CIVL 5552-Sem2, 2019                                      Gymnasium Project
Engineering Project 2                                      Portal Frame Design
Duration: Hand out in:       Week 1 in class
Project due date:            Project 1: Beam portal design due end of Week 7,
                             Project 2: Truss design end of Week 10.
Coordinator:                 Dr Mohamed Elchalakani
1.     INSTRUCTIONS:
1.1 Beam Portal Frame Design (group work 30%) (due end of Week 7)
In group of 4 students (Max), you need to do one design (one beam portal frame) of a Gymnasium to
AS4100 “Australian Steel Design Code” as per the following dimensions and shown 3D drawings. Each
group has different dimensions. The gym must be made of one hall (single span) and has a sloping roof as
shown with roof decking and insulation. No internal column is allowed. It is required to design all
members as designated in the design section. Computer program Space Gass can be used for the analysis
and design. See Table on Page 4 for dimensions. You may like to download the Space Gass student
version on page 13.
                                                                                         Gable
                                                                                     4No. doors 3m x 3m
H                                                                               L    2 doors on each side
                         Fig. 1. Project 1: Beam Design one single span system
                                                                                                            1
    1.2 Truss Frame Design (30%): Individual Work (due end of Week 12) +10% participation in 12
    weeks
    You need to do one design (one truss) of a Gymnasium to AS4100 “Australian Steel Design Code” as per
    the following dimensions and shown 3D drawings. Each student has building configuration and
    dimensions similar to those from Group Project 1. The gym must be made of one hall/single span and has
    a sloping roof as shown with roof decking and insulation. It is required to design all the members of the
    truss manually and compared to computer-aided solutions. Computer program Space Gass can be used for
    the analysis and design. You may like to download the student version, see page 13.
    Important note.
    You only need to design the truss manually and with Space Gass since purlins, girts, roof and wall
    braces, gable end column, slab, foundation, etc. have been designed in the group beam portal frame
    project. Once student has been assigned to a particular building for the group design, this building
    configuration must be followed for both Beam and Truss designs so that it will be a fair comparison in the
    cost analysis of the 2 designs.
                                                                                                  L
                                                                                                  L1
                         Fig. 2. Project 2: Truss Design One Span Structural System
                                                                                                            2
                                                                                                     L
                                 Fig. 3. Wind directions on portal frames
1.3 Brief
The assignment is to develop a preliminary design then followed by a detailed design for the structural
framing of a gymnasium. The objective of a preliminary design is first to select a structural system
suitable for overall span then to estimate the sizes of the principal elements of the structure, to allow the
architect to incorporate these into his design. That is, for the architect to make space within the building
for the structure. Note, H=clear height free of any obstacles such as steel members, etc.
1.4 Information provided
As a project brief to the engineer, a structural roof plan and section are provided.
Being a gymnasium, it is desirable that the inside wall surfaces be flush, without protrusions into the floor
space.
Download Australian Standards: https://www.saiglobal.com/online/autologin.asp
                                                                                                                3
1.5 Group Gym Dimensions
The following table shows the roof pitch angle, the clear height H, the overall span B, and the total gym
length, L. These dimensions are fixed and you cannot change throughout the project. All dimensions are
in meters. Restrictions are:
      Weight of all structural steel (excluding cladding) shall not exceed 100 kg/m2.
      No internal column is allowed
      Priority to use available off-the-shelf rolled and welded sections (more economical) in Space Gass
       library. Try not to use welded built-up sections (expensive).
      H = clear height without any structural obstructions.
      Overall height of the gym is not more than 20 m include cladding and roof purlins.
               Angle       H         B          L                 Angle       H         B          L
     Group                                              Group
                Deg       (m)       (m)       (m)                  Deg       (m)       (m)       (m)
       1         12        4         22        44         31        23        5         26        52
       2         14        6         17        34         32        11        4         20        40
       3         15        4         16        32         33        12        7         23        46
       4         14        4         25        50         34        16        8         17        34
       5         15        4         21        42         35        17        4         23        46
       6         16        6         24        48         36        9         8         26        52
       7         18        8         26        52         37        20        4         20        40
       8         23        4         26        52         38        11        6         15        30
       9         21        6         19        38         39        21        4         20        40
       10        10        4         22        44         40        14        4         20        40
       11        11        4         19        38         41        8         6         24        48
       12        10        6         25        50         42        22        4         26        52
       13        13        7         19        38         43        16        7         24        48
       14        14        5         16        32         44        9         4         23        46
       15        23        6         21        42         45        8         5         21        42
       16        19        7         21        42         46        14        8         22        44
       17        15        5         23        46         47        18        6         17        34
       18        10        8         25        50         48        21        8         16        32
       19        14        8         19        38         49        23        5         22        44
       20        17        6         21        42         50        21        6         19        38
       21        23        8         23        46         51        18        7         26        52
       22        20        5         26        52         52        9         7         17        34
       23        23        4         22        44         53        8         6         23        46
       24        8         8         26        52         54        9         5         24        48
       25        15        8         22        44         55        22        7         16        32
       26        9         6         25        50         56        12        5         23        46
       27        17        6         15        30         57        10        5         22        44
       28        11        5         17        34         58        15        6         16        32
       29        17        7         15        30         59        11        5         21        42
       30        9         8         24        48         60        10        6         20        40
                                                                                                       4
1.6 Roof Materials
The roof & walls of the building will be constructed using profiled steel claddings. The cladding will be
supported by cold formed purlins and girts, in turn supported by rafter or trusses framed from rectangular
hollow sections to AS 1163, for example and columns out of UB sections to AS/NZS 3679.1.
