25-0409 Steel Asia Project - Supply of MDP

Controlgear Electric Corporation has submitted a proposal to Pneumatic Technologies Incorporated for the supply of two Main Distribution Panels (MDP) with a total price of Php 2,803,190.00, inclusive of VAT. The proposal includes specifications, terms of payment, delivery timelines, and exclusions from scope of supply and work. Additional details on components and general terms and conditions are also provided in the document.

Uploaded by

Jareem Pees
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
83 views4 pages

25-0409 Steel Asia Project - Supply of MDP

Controlgear Electric Corporation has submitted a proposal to Pneumatic Technologies Incorporated for the supply of two Main Distribution Panels (MDP) with a total price of Php 2,803,190.00, inclusive of VAT. The proposal includes specifications, terms of payment, delivery timelines, and exclusions from scope of supply and work. Additional details on components and general terms and conditions are also provided in the document.

Uploaded by

Jareem Pees
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

April 02, 2025 Our Ref: CEC.Q.

25-0409

PNEUMATIC TECHNOLOGIES INCORPORATED


Unit 1001 A&B Richville Corp. Tower, Madrigal Business Park,
Muntinlupa City, Philippines

Attention : Mr. Peter James C. Caligan

Subject : Steel Asia Project – Supply of MDP

Dear Sir :

We are pleased to offer for the following for your consideration:

Item
Qty Unit Particulars/Specifications Unit Price Amount
No.
Supply of Main Distribution Panel (CDA MDP 1) rated
2500A, 230V, 3Ø, 3P in NEMA 12, indoor, freestanding, six
(6)) vertical sections, cabinet type, welded enclosure. The
enclosure is made from G.I. Sheet, Ga. #14, for structure,
01 1 assy 2,700,780.00 2,700,780.00
door, & cover, powder coated Wrinkle Light Gray
(RAL7035).

Dimension: 1000mm (D) x 4000mm (W) x 2200mm (H)


Supply of Main Distribution Panel (CDA MDP 2) rated
125A, 230V, 3Ø, 3P in NEMA 12, indoor, wall mounted,
cabinet type, welded enclosure. The enclosure is made from
02 1 assy G.I. Sheet, Ga. #14, for structure, door, & cover, powder 102,410.00 102,410.00
coated Wrinkle Light Gray (RAL7035).

Dimension: 250mm (D) x 550mm (W) x 700mm (H)


Total Lot Price Php (VAT Inclusive) 2,803,190.00

Notes:

1. CEC to supply enclosure, wiring and busbarring consumables.


2. Components BOQ to be supplied by CEC can be found at the last page of this proposal – any
components not specifically listed in the said list will not be supplied by CEC.
3. Site works such as SAT, commissioning, cabling, civil works, interconnection works, and installation
works are not included in our scope of work.
4. Delivery within Metro Manila is included in our offer but limited to unloading only.
5. See attached CEC General Terms and Conditions of Sales.

Very truly yours,

CONTROLGEAR ELECTRIC CORPORATION

Noted by:

________________________ ________________________
Jayvee A. Samonte Julieth B. Cajucom
Sales Engineer – RS Sales Manager – RS

Page 1 of 4
HEAD OFFICE & PLANT Tel/Fax Nos.: (+632) 299-8238, 299-8240
117 R.E. Chico St., Sto. Cristo, (+632) 519-4440, 519-4442
Baliuag, Bulacan (+6344) 766-6923, 767-7107
Email Address: [email protected]
Website: http://cecph.com
GENERAL TERMS AND CONDITIONS OF CEC

