This quick guide provides an overview of the Residential Smart PV Solution, focusing on the single-phase PV and energy storage system (ESS) with smart dongle networking. It details the components involved, including inverters, energy storage systems, backup boxes, and smart power sensors, along with their connections and commissioning procedures. The document also outlines the app-based deployment process and system control parameters for off-grid and grid-tied modes.

Uploaded by

georgedrobot
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
91 views8 pages

Residential Smart PV Solution Quick Guide (Single-Phase PV+ESS Scenario + Smart Dongle Networking)

This quick guide provides an overview of the Residential Smart PV Solution, focusing on the single-phase PV and energy storage system (ESS) with smart dongle networking. It details the components involved, including inverters, energy storage systems, backup boxes, and smart power sensors, along with their connections and commissioning procedures. The document also outlines the app-based deployment process and system control parameters for off-grid and grid-tied modes.

Uploaded by

georgedrobot
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

Residential Smart PV Solution Quick Guide Issue: 04

Date: 2023-11-13
(Single-Phase PV+ESS Scenario + Smart Dongle Networking)

1 Networking 2 Product Overview


Inverter ESS Backup Box Smart Power Sensor Smart Smart PV
Critical load 3
Dongle Optimizer

PV strings
(including optimizers) Slave inverter 2

Critical load 2

PV strings
(including optimizers) Slave inverter 1

Component Model Description

SUN2000-(2KTL-6KTL) -L1
A maximum of three SUN2000-(2KTL-6KTL)-L1 inverters can be cascaded.
Inverter SUN2000-(8K, 10K)-LC0
The SUN2000-(8K, 10K)-LC0 or SUN2000-(8K, 10K)-LC0-ZH inverter cannot be
(master and slave)
SUN2000-(8K, 10K)-LC0-ZH cascaded.
Critical load 1 Common load
LUNA2000-(5-30)-S0 • The capacity of a battery module is 5 kWh. A maximum of two ESSs can be
Energy storage
cascaded and the maximum capacity is 30 kWh.
PV strings system (ESS)
Smart Power • If there is only one ESS, it must be connected to the master inverter.
(including optimizers) Master inverter Sensor
Backup Box-B0 • AC input voltage range: 198–253 V
• If there is only one Backup Box, it must be connected to the master inverter.
Backup Box
АC power • SUN2000-(8K, 10K)-LC0 and SUN2000-(8K, 10K)-LC0-ZH cannot be connected
distribution box Power grid to the Backup Box.

DDSU666-H • The Smart Power Sensor must be connected to the master inverter.
Smart Power Sensor YDS70-C16 • It connects to the inverter over RS485 for output power management and
power limiting.

4G Smart Dongle SDongleA-03 (4G) • The Smart Dongle must be connected to the master inverter.
4G Smart Dongle SDongleB-06 (4G) • It connects to the management system and performs power scheduling.
• The SDongleA-03 (4G) is compatible only with the SUN2000-(2KTL-6KTL)-L1.
SDongleA-05 (WLAN-FE)
FusionSolar
management system SUN2000-450W-P
Ethernet
WLAN-FE SUN2000-600W-P: Long and short input cables are available to connect to PV
Smart PV Optimizer SUN2000-450W-P2
Smart Dongle modules with different cable lengths.
Signal cable
WLAN SUN2000-600W-P
Power cable
FE FusionSolar app
Wireless communication
1. The information in this document is subject to change due to version upgrade or other reasons. Every effort has been made in the preparation
of this document to ensure accuracy of the contents, but all statements, information, and recommendations in this document do not constitute
a warranty of any kind, express or implied.
2. For details about the solution components, installation, and cable connections, see the corresponding user manuals and quick guides.
3. The cable colors involved in this document are for reference only. Select cables in accordance with local cable specifications.

