Record Measurement No.
701
State: Uttar Pradesh
Scheme ID: 20084243
Division Name: Shahjahanpur Division
1. Name of Work: KHUTRIYA & MEERVAISHPUR
2. Situation of Work: KHUTRIYA & MEERVAISHPUR-KANTH
3. Cover Agreement Number: 887/ED/Phase-2/2023-24/XVI/KHUTRIYA
4. Agency By which work executed: NCC LIMITED
5. Reference to agreement of work order: 887/ED/Phase-2/2023-24/XVI/KHUTRIYA
6. Date of commencement: 07 Jun, 2023
7. Date of Loa Completion: 06 Dec, 2024
8. Date of Measurement: 23 May, 2024
9. Date of Actual Completion: 30 Nov, -0001
10. BOQ Name: khutariya meervaishpur
User Info
1. Name: NCC LIMITED
2. Mobile Number: 8884120700
3. Email:
[email protected]4. Designation:
Certificate :
Certified that the work has been satisfactorily done by the Contractor. Certified that the work has been satisfactorily done by the Contractor. Certified that the work has been satisfactorily
done by the Contractor.
Measurement Numbers
Date S.No Particulars Unit Coeff. L B H Contents
type (N1,N2,N3)
Group Name: Common
Item No.: 29 Provide all materials, labour, T&P etc. complete and construct Pump house size (3.6x3.0x3.0)m Chlorinating room size (2.0x1.8x3.0)m as per departmental type design anddrawing
(drawing no?D?2) and as per the specifications for civil work given in the bid document, including supply of all material, labour and T&P etc complete as per instructions of Engineer ?in ?
charge.
Payable
Contractor Quantity:
Contractor Amount: 0 Total Amount: 57119.92 Part Percent: #NA Amount:
0
57119.92
23 May, EXCAVTION-
1 Linear (L) Job 1, 1, 1 0.000 0.100 0.000 0.000 0.1
2024 10%
Total Quantity: 0.1
Item No.: 32.12 Supply of all materials labour T&P etc. for complete construction of R.C.C. Over Head Tank of following capacity and staging above ground level with main components,
including cost of soil testing and assuming bearing capacity of soil as 8 MT, with supply of design and drawings.All the water retaining components of OHT shall be casted in M?30 concrete and
minimum grade of concrete of foundation and staging should be M?25 with approved cement, coarse sand and stone grit as per I.S. 11682 and I.S.456Seismic effects and wind load should be
taken into consideration as per I.S. 1893 for earthquake resistance and I.S. 875 part?III for wind load on structure and including 1M wide RCC staircase, 1 m wide R.C.C. M30 balcony, M.S.
ladder made of 50x50x6 mm angle section and 20mm plain M.S. bars with hand rails of 20mm medium class G.I. pipes, One aluminum ladder inside the tank from top dome to bottom dome,
R.C.C. railing with 20mm dia medium class G.I.pipe (in 3 rows) on both sides of stair case, supported on 50x50x6mm M.S. angle section, spaced at intervals not more than 1.5m, Proper
ventilator at top dome in circular shape of 1.2 m dia, Water level indicator fabricated with sensor connecting to automation, Lightening conductor as per I.S.S.2309 or its latest amendments of
latest electricity rules, consisting of proper elevation rod with 5 or more fork points as prescribed in ISS 2309?1969 and ISS 3013?1966, C.I. manhole of min 60x60cm size with locking
arrangement, Supply, fixing, jointing of D.I.D/F Pipes of appropriate size with D.I.D/F specials conforming to IS 8329/2000 as vertical pipes for inlet, outlet, overflow and washout as per latest /
relevant I.S.specifications with all jointing materials for proper completion of work, Construction of bed blocks in 1:2:4 PCC with cement, coarse sand and approved stone grit , Construction of
