Tailings Management Good Practice Guide February 2025 1740667326
Tailings Management Good Practice Guide February 2025 1740667326
Management
The development of this publication would not have Brant Whiting (Freeport McMoRan), Ian Gordon (Newcrest),
been possible without the input and support of the Briana Gunn, John Lupo and Kim Morrison (Newmont),
individuals below. ICMM gratefully acknowledges the Imran Gillani (Rio Tinto), Greg Puro (Vale).
following contributions:
Member representatives
Writing team Representatives of the ICMM Council Tailings Subgroup and
Unusually for an ICMM publication, no external consultant Tailings Working Group provided valuable direction, input,
was contracted to support the report writing process. In and feedback on iterative drafts and updates to the guide.
practice, this meant that the writing team solely comprised They included: Nerine Botes, Pule Soaisa (African Rainbow
representatives of member companies or associations. Minerals), Matthew Cox, Roy Harvey, Paul Smithall (Alcoa),
Some of these individuals invested very significant Caius Priscu (Anglo American), Joseph Chihota, Roger Welff
amounts of time and energy to ensuring the delivery of a (AngloGold Ashanti), Ivan Arriagada, Jorge Troncoso Boys
high-quality product that was responsive to the views and (Antofagasta Minerals SA), Grant Beringer, Allison Brown,
perspectives of other members. ICMM is indebted to them Bassam El Husseini (Barrick), Matthew Currie, Michal
for their exceptional contributions and service. Kozikowski, Rebecca Getty, Chad Le Poudre (BHP), Magnus
The report was drafted by a writing team led by Tamara Bergknut (Boliden), Rene Orellana (Codelco), Ivan
Johndrow (Freeport-McMoRan) and Charles Dumaresq Glasenberg (Glencore), Richard Adkerson, Thomas Calhoun,
(Mining Association of Canada (MAC)). Their commitment Sheila Deely, Tamara Johndrow, Kanyembo Katapa, Katie
to this work represented a significant investment on their Kruger, Teresa Speigl (Freeport McMoRan), Aaron Chapple
part as well as a substantial in-kind contribution from their (Glencore), Johan Boshoff, Nosimo Macatsha (Gold Fields),
respective employers, which ICMM greatly appreciates. Breno de Matos Castiho, Paschoal Cataldi (Hydro), Shigeru
Oi, Koichiro Tsuchiya (JX Nippon), Mario Velasco (Minera San
Extensive drafting and editing support was provided Cristobal), Nikisi Lesufi, Stephanie Mudau (Minerals Council
by Michael Davies (Teck) and David Machin (MMG). South Africa), Harry Silva (Minsur), Jonathon Crosbie (MMG),
Jo Heyes (Greenroad Group – Mine Closure Management) Veronica Shime (National Mining Association), Ian Gordon
provided expert review and editing support to the 2025 (Newcrest), Brett Byler, Rynhard Kok, John Lupo, Kim
updates made to the good practice guide. Morrison, Kristen Pouw (Newmont), Simon Nouis, Philippe
Crochon, Abdoulaziz Chaibou (Orano), Pavel Grachev, Pavel
Special advisor
Shevelenko (Polyus), Laila Burger, Imran Gillani, J.S. Jacques,
Professor Norbert Morgenstern provided invaluable
Fernanda Maluly Kemeid, John Mulcahy, Marnie Pascoe,
guidance throughout the drafting process providing
Malcolm Talmage (Rio Tinto), Ross Copper, Grant Stuart,
content, collaborating closely with the writing team and
Matt Wolfe (Sibanye Stillwater), Lis Boczek, Matt Lord, Dave
content contributors. Professor Morgenstern’s
Luppnow, Rowena Smith (South32), Marcia Smith, Björn
contributions to the tailings field has been immeasurable
Weeks (Teck), Breno Castilho, Rafael Bittar, Luis Cervantes
over the decades and ICMM deeply appreciates his views.
and Greg Puro, (Vale).
His selfless contribution of expertise and time along with
his patience throughout the development process was ICMM team
crucial to the completion and quality of this Guide. Aidan Davy and Diane Tang-Lee led the process to develop
this guide, with input and support from Hideo Aoyama, Alice
Content contributors
Evans and Kira Scharwey. Sally Innis, Jessica Nicholls and
A number of tailings experts and environment specialists in
Emma Gagen contributed to the 2025 update.
the ICMM membership provided substantial technical
content for the writing team to integrate into the drafts. Alice and Will Beaven (Positive 2), Nic Benton and Ella Yarrow
They included the following: (ICMM) provided creative design support.
ICMM 2
Contents
Foreword 4
01 Overview 7
1.1 Introduction 8
1.3 R
elationship to the Global Industry Standard on Tailings Management,
the ICMM Conformance Protocols and the ICMM Tailings Governance Framework 19
3.4 Design 99
Glossary 140
List of Acronyms 146
‘Tailings dams are complex systems that Assuring safety or otherwise is not achieved by a set of
calculations alone or by observations alone, unless they
have evolved over the years. They are reveal that performance as flawed, or by adopting a
also unforgiving systems, in terms of pre-conceived list of safety indicators that reduces the
the number of things that have to go confirmation of safety to checking the items off in a box.
As revealed by the quotation above, the construction
right. Their reliability is contingent on
and operation of a tailings storage facility incorporating
consistently flawless execution in a dam, is a highly dynamic process, more so than is
planning, in subsurface investigation, common for water dams where there is usually a clearer
in analysis, in construction quality in separation between the Design and Construction
phases and the Operations phase. Therefore, reliable
operational diligence, in monitoring, confirmation of safety requires an equally dynamic
in regulatory action, and in risk process applied to the full lifecycle of the facility so that
management at every level. All of these it can, in turn, reassure all stakeholders.
activities are subject to human error.’ Progress in this regard has already been made by the
publication of the Global Industry Standard on Tailings
Mount Polley Independent Expert Engineering
Management, and its recommendations will be
Investigation and Review Panel (2015)
integrated into ICMM’s industry member commitments.
The Standard makes recommendations both with
regard to Environmental, Social and Governance issues
and technical issues. The Standard might be regarded
as requirements of what has to be done. ICMM has
developed this Guide, which is aligned with the
Standard, but focuses primarily on technical issues and
recommends good practice for design, construction,
operation and closure.
ICMM Foreword 4
From my perspective, this Guide is built upon the — Adopt the technical recommendations put forward
following core elements: for the safe design, construction, operation, and
closure of tailings storage facilities. This should
— Of overarching significance is the safety culture
recognise the enhanced responsibilities of the
expressed by the Operator. It is common to declare a
Engineer of Record for declaring design criteria as
goal of zero fatalities, occupational disease and
opposed to relying on prescriptive values. Where
catastrophic events. Hence, a common denominator
conditions are complex, recognize the value of
for all Operators that share this goal is that tailings
adopting performance-based design. Always
facilities should be designed, constructed, operated
respect regulatory requirements as a minimum.
and closed to such high standards that ‘failure is not
an option’. — Maintain comprehensive documentation of
construction and quality assurance through all
— A governance framework to support the aspirational
phases of the lifecycle, with special emphasis on
goals of the safety culture is recommended,
confirming or adjusting the site characterisation
incorporating roles and responsibilities from the
model as new information is obtained.
Board of Directors to the Engineer of Record and the
Design Team. — As part of the Tailings Management System,
determine what documentation related to safety
— In recognition of the phases associated with tailings
could enter the public domain in order to enhance
management, from Project Conception through to
transparency and trust.
Design, Construction, Operations, Closure and
Post-Closure, ensure that tailings management is While the task of determining the cause of failure is
continually integrated within a sitewide integrated simpler after the event, I have evaluated this Guide in
mine, tailings, water and closure plan. terms of my experience with a significant number of
tailings dam failures and related serious incidents and
— Informed by the integrated planning, develop a
concluded that had this Guide been available and
tailings management system.
adopted, these incidents should not have occurred.
— Engage external Independent Review for technical
Norbert R Morgenstern
matters early in the lifecycle and throughout all of its
Distinguished University Professor (Emeritus),
phases.
University of Alberta (Canada) and Consulting Engineer
— Manage uncertainty through all phases of the
lifecycle by risk-informed decision-making that
assesses uncertainty, conducts risk assessments at
appropriate stages, and carries a risk register
throughout the lifecycle of the facility.
The ICMM Tailings Management: ICMM served as the industry representative in the
development of the Global Industry Standard on Tailings
Good Practice Guide represents the Management, a multi-stakeholder effort designed to
culmination of years of work by ICMM elevate the standard of practice for tailings storage
member companies and external facilities worldwide. ICMM is committed to leading the
mining industry in the safe and responsible design,
experts to develop guidance for safely
construction, operation and closure of tailings facilities.
and responsibly constructing and This is a critical issue at every mine, which must be
managing mine tailings facilities. viewed as such by every mine operator.
Inspired by the pathbreaking work of Dr In the Good Practice Guide, ICMM member company
Norbert R Morgenstern, as set forth in experts build on the Standard promulgated by the
the Sixth Victor de Mello Lecture in 2018, multi-stakeholder initiative. The Good Practice Guide
supports the requirements of the Standard and
ICMM embarked on an undertaking to provides guidance on good governance and
improve safety and management of engineering practices.
tailings storage facilities. The Good Practice Guide is important in achieving
the aspirational goal of eliminating fatalities and
catastrophic failures at tailings facilities. We strongly
encourage all mining companies worldwide, whether
or not they are ICMM members, to incorporate the
Standard and Good Practice Guide into their practices
to improve mine tailings facility performance and to
achieve these safety goals.
Richard C Adkerson
Chairman of the Board, and Chief Executive Officer
Freeport-McMoRan and Chair of ICMM
ICMM Foreword 6
Part 1: Overview
Most tailings facilities are planned, designed, As stated on the ICMM website:
constructed, operated and closed in a safe and
‘Responsible mining companies have an unwavering
responsible manner. However, as recent failure incidents
commitment to the health and safety of workers and
clearly indicate, the physical stability of tailings facilities
their families, local communities and wider society.
has not been universal. Global performance needs
Health and safety has to be at the heart of all operations
to improve.
and processes. Mining presents various hazards that
This guidance is intended to facilitate continual can be of significant consequence, but through
improvement across the global mining sector, leading effective risk management strategies neither safety
to the safe, responsible management of tailings incidents nor the onset of occupational diseases are
worldwide. The guidance presents a comprehensive, inevitable. ICMM members are progressing towards a
holistic approach to tailings management that goal of zero fatalities, occupational disease and
describes good engineering practices and is informed catastrophic events. People have a right to go home
by lessons learned from past failures. It is intended to safe and healthy to their families and their communities
improve performance across all the aspects that at the end of every day.’
underpin safe tailings management. While no guidance
However, the failures of tailings facilities around the
document is perfect, this Guide is intended to be
world, resulting in hundreds of fatalities over the last
part of the continual improvement process of the
three decades, point to the imperative that the mining
mining industry.
industry’s safety culture be applied to tailings
The guidance is ultimately aimed at mitigating what can management.
perhaps be the greatest risk factor: the human element.
