0% found this document useful (0 votes)
13 views10 pages

2025.04.09 3wla Sem 35.R0 (Coterranea)

The document outlines a three-week look ahead for the project aimed at expanding the storage capacity of the Mollendo terminal by 420 MBLS. It includes a detailed schedule of activities, their descriptions, and the planned start and end dates for various tasks related to tank construction and installation of grout. The project is set to commence on April 10, 2025, with specific tasks scheduled throughout the following weeks.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
13 views10 pages

2025.04.09 3wla Sem 35.R0 (Coterranea)

The document outlines a three-week look ahead for the project aimed at expanding the storage capacity of the Mollendo terminal by 420 MBLS. It includes a detailed schedule of activities, their descriptions, and the planned start and end dates for various tasks related to tank construction and installation of grout. The project is set to commence on April 10, 2025, with specific tasks scheduled throughout the following weeks.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 10

THREE WEEK LOOK AHEAD (TWLA)

PROYECTO: AMPLIACIÓN DE LA CAPACIDAD DE ALMACENAMIENTO DEL TERMINAL MOLLENDO EN 420 MBLS BRUTOS FECHA DE INICIO - THREE WEEK LOOK AHEAD
10-abr-25
TM07-003-60-PN-014
CODIGO CLIENTE MONTE AZUL SUR FECHA DE TERMINO - THREE WEEK LOOK AHEAD
153.28 81.00 264.59 89.88 6,437.70 6,291.38 5,262.72 18,580.40 6,779.38 6,868.14 6,809.83 6,600.86 7,017.10 5,688.84 6,229.32 45,992.15 6,315.10 6,536.72 6,410.33 5,381.06 1,476.06 1,458.93 1,374.46 28,947.33
SEMANA 33 89.88 SEMANA 34 SEMANA 35
Metrado Metrado Metrado Fecha Inicio Fecha Fin
Item Activity ID Descripción de la Actividad Und Rend. Duración J V S D L M M Metrado J V S D L M M Metrado J V S D L M M Metrado
total acumulado restante Programada Programada
10 11 12 13 14 15 16 Semanal 17 18 19 20 21 22 23 Semanal 24 25 26 27 28 29 30 Semanal
Tanques 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Cimiento Tanque TK-41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Liberación de fundación para buzones Glb 1.00 - 1.00 1.00 07/04/2025 07/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Solado de concreto para buzones m2 4.00 - 4.00 4.00 08/04/2025 08/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Acero de refuerzo para buzones Kg 93.86 - 93.86 93.86 09/04/2025 09/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado de buzones m2 22.56 - 22.56 11.28 09/04/2025 10/04/2025 2 11.28 0.00 0.00 0.00 0.00 0.00 0.00 11.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Concreto para buzones m3 2.02 - 2.02 2.02 17/04/2025 17/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.02 0.00 0.00 0.00 0.00 0.00 0.00 2.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de buzones m2 22.56 - 22.56 22.56 19/04/2025 19/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 22.56 0.00 0.00 0.00 0.00 22.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Escarificado de pedestal para instalacion de grout Glb 1.00 0.50 0.50 0.50 14/04/2025 14/04/2025 1 0.00 0.00 0.00 0.00 0.50 0.00 0.00 0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado de pedestal para grout Glb 1.00 - 1.00 0.33 15/04/2025 17/04/2025 3 0.00 0.00 0.00 0.00 0.00 0.33 0.33 0.67 0.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Humedecimiento de pedestal para colocación de grout Glb 1.00 - 1.00 0.50 18/04/2025 19/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.50 0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Instalacion de Grout Glb 1.00 - 1.00 1.00 20/04/2025 20/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 0.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de Grout Glb 1.00 - 1.00 1.00 21/04/2025 21/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Cimiento Tanque TK-42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Liberación de fundación para buzones Glb 1.00 - 1.00 1.00 14/04/2025 14/04/2025 1 0.00 0.00 0.00 0.00 1.00 0.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Solado de concreto para buzones m2 4.00 - 4.00 4.00 15/04/2025 15/04/2025 1 0.00 0.00 0.00 0.00 0.00 4.00 0.00 4.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Acero de refuerzo para buzones Kg 93.86 - 93.86 93.86 16/04/2025 16/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 93.86 93.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado de buzones m2 22.56 - 22.56 11.28 16/04/2025 17/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 11.28 11.28 11.28 0.00 0.00 0.00 0.00 0.00 0.00 11.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Concreto para buzones m3 2.02 - 2.02 2.02 18/04/2025 18/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.02 0.00 0.00 0.00 0.00 0.00 2.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de buzones m2 22.56 - 22.56 22.56 20/04/2025 20/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 22.56 0.00 0.00 0.00 22.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Escarificado de pedestal para instalacion de grout Glb 1.00 - 1.00 1.00 17/04/2025 17/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado de pedestal para grout Glb 1.00 - 1.00 0.33 18/04/2025 20/04/2025 3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.33 0.33 0.33 0.00 0.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Humedecimiento de pedestal para colocación de grout Glb 1.00 - 1.00 0.50 21/04/2025 22/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.50 0.50 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Instalacion de Grout Glb 1.00 - 1.00 1.00 23/04/2025 23/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de Grout Glb 1.00 - 1.00 1.00 24/04/2025 24/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00
x Cimiento Tanque TK-43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para pedestales (anillo de tanque) m3 45.41 - 45.41 45.41 17/04/2025 17/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 45.41 0.00 0.00 0.00 0.00 0.00 0.00 45.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de pedestal m2 184.26 - 184.26 92.13 20/04/2025 21/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 92.13 92.13 0.00 0.00 184.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Liberación de fundación para buzones Glb 1.00 - 1.00 1.00 22/04/2025 22/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Solado de concreto para buzones m2 4.00 - 4.00 4.00 23/04/2025 23/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.00 4.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Acero de refuerzo para buzones Kg 93.86 - 93.86 93.86 24/04/2025 24/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 93.86 0.00 0.00 0.00 0.00 0.00 0.00 93.86
Encofrado de buzones m2 22.56 - 22.56 11.28 24/04/2025 25/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11.28 11.28 0.00 0.00 0.00 0.00 0.00 22.56
Concreto para buzones m3 2.02 - 2.02 2.02 26/04/2025 26/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.02 0.00 0.00 0.00 0.00 2.02
Desencofrado de buzones m2 22.56 - 22.56 22.56 28/04/2025 28/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 22.56 0.00 0.00 22.56
Escarificado de pedestal para instalacion de grout Glb 1.00 - 1.00 1.00 29/04/2025 29/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00
Encofrado de pedestal para grout Glb 1.00 - 1.00 0.33 30/04/2025 02/05/2025 3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.33
Humedecimiento de pedestal para colocación de grout Glb 1.00 - 1.00 0.50 03/05/2025 04/05/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Instalacion de Grout Glb 1.00 - 1.00 1.00 05/05/2025 05/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de Grout Glb 1.00 - 1.00 1.00 06/05/2025 06/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Cimiento Tanque TK-44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Instalación de polylock en anillo m 106.82 - 106.82 106.82 12/04/2025 12/04/2025 1 0.00 0.00 106.82 0.00 0.00 0.00 0.00 106.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Instalación de pernos de anclaje Und 64.00 64.00 21.33 13/04/2025 15/04/2025 3 0.00 0.00 0.00 21.33 21.33 21.33 0.00 64.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para pedestales (anillo de tanque) m3 45.41 - 45.41 45.41 18/04/2025 18/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 45.41 0.00 0.00 0.00 0.00 0.00 45.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de pedestal m2 184.26 - 184.26 92.13 21/04/2025 22/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 92.13 92.13 0.00 184.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Liberación de fundación para buzones Glb 1.00 - 1.00 1.00 16/04/2025 16/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Solado de concreto para buzones m2 4.00 - 4.00 4.00 17/04/2025 17/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.00 0.00 0.00 0.00 0.00 0.00 0.00 4.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Acero de refuerzo para buzones Kg 93.86 - 93.86 93.86 18/04/2025 18/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 93.86 0.00 0.00 0.00 0.00 0.00 93.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado de buzones m2 22.56 - 22.56 11.28 18/04/2025 19/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11.28 11.28 0.00 0.00 0.00 0.00 22.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Concreto para buzones m3 2.02 - 2.02 2.02 20/04/2025 20/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.02 0.00 0.00 0.00 2.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de buzones m2 22.56 - 22.56 22.56 22/04/2025 22/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 22.56 0.00 22.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Escarificado de pedestal para instalacion de grout Glb 1.00 - 1.00 1.00 23/04/2025 23/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado de pedestal para grout Glb 1.00 - 1.00 0.33 24/04/2025 26/04/2025 3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.33 0.33 0.33 0.00 0.00 0.00 0.00
Humedecimiento de pedestal para colocación de grout Glb 1.00 - 1.00 0.50 27/04/2025 28/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.50 0.50 0.00 0.00
Instalacion de Grout Glb 1.00 - 1.00 1.00 29/04/2025 29/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 1.00
Desencofrado de Grout Glb 1.00 - 1.00 1.00 30/04/2025 30/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00
x Cimiento Tanque TK-45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado de pedestal m2 101.45 - 101.45 33.82 22/04/2025 24/04/2025 3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 33.82 33.82 67.63 33.82 0.00 0.00 0.00 0.00 0.00 0.00 33.82
Instalación de pases para tubería HDPE 2" Und 4.00 - 4.00 4.00 23/04/2025 23/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.00 4.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Instalación de polylock en anillo ml 58.81 - 58.81 58.81 24/04/2025 24/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 58.81 0.00 0.00 0.00 0.00 0.00 0.00 58.81
Instalación de pernos de anclaje Und 50.00 - 50.00 12.50 25/04/2025 28/04/2025 4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12.50 12.50 12.50 12.50 0.00 0.00 50.00
x Concreto f'c=350 kg/cm2 para pedestales (anillo de tanque) m3 25.37 - 25.37 25.37 29/04/2025 29/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 25.37 0.00 25.37
Desencofrado de pedestal m2 101.45 - 101.45 50.73 02/05/2025 03/05/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Cimiento Tanque TK-46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para zapata (contra terreno) m3 22.06 - 22.06 22.06 19/04/2025 19/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 22.06 0.00 0.00 0.00 0.00 22.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Escarificado de cimentación para encofrado de pedestal m2 14.71 - 14.71 14.71 20/04/2025 20/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14.71 0.00 0.00 0.00 14.71 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado de pedestal m2 101.45 - 101.45 33.82 23/04/2025 25/04/2025 3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 33.82 33.82 33.82 33.82 0.00 0.00 0.00 0.00 0.00 67.63
Instalación de pases para tubería HDPE 2" Und 4.00 - 4.00 4.00 24/04/2025 24/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.00 0.00 0.00 0.00 0.00 0.00 0.00 4.00
Instalación de polylock en anillo ml 58.81 - 58.81 58.81 25/04/2025 25/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 58.81 0.00 0.00 0.00 0.00 0.00 58.81
Instalación de pernos de anclaje Und 44.00 - 44.00 11.00 26/04/2025 29/04/2025 4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11.00 11.00 11.00 11.00 0.00 44.00
x Concreto f'c=350 kg/cm2 para pedestales (anillo de tanque) m3 25.37 - 25.37 25.37 30/04/2025 30/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 25.37 25.37
Desencofrado de pedestal m2 101.45 - 101.45 50.73 03/05/2025 04/05/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Cimiento Tanque TK-47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Excavación de cimentación Glb 1.00 - 1.00 1.00 11/04/2025 11/04/2025 1 0.00 1.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Solado de cimentación m3 9.77 - 9.77 9.77 12/04/2025 12/04/2025 1 0.00 0.00 9.77 0.00 0.00 0.00 0.00 9.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Colocación de acero de cimentación kg 10,670.00 - 10,670.00 5,335.00 14/04/2025 15/04/2025 2 0.00 0.00 0.00 0.00 5,335.00 5,335.00 0.00 10,670.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Colocación de acero de pedestal kg 25,671.00 - 25,671.00 5,134.20 16/04/2025 20/04/2025 5 0.00 0.00 0.00 0.00 0.00 0.00 5,134.20 5,134.20 5,134.20 5,134.20 5,134.20 5,134.20 0.00 0.00 0.00 20,536.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado de cimentación m2 19.54 - 19.54 9.77 19/04/2025 20/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.77 9.77 0.00 0.00 0.00 19.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Colocación de concreto de cimentación m3 97.70 - 97.70 97.70 21/04/2025 21/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 97.70 0.00 0.00 97.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Escarificado de cimentación para encofrado de pedestal m2 48.85 - 48.85 24.43 22/04/2025 23/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 24.43 24.43 48.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado de pedestal m2 337.08 - 337.08 56.18 24/04/2025 29/04/2025 6 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 56.18 56.18 56.18 56.18 56.18 56.18 0.00 337.08
Instalación de polylock ml 195.41 - 195.41 65.14 26/04/2025 28/04/2025 3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 65.14 65.14 65.14 0.00 0.00 195.41
Instalación de pernos de anclaje Und 70.00 - 70.00 14.00 29/04/2025 03/05/2025 5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14.00 14.00 28.00
x Colocación de concreto de pedestal m3 84.27 - 84.27 84.27 04/05/2025 04/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Fo.JJC-CG-05-03 Rev.0 Planificación Intermedia (PI)