Price: Offer is in Philippine Peso (Php) and Inclusive of Exclusions from Scope of Supply
VAT… Metro Manila. Any components, accessories or materials not specifically
listed in our offer will not be supplied by CEC unless an
Terms of Payment: additive amount is agreed by both CEC and its customer.
Fifty Percent (50%) of the Purchase Order (PO) amount as
down payment upon issuance of Purchase Order; Exclusions from Scope of Work
a. Any works or services not specifically listed in our
Fifty Percent (50%) balance, upon delivery;
offer will not be executed by CEC or its extensions.
b. Crating and Shipment (via Air or Sea)
Delivery Time
c. Any Installation works on-site
Estimated six (6) to eight (8) working weeks after the
d. Testing and commissioning on site
following prerequisites:
e. Any civil works
a. Receipt of Purchase Order
f. Any other COVID-19 related requirements except for
b. Receipt of Down payment
RT-PCR
c. Approved CEC supplied components
d. Approved Shop Drawings
Currency Note Price quoted is based on
current exchange rate of Php 57.59/1 USD. Should there be
Price Validity Price offered is valid for Fifteen (15) any significant peso-to-dollar devaluation at the time of order,
days from the date of this quotation, after which, the offer prices shall be adjusted accordingly
price is subject for reconfirmation
Cancellation Clause In case of order cancellation,
Color of Enclosure Unless otherwise specified CEC a minimum charge of 20% of the Total PO/ contract amount
Standard Enclosure Colors are RAL 7032 and RAL 7035 any will be applied from the date of order receipt. The
other color would entail longer lead time and additional cost cancellation charge shall be increased linearly up to 100% of
on the part of the client. the total PO/contract price one month prior to scheduled
delivery.
Warranty CEC maintains that all electrical
enclosures fabricated and assembled in the factory are free Consequential Loss Notwithstanding anything
from defects and as such entitles the customer a claim for contained in any Contract between the Customer and the CEC
repair, rectification or replacement for a period of One (1) to the contrary, CEC shall not be liable for any injury to
year from the date of delivery under normal operating and persons or damage to property or for any special, indirect or
usage conditions. consequential loss or damage whatsoever, such as, but not
limited to loss of revenue, loss of profits, loss of use, loss of
CEC maintains that all components supplied by its third party power, costs of capital, loss of production and costs
suppliers are visually inspected for physical damage and connected with interruption of operations, or cost of
functions as designed under normal usage conditions, should replacement power.
there be any claims against malfunctioning components, and
CEC will facilitate and expedite the cost of replacement or Limitation of Liability Notwithstanding anything
repair of the component within a period of one (1) year from contained in any Contract between the Customer and CEC to
the date of delivery. the contrary, CECs total liability, in any respect of any
and all claims for damages or losses which may arise in
Factory AcceptanceBefore delivery of our Finished connection with CEC’s performance or non-performance
Products, the customer or its duly authorized representatives shall not exceed 10% of the gross purchase order/contract
will be invited to witness the Factory Acceptance Inspection price.
to be conducted at the CEC Assembly Plant in Baliwag,
Bulacan. The factory acceptance inspection may proceed, Other Conditions On issuing the Purchase
even in the absence of the customer or its representative Order/Contract, it is understood that the customer has read
provided the customer –through email, text or fax - and conforms to the above General Terms and Conditions of
communicates his intent and expressly agrees to accept the Sales of CEC. Any deviation in the customer Purchase Order
Factory Acceptance Test Results as declared by CEC. must be approved by a duly authorized CEC representative,
in writing & agreed by both CEC & Customer.
Factory Acceptance Inspection consists of the following
unless otherwise stated:
a. Visual & Mechanical Inspection
b. Functional Test
c. Electrical Test:
• Insulation Resistance Test
• Contact Resistance Test

Page 2 of 4
HEAD OFFICE & PLANT Tel/Fax Nos.: (+632) 299-8238, 299-8240
117 R.E. Chico St., Sto. Cristo, (+632) 519-4440, 519-4442
Baliuag, Bulacan (+6344) 766-6923, 767-7107
Email Address: [email protected]
Website: http://cecph.com
CONTROLGEAR ELECTRIC CORPORATION
117 R.E. Chico St., Sto. Cristo, Baliuag, Bulacan

CUSTOMER : PNEUMATIC TECHNOLOGIES INC.


