Laoag-Burgos Drainage Send Me
Laoag-Burgos Drainage Send Me
PROJECT NAME Construction/ Upgrading/ Rehabilitation of Drainage along National Roads - Primary Roads - Manila North Rd - K0487 + 724 - K0488 + 407, K0488 + 422 - K0489 + 040,
K0489 + 071 - K0489 + 215, K0489 + 1027 - K0490 + 035, K0489 + 215 - K0489 + 560, K0489 + 878 - K0489 + 979, K0489 + 994 - K0489 + 1027, K0489 + 040 - K0489 + 071,
K0489 + 560 - K0489 + 878, K0490 + 035 - K0490 + 497, K0504 + 000 - K0505 + 000, K0505 + 100 - K0505 + 530, K0505 + 729 - K0506 + 037, K0505 + 000 - K0505 + 100,
K0505 + 530 - K0505 + 729, K0506 + 037 - K0506 + 049, K0507 + 302 - K0507 + 350, K0507 + 363 - K0507 + 368, K0507 + 432 - K0507 + 907, K0507 + 956 - K0508 + 050,
K0507 + 350 - K0507 + 363, K0508 + 050 - K0508 + 125, K0508 + 137.80 - K0508 + 281, K0511 + 186 - K0511 + 650, K0511 + 663 - K0512 + 361, K0512 + 393 - K0512 + 506,
K0512 + 668 - K0513 + 442, K0513 + 455 - K0513 + 851, K0513 + 864 - K0514 + 304, K0514 + 802 - K0515 + 109, K0515 + 202 - K0515 + 383, K0522 + 345 - K0522 + 412,
K0522 + 780 - K0525 + 045, K0535 + 084 - K0535 + 378, K0536 + 123 - K0536 + 298
CONTRACTOR : IGWT-JAV CONST. & DEV. CORP.
DURATION : 261 CD
CONTRACT AMOUNT :
Storm Drainage and Downspout 4 2/22/2024 2/25/2024 l.s. 1.00 ₱63,304.43 ₱63,304.43 0.440%
0.440% #DIV/0! #DIV/0! 40.091%
### ### ### ### 1 0.440% 0.440%
40.411%
0.768% #DIV/0! #DIV/0!
Septic Vault (Concrete/CHB) 14 2/7/2024 2/20/2024 l.s. 1.00 ₱110,550.13 ₱110,550.13 0.768%
### ### ### ### ### ### ### ### ### ### ### ### ### ### 1 0.768% 0.768%
0.113% #DIV/0! #DIV/0!
Catch Basin 3 2/14/2024 2/16/2024 l.s. 1.00 ₱16,221.44 ₱16,221.44 0.113%
### ### ### 1 0.113% 0.113%
0.393% 1.628% 0.730% #DIV/0! #DIV/0!
Plumbing Works 49 2/22/2024 4/10/2024 l.s. 1.00 ₱396,257.55 ₱396,257.55 2.752%
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### 1 2.752% 2.752%
Pole Mounted Distribution Transformer (OISC) w/ Complete Accessories 9 2/23/2024 3/2/2024 l.s. 1.00 ₱370,607.58 ₱370,607.58 2.573%
#DIV/0! 2.573% 30.393%
1 1 1 1 1 1 1 1 1 0 0.000% 2.573%
PLANNED
#DIV/0! 5.773%
Airconditioning 7 3/24/2027 3/30/2027 l.s. 1.00 ₱831,348.00 ₱831,348.00 5.773% 27.641%
#DIV/0!