Desencofrado de pedestal m2 337.08 - 337.08 168.54 06/05/2025 07/05/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Cimiento Tanque TK-48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Excavación de cimentación Glb 1.00 - 1.00 1.00 18/04/2025 18/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Solado de cimentación m3 9.77 - 9.77 9.77 19/04/2025 19/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.77 0.00 0.00 0.00 0.00 9.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Colocación de acero de cimentación kg 10,670.00 - 10,670.00 5,335.00 21/04/2025 22/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,335.00 5,335.00 0.00 10,670.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Colocación de acero de pedestal kg 25,671.00 - 25,671.00 5,134.20 23/04/2025 27/04/2025 5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5,134.20 5,134.20 5,134.20 5,134.20 5,134.20 5,134.20 0.00 0.00 0.00 20,536.80
Encofrado de cimentación m2 19.54 - 19.54 9.77 26/04/2025 27/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.77 9.77 0.00 0.00 0.00 19.54
x Colocación de concreto de cimentación m3 97.70 - 97.70 97.70 28/04/2025 28/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 97.70 0.00 0.00 97.70
Escarificado de cimentación para encofrado de pedestal m2 48.85 - 48.85 24.43 29/04/2025 30/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 24.43 24.43 48.85
Encofrado de pedestal m2 337.08 - 337.08 56.18 01/05/2025 06/05/2025 6 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Instalación de polylock ml 195.41 - 195.41 65.14 03/05/2025 05/05/2025 3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Instalación de pernos de anclaje Und 90.00 - 90.00 15.00 06/05/2025 11/05/2025 6 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Colocación de concreto de pedestal m3 84.27 - 84.27 84.27 12/05/2025 12/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de pedestal m2 337.08 - 337.08 168.54 14/05/2025 15/05/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Muros de Contención M-3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M3 - N°34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para pantalla m3 10.24 - 10.24 10.24 4/19/2025 19/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.24 0.00 0.00 0.00 0.00 10.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de pantalla m2 84.18 - 84.18 42.09 4/20/2025 21/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 42.09 42.09 0.00 0.00 84.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desarmado de andamios Glb 1.00 - 1.00 1.00 4/21/2025 21/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Muro M3 - N° 33 (COMPLETADO 100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M3 - Esquina N°4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para pantalla m3 11.92 - 11.92 11.92 4/19/2025 19/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11.92 0.00 0.00 0.00 0.00 11.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de pantalla m2 92.94 - 92.94 46.47 4/20/2025 21/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 46.47 46.47 0.00 0.00 92.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desarmado de andamios Glb 1.00 - 1.00 1.00 4/21/2025 21/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Muro M3 - N°32 (COMPLETADO 100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M3 - N°31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para pantalla m3 10.24 - 10.24 10.24 4/21/2025 21/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.24 0.00 0.00 10.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de pantalla m2 84.18 - 84.18 42.09 4/22/2025 23/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 42.09 42.09 84.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desarmado de andamios Glb 1.00 - 1.00 1.00 4/23/2025 23/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Muro M3 - N°30 (COMPLETADO 100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M3 - N°29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para pantalla m3 10.24 - 10.24 10.24 4/21/2025 21/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.24 0.00 0.00 10.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de pantalla m2 84.18 - 84.18 42.09 4/22/2025 23/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 42.09 42.09 84.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desarmado de andamios Glb 1.00 - 1.00 1.00 4/23/2025 23/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Muro M3 - N°28 (COMPLETADO 100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M3 - N°27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Armado de andamios para encofrados y vaciado de concreto Glb 1.00 - 1.00 1.00 4/23/2025 23/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Montaje de encofrado para pantalla (inc. polylock, waterstop y ochavos) m2 84.18 - 84.18 21.05 4/23/2025 26/04/2025 4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 21.05 21.05 21.05 21.05 21.05 0.00 0.00 0.00 0.00 63.14
x Concreto f'c=350 kg/cm2 para pantalla m3 10.24 - 10.24 10.24 4/27/2025 27/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.24 0.00 0.00 0.00 10.24
Desencofrado de pantalla m2 84.18 - 84.18 42.09 4/29/2025 30/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 42.09 42.09 84.18
Desarmado de andamios Glb 1.00 - 1.00 1.00 4/30/2025 30/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 1.00
x Muro M3 - N°26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Armado de andamios para culminación de acerto de refuerzo en pantalla,
Glb 1.00 - 1.00 1.00 5/1/2025 01/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
colocación de insertos, encofrados y vaciado de concreto
Acero de refuerzo para pantalla (horizontal) Kg 221.00 - 221.00 221.00 5/1/2025 01/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Instalación de insertos para soportes de tubería Und 2.00 - 2.00 2.00 5/1/2025 01/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Montaje de encofrado para pantalla (inc. polylock, waterstop y ochavos) m2 84.18 - 84.18 21.05 5/2/2025 05/05/2025 4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para pantalla m3 10.24 - 10.24 10.24 5/6/2025 06/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de pantalla m2 84.18 - 84.18 42.09 5/7/2025 08/05/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desarmado de andamios Glb 1.00 - 1.00 1.00 5/8/2025 08/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M3 - N°25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Armado de andamios para encofrados y vaciado de concreto Glb 1.00 - 1.00 1.00 4/23/2025 23/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Montaje de encofrado para pantalla (inc. polylock, waterstop y ochavos) m2 84.18 - 84.18 21.05 4/23/2025 26/04/2025 4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 21.05 21.05 21.05 21.05 21.05 0.00 0.00 0.00 0.00 63.14
x Concreto f'c=350 kg/cm2 para pantalla m3 10.24 - 10.24 10.24 4/27/2025 27/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.24 0.00 0.00 0.00 10.24
Desencofrado de pantalla m2 84.18 - 84.18 42.09 4/29/2025 30/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 42.09 42.09 84.18
Desarmado de andamios Glb 1.00 - 1.00 1.00 4/30/2025 30/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 1.00
x Muro M3 - N°24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Armado de andamios para encofrados y vaciado de concreto Glb 1.00 - 1.00 1.00 4/22/2025 22/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Montaje de encofrado para pantalla (inc. polylock, waterstop y ochavos) m2 84.18 - 84.18 21.05 4/22/2025 25/04/2025 4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 21.05 21.05 42.09 21.05 21.05 0.00 0.00 0.00 0.00 0.00 42.09
x Concreto f'c=350 kg/cm2 para pantalla m3 10.24 - 10.24 10.24 4/26/2025 26/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.24 0.00 0.00 0.00 0.00 10.24
Desencofrado de pantalla m2 84.18 - 84.18 42.09 4/29/2025 30/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 42.09 42.09 84.18
Desarmado de andamios Glb 1.00 - 1.00 1.00 4/30/2025 30/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 1.00
x Muro M3 - N°23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Armado de andamios para encofrados y vaciado de concreto Glb 1.00 - 1.00 1.00 4/23/2025 23/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Montaje de encofrado para pantalla (inc. polylock, waterstop y ochavos) m2 84.18 - 84.18 21.05 4/14/2025 17/04/2025 4 0.00 0.00 0.00 0.00 21.05 21.05 21.05 63.14 21.05 0.00 0.00 0.00 0.00 0.00 0.00 21.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para pantalla m3 10.24 - 10.24 10.24 4/18/2025 18/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.24 0.00 0.00 0.00 0.00 0.00 10.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de pantalla m2 84.18 - 84.18 42.09 4/20/2025 21/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 42.09 42.09 0.00 0.00 84.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desarmado de andamios Glb 1.00 - 1.00 1.00 4/21/2025 21/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M3 - N°22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Armado de andamios para encofrados y vaciado de concreto Glb 1.00 - 1.00 1.00 5/3/2025 03/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Montaje de encofrado para pantalla (inc. polylock, waterstop y ochavos) m2 84.18 - 84.18 21.05 5/3/2025 06/05/2025 4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para pantalla m3 10.24 - 10.24 10.24 5/7/2025 07/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de pantalla m2 84.18 - 84.18 42.09 5/10/2025 11/05/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desarmado de andamios Glb 1.00 - 1.00 1.00 5/11/2025 11/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M3 - N°21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Armado de andamios para encofrados y vaciado de concreto Glb 1.00 - 1.00 1.00 4/24/2025 24/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00
Montaje de encofrado para pantalla (inc. polylock, waterstop y ochavos) m2 84.18 - 84.18 21.05 4/25/2025 28/04/2025 4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 21.05 21.05 21.05 21.05 0.00 0.00 84.18
x Concreto f'c=350 kg/cm2 para pantalla m3 10.24 - 10.24 10.24 4/29/2025 29/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.24 0.00 10.24
Desencofrado de pantalla m2 84.18 - 84.18 42.09 5/1/2025 02/05/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desarmado de andamios Glb 1.00 - 1.00 1.00 5/2/2025 02/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M3 - Esquina N°3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Armado de andamios para encofrados y vaciado de concreto Glb 1.00 - 1.00 1.00 5/3/2025 03/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Montaje de encofrado para pantalla (inc. polylock, waterstop y ochavos) m2 84.18 - 84.18 21.05 5/3/2025 06/05/2025 4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para pantalla m3 10.24 - 10.24 10.24 5/7/2025 07/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de pantalla m2 84.18 - 84.18 42.09 5/10/2025 11/05/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desarmado de andamios Glb 1.00 - 1.00 1.00 5/11/2025 11/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Muro M3 - N°20 (COMPLETADO 100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M3 - N°19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Armado de andamios para encofrados y vaciado de concreto Glb 1.00 - 1.00 1.00 5/4/2025 04/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Montaje de encofrado para pantalla (inc. polylock, waterstop y ochavos) m2 84.18 - 84.18 21.05 5/4/2025 07/05/2025 4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para pantalla m3 10.24 - 10.24 10.24 5/8/2025 08/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de pantalla m2 84.18 - 84.18 42.09 5/11/2025 12/05/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desarmado de andamios Glb 1.00 - 1.00 1.00 5/12/2025 12/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Muros de Contención M-2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Fo.JJC-CG-05-03 Rev.0 Planificación Intermedia (PI)