SUBJECT : SUPPLY OF MDP

COMPONENTS BILL OF QUANTITIES


ITEM DESCRIPTION QTY Unit BRAND CAT. NO.
I CDA MDP 1
MAIN
E2.2N 2500 Ekip Dip LSI 3p WMP, 66kA, 500V 2 pc ABB 1SDA072412R1
E2.2 W FP Iu=2500 3p HR HR 2 pc ABB 1SDA073911R1
SHUNT OPENING RELEASE 220-240V AC-DC
2 pc ABB 1SDA073674R1
E1.2..E6.2-XT7-XT7M
SHUNT CLOSING RELEASE 220-240V AC-DC
2 pc ABB 1SDA073687R1
E1.2..E6.2-XT7M
GEARED MOTOR DEVICE 220...250V AC-DC
2 pc ABB 1SDA073725R1
E2.2...E6.2
AUX 2Q 400V + 2Q 24V E2.2...E6.2 2 pc ABB 1SDA073755R1
KIT LEVER MECHANICAL INTERLOCK BETWEEN
2/3 C.BREAKER -TIPO A-B-C-D- FOR FIXED AND 1 pc ABB 1SDA073889R1
PARTIE MOBILE E2.2
MECHANICAL INTERLOCK HORIZONTAL
BETWEEN 3 C.BREAKER -TYPE B-C-D- 2 pc ABB 1SDA073882R1
STANDARDS CABLES E2.2...E6.2
SUPPORT MECHANICAL INTERLOCK BETWEEN
2/3 C.BREAKER -TYPE A-B-D- FOR FIXED AND 2 pc ABB 1SDA073895R1
FIXED PART E2.2...E6.2
CONTROLS
ATS CONTROLLER WITH BATTERY & BATTERY
1 pc COMAP ATS270
CHARGER
DIGITAL POWER METER W/ MODBUS COM 2 pc SIEMENS 7KT0310
MCB 6A, 3P 3 pc ABB S203 C6
MCB 6A, 2P 6 pc ABB S202 C6
CONTROL RELAY 24V WITH BASE 5 pc PHOENIX 2903677
CONTROL RELAY 230V WITH BASE 3 pc PHOENIX 2903688
CPT 500VA 480/230V 1Ph 2 pc LINKWELL
CT 2500/5A 6 pc CAMSCO
PILOT LIGHT GREEN 230V 2 pc IDEC YW1P-2EQM3G
PILOT LIGHT RED 230V 2 pc IDEC YW1P-2EQM3R
PILOT LIGHT ORANGE 230V 2 pc IDEC YW1P-2EQM3A
SELECTOR SWITCH 3POS 1 pc IDEC YW1S-3E21
CBCS PULL TO OPERATE 2 pc YOSUNG YSDNC3402-B4RP10B
LIMIT SWITCH 2 pc CHS Z-15GQ
PANEL LIGHT 230V 2 pc FIREFLY
BRANCHES
XT7S 800 Ekip Dip LS/I In=800A 3p F F, 45kA, 500V 6 pc ABB 1SDA100826R1
DIGITAL POWER METER W/ MODBUS COM 6 pc SIEMENS 7KT0310
MCB 6A, 3P 6 pc ABB S203 C6
MCB 6A, 2P 12 pc ABB S202 C6
CPT 50VA 480/230V 1Ph 6 pc LINKWELL
CT 800/5A 18 pc CAMSCO
BRANCHES

XT2H 160 TMA 125-1250 3p F F, 50kA, 500V 1 pc ABB 1SDA067603R1

Page 3 of 4
HEAD OFFICE & PLANT Tel/Fax Nos.: (+632) 299-8238, 299-8240
117 R.E. Chico St., Sto. Cristo, (+632) 519-4440, 519-4442
Baliuag, Bulacan (+6344) 766-6923, 767-7107
Email Address: [email protected]
Website: http://cecph.com
COMPONENTS BILL OF QUANTITIES
ITEM DESCRIPTION QTY Unit BRAND CAT. NO.
DIGITAL POWER METER W/ MODBUS COM 1 pc SIEMENS 7KT0310
MCB 6A, 3P 1 pc ABB S203 C6
MCB 6A, 2P 2 pc ABB S202 C6
CPT 50VA 480/230V 1Ph 1 pc LINKWELL
II CDA MDP 2
MAIN
XT2H 160 TMA 125-1250 3p F F, 50kA, 500V 1 pc ABB 1SDA067603R1
BRANCHES
XT1C 160 TMD 40-450 3p F F, 18kA, 500V 6 pc ABB 1SDA067393R1

Page 4 of 4
HEAD OFFICE & PLANT Tel/Fax Nos.: (+632) 299-8238, 299-8240
117 R.E. Chico St., Sto. Cristo, (+632) 519-4440, 519-4442
Baliuag, Bulacan (+6344) 766-6923, 767-7107
Email Address: [email protected]
Website: http://cecph.com

You might also like