1 Copyright © Huawei Digital Power Technologies Co., Ltd. 2023. All rights reserved.
Residential Smart PV Solution Quick Guide
(Single-Phase PV+ESS Scenario + Smart Dongle Networking)

3 Cable Connections (Single-Phase Inverter L1 + ESS S0 + Backup Box B0)

Power grid
Before connecting cables, ensure that all
switches are OFF. Otherwise, electric shocks
may occur. To COM-1 of slave inverter 1 To COM-2 of slave inverter 1 AC power
To COM-7 of ESS 1 To COM-4 of ESS 1
To COM-24 of DDSU666-H
distribution box
To COM-25 of DDSU666-H
To X4-2 of Backup Box To COM-3 of ESS 1
Signal cables must be outdoor shielded To COM-2 of ESS 1 The wiring sequence of the Backup Box must be
To X4-1 of Backup Box
twisted pair cables. consistent with that of the inverter AC terminals.

Backup Box
Critical load
Master inverter
PV strings (including optimizers)

Backup load
power
distribution
AC CT
box

ESS 2 ESS 1
(power control module) (power control module)

Shield layer
grounding
Loads

Slave inverter 1 Slave inverter 2


Cable One End The Other End Cable One End The Other End
No. No.
Type Component Port Port Component Type Component Port Port Component
Master PV1+ Positive terminal PV
Shield layer Shield layer AC-L X3-2 (L)
inverter PV1- Negative terminal strings Master Backup
grounding grounding AC-N X3-6 (N)
Master BAT+ BAT+ inverter Box
DC ESS 1 AC-PE X3-10 (PE)
power inverter BAT- BAT-
Backup load L X1-1
cable BAT+ BAT+
ESS 1 ESS 2 power
BAT- BAT- N X1-2 Backup Box
distribution
AC box PE
COM (right) ESS 1 X1-4
power
cable L X2-1
Master COM Slave inverter 1 AC power
inverter COM N X2-4 Backup Box
RS485 distribution box
DDSU666-H X2-6
Signal PE
cable X4 Backup Box AC power L 3
DDSU666-H
To COM-1 of ESS 2 COM (right) COM (left) ESS 1 distribution box N 4
Connect other cables to slave master inverter
To COM-2 of
5
master inverter To COM-1 To COM-2 Slave COM-1 COM-1 Slave AC power DDSU666-H
inverters by referring to the To COM-1 of of slave of slave inverter 1 COM-2 COM-2 inverter 2 distribution box
L
6 CT
To COM-2 of
connection method for the slave inverter 2
slave inverter 2
inverter 1 inverter 1

master inverter.

2
Residential Smart PV Solution Quick Guide
(Single-Phase PV+ESS Scenario + Smart Dongle Networking)

3 Cable Connections (Single-Phase Inverter LC0 + ESS S0)


PV strings
(including optimizers)

Before connecting cables, ensure that all


switches are OFF. Otherwise, electric shocks
may occur. Power grid
Inverter
AC power
Signal cables must be outdoor shielded distribution box
twisted pair cables.

AC

CT

Shield layer grounding

ESS 2 ESS 1
(power control module) (power control module)
Cable One End The Other End Cable One End The Other End
No. No.
Type Component Port Port Component Type Component Port Port Component
Shield layer
Master PV1+ Positive terminal PV Master 24
grounding Signal COM-4
inverter PV1- Negative terminal strings cable inverter COM-3 25 DTSU666-H
DC Master BAT+ BAT+
power ESS 1
inverter BAT- BAT- One End The Other End
cable Cable No.
BAT+ BAT+ Type Component Port Port Component
ESS 1 ESS 2
BAT- BAT- AC-L L
Master AC power
COM-2 (left) COM-2 (right) AC-N N
inverter distribution
Shield layer COM-3 (left) COM-3 (right) AC-PE box
Shield layer AC
PE
grounding grounding COM-4 (left) COM-4 (right)
L 3
ESS 1 power AC power
COM-7 (left) COM-7 (right) ESS 2 cable distribution box DDSU666-H
N 4
Signal COM-8 (left) COM-8 (right)
cable COM-9 (left) AC power 5 DDSU666-H
COM-9 (right) L
distribution box CT
COM-5 COM-2 (right) 6

Master COM-6 COM-3 (right)


inverter ESS 1
COM-4 COM-4 (right)
COM-3 COM-7 (right)