x Muro M2 - N°16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para pantalla m3 19.37 - 19.37 19.37 4/21/2025 21/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 19.37 0.00 0.00 19.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de pantalla m2 115.01 - 115.01 57.50 4/23/2025 24/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 57.50 57.50 57.50 0.00 0.00 0.00 0.00 0.00 0.00 57.50
Desarmado de andamios Glb 1.00 - 1.00 1.00 4/24/2025 24/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00
Muro M2 - N°37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Armado de andamios para encofrados y vaciado de concreto Glb 1.00 - 1.00 1.00 4/24/2025 24/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00
Montaje de encofrado para pantalla (inc. polylock, waterstop y ochavos) m2 115.01 - 115.01 28.75 4/26/2025 29/04/2025 4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 28.75 28.75 28.75 28.75 0.00 115.01
Concreto f'c=350 kg/cm2 para pantalla m3 19.37 - 19.37 19.37 4/30/2025 30/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 19.37 19.37
Desencofrado de pantalla m2 115.01 - 115.01 57.50 5/2/2025 03/05/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desarmado de andamios Glb 1.00 - 1.00 1.00 5/3/2025 03/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Modificación de cimentaciones de muros M-1 (cimentación vaciada) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M1 - N° ESQ-01 - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado para zapata m2 12.20 - 12.20 12.20 4/21/2025 21/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12.20 0.00 0.00 12.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para zapata m3 10.70 - 10.70 10.70 4/22/2025 22/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.70 0.00 10.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de zapata m2 12.20 - 12.20 12.20 4/23/2025 23/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12.20 12.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Muro M1 - N° 001 (COMPLETADO 100%) - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Muro M1 - N° 002 (COMPLETADO 100%) - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

x Muro M1 - N° 005 - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para zapata m3 12.51 - 12.51 12.51 4/17/2025 4/17/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12.51 0.00 0.00 0.00 0.00 0.00 0.00 12.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de zapata m2 12.68 - 12.68 12.68 4/18/2025 4/18/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12.68 0.00 0.00 0.00 0.00 0.00 12.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Muro M1 - N° 006 (COMPLETADO 100%) - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Muro M1 - N° 007 (COMPLETADO 100%) - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

x Muro M1 - N° 008 (COMPLETADO 100%) - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Muro M1 - N° 009 (COMPLETADO 100%) - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

x Muro M1 - N° 013 (COMPLETADO 100%) - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

