NS125 - LV OH Mains - AMD 5
NS125 - LV OH Mains - AMD 5
Revision
DISCLAIMER
This document is bound to the conditions set out in NS002 Network Standards Disclaimer.
Ausgrid maintains a copy of this and other Network Standards together with updates and amendments online at www.ausgrid.com.au.
This document is considered uncontrolled once printed.
UNCONTROLLED IF PRINTED
Table of Contents
Scope ................................................................................................................................................................. 3
Reference Documents...................................................................................................................................... 3
Ausgrid Documents ......................................................................................................................................... 3
Other Standards and Documents ................................................................................................................... 3
Acts and Regulations ....................................................................................................................................... 3
1 Conductor Selection and Details .......................................................................................................... 4
2 Crossarm Selection ............................................................................................................................... 5
3 Streetlighting Circuits ............................................................................................................................ 5
4 Clearance Criteria................................................................................................................................... 5
5 Construction ........................................................................................................................................... 5
List of Annexures
Annexure A Standard construction drawings .................................................................................................. A-1
Annexure B Connections to twin-and-twist ..................................................................................................... B-3
Annexure C Approved tools ............................................................................................................................C-4
Reference Documents
All work covered in this document shall conform to all relevant Legislation, Standards, Codes of Practice and
Network Standards.
Ausgrid Documents
NS001 Glossary of Terms
NS109 Design Standards for Overhead Supply Developments and Distribution Centres
NS119 Public Lighting Design and Construction
NS124 Specification for Overhead Service Connections up to 400 Amps
NS179 Vegetation Management
NS220 Overhead Design Manual
Description Stockcode
Description Stockcode
1Many other conductors exist on the network, and they may continue to be used for maintenance (such as replacement after a failure)
or minor work (such as a pole relocation where a short extension to the mains is required). For current ratings and other electrical
properties refer to NS220
3 Streetlighting Circuits
3.1 As per NS119, all new street lighting luminaires shall be connected to the low voltage mains and
not to dedicated, switched street lighting circuits. Where continuity of an existing dedicated street
lighting circuit is required during maintenance, LV ABC may be installed between existing
sections.
3.2 During maintenance, legacy street lighting circuits (such as those using dedicated crossarms,
swan-neck insulators, or 5-wire arrangements) shall not be converted to any other legacy
arrangements. They shall be maintained as they were, converted to LV ABC for infill between
existing sections of dedicated street lighting circuits, or removed and the luminaires connected to
low voltage mains.
3.3 Where street lighting crossarms are replaced during maintenance, the same length crossarm may
be used.
3.4 Where the low voltage mains are converted to LV ABC, any dedicated street lighting circuit that
exists in the same span shall also be converted to LV ABC.
4 Clearance Criteria
4.1 All clearances shall be met at the time the network is built or altered in any way, including
construction of new overhead mains, pole replacements or relocations, conductor replacements,
and crossarm replacements. This includes the clearances to ground and structures in NS220 and
the vegetation clearances in NS179.
5 Construction
5.1 Overhead mains shall be constructed in accordance with the standard construction drawings
listed in Annexure A.
5.2 LV ABC installation by pulling-in
5.2.1 For LV ABC, the pulling tension shall not exceed 4 kN.
a 1.8m crossarms exist on the network however shall not to be used for new constructions as per Clause 2.3.
Description Stockcode
5.7.4 Connections for bonds shall only be installed on conductors that are not under tension. Where this
is not possible and a connection to conductors under tension is required (such as a tee-off), the
conductors and bonds shall be the same material.
5.7.5 Bimetallic PG clamps shall not be used on mains under tension.
5.7.6 Vertical bonding for LV ABC
5.7.6.1 Vertical bonding must be installed with parallel LV ABC conductors of the same circuit at intervals
not exceeding 100 metres and at:
• substations,
• links,
• terminations, and
• tee connections.
5.7.7 Vertical bonding for bare conductors
5.7.7.1 Where vertical bonds are installed for parallel circuits of bare conductors, they shall be insulated
with a loop installed 150 mm below the bottom circuit to allow for the placement of temporary line
covers.
5.8 Temporary covers
5.8.1 Temporary covers include pipe-type covers (commonly known as Torapoli or tiger tails) and
drape-type covers. Before temporary covers are used, both the mains and temporary covers shall
be inspected for visual defects.
5.8.2 Mains must not be overloaded and must not sag below minimum clearances due to the addition of
temporary covers.
5.8.3 They shall be placed to maintain even sag, and spreaders shall be added if needed.
LV ABC Offset Arm Construction for 0° to 30° Deviation Angle 1-81 232175
LV ABC Offset Twin Arm Construction for 0° to 30° Deviation 1-82 244670
Angle
Connection Description
Bonds to copper conductors Connect insulated copper tails to the mains with split bolts. The split bolts
(including tails to switchgear, fully encapsulate both of the conductors as well as the bonding cable.
copper single UGOHs, PTs This eliminates slipping out of the side and shares the electrical load
etc.) between the conductors.
Wavecon UGOH’s All Wavecon UGOH’s shall be terminated into LV links or a LV ABC link
box. This allows for the tail between the link and the main to be covered
copper and can be connected to the main with the use of the split bolt
procedure mentioned above.
Bonds to aluminium Tails from aluminium conductors (both bare and LV ABC) cannot be
conductors connected directly to the copper twin-and-twist conductors. Instead,
connect insulated copper tails as described above, and then connect the
copper tail to the bare aluminium or LV ABC using PG clamps or IPCs
respectively.
Low voltage services Spread the two conductors and install a service connector on the larger
conductor. If there isn’t already a split bolt clamp around the two mains
conductors (such as from a bond), then install a split bolt no more than
300mm away from the service connector, but not so close that it bends
the conductor.
Straight through attachment Keeping both conductors together, locate them in the top or side groove
to pin insulators of the low voltage pin insulator as appropriate. Use a hand-tie around
both conductors together, treating them as one.
Terminations Keeping both conductors together, take them around the low voltage
shackle insulator and back adjacent to the conductor under tension. Use
pieces of tie wire to make a throat tie around both conductors together,
treating them as one. More detailed instructions are given on the
following page.
Mid-span full tension splices As McIntyre sleeves are no longer available, there is no available solution
for mid-span full tension connections. Instead, terminate the conductors
at the pole either side of the break, and replace with a single copper
conductor appropriately rated for the load and bonded as described
above. There shall be no mid span sleeving on twin-and-twist conductors.
Impact wrench Hilti SIW 6AT-A22 The tool shall be set to Level 3.
The tool shall only be used on connectors
involving 95mm² or 150mm² LV ABC mains.
Drill driver Any Any The tool shall be set or limited to a rotational
speed of less than 500 rpm.
The tool shall not use any impact or hammer
action.