This document outlines the operating procedures and safety practices for the Tradecore Steel Blanking Machine. It details critical steps, significant hazards, safe work practices, and required personal protective equipment (PPE) for machine operation. The document emphasizes the importance of safety measures, proper machine setup, and adherence to protocols during operation and shutdown.

Uploaded by

gremlin864
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
52 views5 pages

TCS Ssop - Blanking Line Operator

This document outlines the operating procedures and safety practices for the Tradecore Steel Blanking Machine. It details critical steps, significant hazards, safe work practices, and required personal protective equipment (PPE) for machine operation. The document emphasizes the importance of safety measures, proper machine setup, and adherence to protocols during operation and shutdown.

Uploaded by

gremlin864
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 5

ORIGINATED BY: M.Muckleston ASSISTED BY: M.

Muckleston
DATE OF REVISION: 08/11/2024
REVISION STATUS: Original
DATE OF ORIGIN: 08/11/2023
REVISED BY: M. Muckleston
OPERATING: Tradecore Steel Blanking Machine Operation DESIGNATION:________________
SIGNING AUTHORITY: ________________________
DATE OF IMPLEMENTATION: 08/11/2023

CRITICAL STEPS SIGNIFICANT HAZARDS SAFE WORK PRACTICE PPE


 Machine Start Up  Trip /fall whilst walking Before Operating
 Slip/fall whilst walking  Blow into the breathalyzer at the  Safety boots
 Hand/foot injuries security gate to allow entrance upon 0% (non-slip
BAC soles)
 Eye/head injurie in the event of a  Be vigilant of overhead cranes moving  Ear
material chip stock protection
 Head/body injuries from moving  Keep to designated walkways as much  High visibility
parts as possible clothing
 Ensure housekeeping is done and the  Gloves
 Cut hands/body on sharp area is clean and safe to work in  Overalls
material and spring back  Be cautious whilst walking through the
factory and be vigilant for moving
 Fire vehicles/parts or uneven ground
 Fit and adjust PPE.
 Dust
 Make sure no clothing is loose
 Be sure to familiarize yourself with the
 Noise Zone
emergency lock out stop
 Electrical Shock  Ensure the machine guards are in place
and that there aren’t any visible defects
 Head/body injury from overhead
 Provide training where required to
crane
other team members
 Before loading/offloading machine,
Reg No. 2015/355509/07 | Vat No. 4240271140
A.C. Hoare, D. Barnes, JP. Briner, R. Barnes
ensure it is on manual.
 Machine to be inspected and check
sheet filled out before operation
 Machine should not be operated if
major faults are noted
 Ensure no loose electrical gear is
exposed
 Upon receiving the job card you must
ensure the job card information and the
coil received have the same serial
number
 Set up both the slitter head and
separator according to the works order
on the job card
 Check the setting before feeding the
coil
 Alignment of the coil is crucial so that
the scrap is as close to equal on both
sides as possible. This means the sides
of the slit will be the same size as the
rest of the strips and the edges won’t
be damaged.
 Ensure that the clearance between each
slitter knife is equal. This will prevent
knives from chipping

 During Operation
 Run the machine and check that the
material is moving through it correctly
Reg No. 2015/355509/07 | Vat No. 4240271140
A.C. Hoare, D. Barnes, JP. Briner, R. Barnes
 Once the slits come through the slitter
head, check them for burrs, check the
width and thickness. This must be
recorded on the QA sheet.
 These recordings must be done at least
three (3) times. Once at the beginning,
then at the middle and then at the end
of the coil across the width

Whilst operating the machine


 Be vigilant for overhead cranes moving
stock
 Be cautious of moving parts in the
machine
 Always keep PPE on & secured whilst in
the warehouse
 Keep to designated walkways as much
as possible
 Be cautious of sharp material whilst
walking through the areas
 Follow the “buddy system” whereby
you are not operating the machine
alone in case of an accident
 Do not try to “fix” or make adjustments
to the machine while it is running
 In the event of a machine malfunction
make sure to push the emergency lock
out stop.
 Continue the production of the job until
completed.
 At the end of each run each strip should
Reg No. 2015/355509/07 | Vat No. 4240271140
A.C. Hoare, D. Barnes, JP. Briner, R. Barnes
be secured by putting tape and/or
welding of strips

Switching Off

 Switching  Ensure no loose hanging clothing


Machine off  Ensure PPE is still in place
 Be wary of moveable parts
 Be cautious of sharp objects
 Be vigilant of overhead cranes
 Keep to designated walkways where
possible
 Switch off the machine at the console
and ensure all moveable parts of the
machine come to a halt before moving
the slits
 Once the machine is at a full stop
continue with the strapping of the
bundle
 If the operator is happy, ensure the slit
is correctly labelled and that all
required fields are filled in on
completed job cards.
 Once the slit has been safely removed
and labelled, refer back to machine
start up and repeat the process
 Do not expose any electrical gear
 Ensure the machine is off and cannot be
accidentally switched on or operated
 Do not try to make any adjustments to
the machine if you are not authorized
Reg No. 2015/355509/07 | Vat No. 4240271140
A.C. Hoare, D. Barnes, JP. Briner, R. Barnes
to do so
 Ensure housekeeping is done once the
production job has been completed and
all waste is picked up, cleaned and
disposed of correctly before starting a
new job
 Only the maintenance team / manager
is authorized to change the blades,
gears, shafts etc.

Employee: _____________________________________ Signature: ____________________________ Date: ______________________


Manager: ______________________________________ Signature: ____________________________ Date: ______________________

Reg No. 2015/355509/07 | Vat No. 4240271140


A.C. Hoare, D. Barnes, JP. Briner, R. Barnes

You might also like