Cold-formed steel purlins & girts, RHS truss members to AS 1163. Base plates to AS/NZS 3678.
    •   The roof & fascia walls of the building are clad with ‘Trimdek’ of 0.42 mm thickness (Blue Scope
        http://www.steel.com.au ). Alternatively, Stratco Topdek700, 0.48mm BMT can be used.
    •   The roof purlins – Lysaght (http://www.steel.com.au) or Stramit (http://www.stramit.com.au). (see
        table below for preliminary sizes). Purlins are spaced the range of 1.0m to 1.5m or within the limit
        by roof sheeting. Stratco purlins can bused as an alternative.
1.7 Research
Initially you need to understand the different building components in a portal frame. You will need to
discover the weights of the construction materials (internet – Lysaght and Stramit), live loads on the roof
(AS 1170.1), and wind pressures (AS1170.2). You will also need to estimate the weights of the structure
in the preliminary stage. Assume sizes for the purlins for the estimate, and revise the weight if necessary
to carry forward into the loads on the beams or trusses. Assume sizes for the truss members and revise if
necessary. For the preliminary stage, it’s not necessary to refine these estimates too closely in the
preliminary stage; a good approximation will do. (With some experience, these things can be estimated
quite accurately.)
1.8 Manual calculations
The completed manual calculations shall include an explanation of how loads will be carried from the
place of application of the load to the ground. This means tracing the load paths. Diagrams can be
helpful and can save lots of words. A description of the load paths from the point of application of a load
to its resistance at the ground. This will comprise statements such as “The roof cladding is supported by
purlins as beam-type elements, which are supported by…”
The analysis can be done using methods of analysis previously in CIVL3110 “Structural Analysis” unit or
by assuming indeterminate structures, or beam/frame formula. A set of calculations:
•   listing the estimate of loads – dead, live and wind loads. This is a detailed design, so it’s necessary to
    use every applicable factor in the wind code, for instance.
•   determine member forces and moments by hand analysis. This needs decisions on which actions are
    critical – moment, shear, axial force.
1.9 Dead and Live Loads to AS1170.1
A set of calculations listing the loads at each point in the load path, eg:
Weight of cladding                0.05 kPa ??
Self-weight of purlins            0.03 kPa ??
Insulations (Rockwool 50 mm) 0.01 kPa ??
Electrical fixtures               0.01 kPa ??
Total dead load                   0.10 kPa ?? x 1.2    =
Live (inaccessible roofs)         0.25 kPa ?? x 1.5    =
Loads to be confirmed by the students form Material Data Sheets or from Australian Standards
Continuing on with loads on rafters, trusses, etc. and followed by analyses to calculate the bending
moments, shear forces and axial forces in the elements of the structure
                                                                                                              5
1.10 Wind loads to AS 1170.2
For wind loads, assume Terrain Category 3, Region A1, R=500 years return period, No shielding, flat
terrain, wind direction multiplier is 1.0. All wind factors to be determined based on single span building.
Assume wind pressure is constant and does not change with height. The structure is effectively sealed and
impermeable (Cpi=-0.2, 0). For internal coefficient, Cpi, negative value means inward suction and positive
value means outward pressure. The wind pressure in AS1170.2 is given by:
p = 0.5 ρ air (Vdes
                 2
                    ,θ )C fig Cdyn
ρair = density of air =1.2 kg/m3
Vdes,θ = Orthogonal design wind speed for 500 years return period for θ=00.
Cfig = Cp,e Ka Kc Kl Kp, for external pressures
Cfig = Cp,i Kc, for internal pressures
Cfig = Cf Kc, for frictional drag forces (ignore)
Cp,e = external pressure coefficient
Ka = area reduction factor
Kc = combination factor = 0.8 when int. & ext. are in the same direction, or assume =1.0 for all cases.