washout / overflow chamber and chambers for sluice / butter fly valves as per departmental type design and drawing, Supply of 200 mm dia PVC pipe as per I.S.? 4985/2000 for disposal of
water from overflow and washout chamber to suitable point outside the water works compound, Painting of all concrete surface and steel pipe works with three coats--200 Kl 16 M Staging
Payable
Contractor Quantity:
Contractor Amount: 0 Total Amount: 605151.6 Part Percent: #NA Amount:
0
605151.6
23 May, EXCAVTION &
1 Linear (L) Job 1, 1, 1 0.000 0.050 0.000 0.000 0.05
2024 PCC-5%
RCC STAGING
-- 2 Linear (L) Job 1, 1, 1 0.000 0.100 0.000 0.000 0.1
UP TO G.L-10%
Total Quantity: 0.15
Item No.: AD- 41D.c 160 mm dia HDPE Pipe On Completion of Testing 5% of item code AD- 41D
Payable
Contractor Quantity:
Contractor Amount: 0 Total Amount: 7440.096 Part Percent: #NA Amount:
0
7440.0955
160 mm dia
23 May, HDPE Pipe On
1 Linear (L) Rmt 1, 1, 1 0.000 229.000 0.000 0.000 229
2024 Completion of
Testing
Total Quantity: 229
Item No.: AD- 41E.c 140 mm dia HDPE Pipe On Completion of Testing 5% of item code AD- 41E
Payable
Contractor Quantity:
Contractor Amount: 0 Total Amount: 6615.059 Part Percent: #NA Amount:
0
6615.0585
140 mm dia
23 May, HDPE Pipe On
1 Linear (L) Rmt 1, 1, 1 0.000 267.000 0.000 0.000 267
2024 Completion of
Testing
Total Quantity: 267
Item No.: AD- 41G.c 110 mm dia HDPE Pipe On Completion of Testing 5% of item code AD- 41G
Payable
Contractor Quantity:
Contractor Amount: 0 Total Amount: 2732.331 Part Percent: #NA Amount:
0
2732.331
110 mm dia
23 May, HDPE Pipe On
1 Linear (L) Rmt 1, 1, 1 0.000 161.000 0.000 0.000 161
2024 Completion of
Testing
Total Quantity: 161
Item No.: 41.03.c 63 mm dia HDPE Pipe On Completion of Testing 5% of item code 41.03
Payable
Contractor Quantity:
Contractor Amount: 0 Total Amount: 28892.6 Part Percent: #NA Amount:
0
28892.6
63 mm dia HDPE
23 May, Pipe On
1 Linear (L) Rmt 1, 1, 1 0.000 4600.000 0.000 0.000 4600
2024 Completion of
Testing 5
Total Quantity: 4,600
Item No.: 53.d Making house connection - Excavation and Backfilling 10% of item code 53
Payable
Contractor Quantity:
Contractor Amount: 0 Total Amount: 69902 Part Percent: #NA Amount:
0
69902
Making house
23 May, connection -
1 Number (N) Nos. 1, 1, 1 0.000 200.000 0.000 0.000 200
2024 Excavation and
Backfilling
Total Quantity: 200
Item No.: 53.e Making house connection - Laying and jointing of HSC items 15% of item code 53
Payable
Contractor Quantity:
Contractor Amount: 0 Total Amount: 104853 Part Percent: #NA Amount:
0
104853
Making house
connection -
23 May,
1 Laying and Number (N) Nos. 1, 1, 1 0.000 200.000 0.000 0.000 200
2024
jointing of HSC
item
Total Quantity: 200
Item No.: 53 A.b Extra Charge for Flow Control Valve_Fixing 20% of item code 53 A
Payable
Contractor Quantity:
Contractor Amount: 0 Total Amount: 15977.6 Part Percent: #NA Amount:
0
15977.6
Extra Charge for
23 May,
1 Flow Control Number (N) Nos. 1, 1, 1 0.000 200.000 0.000 0.000 200
2024
Valve_Fixing
Total Quantity: 200
Item No.: 53 A.c Extra Charge for Flow Control Valve_Testing 5% of item code 53 A
Payable
Contractor Quantity:
Contractor Amount: 0 Total Amount: 3994.4 Part Percent: #NA Amount:
0
3994.4
Extra Charge for
23 May,
1 Flow Control Number (N) Nos. 1, 1, 1 0.000 200.000 0.000 0.000 200
2024
Valve_Testing
Total Quantity: 200
Signed By: P V SATHYA SAI KRISHNA
Signed At: 23 May, 2024 09:30 AM
DSC Serial No.: 016C6289
DSC Issued By: e-Mudhra Sub CA for Class 3 Individual 2022
Signed By: RANJAN KUMAR
Signed At: 25 May, 2024 10:53 AM
DSC Serial No.: 6E40802911338247
DSC Issued By: PantaSign Sub CA for DSC 2022