Beyond driving improvements in practice, the guidance
Individuals, however professional and qualified, make
is aimed at fostering and strengthening the safety
judgements and decisions based on their own
culture associated with tailings management and
experiences and biases. Embedded ignorance, which
provides a roadmap to the continual improvement of
we all have, results from a lack of knowledge, or a failure
tailings safety at both new and existing facilities. To be
to recognise internal weaknesses or limitations.
consistent with this safety culture, tailings facilities
Complacency, over-confidence, competing priorities
should be designed, constructed, operated and closed
and the loss of corporate knowledge over time can be
to such high standards that the goal of eliminating
compounding factors.
fatalities and catastrophic events is achieved.
ICMM Introduction 8
Although regulators, investors, communities and others — Should not be used to assess conformance against
have a role in this cultural shift, the responsibility resides the Standard, which is the purpose of the
primarily with the Operators of mines and the Conformance Protocols. Some examples in the
associated tailings facilities. Conformance Protocols draw upon and refer to
related sections of the Guide.
1.1.3 Objectives
In keeping with these objectives, the Guide presents
This Guide is intended to support the safe and recommendations, not requirements. The use of the
responsible management of tailings across the global word ‘should’ is intended to mean ‘recommended’
mining industry, with the ultimate goal of eliminating not ‘must’.
fatalities and catastrophic events.
1.1.4 Scope of Application of the Guide
It provides guidance on good governance and good
engineering practices that will support continual The Guide describes good governance and good
improvement in the management of tailings facilities and engineering practices for tailings management and may
help to foster and strengthen a corporate safety culture. be applied to:
ICMM Introduction 10
The Tailings Governance Framework and existing
guidance from MAC are focused primarily on tailings
management governance and do not address design
and other technical elements related to tailings
management. Technical resources for tailings facilities
are available from several sources (eg International
Commission on Large Dams, Canadian Dam
Association, Australian National Committee on Large
Dams).
1.2.1 Tailings Management Lifecycle Tailings management does not occur in isolation from
the other activities that occur at mine sites. Tailings
Having a common understanding of the lifecycle of
production is ‘downstream’ of many steps in the mining
tailings management is important for applying this
process and a wide range of decisions related to the
guidance and the requirements of the Standard.
overall process that can impact tailings management
The lifecycle of a tailings facility encompasses all the
are often made without sufficient consideration of those
activities across the life of a tailings facility, from the
potential impacts. For example, decisions about waste
earliest stages of the Project Conception phase
rock management, ore processing and water
through to the Closure and Post-Closure phases. It is
management often have significant implications for
determined on a site-specific basis by a wide range of
tailings management. Similarly, decisions related to
factors and is always subject to change. The lifecycle
tailings management are sometimes taken without
consists of six phases or activities:
adequate consideration of other plans. A failure to
1. Project Conception1 recognise these relationships and potential impacts and
to plan accordingly can compromise the objective of
2. Design
safe tailings management.
3. Construction
Throughout the lifecycle, an integrated approach to
4. Operations mine planning is essential to safe tailings
management. This involves integrating the planning of
5. Closure
all aspects of the mine that can impact tailings
6. Post-Closure. management (Section 3.2.2), such as ore extraction
and processing, sitewide water management and the
The relationship between these phases or activities is
management of waste rock. For new tailings facilities
dynamic and rarely linear. In addition, the lifecycle of a
and proposed mine life extensions, this includes
tailings facility can last for many decades to reach the
integrating planning for tailings management into the
end of the Operating phase, and centuries beyond for
development of Pre-Scoping, Scoping, Pre-Feasibility
the Post-Closure phase.
and Feasibility Studies.
Throughout the lifecycle, change can be a key source of
Such an integrated approach should be adopted for
risk for tailings facilities and needs to be effectively
both new facilities and existing facilities, to help to
managed (Section 2.3.2). Consequently, it is important
ensure that decisions are aligned with the short-,
that Operators recognise and plan for a dynamic
medium- and long-term objectives of tailings
lifecycle and implement a TMS throughout the lifecycle
management.
(Sections 1.2.2.1 and 2.3).
1. For new tailings facilities, the Project Conception and Design phases encompass key steps in the mine planning process: Pre-Scoping Study, Scoping Study, Pre-Feasibility Study,
and Feasibility. Thus, just as conceptual mine planning begins at the pre-scoping and scoping steps, planning for tailings management should also begin at these steps. However, for
Project Conception and Design activities related to proposed material changes or closure planning, there may not be corresponding Pre-Scoping, Scoping, Pre-Feasibility and
Feasibility studies for the broader mine planning process.
— C
onstruction during the Closure phase (eg Post-Closure: This lifecycle phase begins when the
installation of covers, water management closure plan has been implemented and the tailings
infrastructure). facility has transitioned to long-term maintenance
and surveillance. The Post-Closure phase has to
Temporary Suspension
Potential material
changes go to
either Project
Conception or
Design, depending
on complexity
Material Changes
Note: The red boxes and lines indicate activities/relationships expected to occur for all tailings facilities.
The yellow boxes and lines indicate activities/relationships that may occur.
1.2.2 Core Elements of Safe Tailings These elements are equally vital to the safe and
Management responsible management of tailings and should be
implemented together in a fully integrated manner
A comprehensive, holistic approach is needed across
throughout all the phases of the lifecycle. They each
the lifecycle for the safe and responsible management
fulfil a different but essential role:
of tailings. This encompasses two inter-related core
elements: — Effective governance of tailings management
ensures accountability for decisions, provides a
— Governance of tailings management (further
management structure with checks and balances
described in Part 2).
for decision-making, provides the means to
— Implementation of good engineering practices for effectively manage tailings on a day-to-day basis,
tailings management across the lifecycle (further and provides input to mechanisms to respond
described in Part 3). effectively if an emergency occurs.
There are many facets to engineering practices An essential characteristic of managing risk is
related to tailings management, including: recognising and acknowledging uncertainty, managing
risk within the limitations of that uncertainty and
— Recognising and managing uncertainty.
working to reduce uncertainty. Implementing a risk-
— Project conception and design. informed approach is key to managing this uncertainty.
Recognising and Managing Uncertainty — Informed by the results of the risk assessment.
Understanding and managing risk is fundamental to Potential risks and related uncertainties associated
the safe management of tailings but subject to with tailings management are identified, analysed
significant uncertainty. and evaluated during the Project Conception phase,
re-assessed during the Design phase, and re-
Risk is a frequently used but often misunderstood
assessed periodically throughout the lifecycle.
concept. It is important to emphasise that assessing
risk involves the consideration of both the potential — Intended to prevent or eliminate risks to the extent
consequences of an event and the probability or possible and to effectively manage those risks that
likelihood of that event occurring. Risk should not be remain by developing a robust tailings facility design
confused with consequence, nor should these terms with less uncertainty in design criteria.
be used interchangeably.
— Informed by improved site characterisation, the
Risk assessment involves a process of risk identification, results of surveillance, input from the programme for
risk analysis and risk evaluation. Available information is reviewing facility safety (Section 2.6), and updates to
1.3.1 Relationship to the Global Industry For example, Principle 1 of the Standard includes
Standard on Tailings Management and requirements relating to: respect for human rights and
ICMM Conformance Protocols for the Global related due diligence; working to obtain and maintain
Industry Standard on Tailings Management the Free, Prior and Informed Consent (FPIC) of
indigenous or tribal peoples; meaningful engagement of
As noted earlier (Section 1.1.3), this Guide has been project-affected peoples; and the establishment of
informed by the Standard and will help Operators to work effective grievance mechanisms to address the
through how to integrate the related requirements or complaints and grievances of project-affected people.
commitments into their own programmes. The Guide All of these are adequately covered by existing sources
should not be used to assess conformance against the of ICMM guidance.
Standard, which is the purpose of the ICMM
Conformance Protocols for the Global Industry Standard Two principles from the Standard that require some
on Tailings Management (The Conformance Protocols). further explanation are Principles 2 and 3 that deal with
the development and use of an integrated knowledge
The Conformance Protocols have been developed to base. The concept of a ‘knowledge base’ is addressed
enable conformance to be assessed and to support in ICMM’s Integrated Mine Closure: Good Practice Guide
the integration of the Standard into ICMM’s existing (2025), and the basic approach is transferrable to
assurance processes for its member commitments. tailings management. It involves developing,
The Conformance Protocols support either self- documenting and periodically updating information
assessments or independent third-party assessments about the social, environmental and local economic
of progress with implementing the Standard and context of the tailings facility, to support informed
ultimately conformance. It details clearly and concisely decision-making across the tailings facility lifecycle.
criteria that assessors expect to see evidenced for This should be undertaken using approaches aligned
conformance to be assessed, with illustrative examples with international good practice and designed to
of evidence and explanatory notes as appropriate. It is capture uncertainties due to climate change. In terms of
available to be used by company members (or non- updating the knowledge base, this should be revisited
members) or suitably qualified independent third parties at least every five years, and whenever there is a
and maps to the Standard and its 77 requirements. material change to the tailings facility or to the social,
environmental and local economic context.
The social and environmental requirements of the
Standard are referred to within this Guide, but the Other aspects of the knowledge base such as
intention is that these are largely addressed by reference developing, documenting and updating detailed site
to existing guidance from ICMM. Where appropriate, characterisations of tailings facility sites for a range of
these other sources of guidance are referred to within criteria or the conduct and periodic updating of breach
this Guide and within the Conformance Protocols. analysis are addressed in this Guide.
— A
ccountability for the overall governance of tailings facilities Section 2.3: Tailings Management System
resides with the owners and operators.*
Section 2.4: Operation, Maintenance and Surveillance
— O
rganisational structures and roles are established to support
management of tailings facility risks and governance
accountability.
— C
ommunication processes are maintained to ensure that
personnel understand their responsibilities. Training is conducted
to maintain currency of knowledge and skills.
— R
ole competency and experience requirements are defined for
critical roles within the established organisational structures.
— T
ailings facility operating and capital costs, and human resource
needs, are included in relevant business planning processes.
— R
esources necessary to implement and maintain activities within
this governance Framework are provided.
— R
isk controls and their associated verification activities are Section 2.3: Tailings Management System
identified based on failure modes and their associated
Section 2.4: Operation, Maintenance and Surveillance
consequences and evaluated on a tailings facility-specific basis
considering all phases of the tailings facility lifecycle. Section 2.7.2: Assessing Credible Potential Consequences
— S
uitably qualified and experienced experts are involved in tailings Section 3.2.4: Managing Uncertainty and Risk
facility risk identification and analysis, as well as in the
Section 3.3: Projection Conception
development and review of effectiveness of the associated
controls. Section 3.4: Design
— P
erformance criteria are established for risk controls and their Section 3.6: Operations
associated monitoring, internal reporting and verification Section 3.7: Closure and Post-Closure
activities.