Kl = local pressure factor = 1.0 for the portal frame.
Kl = 1.5, 2.0, 3.0 for purlins. For girts Kl = 1, 1.5 for windward wall, 1.5, 2 for side wall (see Table 5.6).
Kp = porous cladding reduction factor = 1.0
Cp,i = internal pressure coefficient, assume fully sealed at Vdes
Cf = frictional drag force coefficient =1.0
Cdyn = Dynamic response factor =1.0
2.       DESIGN REQUIREMENTS (GROUP PROJECT # 1 ONLY): BEAM PORTAL
Download all Australian Standards from: https://www.saiglobal.com/online/autologin.asp
     a) Workout structural system of the building
     b) Roof purlins to AS4600. For wind load analysis, only case where Kl=1.0 is required for the design
         scope (even though cases where Kl=1.5, 2 and 3 will be discussed in class)
     c) Rafters of the portal frame only to AS4100
     d) Columns of the portal frame only to AS4100
     e) Horizontal bracings on roof to AS4100
     f) Vertical bracings on walls to AS4100
     g) Concrete Floor slab. You need to design the floor slab including all details of reinforcement.
     h) Drawing: the followings are required to be presented on drawing
        • Plan showing all structural members. For members not in the design scope, adopt members
            shown in the sample drawing provided with this brief
        • Elevations: minimum two elevations (longitudinal and gable end) are required
        • Section: one section across the building is required
        • Connections: knee connection, ridge connection, fly brace, column to footing connection: these
            connections are not included in the design scope, students can adopt connections shown in the
            sample drawing provided with this brief as standard connections
        • Footing: design of footing is not included in the design scope, students can adopt footing
            shown in the sample drawing provided with this brief (note that in reality, design must be done
            accordingly)
        • Slab on ground: incorporate detail for slab thickness and reinforcement in detail of footing.
            Refer to sample drawing provided with this brief for similar details
                                                                                                                 6
3.      DESIGN REQUIREMENTS (INDIVIDUAL PROJECT # 2 ONLY): ROOF TRUSS
     a) Use dead load and live load similar to Group Project 1. Truss self-weight will be different
     b) Work out wind loads that will be applied on the building. Wind load may be different to those
        used in Group Project 1 because the height has changed to accommodate truss depth
     c) Using loadings in item a) and b) above, analyse one typical truss using determinate simply
        supported truss (ie. pinned and roller supports). Design truss top chord, bottom chord, one vertical
        chord with heaviest forces, and one diagonal chord with heaviest forces to AS4100
     d) Cost comparison: (refer Section 6 for more requirements)
         • Beam: calculate the total costs for the supply, fabricate, and installation of a beam used for the
            portal frame in Project 1 in your Group
         • Truss: calculate the total costs for the supply, fabricate, and installation of a truss used for the
            truss in Project 2
         • Compare the costs of the two options and draw any conclusion regarding the economical use
            of beam or truss in your design
4.      DESIGN PARAMETERS
       Wind load to AS 1170.2: Basic Wind speed Region A1, R=500 years return period, Terrain
        Category 3, No topography-flat terrain, Wind direction multiplier =1.0.
       Deal load to AS 1170.1.
       Live load to AS 1170.1.
5.      PENALTY
      You must submit the report with manual calculations and Space Gass file to get a passing grade.
      Apply penalty as per marking scheme for late submissions. No submission will be received after 7
       days from the date of submission.
6.      QUANTITIES, COSTING, DESIGN COMPARISON AND OTHER REQUIREMENTS:
     6.1 General requirements for quantities and costing
         Provide quantities and costs for the group design in a table format. Consider $1000/m3 for
         concrete include reinforcement and pouring, and $7,000 /ton of structural steel including material,
         fabrication and erection. Consider $200/m2 for sheets/decking, and $100/m for purlins/ side
         rails/girts. Detailed conclusions on a clear comparison between the design and the effect of each
         parameter you have adopted for each option. Printouts for the maximum vertical deflection (∆y)
         and Horizontal (∆x and ∆z)) for the 2 designs. In a table format determine the amount of
         allowable deflection for both vertical (L/250) and horizontal directions (H/125). Determine if the
         design is accepted or not.
     6.2 Project 1:
         Provide quantities and costs for the whole building based on drawings provided by the Group.