1 1 1 1 1 1 1
0.179%
0 0.000% 5.773%
28.192%
Exhaust Fan, Wall Mounted 6 3/27/2024 4/1/2024 sets 9.00 ₱2,856.42 ₱25,707.78 0.179%
1 1 1 1 1 1 0 0.000% 0.179%
15.734%
12.671%
7.440%
3.094%
0.000%
0.000%
DECEMBER JANUARY FEBRUARY MARCH APRIL MAY
CONTRACT ID : 23AA0512
PROJECT NAME : CONSTRUCTION OF MULTI-PURPOSE BUILDING (LEGISLATIVE BUILDING), BARANGAY SAN MATEO, LAOAG CITY, ILOCOS NORTE
40.091%
35.301%
33.560%
36.194%
33.671%
27.641%
24.823% 30.393%
28.192%
22.878%
12.671%
15.734%
3.094%
7.440%
0.000%
0.000%
No. of MONTHS 0 1 2 3 4 5 6
% per Month 0.000% 3.094% 9.577% 12.151% 8.737% 6.53%
Planned Cummulative % per Month 0.000% 3.094% 12.671% 24.823% 27.641% 33.560% 35.301% 40.091% 46.761%
Actual Cummulative % per Month 0.000% 7.440% 15.734% 22.878% 28.192% 30.393% 33.671% 36.194% 40.411%
Slippage % per Month 0.000% 4.346% 3.063% -1.945% 0.551% -3.167% -1.630% -3.897% -6.350%
No. of Days Advance/Delay 0 8 6 -4 1 -6 -3 -8 -12
MAY JUNE JULY AUGUST
120.000%
100.000%
100.000%
Row 57 83.265%
80.000%
60.000%
54.262%
55.440%
49.489%
46.761% 51.812%
40.091%
42.330% 40.000%
35.301% 40.411%
33.560%
36.194%
33.671%
30.393%
20.000%
0.000%
6 8 9 10
9.398% 4.773% 29.003% 16.735%
49.489% 54.262% 83.265% 100.000%
42.330% 51.812% 55.440%
-7.159% -2.450%
-14 -5
DECEMBER JANUARY FEBRUARY MARCH
CONTRACT ID : 23AA0512
120.000%
PROJECT NAME : CONSTRUCTION OF MULTI-PURPOSE BUILDING (LEGISLATIVE BUILDING), BARANGAY SAN MATEO, LAOAG CITY,
ILOCOS NORTE
100.000%
CONTRACTOR : IGWT-JAV CONST. & DEV. CORP. 100.000%
59.262%
60.000%
40.000%
18.576% 20.000%
0.000%
0.000%
0.000%
No. of MONTHS 0 1 2 3 4
% per Month 0.000% 18.576% 40.686% 24.176% 16.563%
Planned Cummulative % per Month 0.000% 18.576% 59.262% 83.438% 100.000%
Actual Cummulative % per Month 0.000%
Slippage % per Month 0.000%
No. of Days Advance/Delay 0
CONTRACT ID :
PROJECT NAME : Construction/ Upgrading/ Rehabilitation of Drainage along National Roads - Primary Roads - Manila North Rd
DURATION :
### ###
CONTRACT AMOUNT :
###
Occupational Safety and Health Program mo. 8.70 ₱108,750.00 ₱217,500.00 0.238%
Traffic Management l.s. 1.00 ₱17,500.00 ₱35,000.00 0.038%
0.146% 0.127%
Mobilization/Demobilization l.s. 1.00 ₱250,000.00 ₱250,000.00 0.273%
###
###
###
###
###
###
###
### ###
###
###
###
###
###
###
###
###
###
PART C EARTHWORKS
0.001% 0.002% 0.002% 0.002% 0.002% 0.001%
Removal of Structures and Obstruction (Existing Canal) cu.m. 9.68 ₱978.79 ₱9,474.69 0.010%
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
### ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
Removal of Actual Structures / Obstruction, 0.28m thick, PCCP(Unreinforced) Sq.m. 8,375.15 ₱92,498.69 ₱895,387.29 0.978%
Structural Concrete, Class A (fc' = 27.58 Mpa), 28 days cu.m. 9,674.73 ₱29.68 ₱29,352,453.59 32.057%