— P
rocesses are applied that involve the identification, Section 3.2.4: Managing Risk and Uncertainty
assessment, control and communication of risks to tailings
Section 3.3: Projection Conception
facility integrity arising from both internally-driven and
externally-driven change, to avoid introducing uncertain, Section 3.4: Design
unacceptable, and/or unmanaged risks.
Section 3.5: Construction
— D
ocuments and records that support tailings facility planning,
Section 3.6: Operations
design, construction, operation, surveillance, management
and governance are maintained and kept suitably current Section 3.7: Closure and Post-Closure
and accessible.
Emergency Preparedness and Response: Section 2.4: Operation, Maintenance and Surveillance
Processes are in place to recognise and respond to impending failure
Section 2.7: Emergency Preparedness and Response
of tailings facilities and mitigate the potential impacts arising from a
potentially catastrophic failure. Section 3.6: Operations
— A
ction thresholds and their corresponding response to early
warning signs of potential catastrophic failure are established.
— E
mergency preparedness and response plans are established
commensurate with potential failure consequences. Such plans
specify roles, responsibilities and communication procedures.
— E
mergency preparedness and response plans are periodically
tested.
— O
utcomes and actions arising from tailings facility review and
assurance processes are recorded, reviewed, closed-out and
communicated.
— P
erformance of risk management programmes for tailings
facilities is reported to executive management on a regular basis.
Outlines commitments
1 2 Outlines 77
December 2016
Supports self-
assessments and
third-party
4 Conformance
Protocols
Tailings
Management
3 Provides guidance on good
governance and engineering
practices for responsible
assessments of Global Industry Standard
on Tailings Management Good Practice Guide
tailings management
progress with Note: Also refers to other relevant
implementing the sources of ICMM guidance that
Draws upon and refers to support implementation such as
Standard ICMM’s ‘Integrated Mine Closure
related sections of Guide Good Practice Guide’ (2019)
February 2023
December 2016
Tailings Governance
Framework
Position Statement
— Managing information
— E
mergency preparedness and response
planning (EPRP).
2.2.1 Introduction — S
hare information about tailings management
with regulators, communities, investors and other
Role clarity is critical to the safe management of tailings.
external parties.
From defining policy at the corporate level to
implementing regular measurements in the field at the
2.2.2 Accountability and Responsibility
technician’s level, and for every task in between, clear
roles and responsibilities enhance individual ownership Accountability, responsibility and authority are closely
of assigned scope. related concepts. The difference between them is
critical but is sometimes not clearly understood. The
Accountability, which cannot be delegated, should be
usage of these terms in this Guide is defined as follows:
underpinned by the Operator’s commitment to the safe
management of tailings, including providing the Accountability: The answerability of an individual for
resources (eg financial, personnel) needed to support their own performance and that of any personnel they
both the short- and long-term objectives for safe and direct, and for the completion of specified deliverables
responsible tailings management. or tasks in accordance with defined expectations. An
accountable person may delegate responsibility for the
The circumstances of each Operator and tailings facility
completion of the deliverable or task but not the
vary, and the governance and organisational structure
accountability.
should be appropriately tailored to suit each facility.
At a minimum, the Operator should: Responsibility: The duty or obligation of an individual or
organisation to perform an assigned duty or task in
— D
efine and document accountabilities and
accordance with defined expectations, and which has a
responsibilities related to tailings management
consequence if the expectations are not met. An
for the:
individual or organisation with responsibility is
- BoD. accountable to the person that delegated that
- Accountable Executive. responsibility to them.
- Responsible Tailings Facility Engineer (RTFE). Authority: The power to make decisions, assign
- Engineer of Record (EOR) and Design Team responsibilities, or delegate some or all authority, as
(Section 2.2.2). appropriate. The ability to act on behalf of the Operator.
— E
stablish and maintain a corporate policy on tailings Personnel with accountability and responsibility for all
management through the BoD. decisions related to tailings management should be
identified and in place. Decisions should be made by
— U
nderstand the competencies required for tailings
persons who have clear accountability or responsibility
management and ensure that relevant personnel
and who are appropriately qualified and experienced.
(employees, contractors and consultants) have those
Those persons with defined accountability and
competencies.
responsibility should also have the authority to make
— E
ngage local communities on matters related to decisions commensurate with their level of
tailings management, including potential risks to responsibility. The Accountable Executive should have
those communities. clear authority commensurate with their accountability
and in cases where they need funding authorisations
— Integrate activities and communicate effectively,
beyond their authority, they should have access to and
both internally (eg between different business units)
communication with those who can provide
and externally, on matters related to tailings
authorisation in a timely manner.
management.
In Detail — M
aintain records related to design, construction
and OMS (Section 2.5).
Examples of the responsibilities of a RTFE include:
— E
nsure inspections (eg dam safety inspections or
— C
oordinate their efforts through the Accountable
DSRs) are completed (Section 2.6).
Executive for an aligned approach to tailings
governance for the Operator. — Review and update the OMS manual (Section 2.4).
— R
elationship between the EOR and members of the The Design Team develops the design of the tailings
Operator’s technical and functional teams and facility. The work involved may include the initial design
contractors related to tailings management. for a new tailings facility, planned construction through
the Operations phase, and any material changes to the
— R
elationship between the EOR and the programme
design of the tailings facility. The Operator should define
for reviewing tailings safety (eg role of the EOR in
and document the roles and responsibilities and
Independent Review).
Establishing a corporate policy on tailings management The corporate policy should be:
provides an important basis for establishing corporate
— Reviewed and endorsed by the BoD.
priorities and performance objectives (Section 3.3.3)
related to tailings management. A policy is an important — Consistent with applicable legal requirements.
tool to demonstrate, both internally and externally, the
— Communicated to employees.
Operator’s commitment to tailings management.
— U
nderstood to a degree appropriate to their roles
The policy should be aligned with the Operator’s
and responsibilities by personnel whose activities
commitment to implementing a corporate safety
may affect tailings management either directly or
culture: prioritising safe and responsible tailings
indirectly.
management with the ultimate goal of zero fatalities
and catastrophic events. — Publicly available.
The policy should be integrated with corporate policies Tailings management is a core business function of the
related to sustainability, health and safety, business mining industry, and as described in Sections 1.2.2.2 and
ethics and other related elements to ensure that: 3.2, planning for tailings management should be
integrated into planning related to relevant aspects of
— C
orporate commitments and goals related to tailings
mining operations, such as ore extraction and
management are integrated with and reflected in
processing, sitewide water management, management
other corporate commitments.
of waste rock and other mine wastes, and sitewide
— O
ther corporate commitments and goals are closure planning. To facilitate this integrated approach,
reflected in tailings management. it is essential that all business units understand the
corporate policy on tailings management and their role
Operators should develop a policy on tailings
in implementing the policy, including the importance of
management that best meets their needs and corporate
integrated mine planning. Furthermore, the corporate
management approach while addressing their legal
policy and site-specific performance objectives for
requirements and commitments to local communities. As
tailings management should be integrated into sitewide
their portfolio of tailings facilities and associated risks will
policies, objectives and plans.
change with time, the Operator should re-evaluate the
adequacy of the policy on a regular basis.
2.2.4 Competency and Promoting Continual
The corporate policy should demonstrate the Operator’s Learning
commitment to:
Tailings management requires the Operator and
— P
rotection of health and safety of employees, personnel involved in tailings management to have a
contractors and the public. level of competence consistent with the requirements
of the tailings facility and its risks. The key elements of
— S
afe and responsible management of tailings with
developing and maintaining competence are
the objective of zero fatalities and eliminating
qualifications, training and experience.
catastrophic failures.
— A
llocation of appropriate resources to support Competency
tailings management activities. Competencies comprise knowledge, skills and abilities
and are typically demonstrated through behaviour.
— Implementing effective governance of tailings
Competency is important for effective performance.
management through the actions of the Operator’s
High level competencies for tailings management may
employees, contractors and consultants.
be identified by the Operator and should reflect the
— A
n organisational culture that promotes learning, Operator’s values. Those broader competencies are
communication, early problem recognition and early often supported by role specific competencies,
escalation of issues. performance indicators, knowledge/skills/abilities and
current learning resources for the position.
— E
mergency preparedness and post-incident
recovery if a failure occurs. As tailings personnel progress through their careers,
they are naturally expected to gain competency in key
— Implementing a programme for reviewing tailings
practice areas. A competency framework should be
safety, including Independent Review.
— A
rticulate a clear, honest assessment of tailings Independent Review
risks to the BoD. Independent Review is conducted by one or more
appropriately qualified and experienced individuals
— A
dvocate for resources needed for tailings
who have not been directly involved with the design
management.
or operation of the particular tailings facility. The
qualifications and experience of reviewers should be
EOR
aligned with the tailings facility’s complexity and risk
The EOR should have education, experience,
profile. Similar to the EOR, Independent Reviewers
capabilities and knowledge commensurate with the
should have education, experience, capabilities and
complexity of the facility and potential consequences
knowledge commensurate with the complexity of the
of a failure in the areas of design, construction,
facility and potential consequences of a failure in the
operation and performance evaluation, which are
areas of design, construction, operation and
gained through directly related experience. This
performance evaluation, which are gained through
includes facility-specific knowledge to a sufficient
directly-related experience.
level of detail that the EOR can demonstrate
— T
raining associated with significant changes such Promoting continual learning will help to ensure that
as updates to the OMS manual or emergency personnel have the competencies and qualifications
preparedness plans. necessary for tailings management and can also help
to ensure staff retention and reduce turnover by
— Training for competency development.
creating more opportunities for career advancement.
Better trained personnel can help to facilitate
Training should address:
improved tailings management, and reducing
— General aspects, such as the Operator’s policy and
turnover reduces risks associated with changes in
commitments related to tailings management, and
personnel.
the overall goals of safe, responsible tailings
management for personnel with direct and indirect Operators should establish mechanisms that
roles related to tailings management. incorporate workers’ experience-based knowledge
into planning, design and operation for all phases of
— S
pecific aspects (eg technical, communication,
the tailings facility lifecycle. Operators should also
management) related to the roles and responsibilities
establish mechanisms that promote cross-functional
of personnel with direct roles related to tailings
collaboration to ensure effective data and knowledge
management.
sharing, communication and implementation of
Operators should aim to develop a corporate culture management measures to support public safety
that promotes continual learning, both formally and and the integrity of the tailings facility.
Further Reading:
ICMM: Stakeholder Research Toolkit
— H
elp to build community capacity, developing
transferable skills and potentially providing a basis
for greater community involvement in surveillance
during the Post-Closure phase.