x Muro M1 - N° 014 - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=280 kg/cm2 para zapata m3 9.04 - 9.04 9.04 4/18/2025 4/18/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.04 0.00 0.00 0.00 0.00 0.00 9.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de zapata m2 9.93 - 9.93 9.93 4/19/2025 4/19/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.93 0.00 0.00 0.00 0.00 9.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Modificación de cimentaciones de muros M-1 (cimentación no vaciada) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Muro M1 - N°03 (COMPLETADO 100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M1 - N°04 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado de zapata m2 19.68 - 19.68 19.68 4/19/2025 19/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 19.68 0.00 0.00 0.00 0.00 19.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para zapata m3 27.36 - 27.36 27.36 4/20/2025 20/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 27.36 0.00 0.00 0.00 27.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de zapata m2 19.68 - 19.68 19.68 4/21/2025 21/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 19.68 0.00 0.00 19.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M1 - N°39 (COMPLETADO 100%) - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para zapata m3 21.28 - 21.28 21.28 4/20/2025 20/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 21.28 0.00 0.00 0.00 21.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de zapata m2 17.28 - 17.28 17.28 4/21/2025 21/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 17.28 0.00 0.00 17.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M1 - N° 010 - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Liberación de fundación para buzones A
Glb 1.00 - 1.00 1.00 12/04/2025 12/04/2025 1 0.00 0.00 1.00 0.00 0.00 0.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
r
Solado de concreto m2
m 34.20 - 34.20 34.20 4/13/2025 13/04/2025 1 0.00 0.00 0.00 34.20 0.00 0.00 0.00 34.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Montaje de Acero de refuerzo para zapata (contractual) akg 1,058.82 - 1,058.82 1,058.82 4/14/2025 14/04/2025 1 0.00 0.00 0.00 0.00 1,058.82 0.00 0.00 1,058.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
d
Acero de refuerzo para ensanchamiento de zapata (Reforzamiento) okg 909.67 909.67 909.67 4/15/2025 15/04/2025 1 0.00 0.00 0.00 0.00 0.00 909.67 0.00 909.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Armado de andamios para aceros verticales gbl 1.00 - 1.00 1.00 4/16/2025 16/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
y
Montaje de Acero de refuerzo para pantalla (contractual) kg 4,642.76 - 4,642.76 1,547.59 4/17/2025 19/04/2025 3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,547.59 1,547.59 1,547.59 0.00 0.00 0.00 0.00 4,642.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Acero de refuerzo para ensanchamiento de pantalla (Reforzamiento) Rkg 1,093.90 - 1,093.90 546.95 4/20/2025 21/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 546.95 546.95 0.00 0.00 1,093.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
e
Retiro de andamios para aceros verticales tgbl 1.00 - 1.00 1.00 4/22/2025 22/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado para zapata im2 20.48 - 20.48 20.48 4/22/2025 22/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 20.48 0.00 20.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
r
x Concreto f'c=280 kg/cm2 para zapata om3 27.36 - 27.36 27.36 4/23/2025 23/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 27.36 27.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de zapata m2 20.48 - 20.48 20.48 4/24/2025 24/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 20.48 0.00 0.00 0.00 0.00 0.00 0.00 20.48
d
Muro M1 - N° 011 e - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Liberación de fundación para buzones Glb 1.00 - 1.00 1.00 12/04/2025 12/04/2025 1 0.00 0.00 1.00 0.00 0.00 0.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
a
Solado de concreto nm2 34.20 - 34.20 34.20 4/13/2025 13/04/2025 1 0.00 0.00 0.00 34.20 0.00 0.00 0.00 34.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
d
Montaje de Acero de refuerzo para zapata (contractual) kg 1,058.82 - 1,058.82 1,058.82 4/25/2025 25/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,058.82 0.00 0.00 0.00 0.00 0.00 1,058.82
a
Acero de refuerzo para ensanchamiento de zapata (Reforzamiento) m kg 909.67 909.67 909.67 4/26/2025 26/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 909.67 0.00 0.00 0.00 0.00 909.67
i
Armado de andamios para aceros verticales gbl 1.00 - 1.00 1.00 4/27/2025 27/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 0.00 0.00 1.00
o
Montaje de Acero de refuerzo para pantalla (contractual) skg 4,642.76 - 4,642.76 1,160.69 4/28/2025 01/05/2025 4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,160.69 1,160.69 1,160.69 3,482.07
Acero de refuerzo para ensanchamiento de pantalla (Reforzamiento) kg 1,093.90 - 1,093.90 1,093.90 5/2/2025 02/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
p
Retiro de andamios para aceros verticales agbl 1.00 - 1.00 1.00 5/3/2025 03/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
r
Encofrado para zapata m2 20.48 - 20.48 20.48 5/3/2025 03/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
a
Concreto f'c=280 kg/cm2 para zapata m3 27.36 - 27.36 27.36 5/4/2025 04/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
a
Desencofrado de zapata m2 20.48 - 20.48 20.48 5/5/2025 05/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
c
x Muro M1 - N° 012 e 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
r
x Concreto f'c=280 kg/cm2 para zapata om3 27.36 - 27.36 27.36 4/20/2025 20/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 27.36 0.00 0.00 0.00 27.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de zapata sm2 20.48 - 20.48 20.48 4/21/2025 21/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 20.48 0.00 0.00 20.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M1 - N° ESQ-02 v 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
e
Posicionamiento de malla de acero rGlb 1.00 - 1.00 1.00 20/04/2025 20/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 0.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Ensanchamiento de armadura de acero de refuerzo para cimentación tkg 1,137.09 - 1,137.09 568.54 4/20/2025 21/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 568.54 568.54 0.00 0.00 1,137.09 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
i
Armado de andamios para aceros verticales cgbl 1.00 - 1.00 1.00 4/22/2025 22/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Instalación de nuevo acero de refuerzo refuerzo vertical de pantalla akg 1,367.38 - 1,367.38 683.69 4/23/2025 24/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 683.69 683.69 683.69 0.00 0.00 0.00 0.00 0.00 0.00 683.69
l
Retiro de andamios para aceros verticales egbl 1.00 - 1.00 1.00 4/25/2025 25/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 1.00
Encofrado para zapata sm2 25.60 - 25.60 25.60 4/25/2025 25/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 25.60 0.00 0.00 0.00 0.00 0.00 25.60
x Concreto f'c=350 kg/cm2 para zapata m3 27.40 - 27.40 27.40 4/26/2025 26/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 27.40 0.00 0.00 0.00 0.00 27.40
Desencofrado de zapata m2 20.50 - 20.50 20.50 4/27/2025 27/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 20.50 0.00 0.00 0.00 20.50
Muro M1 - N° 015 (COMPLETADO 100%) - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Calzaduras de Tks 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Tk-48 - Lado Sur 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado m2 80.00 24.0 56.00 18.67 4/4/2025 07/04/2025 3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Colocación de concreto m3 180.00 - 180.00 60.00 4/8/2025 10/04/2025 3 60.00 0.00 0.00 0.00 0.00 0.00 0.00 60.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado m2 80.00 - 80.00 80.00 4/11/2025 11/04/2025 1 0.00 80.00 0.00 0.00 0.00 0.00 0.00 80.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Tk-49 - Lado Sur 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Perfilado y limpieza de calzadura gbl 1.00 - 1.00 1.00 4/20/2025 20/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 0.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado m2 80.00 - 80.00 40.00 4/21/2025 22/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 40.00 40.00 0.00 80.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Colocación de concreto m3 180.00 - 180.00 60.00 4/23/2025 25/04/2025 3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 60.00 60.00 60.00 60.00 0.00 0.00 0.00 0.00 0.00 120.00
Desencofrado m2 80.00 - 80.00 80.00 4/26/2025 26/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 80.00 0.00 0.00 0.00 0.00 80.00
Construcción de muros M-1 (Lado Sur) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M1 - N° 009 - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Armado de andamios gbl 1.00 - 1.00 0.50 3/20/2025 21/03/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Colocación de insertos en muro und 2.00 - 2.00 2.00 3/22/2025 22/03/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Pre-armado de encofrado de muro gbl 1.00 - 1.00 0.33 3/21/2025 23/03/2025 3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Suministro e instalación de polylock en muro ml 9.00 - 9.00 4.50 3/22/2025 23/03/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Fo.JJC-CG-05-03 Rev.0 Planificación Intermedia (PI)


Encofrado de muro m2 146.00 65.0 81.00 81.00 4/1/2025 01/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para Muro m3 41.00 41.00 41.00 4/10/2025 10/04/2025 1 41.00 0.00 0.00 0.00 0.00 0.00 0.00 41.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de muro m2 146.00 146.00 146.00 4/12/2025 12/04/2025 1 0.00 0.00 146.00 0.00 0.00 0.00 0.00 146.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M1 - N° 001 - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Armado de andamios gbl 1.00 - 1.00 0.50 3/26/2025 27/03/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Pre-armado de encofrado de muro gbl 1.00 - 1.00 0.33 3/27/2025 29/03/2025 3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Colocación de insertos en muro und 2.00 - 2.00 2.00 3/30/2025 30/03/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Suministro e instalación de polylock en muro ml 9.00 - 9.00 4.50 3/31/2025 01/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado de muro m2 146.00 73.0 73.00 73.00 4/9/2025 09/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para Muro m3 41.00 41.00 41.00 4/10/2025 10/04/2025 1 41.00 0.00 0.00 0.00 0.00 0.00 0.00 41.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de muro m2 146.00 146.00 146.00 4/12/2025 12/04/2025 1 0.00 0.00 146.00 0.00 0.00 0.00 0.00 146.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
LINEA DE MEDIA TENSIÓN 0.00 ### ### ### ### ### ### 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Banco de ductos - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Excavación para banco de ductos Tramo 1 ml 15.40 - 15.40 5.13 4/14/2025 16/04/2025 3 0.00 0.00 0.00 0.00 5.13 5.13 5.13 15.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Perfilado de Excavación para banco de ductos Tramo 5 glb 1.00 1.0 - - 3/27/2025 28/03/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Perfilado de Excavación para banco de ductos Tramo 4 glb 1.00 0.1 0.86 0.14 4/9/2025 14/04/2025 6 0.14 0.14 0.14 0.14 0.14 0.00 0.00 0.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Perfilado de Excavación para banco de ductos Tramo 3 glb 1.00 - 1.00 0.33 4/15/2025 17/04/2025 3 0.00 0.00 0.00 0.00 0.00 0.33 0.33 0.67 0.33 0.00 0.00 0.00 0.00 0.00 0.00 0.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Perfilado de Excavación para banco de ductos Tramo 2 glb 1.00 - 1.00 0.33 4/18/2025 20/04/2025 3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.33 0.33 0.33 0.00 0.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Perfilado de Excavación para banco de ductos Tramo 1 glb 1.00 - 1.00 0.20 4/21/2025 25/04/2025 5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.20 0.20 0.20 0.60 0.20 0.20 0.00 0.00 0.00 0.00 0.00 0.40
SISTEMA CONTRAINCENDIO (SCI) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Casa de valvula hacia el cubeto 4 (generar acceso LADO ESTE ) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Excavación lado este ml 72.00 36.0 36.00 18.00 17/04/2025 4/18/2025 2.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18.00 18.00 0.00 0.00 0.00 0.00 0.00 36.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Fo.JJC-CG-05-03 Rev.0 Planificación Intermedia (PI)