         Note that drawing shall reflect the design calculations of the Group. If design calculations have
         been undertaken for an element, that element shall be shown on drawing. The elements taken into
         account for quantities include, but not limited to roof and wall sheeting, purlins and girts, rafters,
         columns, beams, fly braces, roof and wall braces, all connections, footing including
         reinforcement, slab on ground including reinforcement, and all other elements shown on your
         group drawing.
                                                                                                              7
           Provide Tables for the sizes of steel sections, footing, slab and reinforcement. For elements that
           are not in the design scope such as footing, gable end beam and columns, fly braces, girts, holding
           down bolts, adopt details for these elements as shown on sample drawing provided with this brief.
      6.3 Project 2:
           Assuming that all purlins, girts, columns, footings and slab will be the same for two beam and
           truss options, and that the only difference between the two options will be the quantity of beam
           and truss resulted from respective option, design comparison is therefore only for the roof beam
           and truss.
           Provide Tables for the sizes of steel sections of the beam (including fly braces as shown in sample
           drawing) and truss (including strut S1 as shown in sample drawing) options. You need to explain
           the design very well for each option to show any significant difference between the two options
           and how the difference will affect the costs.
7. EXAMPLE
7.1        MEMBER SIZES
ITEM                                               DESIGN
COLUMNS
      1. CORNER, END (C1)                          410UB53.7
      2. MIDDLE, END (C2) AT GABLE
      3. CORNER, INNER (C3)
TRUSSES
      1.   Top Chord                               150X100X4 RHS
      2.   Bottom Chord
      3.   Verticals
      4.   Diagonals
      5.   Columns
      6.   Splices
      7.   Connections
BEAM
  1. Beam                                          410UB53.7
  2. Roof Purlins                                  Z15015
  3. Wall girts
  4. Horizontal bracings
  5. Vertical Bracings
  6. Connections
FOOTINGS
              A. CONCRETE                          1.0mx1.0 mx0.5m
              B. REINFORCEMENT                     N16-200 both ways
                                                                                                              8
7.2     Preliminary Sizes
Ideally this phase for the preliminary structural member sizes needs experience. If you do not have
experience, you can start with some guess work. The table below will help you in this process. This step
in the project can take few cycles (iterations) until you reach the final sizes which meet the design criteria
in AS4100. You may find at the first iteration that some or all the members do not meet the load factor of
1.0 or more. A load factor of 1.0 is the minimal requirement of AS4100 which means the member has a
member capacity equal to the ultimate straining actions.
Columns
Span (B) in meters            Column Size                 Shape
B<6m                          200UB                       H-shape
6m<B<8m                       250UB                       H-shape
8 m < B < 15 m                310UB                       H-shape
15m < B < 25 m                410UB                       H-shape
25m < B < 35 m                530UB                       H-shape
Roof Purlins and wall girts
Span (L) in meters            Purlin/girt Size            Shape
L<5m                          Z 150                       Z-shape
5m<L<7m                       Z150                        Z-shape
7m<L<8m                       Z 200                       Z-shape
8m<L<9m                       Z 250                       Z-shape
Rafters and Eave-beams
Span                          Rafter/Beam Size            Shape
Rafters up to 30 m            S/40                        I-shape
Eave-beams                    D/20                        I-shape
Roof Truss
Distance (B) in meters        Purlin Size                 Size
Truss depth                   Span/(10 to 20)             Depends on the shape
                                                          of truss
B<6m                          Top/Bottom Chord            100x50 RHS
                              Diagonal/Vertical           75x75 SHS
6m<B<8m                       Top/Bottom Chord            150x100 RHS
                              Diagonal/Vertical           100x100 SHS
8 m < B < 12 m                Top/Bottom Chord            150X100 RHS
                              Diagonal/Vertical           100X100 SHS
                                                                                                             9
8.      REPORT FORMAT
     1. Abstract
     2. Introduction (Research)
            a. Portal Frame buildings design concepts.
               A short essay on portal frames and roof trusses and the structure shown in the brief,
               commenting on whether it is a complete structure or not and explain the members needed
               for stability.
            b. Truss Frame Design method (for individual project 2)
            c. Rafter Frame Design Method (for group project 1)
            d. Cladding types for steel buildings
            e. Portal Frame buildings construction
            f. Shallow foundation design
     3. Design Sections
           a. Manual calculations
           b. Space Gass results. You need to take screen shots of the working deflections in X, Y, Z
               directions. You need to take screen shots of ultimate bending moment, shear force and
               axial force diagrams.
           c. Steel sizes in table format for members that are in the design scope only
           d. Slab on ground thickness and reinforcement
           e. Comparison between Manual Calculations and Software in a table format
     4. Cost Summary for Project 1. Check that weight does not exceed 100 kg/m2.
     5. Cost comparison for individual Project 2.
     6. Professional AutoCAD / Revit Drawings for the steel structure and foundations (See Appendix A)
         for Project 1 only
     7. Conclusions
     8. References
     9. Appendix A, contain all datasheets of material used, cladding, purlins, etc.
     10. Appendix B, Space Gass Design Output (plots).
     11. A bound hard pack (hard copy) of the project must be submitted in “CIVL5552 Mail Box” at the
         ground floor of the engineering building. A soft copy include PDF/DOC of the report and Space
         Gass File (groupNo.SG) shall be submitted using USB.