3
Residential Smart PV Solution Quick Guide
(Single-Phase PV+ESS Scenario + Smart Dongle Networking)

4 System Commissioning

App-based Deployment Procedure Installer Registration

Download and install the FusionSolar app Initial registration Non-initial registration
If the company requires multiple installer accounts, log in to the FusionSolar app and tap Add user to
Create the first installer account, and generate a domain named after the company.
Sign up as an installer (optional, required create another installer account.
for initial registration)

Enter setup wizard

Check the device status

Downloading and Installing the Or


FusionSolar App
• Search for FusionSolar in the app store to
download the app.
• Scan the QR code below to download the app.

FusionSolar

Setup Wizard (Connecting to the Inverter WLAN for Commissioning)

(Optional) Cascade inverters.

Ensure that the devices in


Log in as an installer. The
the device list are
initial password is 00000a. Set the local grid code. consistent with the
If the system prompts you
Scan the QR connected devices.
to set the password, set
code of the the password and then
master inverter. log in.

If you enable Sync phone


time, the time and time zone
of the inverter are
At the first login, the synchronized with those of
Quick settings screen the mobile phone.
is displayed by default.

4
Residential Smart PV Solution Quick Guide
(Single-Phase PV+ESS Scenario + Smart Dongle Networking)

Set the energy storage working mode. Set the communication networking.

WLAN communication 4G communication FE communication

Select the ESS


Installation
Environment and
working mode intl.fusionsolar.huawei.com Or intl.fusionsolar.huawei.com Or intl.fusionsolar.huawei.com
settings of the battery By default, APN mode is
set to Automatic. If you If the Ethernet parameter
cannot access the Internet is displayed, the network
Select the desired
You can tap to in Automatic mode, set it cable is not connected.
Note: router and enter the
obtain the detailed to Manual. In this case, set Reconnect the network
In a non-Battery scenario, router password.
working mode the parameters related to cable.
the step of Energy
information. the SIM card with the
storage control is not
information obtained from
involved.
the carrier.

Add a plant. Create an owner account.

In an inverter cascading
scenario, the parameter
synchronization result is
displayed.

Checking the Plant Status

5
Residential Smart PV Solution Quick Guide
(Single-Phase PV+ESS Scenario + Smart Dongle Networking)

5 Off-Grid/Grid-tied Control Parameters

Enabling Off-Grid Mode

Settings

Feature parameters

• Off-grid mode
• Backup power SOC
• Grid-tied/Off-grid mode
switching

Setting Grid-tied Point Control

Power adjustment

Grid-tied point control

Active power

Control mode
• Unlimited
• Grid connected with zero power
• Power-limited grid connected

6
Residential Smart PV Solution Quick Guide
(Single-Phase PV+ESS Scenario + Smart Dongle Networking)

6 Physical Layout of Smart PV Optimizers

Attaching SN Labels Taking a Photo of the Physical Layout Template Generating a Physical Layout on the App
Ensure that the four positioning points on the Enter the Layout screen.
Remove the SN labels from optimizers and attach them to the physical layout template based
on the actual positions of the optimizers in the plant. template are within the frame.

Positioning point

Tap a plant that is


equipped with
optimizers.

Generating a Physical Layout on the App

Upload the template and generate a layout.

If some QR codes cannot


be identified or the plant
layout needs to be
adjusted, refer to
Take a photo of the "Creating a Physical
template with the QR Layout on the App
Set optimizer codes attached, or Manually."
parameters. select the photo from
Tap to add a physical your phone album.
layout template.

After all templates are


uploaded, tap Layout
Generation to
generate the physical
layout.

7
Residential Smart PV Solution Quick Guide
(Single-Phase PV+ESS Scenario + Smart Dongle Networking)

Creating a Physical Layout on the App Manually

Edit the physical layout and specify the quantity of inverters and PV modules as required.

Bind the inverter or optimizer SN. Adjust the physical layout.

Bind the inverter or


optimizer SN.
Select the PV modules that
need to have the azimuth
adjusted.