
the overall site. Construction debris and the like shall be cleared regularly
or as when directed by the S.O to a lawfully recognised dump tip and all
cost, expenses, contributions and/or royalties shall be deemed to have The amount
allowed for in the Tender. needs to be filled
into the Bill of
The S.O. / S.O. Representative shall reserve the right to employ others to Quantity section in
clean up all debris accumulated on site or the Works at the cost and PROCUREHERE
expense of the Contractor should he fail to comply with the above under BILL NO. 1:
requirement. PRELIMINARIES
The Contractor shall also remove all debris arising from the construction
work from the site. Before handing over the Works to the S.O, the
Contractor is to clean the site all to the satisfaction of the S.O.
BQ.1 / 15 of 18
PROPOSED REPLACEMENT OF JOINT SEALANT AND CONCRETE REPAIR AT APRON AREA AND ITS
ASSOCIATED WORKS AT SULTAN AHMAD SHAH AIRPORT, KUANTAN, PAHANG
AMOUNT
ITEM DESCRIPTION
(RM)
The Contractor to submit to the S.O. ten (10) certified copies signed by the
Licensed Surveyor, the as-built underground mapping drawings showing
those utilities and services line buried underground in A1 size (838mm x
584mm), digital copy (CD) and a tracing sheet on completion of the
underground mapping works. The Contract price shall be deemed to
include the cost of preparation, supply and deliver of all drawings and
information required.
Before commencing any Works, etc., the Contractor shall inquire from the The amount
various Authorities whether any underground pipes, cable etc., are present needs to be filled
on the Site (including those beyond the limit of this Contract but within the into the Bill of
proposed development site) and if so, he shall make arrangements for the Quantity section in
protection of or disconnection, removal and reconnection or diversion of PROCUREHERE
such services and pay all necessary costs and fees in connection under BILL NO. 1:
therewith. PRELIMINARIES
The Contractor shall be held responsible for making good all damage to
cables etc., and shall indemnify the Employer against any claims as a
result of such damage.
The Contractor shall give every possible assistance at no extra cost to the
Contract, in the diversion, re-alignment of existing services which are
intended to be carried out by other Contractors or Local Authorities or
Statutory bodies.
BQ.1 / 16 of 18
PROPOSED REPLACEMENT OF JOINT SEALANT AND CONCRETE REPAIR AT APRON AREA AND ITS
ASSOCIATED WORKS AT SULTAN AHMAD SHAH AIRPORT, KUANTAN, PAHANG
AMOUNT
ITEM DESCRIPTION
(RM)
a) Comply with all rules and regulations under the Prevention and Control of
Infectious Diseases (Measures within the Infected Local Areas)
Regulations 2020 (Act) and/or relevant laws issued and enforced by the
relevant authorities.
c) Provision of isolation room, movement restriction at site, working time The amount
restriction, transport arrangement to facilitate movement of labour, health needs to be filled
screening before getting to work, regular temperature measure and into the Bill of
symptoms screening, regular site disinfection and sanitising, etc. Quantity section in
PROCUREHERE
d) Provide all safety gears including approved Personal Protective Equipment under BILL NO. 1:
(PPE), tools for regular screening and chemical required disinfecting at site PRELIMINARIES
as deliberated in the SOP and report immediately to MoH on any case
arise from his labour and site management team and give full cooperation
to Ministry of Health to conduct contact tracing and bear all medical cost of
the worker/s concerned and relevant disinfection procedure required at the
construction site/premises.
The Contractor shall keep the Employer harmless from any and all claims,
penalties, demands, civil actions, negligence suits, losses, charges,
expenses, damages and liabilities whatsoever which the Employer may
require to pay, sustain, suffer or incur by reason of or in connection with
any breach and/or non-compliance with the above item (a) to (d).
The Tender Price shall include all costs incurred resulting from compliance
with the above requirements for the entire course of the Contract.
BQ.1 / 17 of 18
PROPOSED REPLACEMENT OF JOINT SEALANT AND CONCRETE REPAIR AT APRON AREA AND ITS
ASSOCIATED WORKS AT SULTAN AHMAD SHAH AIRPORT, KUANTAN, PAHANG
AMOUNT
ITEM DESCRIPTION
(RM)
The amount
needs to be filled
into the Bill of
Quantity section in
PROCUREHERE
under BILL NO. 1:
PRELIMINARIES
BQ.1 / 18 of 18
BILLS OF QUANTITIES
Note:
1) The Contractor shall price-in all the items and obliged to carry out any repair works when instructed by the
Employer. All prices quoted shall include the supply of labour with competent, skilled and experience, tools,
equipment, transporting charges, communication, consumable items, overtime, wages and profit. The rates
shall apply up to the date of expiry of this Contract.
2) The Rate and Amount needs to be filled into the Bill of Quantity section in PROCUREHERE under
BILL NO. 2 : JOINT SEALANT WORKS (ALL PROVISIONAL).
RATE AMOUNT
ITEM DESCRIPTIONS UNIT QTY
(RM) (RM)
Notes :
The site will be handed over to the Contractor in its present state
and condition. The Contractor shall remove any debris and
rubbish lying about the site/working area. The Contractor to
protect any existing utilities and airside fitting accessories during
the course of the construction works.
Debonding Tape
BQ.2 / 1 of 3
PROPOSED REPLACEMENT OF JOINT SEALANT AND CONCRETE REPAIR AT APRON AREA AND ITS
ASSOCIATED WORKS AT SULTAN AHMAD SHAH AIRPORT, KUANTAN, PAHANG
Note:
1) The Contractor shall price-in all the items and obliged to carry out any repair works when instructed by the
Employer. All prices quoted shall include the supply of labour with competent, skilled and experience, tools,
equipment, transporting charges, communication, consumable items, overtime, wages and profit. The rates
shall apply up to the date of expiry of this Contract.
