Question 1 1 / 1 pts
X and X formed a partnership and have opened an advertising firm. Their
first project consists of activities listed in the following table. Perform
PERT-CPM.
Imm
Activity To Tp Tp
Predecessor
A - 5 6 14
B A 8 8 15
C B 3 5 8
D A 9 6 10
E D 3 4 6
F C, E 3 3 5
This study source was downloaded by 100000883051437 from CourseHero.com on 03-27-2024 05:31:53 GMT -05:00
https://www.coursehero.com/file/79213873/Quiz-on-PERT-CPM-with-Crashingpdf/
Crashing information are:
Activity Normal Time Crash Time Cost/day
A 5 11,000
B 8 3,000
C 3 6,000
D 5 1,000
E 3 6,000
F 3 2,000
QUESTION: What is the expected time of activity A?
Correct! 7
Question 2 1 / 1 pts
What is the expected time of activity D
Correct! 7
This study source was downloaded by 100000883051437 from CourseHero.com on 03-27-2024 05:31:53 GMT -05:00
https://www.coursehero.com/file/79213873/Quiz-on-PERT-CPM-with-Crashingpdf/
Question 3 1 / 1 pts
What is the expected time of activity F?
Correct! 3
Question 4 1 / 1 pts
What is the earliest finish of activity C?
18
19
Correct! 21
20
Question 5 1 / 1 pts
What is the earliest finish of activity E?
20
This study source was downloaded by 100000883051437 from CourseHero.com on 03-27-2024 05:31:53 GMT -05:00
https://www.coursehero.com/file/79213873/Quiz-on-PERT-CPM-with-Crashingpdf/
Correct! 18
19
17
Question 6 1 / 1 pts
What is the earliest finish of activity F?
21
22
23
Correct! 24
Question 7 1 / 1 pts
What is the latest finish of activity C?
23
22
24
Correct! 21
This study source was downloaded by 100000883051437 from CourseHero.com on 03-27-2024 05:31:53 GMT -05:00
https://www.coursehero.com/file/79213873/Quiz-on-PERT-CPM-with-Crashingpdf/
Question 8 1 / 1 pts
What is the latest finish of activity E?
18
Correct! 21
20
22
Question 9 1 / 1 pts
What is the latest finish of activity F?
26
Correct! 24
23
25
Question 10 1 / 1 pts
What is the expected project completion time?
22
This study source was downloaded by 100000883051437 from CourseHero.com on 03-27-2024 05:31:53 GMT -05:00
https://www.coursehero.com/file/79213873/Quiz-on-PERT-CPM-with-Crashingpdf/
25
Correct! 24
23
Question 11 4 / 4 pts
What is the critical path
Correct! ABCF
DEF
ABCD
ADEF
Question 12 3 / 3 pts
Crash five days off the project. What is the lenght of path ABCF on day 5?
Correct! 19
20
21
18
This study source was downloaded by 100000883051437 from CourseHero.com on 03-27-2024 05:31:53 GMT -05:00
https://www.coursehero.com/file/79213873/Quiz-on-PERT-CPM-with-Crashingpdf/
Question 13 3 / 3 pts
Crash five days off the project. What is the lenght of path DEF on day 5?
28
Correct! 19
18
21
Question 14 1 / 1 pts
What is the activity crashed on day 1?
Correct! B
Question 15 1 / 1 pts
What is the activity crashed on day 4?
This study source was downloaded by 100000883051437 from CourseHero.com on 03-27-2024 05:31:53 GMT -05:00
https://www.coursehero.com/file/79213873/Quiz-on-PERT-CPM-with-Crashingpdf/
F
Correct! A
Question 16 1 / 1 pts
How much will it cost the company to crash five days off the estimated
project completion time?
47,000
73,000
27,000
Correct! 37,000
Quiz score: 23 out of 23
This study source was downloaded by 100000883051437 from CourseHero.com on 03-27-2024 05:31:53 GMT -05:00
https://www.coursehero.com/file/79213873/Quiz-on-PERT-CPM-with-Crashingpdf/
Powered by TCPDF (www.tcpdf.org)