Figure 4: Elements of a tailings management system and application across the lifecycle
Act: Plan:
Review and develop Develop plans for
action plans Tailings Facility Lifecycle tailings management
Material Changes
Project
Design Operations Closure Post-Closure
Conception
Construction
Check: Do:
Evaluate Implement the tailings
performance management system
— TMS
In Detail
— OMS manual
Changes in Personnel in Key Roles
Succession plans should be in place for key roles — Closure plan
related to tailings management, including the EOR,
— Assignment of accountability and responsibility
RTFE, Accountable Executive and Independent
Reviewers. The focus of such planning is not on the — Competency of personnel in key positions
staffing or human resources aspects. Rather, it is to
— Performance of the tailings facility
ensure that a plan is put in place, proactively, to
manage changes in such key roles, whether the — R
ecord of conformance, including compliance
changes are expected or unexpected. with legal requirements
— C
onducting long-term OMS activities, as necessary, Evaluating Performance should include the identification
in accordance with the closure plan. of deficiencies and opportunities for improvement.
In cases where changes are made, those changes Evaluating Performance is an ongoing, iterative process
should be: that involves two-way communication between a range
of personnel involved in tailings management. Through
— D
ocumented, including incorporation into design the surveillance of performance criteria associated with
or operational documents where relevant. risk controls (Section 3.6.4), Evaluating Performance
— C
ommunicated to relevant personnel provides essential short-term input to decision-making.
(proactively when possible). The RTFE, EOR and Independent Reviewers all have
roles to play including providing input to and receiving
— S
upported with appropriate training, depending outputs from Evaluating Performance, depending on
on the nature of the change (Section 2.2.4). both the information and time scale involved.
— H
ow can a similar event be prevented from
happening in the future?
— W
ere any mistakes made that led to the incident,
In Detail or in responding to the incident? If so, how can
those mistakes be avoided in the future?
As part of Evaluating Performance, the Operator
should establish a mechanism to conduct post- — W
hat can be done to improve response if a similar
incident analyses for incidents related to tailings incident occurs in the future?
management that may occur, such as cases of
— A
re there any recommendations for changes to
non-conformance, unanticipated upset conditions, or
the TMS, EPRP or OMS manual as an outcome of
an emergency. This is particularly important for
the post-incident analysis?
incidents with material impacts (eg business
disruption, release of material, non-compliance with If an incident occurs, a post-incident analysis should
legal requirements) and in such cases, post-incident be initiated as soon as possible afterwards, while the
analyses may be conducted in more detail and with memories of the personnel involved remain fresh. The
more intense scrutiny. It is important to learn from results of the analysis should be documented and
such analyses to help prevent similar incidents from reported to the RTFE, Accountable Executive and
occurring in the future. Post-incident analyses should BoD, as appropriate. Operators are encouraged to
consider both the technical and governance aspects share their analyses and outcomes with the industry
that potentially contributed to the incident and the more broadly, so that others may learn and
Operator’s response to the incident. They could also subsequently improve their tailings management
consider a range of questions such as: practices.
— W
hat was the root cause of the incident, and what
were the contributing factors?
Identifying Actions to Improve Performance should be As part of Identifying Actions to Improve Performance,
conducted on a regular basis. The objective is to review the Operator should also consider future plans, such as
current performance and future plans, and to drive planned future construction, facility expansions or other
improvement in tailings facility performance by relevant planned changes. Action plans should be
developing action plans to address deficiencies and developed accordingly to ensure that the systems,
opportunities for continual improvement. This element of information and plans developed as part of Developing
the TMS integrates and is informed by all available, Plans for Tailings Management are revised as needed.
relevant information including the outcomes of Evaluating This effectively completes the Plan-Do-Check-Act cycle
Performance and inputs, advice and recommendations of the TMS, in that the Act stage informs the
from a programme for reviewing tailings safety, including subsequent Plan stage.
Independent Review (Section 2.6).
The frequency of Identifying Actions to Improve
Conducted by the RTFE, EOR and other personnel Performance varies, but is typically annual except
involved in tailings management, this element of the during the Post-Closure phase, when a lower frequency
TMS should evaluate: may be appropriate.
— Suitability, effectiveness and the need for To ensure that information is communicated to allow the
changes to: Operator to understand whether tailings are being
- The TMS and all associated elements, including managed in a safe, responsible manner, the results and
the systems, information and plans listed in action plans developed should be reported, at an
Section 2.3.2. appropriate level of detail to:
— A
dequacy of resources committed to tailings — EOR
management, including adequacy of human
— Accountable Executive (or delegate)
resources and competencies required.
— BoD, where appropriate
If deficiencies or opportunities for continual
improvement are identified, then action plans should be These reports can also be provided to other business
developed with input from the EOR and mechanisms units (eg management responsible for ore processing) to
implemented as part of a programme for reviewing help ensure the continued coordination of activities
tailings safety. directly and indirectly related to tailings management.
Identifying Actions to Improve Performance should also In addition, these reports can help to form the basis for the
provide an update on the status of the implementation public disclosure of information (Section 2.2.7 and 2.6).
In Detail — C
onformance with the performance objectives
and design intent.
Identifying Actions to Improve Performance provides
an opportunity for the RTFE, EOR and other personnel — C
ompliance with legal requirements, conformance
involved in tailings management to: with standards, policies and commitments, and
status of corrective actions.
— R
econfirm alignment between design intent, risk
management plan, and OMS activities. — Tailings facility maintenance and surveillance.
— D
iscuss realised or anticipated changes and their — Input from the programme for reviewing tailings
implications/management. safety ().
— C
hanges to legal requirements, standards and — If needed, action plans to:
guidance, industry best practice and
— Ensure that performance objectives are met.
commitments to communities.
— A
ddress non-conformance with requirements,
— C
hanges in mine operating conditions (eg
standards, policy or commitments.
production rate) or site environmental conditions.
— Implement recommendations for continual
— C
hanges outside the mine property that may
improvement.
influence the nature and significance of potential
impacts resulting from the tailings facility on the — A
ny recommendations for modifications to the
external environment or vice versa. TMS, OMS manual or EPRP.
OMS activities are fundamental to the day-to-day — Conformance management plan (Section 2.3.2.2).
management of tailings facilities. The TMS, performance
The OMS manual should also describe the linkages with
objectives, risk management plan and design intent
emergency preparedness and response (Sections 2.4.5
provide a framework for safe, responsible tailings
and 2.7).
management, but OMS activities are needed to implement
them on a day-to-day basis. Operators that do not OMS is applicable across the lifecycle. It is important to
effectively implement OMS activities cannot adequately emphasise the operation does not just include activities
understand their risks, proactively manage tailings, make related to the active placement of tailings during the
informed decisions or have any confidence that tailings Operations phase of the lifecycle. It also includes
and associated risks are being effectively managed. activities related to water management, reclamation
and, where applicable, the management of other
OMS activities should be documented in an OMS
materials (eg residues from water treatment such as
manual, and should be aligned with:
lime treatment sludge) that may continue to be
— TMS (Section 2.3) and overall governance structures deposited into the tailings facility after the end of the
for tailings management. Operations phase. Thus, in most cases, operation
activities will be necessary in the Closure phase and
— Lifecycle phase of the facility (Section 1.2.1).
may also be necessary in the Post-Closure phase.
— P
erformance objectives, criteria and indicators to be
While the need for operation activities may cease at
included in the design of the surveillance
some point (eg reclamation is complete and there is no
programmes that measure performance throughout
longer a need for active water management), the need
the tailings facility lifecycle (Section 3.3.3).
for maintenance and surveillance activities continues
— Closure plan and objectives. until the tailings facility reaches a point where ongoing
maintenance and surveillance are no longer needed to
— R
isk management plan including risks controls and
ensure that the facility is safe and that the performance
associated performance criteria (Sections 3.6.4 and
objectives for closure continue to be met. This is directly
3.2.4).
tied to completion of the closure success criteria
(Section 3.7.3) and the transition from an active facility
to a closed facility (Section 3.7.4.1).
Further Reading:
MAC (2019): Developing an Operation, Maintenance, and
Surveillance Manual for Tailings and Water Management
Facilities
— P
erformance of the facility, including any deficiencies — A
ddress site-specific aspects of OMS governance,
in performance. building on overall accountability and responsibility
for tailings management (Section 2.2.2), and should
— T
ailings facility design and any deviations from the
document site-specific OMS activities.
design.
— D
efine and describe plans and procedures for
— C
urrent constructed conditions (Section 3.5) and
implementing activities related to the transport,
construction history.
placement and permanent storage of tailings and,
— Current lifecycle phase of the facility. where applicable, water and the recycling of water.
— Future plans for the tailings facility. — Competencies required for various roles.
— R
eporting relationships between different individuals
and business units with direct and indirect roles
related to tailings management.
— H
ow information related to specific OMS activities
should flow.
— P
rocesses and procedures for reporting outcomes
of OMS activities.
— R
emoval of debris from a spillway based on debris
accumulation.
— R
eplacement of a broken pump or failed
section of pipeline.
— P
rocesses and procedures for documenting
observations (eg a checklist may be provided to
In Detail personnel with instructions for written and
photographic documentation of observed
Surveillance activities should be aligned with the
conditions).
design intent (Section 3.4.5), performance objectives
(Sections 3.2 and 3.3) and the risk management plan — P
rocesses for reporting any observations that
(Sections 3.2 and 3.4). A failure to conduct have been documented.
surveillance of the necessary parameters or
For inspections, an OMS manual should describe the:
conducting surveillance at an inadequate frequency
could result in a failure to identify instances where — Scope and objective of the inspection.
action needs to be taken. Similarly, a failure to analyse
— F
requency for conducting the inspection (eg could
and report results in a timely manner could result in
be once or more per shift for some types of
actions being taken too late, if at all, leading to a loss
inspections, weekly, monthly or quarterly for
of control.
others).
For all surveillance activities, an OMS manual should - How often should visual observations or
describe: inspections be made to give you the information
you need?
— T
he expected range of observations or
- What should the person(s) observing or
performance of surveillance parameters, so any
inspecting be looking for?
results outside that range can be identified and
- Who should they tell if they see something of
reported.
potential concern?
— Quality management plan (Section 3.5.2). Information that is identified by the Operator as
necessary to safe tailings management, throughout
— T
ailings transportation and deposition plan
the lifecycle of the tailings facility, should be controlled.
(Section 3.4.4).
Control of information includes establishing and
— Water management plan (Section 3.2.3).
implementing a process to ensure necessary
— Information on the construction of the tailings facility information is documented, and that key documents
(initial construction and construction activities and information are maintained, retained and archived.
through the balance of the lifecycle) (Section 3.5). There are two aspects to the control of information:
- Status of development of the closure plan, — Identification and retention of records that are
including opportunities for progressive closure potentially useful to the future management of the
activities. tailings facility.