2) The Rate and Amount needs to be filled into the Bill of Quantity section in PROCUREHERE under
BILL NO. 2 : JOINT SEALANT WORKS (ALL PROVISIONAL).
RATE AMOUNT
ITEM DESCRIPTIONS UNIT QTY
(RM) (RM)
Note :
1. Please refer to the Preliminaries on the permitted working hours
and shall make necessary allowance for it
2. Contractor shall submit at least five (5) years of product warranty
via letter/certificate for joint sealant product after the completion
of the works
Hot Pour
To supply, deliver and apply sealant joint of 'hot pour' at the The Rate and Amount
surrounding perimeter of the concrete apron complete with needs to be filled into
necessary protection to the existing apron including all the Bill of Quantity
necessary works required in accordance with the manufacturer's section in
instruction and to the satisfaction of S.O / S.O's representative to PROCUREHERE under
the following areas : BILL NO. 2 : JOINT
SEALANT WORKS
(ALL PROVISIONAL)
B Parking Apron Bay 1 to Bay 3 M 510
Note :
1. Please refer to the Preliminaries on the permitted working hours
and shall make necessary allowance for it
2. Contractor shall submit at least five (5) years of product warranty
via letter/certificate for joint sealant product after the completion
of the works
BQ.2 / 2 of 3
PROPOSED REPLACEMENT OF JOINT SEALANT AND CONCRETE REPAIR AT APRON AREA AND ITS
ASSOCIATED WORKS AT SULTAN AHMAD SHAH AIRPORT, KUANTAN, PAHANG
Note:
1) The Contractor shall price-in all the items and obliged to carry out any repair works when instructed by the
Employer. All prices quoted shall include the supply of labour with competent, skilled and experience, tools,
equipment, transporting charges, communication, consumable items, overtime, wages and profit. The rates
shall apply up to the date of expiry of this Contract.
2) The Rate and Amount needs to be filled into the Bill of Quantity section in PROCUREHERE under
BILL NO. 2 : JOINT SEALANT WORKS (ALL PROVISIONAL).
RATE AMOUNT
ITEM DESCRIPTIONS UNIT QTY
(RM) (RM)
A Saw cutting and hack the existing concrete pavement panel not M2 30
exceeding 100mm thick using the method approved by S.O,
scrap off and removes hacked and loosed concrete pavement
including cleaning of existing pavement from dust, dirt and other
loose materials and remove all debris to contractor's dumping
area approved by S.O
BQ.2 / 3 of 3
SECTION A3(C)
Any work ordered by the MALAYSIA AIRPORTS SDN BHD to be carried out by the
works shall be paid for at the rates entered hereunder subjet to the following conditions :
1. The rate entered for labour shall be deemed to include all on-costs associated with the employment of
such labour including (inter alia), head office cares, overhead charges, profit, site expenses, subsistence
allowances, time lost due to inclement weather, bonus, holiday and sick pay, and any other employee's
fringe benefit(s), small tools and consumable store, temporary equipment such as wages, tempoary
tracks, ladders, staging scaffolding and all item of a similar nature unless these are provided or set up
exclusively for day works.
2. The wage of ganger and leading hands working with their gangs shall be paid for at the appropriate rates,
but the time of walking ganger, sub-foreman and foreman will not be included and shall be deemed to be
included in the rates entered for labour under site supervision and staff.
3. Payment for overtime works, if chargeable and approved by the MALAYSIA AIRPORTS SDN BHD shall
be made at the rates entered herein, but the time so worked as overtime shall be adjusted in the same
proportion as that used for paying the normal workmen on the site and approved by the MALAYSIA
AIRPORTS SDN BHD. Thus, if a man works 1 hour overtime for which the rate in the day works
schedule.
NOTE : Overtime is working time over and above 8 hour per working day including Saturday or 48
hours per week
4. The cost of special watching and lighting necessitated by day works shall be included in the rates.
5. The rates entered for plant shall apply only to plant which the contractor has available on the site. Such
rates shall be deemed to be include all over head charges, profit, site supervision and staff, hire charges,
fuel, maintenance, consumable store, spare part, insurances, etc., but shall exclude the cost wages for
drivers and operators, which shall be payable in days separately as dealt with under paragraph 1 above.
6. Payment for mechanically operated plant shall be made only at such times as the plants is engaged in
day work and shall exclude all standing, idle or down time.
7. If any workmen or items of plant on day works do nor readily belong to any classification include in the
schedule or inserted by the Contractors at the time of tendering, the MALAYSIA AIRPORTS SDN BHD
shall determine the equivalent classification to be adopted for such workmen or items or plant and
payment for such will be made accordingly.
8. Only time on works will be allowed A "DAY" is considered to be a normal working day of 8 hours
Fractions of a day will be paid for "Pro-Rata"
SODR / 1 of 3
SCHEDULE OF DAYWORK RATES
…………………………….. ……………………………..
Tenderer Witness
SODR / 2 of 3
SCHEDULE OF PLANT RATES
Lorries
-Ordinary 8-10 tonne hour …………………………………..
-Heavy Haulage 13 tonne hour …………………………………..
…………………………….. ……………………………..
Tenderer Witness
SODR / 3 of 3
SECTION A4(C)
The Contractor shall insert the price ex-site of the following basic materials which shall be used as a basis
for derivation of new rates for variation as per related clauses of the Conditions of Contract and for Interim
Valuations :-
2 Sand M3
BMP / 1 of 1