Mobilization Schedule For Waterpan

The document outlines a detailed mobilization schedule for the waterpan construction project, including phases such as pre-mobilization, planning and procurement, mobilization activities, site preparation, and handover. Key activities include stakeholder meetings, site assessments, material procurement, and final inspections to ensure readiness for construction. It emphasizes the importance of regular monitoring and adjustments based on project-specific factors.

Uploaded by

naomichumba046
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
13 views3 pages

Mobilization Schedule For Waterpan

The document outlines a detailed mobilization schedule for the waterpan construction project, including phases such as pre-mobilization, planning and procurement, mobilization activities, site preparation, and handover. Key activities include stakeholder meetings, site assessments, material procurement, and final inspections to ensure readiness for construction. It emphasizes the importance of regular monitoring and adjustments based on project-specific factors.

Uploaded by

naomichumba046
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Project: Mobilization Schedule for Waterpan Construction

Objective: To plan and schedule the activities necessary to mobilize resources and prepare the site
for the waterpan construction.

1. Pre-Mobilization Phase:

1.1 Project Kickoff Meeting (Day 1):

• Gather key stakeholders, including project managers, engineers, and contractors, to discuss
project goals, timelines, and responsibilities.

1.2 Site Assessment and Survey (Days 2-7):

• Conduct a comprehensive survey of the construction site to confirm site dimensions, soil
conditions, and access points.

• Prepare a detailed report based on the survey findings.

2. Planning and Procurement Phase:

2.1 Design Review and Material Procurement (Days 8-20):

• Review project plans and specifications in detail.

• Procure necessary materials such as geomembrane liner, geotextile layers, concrete, pipes,
fittings, and other construction materials.

2.2 Permits and Approvals (Days 21-30):

• Apply for necessary permits, licenses, and approvals required for construction from local
authorities.

• Ensure compliance with legal and regulatory requirements before commencing work.

3. Mobilization Activities:

3.1 Resource Mobilization (Days 31-40):

pg. 1
• Arrange transportation and logistics for materials, equipment, and workforce to the
construction site.

• Establish temporary site facilities, including offices, storage areas, and worker facilities.

3.2 Setting Up Site Infrastructure (Days 41-50):

• Prepare access roads and entry points to the construction site.

• Install temporary fencing or barriers for site security.

• Set up temporary utilities such as electricity, water, and communication systems if needed.

4. Site Preparation:

4.1 Excavation and Foundation Preparation (Days 51-60):

• Mobilize excavation equipment and begin excavation based on the site survey and
engineering specifications.

• Prepare the foundation area by leveling and compacting the excavated site.

4.2 Lining Material Inspection and Handling (Days 61-70):

• Inspect geomembrane liner and geotextile layers upon delivery for any damages or
discrepancies.

• Arrange storage and handling of lining materials in a controlled environment to prevent


damage.

5. Handover and Preparation for Construction:

5.1 Project Handover (Day 71):

• Conduct a handover meeting with the construction team, ensuring everyone is briefed on
the site's condition and readiness for construction activities.

5.2 Pre-Construction Inspection (Day 72):

• Perform a final inspection of the site to confirm that all preparations are complete and meet
safety and quality standards.

pg. 2
6. Documentation and Reporting:

6.1 Mobilization Report (Day 73):

• Compile a comprehensive mobilization report documenting all activities undertaken during


the mobilization phase.

• Include details on procurement, site preparation, approvals obtained, and resource


mobilization.

This mobilization schedule provides a structured plan for preparing the site and mobilizing
resources required for the waterpan construction project. Adjust the timeline and activities
according to the specific project requirements, considering factors such as weather conditions,
resource availability, and any unforeseen delays. Regular monitoring and coordination are essential
to ensure a smooth transition into the construction phase.