- Community engagement activities related to
closure plan development and implementation.
- Schedule for review and updates to the closure
plan.
— H
as the Operator developed a tailings facility
In Detail design that is consistent with the objectives of safe,
responsible tailings management (Section 3.4)?
Questions that may be addressed by a review
programme include: — H
as the Operator developed a risk management
plan that eliminates risk where possible, and
— A
re governance structures and systems
describes measures to reduce or mitigate
appropriate and are they being implemented
remaining risks (Section 3.2.4.3)? Is the risk
effectively? Do these structures and systems
management plan being implemented effectively?
include adequate mechanisms to manage
change, and are these mechanisms being — H
as the tailings facility been constructed in a
implemented effectively (Section 2.3.2.1)? manner consistent with the design intent? Have
deviations (Section 3.5.3) and as-built conditions
— D
o personnel with accountability, responsibility
(Section 3.5.4) been adequately documented?
and authority related to tailings management have
the necessary competencies? — H
as the Operator developed OMS activities that
are aligned with the performance objectives, risk
— A
re lines of communication clear and adequate,
management plan and design intent (Section 2.4)?
and is communication effective?
Are these OMS activities being implemented
— A
re personnel encouraged to report problems, effectively?
errors or concerns in a prompt manner, and are
— Is the tailings facility performing in accordance
they free from potential negative repercussions if
with the performance objectives, risk
they do so?
management plan and design intent (Section
— D
oes the Operator have information on the site 2.3.4)? Is the tailings facility expected to continue
characteristics necessary to inform decisions to perform in this manner?
throughout the lifecycle (Section 3.3.2)?
— H
as the Operator identified closure objectives and
— D
oes the Operator understand the risk to the a post-closure land use (Sections 3.3.3 and 3.7)?
degree necessary to inform decisions through the
— H
as the tailings facility been planned,
lifecycle (Section 3.2.4)?
designed, constructed and operated in a manner
— D
oes the Operator recognise and understand consistent with the closure objectives and post-
uncertainties associated with risk? Has the closure land use?
Operator taken steps to reduce uncertainty
— A
re there deficiencies in the responses to any of
(Section 3.2.4)?
the above questions?
— H
as the Operator developed performance
— A
re there opportunities for continual
objectives, indicators and criteria that are
improvement?
— H
ow frequently is review needed to reflect the state
of change of the tailings facility?
Programme
— A
re there relevant legal requirements or other to review
requirements or commitments that need to be tailings safety
— C
ompetencies required for reviewers for each impartial and objective manner. Reviewers must be
mechanism, taking into account the mandate and empowered to bring forward observations, advice and
objectives, and the complexity and risks associated recommendations for safe, responsible tailings
with the tailings facility. management, including constructive criticism of the
Operator. Reviewers must be able to conduct the review
— The degree of independence expected. free of the risk of negative repercussions, particularly in
The Operator should also consider and describe the the case of employees who are involved in reviews.
relationship between different review mechanisms Reviewers would be considered independent if they
within the programme, how each mechanism is have not been directly involved with the design or
intended to address the overall objectives of the review operation of the particular tailings facility. Independence
programme, and how these mechanisms will be is important because an independent reviewer can bring
integrated with each other. Different Operators may, for a fresh, outside perspective. They may recognise
example, define the scope of Independent Review deficiencies or opportunities that someone more familiar
versus a tailings stewardship review differently. There is with the tailings facility may overlook or fail to recognise.
no ‘right’ definition of the scope of these mechanisms. Independence also lends credibility.
However, when designing a review programme the
scope of these mechanisms should be made clear to — However, as noted above, tailings facilities and the
avoid confusion. associated systems to manage them are complex.
It can take a long time to fully understand this
The review programme should be designed to be complexity. The more independent a reviewer is,
integrated with the TMS to ensure that reviews are fully the less familiar they may be. As a result, there is a
informed by, and in turn inform, the ongoing Plan-Do- potential for their observations or recommendations
Check-Act cycle of the TMS, including developing and to be based on an incomplete understanding of the
implementing action plans to address deficiencies and tailings facility and associated systems. On the other
opportunities for continual improvement. This is hand, this lack of familiarity may lead them to identify
illustrated in Figure 5. concerns not necessarily evident to those more
A further consideration for an Operator in developing a familiar with the facility. There is an important role to
review programme is balancing the need for the play in the review programme both for reviewers with:
independence of reviewers with the need for familiarity — G
reater familiarity and a more complete
with the tailings facility and how it is managed. understanding of the tailings facility in question.
Regardless of who is involved in conducting a review, it — L ess familiarity with the tailings facility in question,
is essential that they undertake the review in an but a greater degree of independence.
— S
tatus of actions taken on recommendations from
previous tailings stewardship reviews.
— S
urveillance programme, including parameters,
In Detail frequency of data collection and instrumentation.
— C
urrent status and future plans regarding the — Results of Independent Review.
tailings facility.
— S
tatus of site characterisation and the site
— History of the tailings facility, including: characterisation model.
- The design intent and the design basis.
— R
esults of modelling of current and future tailings
- The evolution of the facility from the facility performance.
Construction phase onwards.
— S
tatus of the OMS manual, EPRP, and related
- Deviations from the design intent and design
documents.
basis.
- Material changes that have been implemented — S
tatus of training for personnel with direct roles
since the last stewardship review. related to tailings management.
— Risk assessment. — C
urrent and future operational or technical
challenges.
— Closure plan.
2. In the context of emergency preparedness, communities include places where people reside permanently or temporarily,
including individual residences and recreational sites such as campgrounds.
Once credible failure modes have been identified, a Flow failures are the failure mode most often
preliminary analysis should be conducted to identify associated with catastrophic consequences when
and assess the scenarios that could develop and the failures occur.
potential consequences of those scenarios, including
For credible failure scenarios that would include a flow
impacts on human health and safety, the environment
of material, a breach analysis should be conducted to
and infrastructure. This provides the basis for
estimate:
identifying and describing credible failure scenarios to
be addressed in the EPRP. — T
he physical area that would be impacted by a
potential failure.
A credible failure mode and a credible failure scenario
are related, but different. A simplified explanation of — F
low arrival times at various downstream locations
the difference is as follows: (eg communities, bridges).
— T
ailings that are sufficiently unsaturated that they Figure 6: Decision tree for evaluating potential
could not flow in the event of a failure, but could consequences of credible failure modes to
become mobile (eg credible failure modes could inform development of EPRPs
lead to a slump).
No, or with
However, not all credible failure modes are negligible Facility has one or more
likelihood credible failure scenarios?
geotechnical in nature. For example, the EPRP for
tailings management may address credible failures Yes
associated with tailings transportation such as a No, or with If a failure occurs could
negligible
break of a tailings pipeline. In addition, sitewide tailings and water flow
likelihood impactfully?
emergencies such as wildfire could also lead to
credible failure modes related to tailings under some Yes
2.7.3 Description of Measures the Operator An EPRP for a tailings facility in the Closure or Post-
Should Take Closure phases of the lifecycle should be adapted to
those phases, when there may be fewer personnel and
The EPRP should include a description of the measures
less equipment on site, and thus fewer resources on
the Operator will take to prepare for emergencies, and
hand to be able to respond to an emergency. The EPRP
to respond if an emergency occurs. Although some
may need to involve local contractors who could provide
aspects of this element of the EPRP may involve
heavy equipment and operators, as well as measures to
external parties, it is intended to be an internal
ensure that equipment, fuel and personnel can be
document. Elements of an EPRP that would be
transported to the site. Contingency plans may be
implemented by external parties should be developed
needed for power generation on site and
cooperatively and be provided to them.
communication infrastructure.
— P
rocedures to activate the EPRP, including internal
In Detail and external notification and communication plans
for emergency response, including up-to-date
An EPRP should describe the following, regarding the
contact information (eg phone numbers and email
measures the Operator will take to prepare for an
addresses) for relevant personnel, both internal
emergency, and to respond if an emergency occurs:
and external.
— C
redible failure scenarios that may occur and the
— T
raining requirements and plans for relevant
conditions that would trigger implementation of
personnel, including external parties such as
the EPRP.
off-site emergency responders.
— P
otential impacts of credible failure scenarios, and
— Procedures or actions to be taken to:
the likelihood of those scenarios.
- Prevent an upset or unusual condition from
— R
esources (people, equipment, materials) required becoming an emergency.
to respond to an emergency, including identifying
- Mitigate on and off-site safety, environmental,
resources that need to be retained on site (eg
and infrastructure impacts associated with
equipment, stockpiles of rip rap or other
emergency situations.
materials).
- Mitigate consequences if an emergency occurs
— R
oles and responsibilities of the Operator’s (eg through the development of evacuation and
employees, contractors, and consultants, and rescue plans).
relevant external parties (eg public sector
agencies, off-site emergency responders) and the — M
echanisms to alert potentially affected parties of
overall command structure (who is in charge of an imminent or developing emergency situation
response and associated reporting relationships) (eg alarms to notify downstream communities in
in the event of an emergency. the event of a tailings facility failure).
— A
ny mutual aid agreements with external parties, — M
easures to provide humanitarian aid, if
such as public sector agencies, other industrial necessary.
facilities (eg nearby mines) or contractors (eg — S
urveillance requirements to be described in OMS
heavy machinery). manual (Section 2.4), to be able to identify the
— D
escription of features and characteristics on and onset of an emergency.
off-site relevant to emergency response, including: — Procedures and frequencies to test the EPRP.
- Access, including primary and secondary means
— P
rocedures for the administration and update of
to access the mine site, tailings facility and
the EPRP.
potentially impacted areas, and means of
reaching the site of a potential emergency under
various conditions (eg foot, boat, helicopter,
all-terrain vehicle etc.).
All relevant personnel, including external parties, should In the case of an actual catastrophic tailings facility
be familiar with the EPRP and their roles and failure, an operator should provide immediate response
responsibilities if an emergency occurs. They should to save lives, supply humanitarian aid and minimise
also know how to access relevant portions of the EPRP, environmental harm.
recognising the external parties may not be provided
access portions of the EPRP related to any emergencies
that would not have off-site impacts, or any portions
containing confidential information.
Through studying lessons learned in case histories, Examples of integration aspects include:
Operators now understand the need to consider all
— T
he life of the mine reserve and resource should be
material aspects of the mine site when conducting
integral in determining tailings capacity
‘mine planning’. Likewise, Operators increasingly
requirements.
recognise the interdependence of sitewide water
management on the integrated understanding and — O
re processing approaches and anticipated ore
management of tailings facilities. variability.
— M
anagement of other mine wastes such as waste Change management is integral to integrated mine
rock planning as well, as described in Section 2.3.1.