PROGRAMA DE CONCRETO
PROYECTO:
AMPLIACIÓN DE LA CAPACIDAD DE ALMACENAMIENTO DEL TERMINAL MOLLENDO EN 420 MBLS BRUTOS

DESCRIPCIÓN TIPO CONCRETO FECHA ELEMENTO

TANQUES
TANQUE TK-41 - COMPLETADO
TANQUE TK-42 - COMPLETADO
TANQUE TK-43 - 45.41 4/17/2025 ANILLO
TANQUE TK-44 - 45.41 4/18/2025 ANILLO
TANQUE TK-45 - 25.37 4/29/2025 ANILLO
TANQUE TK-46 - 22.06 4/19/2025 CIMENTACIÓN
- 25.37 4/30/2025 ANILLO
TANQUE TK-47 - 97.70 4/21/2025 CIMENTACIÓN
- 84.27 5/4/2025 ANILLO
TANQUE TK-47 - 97.70 4/28/2025 CIMENTACIÓN
- 84.27 5/12/2025 ANILLO
MUROS M-3
MURO N°19 M3 10.24 5/8/2025 PANTALLA
MURO N°20 M3D COMPLETADO
MURO ESQ. N°3 M3C 10.24 5/7/2025 PANTALLA
MURO N°21 M3 10.24 4/29/2025 PANTALLA
MURO N°22 M3 10.24 5/7/2025 PANTALLA
MURO N°23 M3 10.24 4/18/2025 PANTALLA
MURO N°24 M3 10.24 4/26/2025 PANTALLA
MURO N°25 M3 10.24 4/27/2025 PANTALLA
MURO N°26 M3 10.24 5/6/2025 PANTALLA
MURO N°27 M3 10.24 4/27/2025 PANTALLA
MURO N°28 M3 COMPLETADO
MURO N°29 M3 10.24 4/21/2025 PANTALLA
MURO N°30 M3 COMPLETADO
MURO N°31 M3 10.24 4/21/2025 PANTALLA
MURO N°32 M3 COMPLETADO
MURO ESQUINA N°4 M3B 11.92 4/19/2025 PANTALLA
MURO N°33 M3A COMPLETADO
MURO N°34 M3 10.24 4/19/2025 PANTALLA
MUROS M-2
MURO N°16 M2 19.37 4/21/2025 PANTALLA
MURO N°17 M2 PENDIENTE SOLADO
PENDIENTE ZAPATA
PENDIENTE PANTALLA
MURO N°18 M2A PENDIENTE SOLADO
PENDIENTE ZAPATA
PENDIENTE PANTALLA
MURO N°35 M2A PENDIENTE SOLADO
PENDIENTE ZAPATA
PENDIENTE PANTALLA
MURO N°36 M2 PENDIENTE SOLADO
PENDIENTE ZAPATA
PENDIENTE PANTALLA
PROGRAMA DE CONCRETO
PROYECTO:
AMPLIACIÓN DE LA CAPACIDAD DE ALMACENAMIENTO DEL TERMINAL MOLLENDO EN 420 MBLS BRUTOS

DESCRIPCIÓN TIPO CONCRETO FECHA ELEMENTO

MURO N°37 M2 19.37 4/30/2025 PANTALLA


Modificación de cimentaciones de muros M-1 (cimentación vaciada)
ESQUINA N°01 M1 10.70 4/22/2025 ZAPATA
MURO N°01 M1 COMPLETADO ZAPATA
MURO N°02 M1 COMPLETADO ZAPATA
MURO N°05 M1 12.51 4/17/2025 ZAPATA
MURO N°06 M1 COMPLETADO ZAPATA
MURO N°07 M1 COMPLETADO ZAPATA
MURO N°08 M1 COMPLETADO ZAPATA
MURO N°09 M1 COMPLETADO ZAPATA
MURO N°13 M1 COMPLETADO ZAPATA
MURO N°14 M1 9.04 4/18/2025 ZAPATA
Modificación de cimentaciones de muros M-1 (cimentación no vaciada)
MURO N°03 M1 COMPLETADO ZAPATA
MURO N°04 M1 27.36 4/20/2025 ZAPATA
MURO N°10 M1 27.36 4/23/2025 ZAPATA
MURO N°11 M1 27.36 5/4/2025 ZAPATA
MURO N°12 M1 27.36 4/20/2025 ZAPATA
ESQUINA N°02 M1 27.40 4/26/2025 ZAPATA
MURO N°15 M1 COMPLETADO ZAPATA
MURO N°39 M1 21.28 4/20/2025 ZAPATA
TOTALES 891.48
THREE WEEK LOOK AHEAD (TWLA)

