PAC OAC Observation Burimari

NESCO provided comments on the commissioning punch list for the Burimari 33/11KV Substation, addressing various issues including insufficient lighting, missing equipment, and incomplete software configurations. Several items have been resolved, while others remain outstanding, such as the supply of specific test equipment and completion of SAS work. The document also highlights necessary actions for compliance with safety and operational standards, including the installation of additional infrastructure and equipment.

Uploaded by

Md.Sajedul Islam
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
16 views5 pages

PAC OAC Observation Burimari

NESCO provided comments on the commissioning punch list for the Burimari 33/11KV Substation, addressing various issues including insufficient lighting, missing equipment, and incomplete software configurations. Several items have been resolved, while others remain outstanding, such as the supply of specific test equipment and completion of SAS work. The document also highlights necessary actions for compliance with safety and operational standards, including the installation of additional infrastructure and equipment.

Uploaded by

Md.Sajedul Islam
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 5

Comments of NESCO on the Commissioning Punch List of Burimari 33/11KV SS, Lalmonirhat

SL.
PARTICULARS REVERIE REPLY REMARKS(NESCO)
NO.
Four DC lights with low
Necessary DC Lighting inside the illuminance are installed
control room & cable room shall Supplied and installed at both ends of the
1
be provided. control room; however,
it is not sufficient.
All 33kV & 11 kV Panels shall
have proper nameplate & number Partially done. Name
Supplied and installed
2 marking with CT, PT Ratio and Plate in some panels
commissioning date. were not found.
Related software and accessories
with license key and other
Find the software and
accessories 02 (Two) set for each Done.
3 License key in hard drive
substation) within the scope of
supply shall be provided.
Meter Parameterization Software
02 (Two) sets for each substation
(As per section 7.1.3.38 of tender Find the software and 01 (One) Set for Each
4 document) shall be provided with License key in hard drive Substation Provided.
software keys for controlling and
duplication.
As per the manufacturer's
confirmation, the 1G & 2G
modem, as specified in the
tender clause, are no longer
External Modem with accessories in production.
for Energy Meter (As per section The energy meter will
5 Not Provided
7.1.3.38 of tender document) shall communicate with the SAS
be supplied. and can extend reporting to
the central database through
the upcoming
telecommunication network
technology
Placement of SAS Operating
Table is not appropriate. It shall be
6 placed in the convenient place Solved
Done.
from where every panel can be
seen properly.
Blank space for further extension
of 33 KV spare panel must be
7 Solved Done.
covered temporarily with checker
plate. It is important for safety.
All spare parts except 11 kV Spare parts except 11
Mandatory spare parts within the
CT & protection relay kV CT & protection
scope of supply shall be provided.
8 officially handed over to relay officially handed
Spare parts which are not found
Nesco central Store at over to Nesco central
during PLI must be supplied.
Rangpur Store at Rangpur.
9 Cover of 11 KV Bus-bar from Solved Done.
transformer bushing to cable shall
be provided for both transformers.
After finalizing the relay setting,
relay configuration project file
Please find the backup at
must be provided to the System
10 hard disk also in Done.
Protection office with dedicated
engineering laptop
storage device. It shall be provided
to engineering work station.
IEC 61850 up back file must be Please find the backup at
11 provided using dedicated storage hard disk also in
Done.
device. engineering laptop
Back up file of SAS (Wincc and
SICAM) must be provided to the Please find the backup at
12 EWS laptop and System hard disk also in
Done.
Protection Department with engineering laptop
dedicated storage device.
Nut Bolt of Copper bar and
connectors at transformer shall be
13 Solved Not Solved Yet.
changed with non-ferrous
material.
Battery charger setting calculation,
Please find the backup at
HMI interfacing ID, Password Provided.
14 hard disk
shall be provided.
CCTV, Air conditioner, TV,
Computer within the scope of Solved Provided.
15
supply shall be provided.
Soft and hard copies of all Within 15th March 2025 all
drawings (Civil, Electrical, Layout layout, Civil and electrical
etc.) shall be made as built after drawing will be submitted
Provided.
modification and supplied to to PD office. Except 33kv
16
concerned department as per GIS and 11 KV AIS as-
contract document. built.
All equipment manuals, IP
All Documents Except
addresses, pre-commissioning &
Please find the backup at Pre-commissioning &
commissioning reports of
17 hard disk Commissioning Report
equipment must be provided to the
provided.
substation.
All test machine has been
Meter testing set ZERA, Insulation
supplied except ZERA.
tester, Clamp On meter and All test machine have
18 Within April 30th 2025 we
instruments been supplied except
will arrange AIR shipment
within the scope shall be supplied. ZERA test kit.
for supply ZERA test kit.
Remaining earthing work should
be completed as early as possible
19 Solved Not Done
to avoid any unexpected
circumstances.
20 SAS work was not completed 33KV & 11KV Energy Work mentioned in the
during substation charging, meter reporting to SAS comment with SAIDI &
remaining work must be pending due to SIEMENS SAIFI not completed.
completed with compliance of and ABB converter short of
approved SAS signal list and supply. Within April 2025
satisfactorily. we will finish this work.
After completion of SAS work RTU, Firewall
necessary software, IP addresses configuration Software
Please find the backup at
21 of IED, RTU, Firewall etc. must not provided. RTU,
hard disk
be provided to concern Firewall Configuration
department. work not done.
All cable trenches must be covered
22 Solved Done.
appropriately.
All cable trays should be earthed
23 (at least 02 (two) numbers of each Solved Done.
tray properly.
Cable trench of Auxiliary As per design approval we
24 Transformer area should be have completed all cable Done.
installed. trench
Conduits under the ODF Junction
25 Solved Done.
box should be covered properly.
Conduits at top and bottom side of
26 the boxes (behind the OWS) Solved Done.
should be visible.
Firefighting equipment should be
supplied & installed properly at
27 Solved Foam Type: Not Found.
switchyard, cable room, control
room etc.
All communication cable both
28 Optical Fiber & Ethernet shall Solved Not Done.
have sticker type ferrule marking.
Daily triggering of interruption
time and frequency, Monthly,
Half-yearly, yearly report for
Will be solved during
29 SADI SAFI of whole substation Not Done.
energy meter integration
shall be implemented. Only
monthly triggering and value has
been shown in SAS.
At 11kV Outgoing/Incoming
feeder, the following signals are
missing as per the approved signal All Protection Pickup
list: already witnessed done.
30 a) Under voltage pickup Phase angle implemented in Done
b) Over frequency pickup the time of energy meter
c) Under frequency pickup configuration time.
d) Phase angle needs to be shown
at relay measurement
At 11kV Bus-coupler feeder, the
following signals are missing as
per the approved signal list:
31 Solved Done.
a) CB faulty
b) SAS locally selected
c) SAS remotely selected
At 11kV Bus-coupler / Incoming
feeder, the Following signals are
missing:
a) For synchronization check
Voltage Deviation Value dV shall
Must be solved during
be shown in feeder page Resolve this testing time of
32 testing time of energy
b) For synchronization cheek energy meter configuration
meter configuration.
frequency deviation value df shall
be shown in the feeder page
c) For synchronization cheek
phase deviation value da shall be
shown in feeder page.
Signal from battery charger,
Must be solved during
DCDB, ACDB have not been Resolve this testing time of
33 testing time of energy
taken to SAS. It shall be taken energy meter configuration
meter configuration.
mandatorily.
Shortage of Power Transformer Oil in transformer perfectly
34 Oil needs to be filled.
Oil okay
As per price schedule, Air
35 Solved Done.
conditioners not yet supplied.