— Mine closure. Figure 7 illustrates the lifecycle phases, the key tailings
management outcomes of each phase, and the
An integrated approach to mine planning is particularly
linkages with integrated mine planning across the
important for:
lifecycle, including closure plan development and
implementation.
Temporary Suspension
Potential material
changes go to
either Project
Conception or
Design, depending
on complexity
Material Changes
Note: The red boxes and lines indicate activities/relationships expected to occur for all tailings facilities.
The yellow boxes and lines indicate activities/relationships that may occur.
3.2.3 Integration of Tailings and Water This inextricable linkage between tailings and water
Management management necessitates a good understanding of all
water inflows and outflows to a tailings facility, including
Water management is an important aspect in safety
variations over time and uncertainties in those
and stability considerations for all surface disposal
variations. Many credible failure modes for tailings
tailings facilities. This is true even for facilities where the
facilities are rooted in water management and the
tailings have been filtered and are unsaturated, with the
presence of water exacerbates the consequences of a
tailings stacked and no water storage pond associated
potential failure even if water is not an initial failure
with the tailings facility. It is important to evaluate
trigger.
efficient measures to minimise the water in or on the
tailings facility as part of the site water management There are two concepts fundamental to water
plan. That said, in some cases, storage of water in a management:
tailings facility is integral to the design intent, as an
— When practicable, keep water that has not come in
environmental control or to manage seasonal
contact with the mine site from coming into contact
fluctuations at a mine site. Another driver in sitewide
with the tailings and other parts of the mine site by
water management is to ensure adequate supply of
diversion of surface water or other means.
water is always available to the ore processing facility
while minimising impacts on water supply for the — For the water that does enter the site, establish
surrounding area and communities. While these drivers engineering controls to mitigate geotechnical and
are valid, safety of the facility must always be geochemical risks across the mine site.
paramount.
— A
ssess the performance of future water — Tailings deposit density and voids entrainment.
management improvements through evaluation of
— Infiltration and seepage, and interaction of
scenarios.
groundwater with tailings facility.
— S
upport water reporting requirements on water
— Evaporation.
inflows/outflows, water use and reuse / recycle,
and other water metrics. — M
etered and unmetered inflows and outflows
including contributions from precipitation run-off.
— Identify flow monitoring requirements.
— U
ncertainties and sensitivities of physical system
— P
rovide estimates of future flows for closure
such as difficult to measure parameters, error,
planning.
operational change and trends in climate.
— T
he flow diagram and list of flow components is - Meet the specific objectives decided upon by
comprehensive to include all flows (metered and the development stakeholders.
non-metered) that will be modelled and those - Inform and improve a site’s current and future
necessary to meet the objectives of the model. water management practices.
- Provide data to report on water metrics.
— T
he list of flow components contains a clear and
concise description for each flow component and - Assess water performance against pre-defined
the location surveillance instrumentation. targets.
— T
he flow components naming convention is — M
odel complexity and detail is supported by
consistent with the water balance model. available data and specific purpose to meet the
objective.
The flow diagrams and the associated list of flow
components should be reviewed and updated — The assumptions and uncertainties associated
periodically or following changes to site water with the model are considered:
management practices. During the water balance - Calibration is regularly reviewed and validated or
review process, input should be gathered from site adjusted as needed to improve forecasts.
3.2.4 Managing Uncertainty and Risk Figure 8: Framework for a risk-informed approach
for tailings management
3.2.4.1 Introduction
Requirement 10.1 of the Standard states, ‘Conduct and Risk Assessment
update risk assessments with a qualified multi- Risk Identification
disciplinary team using good practice methodologies at
Risk Analysis
a minimum every three years and more frequently
whenever there is a material change either to the Risk Evaluation
— T
he effectiveness of risk management measures in Risk Evaluation
reducing likelihood, consequence, or both. Risk evaluation compares the outcomes of risk analysis
for existing conditions to determine if risks are within
— T
he changing nature of some risks (hazard creep) for
acceptable limits, whether present risk measures and
which likelihood or consequence may change over
controls are adequate, and what additional alternative
time (site characterisation, Section 3.3.2). This
risk reduction measures could be considered.
includes changes in climate, downstream conditions
(eg new communities or infrastructure) or legal The process typically considers the following, among
requirements. other aspects: robustness of design, past and future
performance monitoring, site context, and practicality of
Risk estimates will have a degree of uncertainty that
any remediation considered. Guidelines from regulatory
should be characterised. This includes acknowledging
agencies, governing bodies, other industries associated
that there is a degree of subjectivity in estimating risk,
with tailings facility safety, and corporate governance
reflecting various factors such as the experience and
should all be reviewed to determine what risks are within
expertise of those involved in developing the estimate,
normal operating limits. Understanding environmental,
the models used, and the comprehensiveness of
social, cultural, ethical, political, and legal considerations
available site characterisation information. Uncertainty
should also be included in risk evaluation.
may be represented by assigning ranges to estimates
of both likelihood and consequence. The team typically considers risk mitigation alternatives
at this stage. The outcome of the risk assessment
When uncertainty is high, it is important to consider
includes recommendations for actions deemed justified
applying conservative assumptions in the selection of
by the team.
input parameters and the analysis of the likelihood or
potential consequences of an event. Steps should also
3.2.4.3 Risk Management
be taken to reduce uncertainty, such as:
Risk management includes assessing effects due to
— Improving the understanding of the tailings facility
changes or deviations both in isolation and as a
and factors influencing it through improved site
compounding effect. Risk management builds upon the
characterisation (Section 3.3.3).
results of risk assessment as well as uncertainty
— R
efined modelling of potential consequences analysis and involves the systematic development and
(Section 2.7.2). implementation of strategies to eliminate or reduce
risks. These strategies include potential actions to
— D
eveloping a robust tailings facility design with less
reduce the likelihood of occurrence and/or the
uncertainty in design criteria (Section 3.4).
magnitude of consequences of credible failure modes
— A
ccurately documenting constructed conditions to that were evaluated to have a higher risk.
reduce uncertainty about the characteristics of the
Typical strategies may include recurring and monitoring
tailings facility and associated embankments
activities such as routine and special inspections,
(Section 3.5.4).
instrumentation and its evaluation, structural analyses,
— U
sing the results of Evaluating Performance site investigations, development and testing of EPRPs,
(Section 2.3.4) including surveillance (Section 2.4.3) Independent Review and regulatory reviews, and/or
and the programme for reviewing tailing safety, implementation of constructed risk reduction measures,
including Independent Review (Section 2.6) to review projects or improved operational controls.
and update the risk assessment and validate the
Risk management should also consider and document
design basis of the tailings facility throughout the
estimated risk after a remedial action and/or enhanced
lifecycle.
Resources
Risk
key concept in risk-informed decision-making is Le
vel
reducing identified risks (likelihood and/or of ri
sk
ALARP
consequence) to levels that are ALARP. As defined in
the Standard, ALARP requires that all reasonable Resources, effort
measures be taken with respect to ‘tolerable’ or
acceptable risks to reduce them even further until the Cost / Benefit
cost and other impacts of additional risk reduction are
grossly disproportionate to the benefit.
to further reduce risk and the amount of risk reduction
Factors involved in applying ALARP include: achieved) and then comparing it to other risk reduction
actions implemented by peers in the industry. If the
— Application of relevant good practice.
costs to achieve an additional level of risk reduction are
— T
he level of incremental risk in relation to the grossly disproportional to achieving the same
established risk guidelines. magnitude of risk reduction at other tailings facilities,
the current risk may be considered ALARP. This comes
— T
he cost-effectiveness of the risk reduction
with the caveat that operating contexts differ and that
measures in relation to likelihood and/or
this will have a bearing on the determination of ALARP.
consequence.
There are many factors that can contribute to the
— R
emaining life of the facility and potential alignment decision that ALARP has been satisfied and no further
with closure planning which may reduce likelihood action is justified. There may be some instances when
and/or consequence. ALARP is achieved that an Operator may wish to
consider other alternatives at their discretion to further
— S
ocietal concerns as revealed by consultation with
lower risk. This is indicated in Requirement 5.7 whereby
the community and other stakeholders.
Operators identify additional reasonable steps to
— O
ther factors such as consideration of standards- reduce potential consequences (ie by re-evaluating
based approaches, benchmarking, direct business alternatives for new facilities or considering various
impacts, constructability, implementation schedule engineering solutions for existing facilities).
and environmental consequences.
The Standard states that the Accountable Executive
The concept of ALARP is illustrated in Figure 9. must confirm and document that specific tailings
The ‘Resources, effort’ line in this graph represents a facilities meet ALARP (Requirement 4.7, 5.7). The RTFE
multiple of potential factors whereby the sharp rise in should, with input from the EOR and the Operator’s site
resources to reduce risks would be grossly leadership, present the Accountable Executive with risk
disproportionate to the benefit realised. Each Operator management measure to achieve ALARP, ideally after
will have its own processes to address such factors seeking advice from Independent Review. It is good
including use of good practice guidance and practice to provide more than one option for
jurisdictional requirements on risk evaluations and consideration such that risk levels and resource
management. requirements are understood and aligned with the
Operator’s policy.
When a judgement is made that risks are ALARP, this is
often determined by comparing the effectiveness of The urgency of completing safety actions should be
reducing risk further (evaluated by considering the cost commensurate with risk. Prioritisation of risk reduction
Figure 10: Key activities of the Project Conception phase of the lifecycle
Project Conception
Select preferred alternative to
advance to design, informed by:
– Site characterisation models
– Performance objectives Temporary Suspension
– Conceptual closure plan
– Risk identification and analysis
Prepare:
– Site characterisation models
– Evaluation of Alternatives Design Construction Operations Closure Post-Closure
– Design Basis Report (DBR)
Potential material
changes go to either
Project Conception
or Design, depending
on complexity
Material Changes
Note: The red boxes and lines indicate activities/relationships expected to occur for all tailings facilities.
The yellow boxes and lines indicate activities/relationships that may occur.
— A
cceptable post-closure use within a feasible
3.3.3 Performance Objectives
technical and economic framework.
Setting performance objectives underpins safe tailings
Setting performance objectives begins during the
management. Performance objectives should be
Project Conception phase. Although performance
aligned with and translate the corporate policy on
objectives set at this phase may be high level, they are
tailings management into specific performance
crucial to providing a basis for the multi-criteria
expectations for a tailings facility throughout its
alternatives analysis.
lifecycle. When considering the Closure and Post-
Closure phases of the lifecycle, the development of Performance objectives should then be refined and
success criteria as early as possible is important to developed in more detail, particularly during the Design
establish appropriate indicators for closure and phase (Section 3.4) (eg more specific performance
landform performance (Section 3.7.3). objectives for water management or geotechnical
aspects of design and operation). Going into the
Performance objectives and associated performance
Construction and Operations phases, performance
indicators and performance criteria should address:
objectives should be quantifiable for a given tailings
— Protection of employee and public health and safety. facility.