PROYECTO: AMPLIACIÓN DE LA CAPACIDAD DE ALMACENAMIENTO DEL TERMINAL MOLLENDO EN 420 MBLS BRUTOS

CODIGO: TM07-003-60-PN-014 CLIENTE MONTE AZUL SUR

261.60 108.68 284.58 124.91 6,475.63 6,333.67 5,254.97 18,844.05


SEMANA 33
Metrado Fecha Inicio Fecha Fin Fecha Inicio Fecha Fin
Item Activity ID Descripción de la Actividad Und Metrado total Metrado restante Rend. Ratio HH Total HH Duración J V S D L M M Metrado
acumulado Programada Programada Real Real
10 11 12 13 14 15 16 Semanal
Tanques 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Cimiento Tanque TK-41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Liberación de fundación para buzones Glb 1.00 - 1.00 1.00 07/04/2025 07/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Solado de concreto para buzones m2 4.00 - 4.00 4.00 08/04/2025 08/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Acero de refuerzo para buzones Kg 93.86 - 93.86 93.86 09/04/2025 09/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado de buzones m2 22.56 - 22.56 11.28 09/04/2025 10/04/2025 2 11.28 0.00 0.00 0.00 0.00 0.00 0.00 11.28
Concreto para buzones m3 2.02 - 2.02 2.02 11/04/2025 11/04/2025 1 0.00 2.02 0.00 0.00 0.00 0.00 0.00 2.02
Desencofrado de buzones m2 22.56 - 22.56 22.56 13/04/2025 13/04/2025 1 0.00 0.00 0.00 22.56 0.00 0.00 0.00 22.56
Escarificado de pedestal para instalacion de grout Glb 1.00 0.50 0.50 0.50 10/04/2025 10/04/2025 1 0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.50
Encofrado de pedestal para grout Glb 1.00 - 1.00 0.33 11/04/2025 13/04/2025 3 0.00 0.33 0.33 0.33 0.00 0.00 0.00 1.00
Humedecimiento de pedestal para colocación de grout Glb 1.00 - 1.00 0.50 14/04/2025 15/04/2025 2 0.00 0.00 0.00 0.00 0.50 0.50 0.00 1.00
Instalacion de Grout Glb 1.00 - 1.00 1.00 16/04/2025 16/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 1.00 1.00
Desencofrado de Grout Glb 1.00 - 1.00 1.00 17/04/2025 17/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Cimiento Tanque TK-42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Liberación de fundación para buzones Glb 1.00 - 1.00 1.00 10/04/2025 10/04/2025 1 1.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00
Solado de concreto para buzones m2 4.00 - 4.00 4.00 11/04/2025 11/04/2025 1 0.00 4.00 0.00 0.00 0.00 0.00 0.00 4.00
Acero de refuerzo para buzones Kg 93.86 - 93.86 93.86 12/04/2025 12/04/2025 1 0.00 0.00 93.86 0.00 0.00 0.00 0.00 93.86
Encofrado de buzones m2 22.56 - 22.56 11.28 12/04/2025 13/04/2025 2 0.00 0.00 11.28 11.28 0.00 0.00 0.00 22.56
Concreto para buzones m3 2.02 - 2.02 2.02 14/04/2025 14/04/2025 1 0.00 0.00 0.00 0.00 2.02 0.00 0.00 2.02
Desencofrado de buzones m2 22.56 - 22.56 22.56 16/04/2025 16/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 22.56 22.56
Escarificado de pedestal para instalacion de grout Glb 1.00 - 1.00 1.00 13/04/2025 13/04/2025 1 0.00 0.00 0.00 1.00 0.00 0.00 0.00 1.00
Encofrado de pedestal para grout Glb 1.00 - 1.00 0.33 14/04/2025 16/04/2025 3 0.00 0.00 0.00 0.00 0.33 0.33 0.33 1.00
Humedecimiento de pedestal para colocación de grout Glb 1.00 - 1.00 0.50 17/04/2025 18/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Instalacion de Grout Glb 1.00 - 1.00 1.00 19/04/2025 19/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de Grout Glb 1.00 - 1.00 1.00 20/04/2025 20/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Cimiento Tanque TK-43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para pedestales (anillo de tanque) m3 45.41 - 45.41 45.41 14/04/2025 14/04/2025 1 0.00 0.00 0.00 0.00 45.41 0.00 0.00 45.41
Desencofrado de pedestal m2 184.26 - 184.26 92.13 17/04/2025 18/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Liberación de fundación para buzones Glb 1.00 - 1.00 1.00 19/04/2025 19/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Solado de concreto para buzones m2 4.00 - 4.00 4.00 20/04/2025 20/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Acero de refuerzo para buzones Kg 93.86 - 93.86 93.86 21/04/2025 21/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado de buzones m2 22.56 - 22.56 11.28 21/04/2025 22/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Concreto para buzones m3 2.02 - 2.02 2.02 23/04/2025 23/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de buzones m2 22.56 - 22.56 22.56 25/04/2025 25/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Escarificado de pedestal para instalacion de grout Glb 1.00 - 1.00 1.00 26/04/2025 26/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado de pedestal para grout Glb 1.00 - 1.00 0.33 27/04/2025 29/04/2025 3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Humedecimiento de pedestal para colocación de grout Glb 1.00 - 1.00 0.50 30/04/2025 01/05/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Instalacion de Grout Glb 1.00 - 1.00 1.00 02/05/2025 02/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de Grout Glb 1.00 - 1.00 1.00 03/05/2025 03/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Cimiento Tanque TK-44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Instalación de polylock en anillo m 106.82 - 106.82 106.82 10/04/2025 10/04/2025 1 106.82 0.00 0.00 0.00 0.00 0.00 0.00 106.82
Instalación de pernos de anclaje Und 64.00 64.00 21.33 11/04/2025 13/04/2025 3 0.00 21.33 21.33 21.33 0.00 0.00 0.00 64.00
x Concreto f'c=350 kg/cm2 para pedestales (anillo de tanque) m3 45.41 - 45.41 45.41 15/04/2025 15/04/2025 1 0.00 0.00 0.00 0.00 0.00 45.41 0.00 45.41
Desencofrado de pedestal m2 184.26 - 184.26 92.13 18/04/2025 19/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Liberación de fundación para buzones Glb 1.00 - 1.00 1.00 16/04/2025 16/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 1.00 1.00
Solado de concreto para buzones m2 4.00 - 4.00 4.00 17/04/2025 17/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Acero de refuerzo para buzones Kg 93.86 - 93.86 93.86 18/04/2025 18/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado de buzones m2 22.56 - 22.56 11.28 18/04/2025 19/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Concreto para buzones m3 2.02 - 2.02 2.02 20/04/2025 20/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de buzones m2 22.56 - 22.56 22.56 22/04/2025 22/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Escarificado de pedestal para instalacion de grout Glb 1.00 - 1.00 1.00 23/04/2025 23/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado de pedestal para grout Glb 1.00 - 1.00 0.33 24/04/2025 26/04/2025 3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Humedecimiento de pedestal para colocación de grout Glb 1.00 - 1.00 0.50 27/04/2025 28/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Instalacion de Grout Glb 1.00 - 1.00 1.00 29/04/2025 29/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de Grout Glb 1.00 - 1.00 1.00 30/04/2025 30/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Cimiento Tanque TK-45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado de pedestal m2 101.45 - 101.45 33.82 19/04/2025 21/04/2025 3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Instalación de pases para tubería HDPE 2" Und 4.00 - 4.00 4.00 20/04/2025 20/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Instalación de polylock en anillo ml 58.81 - 58.81 58.81 21/04/2025 21/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Instalación de pernos de anclaje Und 50.00 - 50.00 12.50 22/04/2025 25/04/2025 4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para pedestales (anillo de tanque) m3 25.37 - 25.37 25.37 26/04/2025 26/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de pedestal m2 101.45 - 101.45 50.73 29/04/2025 30/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Cimiento Tanque TK-46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para zapata (contra terreno) m3 22.06 - 22.06 22.06 16/04/2025 16/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 22.06 22.06

Fo.JJC-CG-05-03 Rev.0 Planificación Intermedia (PI)


Escarificado de cimentación para encofrado de pedestal m2 14.71 - 14.71 14.71 17/04/2025 17/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado de pedestal m2 101.45 - 101.45 33.82 20/04/2025 22/04/2025 3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Instalación de pases para tubería HDPE 2" Und 4.00 - 4.00 4.00 21/04/2025 21/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Instalación de polylock en anillo ml 58.81 - 58.81 58.81 22/04/2025 22/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Instalación de pernos de anclaje Und 44.00 - 44.00 11.00 23/04/2025 26/04/2025 4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para pedestales (anillo de tanque) m3 25.37 - 25.37 25.37 27/04/2025 27/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de pedestal m2 101.45 - 101.45 50.73 30/04/2025 01/05/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Cimiento Tanque TK-47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Excavación de cimentación Glb 1.00 - 1.00 1.00 11/04/2025 11/04/2025 1 0.00 1.00 0.00 0.00 0.00 0.00 0.00 1.00
x Solado de cimentación m3 9.77 - 9.77 9.77 12/04/2025 12/04/2025 1 0.00 0.00 9.77 0.00 0.00 0.00 0.00 9.77
Colocación de acero de cimentación kg 10,670.00 - 10,670.00 5,335.00 14/04/2025 15/04/2025 2 0.00 0.00 0.00 0.00 5,335.00 5,335.00 0.00 10,670.00
Colocación de acero de pedestal kg 25,671.00 - 25,671.00 5,134.20 16/04/2025 20/04/2025 5 0.00 0.00 0.00 0.00 0.00 0.00 5,134.20 5,134.20
Encofrado de cimentación m2 19.54 - 19.54 9.77 19/04/2025 20/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Colocación de concreto de cimentación m3 97.70 - 97.70 97.70 21/04/2025 21/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Escarificado de cimentación para encofrado de pedestal m2 48.85 - 48.85 24.43 22/04/2025 23/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado de pedestal m2 337.08 - 337.08 56.18 24/04/2025 29/04/2025 6 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Instalación de polylock ml 195.41 - 195.41 65.14 26/04/2025 28/04/2025 3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Instalación de pernos de anclaje Und 70.00 - 70.00 14.00 29/04/2025 03/05/2025 5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Colocación de concreto de pedestal m3 84.27 - 84.27 84.27 04/05/2025 04/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de pedestal m2 337.08 - 337.08 168.54 06/05/2025 07/05/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Cimiento Tanque TK-48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Excavación de cimentación Glb 1.00 - 1.00 1.00 18/04/2025 18/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Solado de cimentación m3 9.77 - 9.77 9.77 19/04/2025 19/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Colocación de acero de cimentación kg 10,670.00 - 10,670.00 5,335.00 21/04/2025 22/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Colocación de acero de pedestal kg 25,671.00 - 25,671.00 5,134.20 23/04/2025 27/04/2025 5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado de cimentación m2 19.54 - 19.54 9.77 26/04/2025 27/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Colocación de concreto de cimentación m3 97.70 - 97.70 97.70 28/04/2025 28/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Escarificado de cimentación para encofrado de pedestal m2 48.85 - 48.85 24.43 29/04/2025 30/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado de pedestal m2 337.08 - 337.08 56.18 01/05/2025 06/05/2025 6 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Instalación de polylock ml 195.41 - 195.41 65.14 03/05/2025 05/05/2025 3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Instalación de pernos de anclaje Und 90.00 - 90.00 15.00 06/05/2025 11/05/2025 6 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Colocación de concreto de pedestal m3 84.27 - 84.27 84.27 12/05/2025 12/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de pedestal m2 337.08 - 337.08 168.54 14/05/2025 15/05/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Muros de Contención M-3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M3 - N°34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para pantalla m3 10.24 - 10.24 10.24 4/16/2025 16/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 10.24 10.24
Desencofrado de pantalla m2 84.18 - 84.18 42.09 4/17/2025 18/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desarmado de andamios Glb 1.00 - 1.00 1.00 4/18/2025 18/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Muro M3 - N° 33 (COMPLETADO 100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M3 - Esquina N°4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para pantalla m3 11.92 - 11.92 11.92 4/16/2025 16/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 11.92 11.92
Desencofrado de pantalla m2 92.94 - 92.94 46.47 4/17/2025 18/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desarmado de andamios Glb 1.00 - 1.00 1.00 4/18/2025 18/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Muro M3 - N°32 (COMPLETADO 100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M3 - N°31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para pantalla m3 10.24 - 10.24 10.24 4/18/2025 18/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de pantalla m2 84.18 - 84.18 42.09 4/19/2025 20/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desarmado de andamios Glb 1.00 - 1.00 1.00 4/20/2025 20/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Muro M3 - N°30 (COMPLETADO 100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M3 - N°29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para pantalla m3 10.24 - 10.24 10.24 4/18/2025 18/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de pantalla m2 84.18 - 84.18 42.09 4/19/2025 20/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desarmado de andamios Glb 1.00 - 1.00 1.00 4/20/2025 20/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Muro M3 - N°28 (COMPLETADO 100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M3 - N°27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Armado de andamios para encofrados y vaciado de concreto Glb 1.00 - 1.00 1.00 4/20/2025 20/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Montaje de encofrado para pantalla (inc. polylock, waterstop y ochavos) m2 84.18 - 84.18 21.05 4/20/2025 23/04/2025 4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para pantalla m3 10.24 - 10.24 10.24 4/24/2025 24/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de pantalla m2 84.18 - 84.18 42.09 4/26/2025 27/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desarmado de andamios Glb 1.00 - 1.00 1.00 4/27/2025 27/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M3 - N°26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Armado de andamios para culminación de acerto de refuerzo en pantalla,
Glb 1.00 - 1.00 1.00 4/28/2025 28/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
colocación de insertos, encofrados y vaciado de concreto
Acero de refuerzo para pantalla (horizontal) Kg 221.00 - 221.00 221.00 4/28/2025 28/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Instalación de insertos para soportes de tubería Und 2.00 - 2.00 2.00 4/28/2025 28/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Montaje de encofrado para pantalla (inc. polylock, waterstop y ochavos) m2 84.18 - 84.18 21.05 4/29/2025 02/05/2025 4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para pantalla m3 10.24 - 10.24 10.24 5/3/2025 03/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de pantalla m2 84.18 - 84.18 42.09 5/4/2025 05/05/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desarmado de andamios Glb 1.00 - 1.00 1.00 5/5/2025 05/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M3 - N°25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Armado de andamios para encofrados y vaciado de concreto Glb 1.00 - 1.00 1.00 4/20/2025 20/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Montaje de encofrado para pantalla (inc. polylock, waterstop y ochavos) m2 84.18 - 84.18 21.05 4/20/2025 23/04/2025 4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para pantalla m3 10.24 - 10.24 10.24 4/24/2025 24/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de pantalla m2 84.18 - 84.18 42.09 4/26/2025 27/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desarmado de andamios Glb 1.00 - 1.00 1.00 4/27/2025 27/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M3 - N°24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Armado de andamios para encofrados y vaciado de concreto Glb 1.00 - 1.00 1.00 4/22/2025 22/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Montaje de encofrado para pantalla (inc. polylock, waterstop y ochavos) m2 84.18 - 84.18 21.05 4/22/2025 25/04/2025 4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Fo.JJC-CG-05-03 Rev.0 Planificación Intermedia (PI)