Punch List of OAC/PAC at Burimari 33/11 KV GIS Substation


1. Report and Trend pages, measurements are not active at SAS as Energy meter data have not
been taken to SAS.
2. SAIDI & SAIFI have not been implemented as per instruction and punch list of
commissioning.
3. Oil Leakage has been found at inlet valve of Transformer-02 and OLTC chamber of
Transformer-02.
4. All kinds of approved drawing and catalogues (5sets) shall be submitted in bound book as per
contract document.
5. All drawings (.dwg) file of approved layout shall be submitted to design & Inspection division.
6. 11kV Outgoing feeder cable trench from building to rising pole shall be constructed.
7. A simple bit below the unloading door shall be constructed to resist heavy rain water.
8. Main gate height shall be increased.
9. One deep tube well should be installed for the convenience of drinking water.

10. Boundary drain shall be repaired for solving the problem of waterlogging.
11. Power cables are laid and coiled on the floor of cable room. Cable rack shall be installed and
cable shall be laid on that for the convenience of further maintenance work and safety.
12. As per the item no:2 of schedule-1 there is scope of supply of LA, DOFC and MCCB. No LA,
DOFC and MCCB was provided at Burimari site.
13. Rubber pad in front of 33kV panel shall be provided.
14. As per the item no:24 of schedule-1 earthing resistance of the substation shall be maximum
0.25 ohm. 4 (Four) nos. of 100m boring shall be done at four corners of the switchyard mesh.
15. Outdoor lighting is not sufficient at Burimari. Street lighting must be installed as per TD.
16. Extra glass on the table shall be installed as it is mentioned in the contract document.
17. Fiber Ladder shall be supplied for the convenience of taking energy meter reading.
18. The scheduled quantity for 33kV, 11kV, and 0.4kV underground power cables, along with the
PLI quantity, consumed quantity, and store returned quantities, do not match. Kindly provide
proper clarifications to reconcile these discrepancies.
19. Lightening protection of building & substation is provided without any design approval. Need
proper approval and clarification.