— D
esign objectives and criteria, including The tailings facility should be constructed, operated,
geotechnical, geochemical, operational, community and closed in accordance with the performance
and environmental performance objectives that the objectives, while recognising that those objectives
tailings facility is expected to achieve. should be reviewed and updated, as appropriate, during
these lifecycle phases.
Decisions made based on the evaluation of 5. Assess remaining alternatives using MAA or a
alternatives require an understanding of the potential similar decision-making tool. MAA can be broken
positive and negative impacts of each alternative down into two sub-steps:
evaluated across a range of site-specific aspects a . Describe all factors that will be considered in
encompassing technical, environmental and socio- the analysis by establishing accounts (eg
economic considerations, and project economics. environmental, technical, and socio-economic
Evaluating and balancing these potential positive and considerations), sub-accounts within each
negative impacts is important in making the optimum account, and indicators for each sub-account.
decision, but it is challenging to evaluate such
b. Conduct a value-based decision process to
disparate aspects. An evaluation of alternatives
assess the combined benefits and impacts
methodology, including MAA, provides a tool to do
(advantages and disadvantages) for each of the
this, while allowing inputs to and outcomes of the
alternatives assessed.
decision- making process to be communicated
internally and externally in a transparent manner. 6. Conduct a sensitivity analysis to test the
robustness and validity of the outcomes of the
Evaluation of alternatives should be conducted as a
MAA against various biases and assumptions.
multi-step process:
MAA provides a method of integrated assessment of
1. Identify the objective and scope – the decision
different characteristics of alternatives (eg for
that is to be informed by the evaluation of
comparing potential impacts on wildlife with capital
alternatives process and factors that will be
costs). In effect, these tools provide a rigorous,
considered.
semi-quantitative means of comparing otherwise
2. Develop a plan for conducting the evaluation of unrelated elements.
alternatives, including who will be involved.
ICMM 98
Design 3.4
3.4.1 Introduction — E
stablishing the Design Team , including
engineering consultants (typically from the same
The design process is iterative, starting during the
firm as the EOR, recognising that other models may
Project Conception phase when conceptual designs
exist) including the Operator’s representatives who
are developed for alternatives to be evaluated (Section
engage in the design process (typically includes
3.3.4). Those conceptual designs are further refined to
the RTFE and other experienced operational
preliminary designs for the detailed analysis leading to
experts).
the selection of the preferred alternative. During the
Design phase, the preliminary design for the preferred — D
efining the roles and responsibilities of the EOR
alternative is developed to the stage of a detailed and Design Team and their relationship through the
design for approval, and ultimately to an executable design process.
design for construction.
— E
ngaging Independent Reviewers in the design
The objective for this design process throughout the process.
lifecycle of the tailings facility should be to limit credible
— Developing a formal change management system.
failure modes, either to having no credible failure modes
or, where credible modes cannot be eliminated, — R
efining site characterisation information and the
ensuring that potentially catastrophic credible failure site characterisation model to a degree where
modes are managed using the ALARP approach residual uncertainties are acceptable.
through the phase(s) of the facility’s lifecycle where they
— R
efining the risk assessment to reduce
are present (Section 3.2.4).
uncertainties and addressing residual uncertainties
The main activities for the Design phase are: in the design and risk management plan.
— A
ppointing an EOR for the Design phase if the EOR — Developing the tailings facility design:
from the Project Conception phase is not retained. - Develop the design initially using the
This EOR will likely have a longer-term responsibility. precautionary-based approach.
- Enhance
the design based on adoption of the
performance-based approach or define why this
is not necessary.
- Incorporate closure requirements into design
criteria.
— E
stablishing quality management specifications
including requirements for consideration and
documentation of deviations and documentation of
constructed conditions.
— D
ocumenting the design criteria and intent in the
Design Basis Report (DBR).
— D
eveloping the tailings transportation and
deposition plan.
Design
Finalise detailed design,
informed by:
– Site characterisation models
– Performance objectives
Temporary Suspension
– Conceptual closure plan
– Risk assessment
Prepare:
– Updated site
Project characterisation models Construction Operations Closure Post-Closure
Post-Closure
Conception – Updated DBR
Potential material
changes go to either
Project Conception
or Design, depending
on complexity
Material Changes
Note: The red boxes and lines indicate activities/relationships expected to occur for all tailings facilities.
The yellow boxes and lines indicate activities/relationships that may occur.
The outcome of the Design phase is an executable The conduct of social, environmental and local economic
engineering design with detailed specifications, impact assessments is not addressed in this Guide.
including quality management, to be used for the
Figure 11 illustrates the key activities of the Design
subsequent Construction, Operations and Closure
phase of the lifecycle.
phases, as well as any other documents required for
final approval and initiation of construction. The design
3.4.2 Managing Uncertainty and Assessing
should be reviewed and updated as performance and
Risk in Design
site data become available and in response to material
changes to the tailings facility or its performance. Risk assessment during the Design phase continues the
work done during the Project Conception phase but is
In parallel, a full assessment of the potential social,
focused on supporting the design process.
environmental and local economic impacts of the
tailings facility and of any credible failure modes The objectives are to:
throughout its lifecycle, including Closure and Post-
— R
educe the uncertainty associated with key design
Closure, should be undertaken, to inform the design
elements and design the tailings facility to reduce
process. Closure objectives and activities should be
or eliminate specific risks, to the extent feasible.
considered during the design phase and be informed by
trade-off analyses completed during project conception — D
evelop a risk management plan to limit the impact
(Section 3.3.4). Where impact assessments predict of residual risks.
material acute or chronic impacts, the Operator should
— D
evelop a surveillance plan to sufficiently inform
develop, document and implement impact mitigation
implementation of the risk management plan.
and management plans using the mitigation hierarchy.
3.4.3.1 Overview
Failure of a tailings facility is unacceptable, particularly
any failure that leads to fatalities or otherwise
catastrophic outcomes. Thus, designing, constructing,
operating and closing facilities to reduce or eliminate
credible failure modes is of paramount importance.
The prescriptive approach to designing tailings facilities A further limitation of the FoS is that formulating a valid
came to prominence in the 1970s as an adaptation from FoS for a given tailings facility is dependent upon the
design practices for water dams. In its basic form, the selection of appropriate parameters and access to
approach often uses a prescribed Factor of Safety (FoS) reliable data (eg extensive field and laboratory studies
as a criterion that is perceived by some to denote as part of site characterisation (Section 3.3.3)). It is also
whether or not a tailings facility is safe. Due to the dependent upon the competency and experience of
seemingly straightforward application of FoS, it has those involved. If the FoS has been erroneously
broad appeal. calculated to be above a prescribed value, but the
actual FoS is really below that value, then the tailings
3.4.3.3 Limitations of Prescriptive Approach facility may be less safe than assumed by the Operator.
Additionally, since the FoS is calculated for an
A FoS is often misinterpreted as a sole measure of safety.
embankment as a whole, it may not adequately account
It is based on the premise that a higher FoS reduces the for zones of local resistance and/or weakness within an
likelihood of failure. However, a FoS is not a measurable embankment, thus potentially overlooking or not
value; it is an outcome based on inputs which are derived recognising the significance of the ‘weakest link’ in an
by the designer based on site data, laboratory testing embankment. Solutions to addressing these limitations
and modelling. Natural variations in site and laboratory are outlined in the following sub-sections.
data give rise to uncertainty around the calculated FoS.
However, FoS values are rarely reported with uncertainty 3.4.3.4 Precautionary Approach to Tailings
limits. Further, a given value of FoS has an entirely Facility Design
different meaning if an identical value exists for both a
site with a brittle credible failure mode and one with only Despite the limitations regarding FoS, many tailings
non-brittle credible failure modes. facilities have been safely constructed and operated
by combining a prescriptive approach with the
An over-reliance on FoS can lead to complacency – a Observational method, which is referred to in this Guide
sense that if the design FoS is met then the facility is as the ‘precautionary approach’. Performance that is
safe. Complacency can also lead to an inadequate indicative of a potential failure mode is identified and
standard of care regarding other factors that may be monitored in order to validate whether the design basis
just as important, if not more so, to the safety of a given remains sound and if not, to initiate mitigation
tailings facility, such as using engineering analysis measures. The amount by which variances from
methodology that may not be applicable to a specific expected performance can be tolerated is often then
situation, just because the method is convenient or supported by additional design calculations and
familiar, or a lack of urgency to act in response to judgement. During the Construction, Operations, and
specific problematic observations in the field. Closure phases, performance behaviour surveillance is
conducted in accordance with the design criteria and
As noted, the concept of FoS was originally developed
expected ranges such that appropriate corrective
for water dams and has been adapted to tailings
action can be taken when exceedances are
facilities. One significant difference between water
encountered. The precautionary approach also requires
dams and tailings facilities is that water dams are
a contingency design to be implementable when and if
typically built to final height at the outset, whereas
observations require that mitigation is necessary.
tailings facility embankments are typically constructed
in stages, with a starter embankment before deposition Currently, the use of the precautionary approach is
of tailings commences, and raises to increase capacity widespread across the mining industry, and in many
through the Operations phase of the lifecycle. There cases the continued use of this approach is appropriate
— T
here are existing tailings facilities that have been An illustration of the precautionary approach for design,
safely designed, constructed and operated using this construction, operation and closure is presented in
approach. If properly understood and calibrated with Figure 13. As illustrated, this approach relies on defining
relevant experience, the precautionary approach can the acceptance criteria for the facility, which is often the
continue to be used for such facilities. minimum acceptable FoS, either prescribed by
regulation or defined by the EOR or Design Team
— T
he application of the precautionary approach can be
(recognising that separate FoS values may be adopted
validated by precedence and by confirmation that
for the Construction, Operations, and Closure phases).
neither the foundation materials nor the foundations
During the life of the tailings facility observations are
themselves or other structural components of the
made via surveillance to assess whether the facility is
tailings facility are susceptible to strain weakening
meeting the intent of the design, and hence consistent
failure under the design criteria or other elements of
with the required FoS.
non-homogeneous straining.
Establish Surveillance
Programme to address
Credible Failure Modes
It should be noted that most of the recent high-profile representation of pore pressure conditions and external
failures of tailings facilities had an acceptable FoS within loading conditions, along with appropriate surveillance
the context of the precautionary approach, although for all credible failure modes is necessary with the
there were challenges with its application and precautionary approach.
understanding. The precautionary approach is not
A key point of the precautionary approach is that the
appropriate when brittle failure modes are present,
tailings facility response (via surveillance) is always
especially if they are not recognised and eliminated.
reactive, based on what has been observed.
Appropriate material characterisation with appropriate
— D
esign FoS are not prescribed but should be
determined by the EOR and the Design Team and
should be endorsed by Independent Review.