x Concreto f'c=350 kg/cm2 para pantalla m3 10.24 - 10.24 10.24 4/26/2025 26/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de pantalla m2 84.18 - 84.18 42.09 4/29/2025 30/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desarmado de andamios Glb 1.00 - 1.00 1.00 4/30/2025 30/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M3 - N°23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Armado de andamios para encofrados y vaciado de concreto Glb 1.00 - 1.00 1.00 4/20/2025 20/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Montaje de encofrado para pantalla (inc. polylock, waterstop y ochavos) m2 84.18 - 84.18 21.05 4/14/2025 17/04/2025 4 0.00 0.00 0.00 0.00 21.05 21.05 21.05 63.14
x Concreto f'c=350 kg/cm2 para pantalla m3 10.24 - 10.24 10.24 4/18/2025 18/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de pantalla m2 84.18 - 84.18 42.09 4/20/2025 21/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desarmado de andamios Glb 1.00 - 1.00 1.00 4/21/2025 21/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M3 - N°22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Armado de andamios para encofrados y vaciado de concreto Glb 1.00 - 1.00 1.00 4/30/2025 30/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Montaje de encofrado para pantalla (inc. polylock, waterstop y ochavos) m2 84.18 - 84.18 21.05 4/30/2025 03/05/2025 4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para pantalla m3 10.24 - 10.24 10.24 5/4/2025 04/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de pantalla m2 84.18 - 84.18 42.09 5/7/2025 08/05/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desarmado de andamios Glb 1.00 - 1.00 1.00 5/8/2025 08/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M3 - N°21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Armado de andamios para encofrados y vaciado de concreto Glb 1.00 - 1.00 1.00 4/21/2025 21/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Montaje de encofrado para pantalla (inc. polylock, waterstop y ochavos) m2 84.18 - 84.18 21.05 4/22/2025 25/04/2025 4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para pantalla m3 10.24 - 10.24 10.24 4/26/2025 26/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de pantalla m2 84.18 - 84.18 42.09 4/28/2025 29/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desarmado de andamios Glb 1.00 - 1.00 1.00 4/29/2025 29/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M3 - Esquina N°3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Armado de andamios para encofrados y vaciado de concreto Glb 1.00 - 1.00 1.00 4/30/2025 30/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Montaje de encofrado para pantalla (inc. polylock, waterstop y ochavos) m2 84.18 - 84.18 21.05 4/30/2025 03/05/2025 4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para pantalla m3 10.24 - 10.24 10.24 5/4/2025 04/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de pantalla m2 84.18 - 84.18 42.09 5/7/2025 08/05/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desarmado de andamios Glb 1.00 - 1.00 1.00 5/8/2025 08/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Muro M3 - N°20 (COMPLETADO 100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M3 - N°19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Armado de andamios para encofrados y vaciado de concreto Glb 1.00 - 1.00 1.00 5/1/2025 01/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Montaje de encofrado para pantalla (inc. polylock, waterstop y ochavos) m2 84.18 - 84.18 21.05 5/1/2025 04/05/2025 4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para pantalla m3 10.24 - 10.24 10.24 5/5/2025 05/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de pantalla m2 84.18 - 84.18 42.09 5/8/2025 09/05/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desarmado de andamios Glb 1.00 - 1.00 1.00 5/9/2025 09/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Muros de Contención M-2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M2 - N°16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para pantalla m3 19.37 - 19.37 19.37 4/18/2025 18/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de pantalla m2 115.01 - 115.01 57.50 4/20/2025 21/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desarmado de andamios Glb 1.00 - 1.00 1.00 4/21/2025 21/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Muro M2 - N°37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Armado de andamios para encofrados y vaciado de concreto Glb 1.00 - 1.00 1.00 4/21/2025 21/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Montaje de encofrado para pantalla (inc. polylock, waterstop y ochavos) m2 115.01 - 115.01 28.75 4/23/2025 26/04/2025 4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Concreto f'c=350 kg/cm2 para pantalla m3 19.37 - 19.37 19.37 4/27/2025 27/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de pantalla m2 115.01 - 115.01 57.50 4/29/2025 30/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desarmado de andamios Glb 1.00 - 1.00 1.00 4/30/2025 30/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Modificación de cimentaciones de muros M-1 (cimentación vaciada) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M1 - N° ESQ-01 - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado para zapata m2 12.20 - 12.20 12.20 4/18/2025 18/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para zapata m3 10.70 - 10.70 10.70 4/18/2025 18/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de zapata m2 12.20 - 12.20 12.20 4/19/2025 19/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Muro M1 - N° 001 (COMPLETADO 100%) - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Muro M1 - N° 002 (COMPLETADO 100%) - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

x Muro M1 - N° 005 - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para zapata m3 12.51 - 12.51 12.51 4/14/2025 4/14/2025 1 0.00 0.00 0.00 0.00 12.51 0.00 0.00 12.51
Desencofrado de zapata m2 12.68 - 12.68 12.68 4/15/2025 4/15/2025 1 0.00 0.00 0.00 0.00 0.00 12.68 0.00 12.68
Muro M1 - N° 006 (COMPLETADO 100%) - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Muro M1 - N° 007 (COMPLETADO 100%) - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

x Muro M1 - N° 008 (COMPLETADO 100%) - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Muro M1 - N° 009 (COMPLETADO 100%) - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

x Muro M1 - N° 013 (COMPLETADO 100%) - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

x Muro M1 - N° 014 - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=280 kg/cm2 para zapata m3 9.04 - 9.04 9.04 4/15/2025 4/15/2025 1 0.00 0.00 0.00 0.00 0.00 9.04 0.00 9.04
Desencofrado de zapata m2 9.93 - 9.93 9.93 4/16/2025 4/16/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 9.93 9.93
Modificación de cimentaciones de muros M-1 (cimentación no vaciada) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Muro M1 - N°03 (COMPLETADO 100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M1 - N°04 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado de zapata m2 19.68 - 19.68 19.68 4/16/2025 16/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 19.68 19.68
x Concreto f'c=350 kg/cm2 para zapata m3 27.36 - 27.36 27.36 4/17/2025 17/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de zapata m2 19.68 - 19.68 19.68 4/18/2025 18/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M1 - N°39 (COMPLETADO 100%) - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para zapata m3 21.28 - 21.28 21.28 4/17/2025 17/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de zapata m2 17.28 - 17.28 17.28 4/18/2025 18/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M1 - N° 010 - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Liberación de fundación para buzones Glb 1.00 - 1.00 1.00 12/04/2025 12/04/2025 1 13/04/2025 0.00 0.00 1.00 0.00 0.00 0.00 0.00 1.00
Solado de concreto m2 34.20 - 34.20 34.20 4/13/2025 13/04/2025 1 0.00 0.00 0.00 34.20 0.00 0.00 0.00 34.20
Montaje de Acero de refuerzo para zapata (contractual) kg 1,058.82 - 1,058.82 1,058.82 4/14/2025 14/04/2025 1 0.00 0.00 0.00 0.00 1,058.82 0.00 0.00 1,058.82