                                                                                                        10
9.      SPACE GASS ANALYSIS AND DESIGN STEPS
     1. Check attached list for your building geometry. You may like to use the “Portal frame Builder”.
     2. The preliminary size of the columns, beams, purlins and top and bottom chords are given in the
        preliminary design section.
     3. Input geometry and supports. Pin support is often used for steel buildings but if lateral defections
        are high use fixed support.
     4. Insert Dead load according to your loading calculations.
     5. Primary load cases P1=D, P2=L, P3=Wx,up, P4=Wx,dn, P5=Wz,up, P6=Wz,dn.
     6. Check Load Combinations to AS1170.0 (D=Dead, L=Live, W=Wind, dn=down, up = upward):
               C11 =1.35D                             C20= 1.2D + 1.5L
               C21= 0.9D + 1.0Wx,up                   C22= 1.2D + 1.0Wx,dn
               C23= 0.9D + 1.0Wz,up                   C24= 1.2D + 1.0Wz,dn
               C30=1.0D + 0.7 L (∆y) “ Check for vertical deflection span/250 (note: ψs=0.7)
               C31= 1.2D + 0.67Wx (∆z), Check for horizontal Deflection H/125.
               C32=1.0D + 0.67Wz (∆z), Check for horizontal Deflection H/125.
           Note:
          •    To convert ultimate wind pressure to serviceability pressure, (37/45)2 = 0.67 factor is used in
               the above combinations where 37 and 45 are serviceability and ultimate wind speeds
               respectively
          •    Wx: wind at 0o and Wz: wind at 90o
     7. Check Maximum displacement ∆y< Max Span/250, ∆x< Height/150 or rafter spacing/200, ∆z <
        Height/150 or rafter spacing/200. If these limits are met proceed to the design links, otherwise
        redesign by increasing member sizes.
     8. Design Links
              a. Steel Member Design
                       Columns (corner, side, end)
                       Beam
                       Truss (top, bottom, verticals, diagonals) for project 2 only
                       Gable end Beam
                       Roof Purlins and wall girts
              b. Slab on ground design
     9. Record Reactions for foundation designing purpose only
                                                                                                           11
10.      SPACE GASS DOWNLOAD / SELF-LEARNING STEPS
To download the Installer, go to the following link –
https://cloudstor.aarnet.edu.au/plus/index.php/s/o4J0WKIKW5TqA4n
In the following 12 steps you can have your Space Gass running in your Laptop !
      1. Copy/download the SG vr 12.5 folder to your desktop
      2. Run SpaceGassFullSetup.exe as administrator (right click on it, choose the “Run as administrator”
         option)
      3. Click Yes, if prompted about whether you want to allow the program to make changes to your
         computer
      4. Click Install, in the Space Gass 12.5 Setup dialog – no need to change the install location
      5. Click “Yes” to optimize Space Gass to operate correctly with your computer’s graphics hardware.
      6. This will bring up a web page with instructions about – go through the steps to get best graphics
         quality and performance for SpaceGass
      7. The first time you run SpaceGass, you’ll want to click Yes, to agree to the License terms
      8. You can choose the default option to “Start just the renderer”
      9. Next, click the button to “Connect to Titan on the Network”
      10. Type in spacegass.civil.uwa.edu.au for the Titan network connection
      11. You’ll need to enter that again, in place of localhost, in the Titan Client Tool that comes up, then
          click “Test Connection to Titan Server”
      12. If the test was successful, click “Save and Close” at top right – if the test was not successful, make
          sure that you are connected to the Internet, and ECM VPN.
      13. Self-learning by watching the most important videos from this link
          http://spacegass.com/training/index.htm#2. These videos are (1) graphical interface; Portal frame
          builder; (3) Analysis; (4) Steel member design; and (5) Steel connection design;
                                                                                                             12
APPENDIX A: EXAMPLE DRAWING: BEAM PORTAL DESIGN WITH ONE SPAN.
                                                                 13
APPENDIX B: EXAMPLE DRAWING: TRUSSED PORTAL DESIGN WITH SINGLE SPAN.
                                                                       14