0% found this document useful (0 votes)
75 views8 pages

Quiz On PERT CPM With Crashing

The document outlines a quiz on PERT-CPM with crashing, consisting of 16 multiple-choice questions, available for a limited time. The quiz was completed successfully with a score of 23 out of 23. It includes questions about expected times, earliest and latest finishes of activities, critical paths, and costs associated with crashing project activities.

Uploaded by

ajillianglp
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
75 views8 pages

Quiz On PERT CPM With Crashing

The document outlines a quiz on PERT-CPM with crashing, consisting of 16 multiple-choice questions, available for a limited time. The quiz was completed successfully with a score of 23 out of 23. It includes questions about expected times, earliest and latest finishes of activities, critical paths, and costs associated with crashing project activities.

Uploaded by

ajillianglp
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

Quiz on PERT-CPM with Crashing

Due 20 Nov at 17:45 Points 23 Questions 16


Available 20 Nov at 15:40 - 20 Nov at 17:45 about 2 hours Time limit 60 Minutes

Instructions
Multiple Choice. Select the correct answer.

This quiz was locked 20 Nov at 17:45.

Attempt history
Attempt Time Score
LATEST Attempt 1 23 minutes 23 out of 23

Score for this quiz: 23 out of 23


Submitted 20 Nov at 17:03
This attempt took 23 minutes.

Question 1 1 / 1 pts

X and X formed a partnership and have opened an advertising firm. Their


first project consists of activities listed in the following table. Perform
PERT-CPM.

Imm
Activity To Tp Tp
Predecessor
A - 5 6 14

B A 8 8 15

C B 3 5 8

D A 9 6 10

E D 3 4 6

F C, E 3 3 5
This study source was downloaded by 100000883051437 from CourseHero.com on 03-27-2024 05:31:53 GMT -05:00

https://www.coursehero.com/file/79213873/Quiz-on-PERT-CPM-with-Crashingpdf/
Crashing information are:

Activity Normal Time Crash Time Cost/day


A 5 11,000
B 8 3,000
C 3 6,000
D 5 1,000
E 3 6,000
F 3 2,000

QUESTION: What is the expected time of activity A?

Correct! 7

Question 2 1 / 1 pts

What is the expected time of activity D

Correct! 7

This study source was downloaded by 100000883051437 from CourseHero.com on 03-27-2024 05:31:53 GMT -05:00

https://www.coursehero.com/file/79213873/Quiz-on-PERT-CPM-with-Crashingpdf/
Question 3 1 / 1 pts

What is the expected time of activity F?

Correct! 3

Question 4 1 / 1 pts

What is the earliest finish of activity C?

18

19

Correct! 21

20

Question 5 1 / 1 pts

What is the earliest finish of activity E?

20

This study source was downloaded by 100000883051437 from CourseHero.com on 03-27-2024 05:31:53 GMT -05:00

https://www.coursehero.com/file/79213873/Quiz-on-PERT-CPM-with-Crashingpdf/
Correct! 18

19

17

Question 6 1 / 1 pts

What is the earliest finish of activity F?

21

22

23

Correct! 24

Question 7 1 / 1 pts

What is the latest finish of activity C?

23

22

24

Correct! 21

This study source was downloaded by 100000883051437 from CourseHero.com on 03-27-2024 05:31:53 GMT -05:00

https://www.coursehero.com/file/79213873/Quiz-on-PERT-CPM-with-Crashingpdf/
Question 8 1 / 1 pts

What is the latest finish of activity E?

18

Correct! 21

20

22

Question 9 1 / 1 pts

What is the latest finish of activity F?

26

Correct! 24

23

25

Question 10 1 / 1 pts

What is the expected project completion time?

22

This study source was downloaded by 100000883051437 from CourseHero.com on 03-27-2024 05:31:53 GMT -05:00

https://www.coursehero.com/file/79213873/Quiz-on-PERT-CPM-with-Crashingpdf/
25

Correct! 24

23

Question 11 4 / 4 pts

What is the critical path

Correct! ABCF

DEF

ABCD

ADEF

Question 12 3 / 3 pts

Crash five days off the project. What is the lenght of path ABCF on day 5?

Correct! 19

20

21

18

This study source was downloaded by 100000883051437 from CourseHero.com on 03-27-2024 05:31:53 GMT -05:00

https://www.coursehero.com/file/79213873/Quiz-on-PERT-CPM-with-Crashingpdf/
Question 13 3 / 3 pts

Crash five days off the project. What is the lenght of path DEF on day 5?

28

Correct! 19

18

21

Question 14 1 / 1 pts

What is the activity crashed on day 1?

Correct! B

Question 15 1 / 1 pts

What is the activity crashed on day 4?

This study source was downloaded by 100000883051437 from CourseHero.com on 03-27-2024 05:31:53 GMT -05:00

https://www.coursehero.com/file/79213873/Quiz-on-PERT-CPM-with-Crashingpdf/
F

Correct! A

Question 16 1 / 1 pts

How much will it cost the company to crash five days off the estimated
project completion time?

47,000

73,000

27,000

Correct! 37,000

Quiz score: 23 out of 23

This study source was downloaded by 100000883051437 from CourseHero.com on 03-27-2024 05:31:53 GMT -05:00

https://www.coursehero.com/file/79213873/Quiz-on-PERT-CPM-with-Crashingpdf/
Powered by TCPDF (www.tcpdf.org)

You might also like