Fo.JJC-CG-05-03 Rev.0 Planificación Intermedia (PI)


A
r
m
a
d
Acero de refuerzo para ensanchamiento de zapata (Reforzamiento) okg 909.67 909.67 909.67 4/15/2025 15/04/2025 1 0.00 0.00 0.00 0.00 0.00 909.67 0.00 909.67
Armado de andamios para aceros verticales gbl 1.00 - 1.00 1.00 4/16/2025 16/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 1.00 1.00
y
Montaje de Acero de refuerzo para pantalla (contractual) kg 4,642.76 - 4,642.76 1,547.59 4/17/2025 19/04/2025 3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Acero de refuerzo para ensanchamiento de pantalla (Reforzamiento) Rkg 1,093.90 - 1,093.90 546.95 4/20/2025 21/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
e
Retiro de andamios para aceros verticales tgbl 1.00 - 1.00 1.00 4/22/2025 22/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado para zapata im2 20.48 - 20.48 20.48 4/22/2025 22/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
r
x Concreto f'c=280 kg/cm2 para zapata om3 27.36 - 27.36 27.36 4/23/2025 23/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de zapata m2 20.48 - 20.48 20.48 4/24/2025 24/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
d
Muro M1 - N° 011 e - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Liberación de fundación para buzones Glb 1.00 - 1.00 1.00 12/04/2025 12/04/2025 1 0.00 0.00 1.00 0.00 0.00 0.00 0.00 1.00
a
Solado de concreto nm2 34.20 - 34.20 34.20 4/13/2025 13/04/2025 1 0.00 0.00 0.00 34.20 0.00 0.00 0.00 34.20
d
Montaje de Acero de refuerzo para zapata (contractual) kg 1,058.82 - 1,058.82 1,058.82 4/25/2025 25/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
a
Acero de refuerzo para ensanchamiento de zapata (Reforzamiento) m kg 909.67 909.67 909.67 4/26/2025 26/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
i
Armado de andamios para aceros verticales gbl 1.00 - 1.00 1.00 4/27/2025 27/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
o
Montaje de Acero de refuerzo para pantalla (contractual) skg 4,642.76 - 4,642.76 1,160.69 4/28/2025 01/05/2025 4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Acero de refuerzo para ensanchamiento de pantalla (Reforzamiento) kg 1,093.90 - 1,093.90 1,093.90 5/2/2025 02/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
p
Retiro de andamios para aceros verticales agbl 1.00 - 1.00 1.00 5/3/2025 03/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
r
Encofrado para zapata m2 20.48 - 20.48 20.48 5/3/2025 03/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
a
Concreto f'c=280 kg/cm2 para zapata m3 27.36 - 27.36 27.36 5/4/2025 04/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
a
Desencofrado de zapata m2 20.48 - 20.48 20.48 5/5/2025 05/05/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
c
x Muro M1 - N° 012 e 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
r
x Concreto f'c=280 kg/cm2 para zapata om3 27.36 - 27.36 27.36 4/17/2025 17/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de zapata sm2 20.48 - 20.48 20.48 4/18/2025 18/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M1 - N° ESQ-02 v 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
e
Posicionamiento de malla de acero Glb
r 1.00 - 1.00 1.00 17/04/2025 17/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Ensanchamiento de armadura de acero de refuerzo para cimentación tkg 1,137.09 - 1,137.09 568.54 4/17/2025 18/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
i
Armado de andamios para aceros verticales cgbl 1.00 - 1.00 1.00 4/19/2025 19/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Instalación de nuevo acero de refuerzo refuerzo vertical de pantalla akg 1,367.38 - 1,367.38 683.69 4/20/2025 21/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
l
Retiro de andamios para aceros verticales egbl 1.00 - 1.00 1.00 4/22/2025 22/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado para zapata sm2 25.60 - 25.60 25.60 4/22/2025 22/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para zapata m3 27.40 - 27.40 27.40 4/23/2025 23/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado de zapata m2 20.50 - 20.50 20.50 4/24/2025 24/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Muro M1 - N° 015 (COMPLETADO 100%) - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Calzaduras de Tks 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Tk-48 - Lado Sur 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado m2 80.00 24.0 56.00 18.67 4/4/2025 07/04/2025 3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Colocación de concreto m3 180.00 - 180.00 60.00 4/8/2025 10/04/2025 3 60.00 0.00 0.00 0.00 0.00 0.00 0.00 60.00
Desencofrado m2 80.00 - 80.00 80.00 4/11/2025 11/04/2025 1 0.00 80.00 0.00 0.00 0.00 0.00 0.00 80.00
x Tk-49 - Lado Sur 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Perfilado y limpieza de calzadura gbl 1.00 - 1.00 1.00 4/20/2025 20/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado m2 80.00 - 80.00 40.00 4/21/2025 22/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Colocación de concreto m3 180.00 - 180.00 60.00 4/23/2025 25/04/2025 3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Desencofrado m2 80.00 - 80.00 80.00 4/26/2025 26/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Construcción de muros M-1 (Lado Sur) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Muro M1 - N° 009 - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Armado de andamios gbl 1.00 - 1.00 0.50 3/20/2025 21/03/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Colocación de insertos en muro und 2.00 - 2.00 2.00 3/22/2025 22/03/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Pre-armado de encofrado de muro gbl 1.00 - 1.00 0.33 3/21/2025 23/03/2025 3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Suministro e instalación de polylock en muro ml 9.00 - 9.00 4.50 3/22/2025 23/03/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado de muro m2 146.00 65.0 81.00 81.00 4/1/2025 01/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para Muro m3 41.00 41.00 41.00 4/10/2025 10/04/2025 1 41.00 0.00 0.00 0.00 0.00 0.00 0.00 41.00
Desencofrado de muro m2 146.00 146.00 146.00 4/12/2025 12/04/2025 1 0.00 0.00 146.00 0.00 0.00 0.00 0.00 146.00
x Muro M1 - N° 001 - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Armado de andamios gbl 1.00 - 1.00 0.50 3/26/2025 27/03/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Pre-armado de encofrado de muro gbl 1.00 - 1.00 0.33 3/27/2025 29/03/2025 3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Colocación de insertos en muro und 2.00 - 2.00 2.00 3/30/2025 30/03/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Suministro e instalación de polylock en muro ml 9.00 - 9.00 4.50 3/31/2025 01/04/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Encofrado de muro m2 146.00 73.0 73.00 73.00 4/9/2025 09/04/2025 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
x Concreto f'c=350 kg/cm2 para Muro m3 41.00 41.00 41.00 4/10/2025 10/04/2025 1 41.00 0.00 0.00 0.00 0.00 0.00 0.00 41.00
Desencofrado de muro m2 146.00 146.00 146.00 4/12/2025 12/04/2025 1 0.00 0.00 146.00 0.00 0.00 0.00 0.00 146.00
LINEA DE MEDIA TENSIÓN
Banco de ductos - - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Excavación para banco de ductos Tramo 1 ml 15.40 - 15.40 5.13 33% 5.13 4/14/2025 16/04/2025 3 0.00 0.00 0.00 0.00 5.13 5.13 5.13 15.40
Perfilado de Excavación para banco de ductos Tramo 5 glb 1.00 1.0 - - 0% - 3/27/2025 28/03/2025 2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Perfilado de Excavación para banco de ductos Tramo 4 glb 1.00 0.1 0.86 0.14 14% 0.14 4/9/2025 14/04/2025 6 0.14 0.14 0.14 0.14 0.14 0.00 0.00 0.72
Perfilado de Excavación para banco de ductos Tramo 3 glb 1.00 - 1.00 0.33 33% 0.33 4/15/2025 17/04/2025 3 0.00 0.00 0.00 0.00 0.00 0.33 0.33 0.67
Perfilado de Excavación para banco de ductos Tramo 2 glb 1.00 - 1.00 0.33 33% 0.33 4/18/2025 20/04/2025 3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Perfilado de Excavación para banco de ductos Tramo 1 glb 1.00 - 1.00 0.20 20% 0.20 4/21/2025 25/04/2025 5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
SISTEMA CONTRAINCENDIO (SCI) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Casa de valvula hacia el cubeto 4 (generar acceso LADO ESTE ) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Excavación lado este ml 72.00 36.0 36.00 18.00 17/04/2025 4/18/2025 2.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Fo.JJC-CG-05-03 Rev.0 Planificación Intermedia (PI)

You might also like