— T
he sensitivities of safe design to material
characterisation and site characterisation should
be recognised by the EOR and the Design Team
and their evaluations should be endorsed by
Independent Review. Significant consideration
should be given to selecting appropriately
conservative material strength parameters for
deterministic analysis of the FoS.
— T
he reliance on and limitations of the observational
method should be recognised (see below).
Does
Predicted
Develop surveillance
Revise design No Performance Yes
programme
and/or objectives Meet
and complete design
Objectives?
No
The following are key to this approach: forecasting may utilise advanced numerical
techniques such as finite element or finite difference
During the design process:
models. These tools are often initially constructed
— U
se site characterisation data (geotechnical, using case study inputs and the somewhat limited
geologic, hydrogeologic, seismic, climate) to site characterisation data that are available during
establish performance objectives for the tailings the Design phase. The ability to calibrate many of
facility. These objectives should focus on the critical these models during the Design phase is limited.
elements that would affect safe construction,
During the Construction, Operations, Closure, and
operation, and closure.
Post-Closure phases:
— F
orecast behaviour as part of the design process to
— Assess current behaviour.
inform the evolution and finalisation of the design to
meet the performance objectives. Forecasting tools — C
alibrate and re-forecast the performance of the
are selected dependant on the complexity of the facility, comparing against the performance
challenges and the questions that need to be objectives. If the re-forecast does not meet the
answered. The tools may be relatively simple performance objectives, changes to the design and/
analytical models but, where appropriate,
— T
he improved simulation and calibration with time Furthermore, the adoption of the principles of risk-
also provides a more authoritative record that the informed decision-making enhances the capacity to
overall response of the facility based on constructed convey safety assessments to multiple stakeholders.
conditions is in accordance with the design intent.
3.4.3.7 Limitations of the Performance-Based
— S
eismic resistant design relies on the approach to
Approach
assess potential deformations.
The performance-based approach is a natural
— T
he onset of localisation of deformations and
extension of the observational method that is
progressive failure can be determined.
established good practice within the precautionary
— E
xperience indicates that regulators benefit from approach. It extends to the evaluation of total
more observable performance objectives to meet performance of the tailings facility throughout its
their needs and this is facilitated by the lifecycle from construction to closure. By validating total
performance-based approach. performance of the tailings facility, the evaluation of
safety is enhanced. Total performance includes
The performance-based approach can be applied to all
deformations, pore pressures, and other aspects such
tailings facilities, but based upon the analysis of past
as drain performance and cracking (if tolerable). The
failures, it can be particularly valuable to achieve robust
capacity to undertake performance-based design
design and maintain integrity to prevent the failure of
requires the knowledge of current advances in
tailings facilities that:
deformation and pore pressure modelling as well as
— A
re spatially complex and variable, including having advances in surveillance technology and methodology
issues of strain compatibility and interaction of needed to be able to apply the performance-based
material within the facility and foundation zones. approach to validate performance. This relies on the
EOR and Design Team having the necessary
— E xhibit the potential for strain weakening (brittle).
competency to undertake design on this basis, and to
— A
re susceptible to liquefaction leading to potential determine adequate deformation and resistance limits
flow failure. to ensure safety. Broad application of the performance-
— T
he storage of the MDF event, or a portion thereof,
that results in temporary wetting and restoration
of the beach.
In Detail — U
se of good practices for estimating the design
flood, considering climate trends and the potential
Overtopping
for a series of events to occur consecutively (wet
Tailings facilities are not typically designed to
season or year, as is appropriate for local conditions).
accommodate overtopping. Exceptions can exist when
the embankment(s) is composed of sufficiently coarse — W
here present, the malfunction of spillways that
rockfill or other erosion-resistant material and is may be relied upon to manage the extreme design
designed to act as a flow-through embankment. In flood event.
general, safety with respect to overtopping is ensured
— L ong-term settlement of tailings and
by the provision of adequate freeboard that can include
embankments.
a sufficiently sized and operating spillway. This design
consideration is incorporated in the water balance — E
arthquake-related settlement of tailings and
(Section 3.2.3) around the tailings facility as an element embankments.
that reflects the construction schedule of the facility.
— T
he potential for cracking due to desiccation in
The construction plan should incorporate the the upper portion of the beach.
consideration of the ore processing facility’s tailings
— T
he operational beach length that would be a
production plan as well as the tailings transport and
performance requirement under normal operating
deposition plan, water management requirements,
conditions.
tailings deposit density, associated contingencies,
and adequate freeboard to safely manage the — R
estriction on the migration of the reclaim pond(s)
extreme design flood event. Maintaining freeboard within the tailings facility.
requirements is a critical performance objective of
— R
ecognition of competing water utilisation
any tailings facility where overtopping is a credible
objectives such as management of geochemical
failure mode. Violating this requirement has been
risks or fugitive dust.
known to aggravate consequences even if initial
overtopping was not the cause of a failure. — Ice formation that may interrupt/impact the water
reclaim system.
Some design considerations related to freeboard
requirements are: — P
resence of upstream hazards or structures that
could fail and cause a cascading failure of the
— T
he implications of wind-generated waves and
tailings facility.
reservoir setup.
— Slope stability
— T
opographic survey methodology, datum/ — D
esign criteria for electrical infrastructure (eg
coordinate system pumps, surveillance instruments, etc.)
— G
eology (including structural geology and — Costing basis and drawing standards.
presence of faults) and hydrogeology
Beyond integrating the underpinning models, the DBR
— Geological and hydrogeological characterisation defines whether the tailings facility approach will use
precautionary design or performance-based design
— S
ite geotechnical characterisation – including
and provides important design criteria such as FoS
foundation and borrow materials
and allowable deformations, potential for strain
— Seismicity and seismic design requirements weakening, etc. It describes the scope and level of
detail of information and analyses used to make
— Surface water management
decisions, along with applicable legal requirements
— Geochemical considerations and guidelines, demonstrating the validity of those
decisions.
— Tailings characteristics and rheology
— Water balance
Construction
Construct in accordance
with the DBR.
Prepare and update across
the life cycle:
– Construction vs Design
Intent Verification
– Deviance Accountability
Report Temporary Suspension
– Construction Records Report
Prepare:
– Updated site
Project Design characterisation models Operations Closure Post-Closure
Conception – Updated DBR
Potential material
changes go to
either Project
Conception or
Design, depending
on complexity
Material Changes
Note: The red boxes and lines indicate activities/relationships expected to occur for all tailings facilities.
The yellow boxes and lines indicate activities/relationships that may occur.
3.5.2 Construction Management Plan application, and revised and improved as warranted. It is
not intended to be a step-by-step procedure for each
The execution of the engineering design requires a
activity. Typically, it is a document that outlines general
well-developed management framework to ensure its
activities, procedures, requirements and schedules for
successful implementation. The management
successful completion.
framework encompasses the development of a
construction management plan to establish uniform The construction management plan typically includes
policies and procedures that ensure facility construction several elements that may be packaged in a variety of
is conducted safely in accordance with the construction formats at the preference of the Operator. The planning
drawings, technical specifications and the QA/QC process and clarity of outcomes is the important aspect
programme. The construction management plan is an of the following, not the specific nomenclature or how
overarching plan and is intended to be flexible in its the outcomes are packaged:
— T
he design intent, as per the DBR, has been Any unresolved deviations identified in the CRR can be
implemented and is still being met if the site carried into the DAR process. The DAR process can be
conditions encountered during construction varied used throughout the lifecycle of the tailings facility,
from the design assumptions. identifying and reviewing potential implications of
changes to the facility and evaluating their acceptability.
— A
ny discrepancies between the field conditions
The DAR is discussed further in Section 3.6.3.
encountered during construction and the design
assumptions are clearly identified and reviewed, The CRR should document the initial construction of a
such that the design can be reviewed and adjusted new tailings facility and should be updated to reflect
as required to account for the actual field conditions. other construction activities when they occur
This information is critical for the design of throughout the lifecycle, including:
subsequent facility stages.
— O
ngoing construction through the Operations phase
The results of the CDIV should be included in a CRR for to increase the capacity of the tailings facility.
new tailings facilities or other relevant documents such
— Construction for any material changes.
as an annual report for operating tailings facilities.
— D
esign modifications and implementation of the
3.5.4 Documentation of Constructed closure plan.
Conditions
Construction records, including QA/QC documentation,
Accurate documentation of as-constructed conditions construction surveys and as-built drawings, and
is critical. Such documentation provides the information commissioning documentation should be retained to
needed to: provide the documentation that the construction was in
accordance with the construction drawings and
— C
ontinue construction of the tailings facility during
technical specifications. These may be consolidated in
the Operations phase.
the CRR. These records are important for the ongoing
— Inform any future consideration of changes in the management of the tailings facility and provide a critical
design of the tailings facility. database for ongoing construction and geotechnical
assessments. If construction is conducted in multiple
— U
nderstand and remedy problems that may arise
stages, it is helpful to consolidate the CRR and drawings
in the future.
as a complete reference of the cumulative facility
Constructed conditions should be documented in a construction or develop another equivalent approach to
CRR signed by the EOR and RTFE per Requirement 6.3 integrating information.
of the Standard. Through the CDIV and Independent
To facilitate ease of access and the analysis of
Review, this includes verification of whether the
constructed conditions this information may include
constructed conditions meet the design intent and
detailed geo-location data and be compiled in a
specifications.
comprehensive GIS-based retrievable system. This may
The CRR should also summarise the results of the CDIV not be possible for existing sites with incomplete
to ensure that all changes to the design or any aspect construction records.
3.6.1 Introduction — R
isk management plan is implemented and is
reviewed and updated regularly (Sections 3.2.4 and
The Operations phase is the period in the lifecycle when
3.4).
tailings are transported to, and placed in, the tailings
facility. It may also include the temporary suspension of — O
MS activities are implemented to operationalise the
mine operations (Section 3.6.5). TMS and risk management plan (Section 2.4).
Operations
Conduct OMS activities in
accordance with:
– Performance objectives
– Risk management plan
– Design intent
– Closure plan
Evaluate performance of
tailings facility and tailings
management governance:
– Address deficiencies
– Implement measures for
continual improvement
Review/update:
Temporary Suspension
– DBR
– Tailings management system
– OMS manual
– EPRP
Project Design Construction – Site characterisation models Closure Post-Closure
Conception – Risk assessment
Potential material
changes go to
either Project
Conception or
Design, depending
on complexity
Material Changes
Note: The red boxes and lines indicate activities/relationships expected to occur for all tailings facilities.
The yellow boxes and lines indicate activities/relationships that may occur.
— D
ocumentation related to tailings facility — Closure plan.
engineering and management, if available, even if
In addition, the Operator should consider the continued
under different name/format:
suitability of application of the precautionary approach,
- Site characterisation information and models versus adoption of a performance-based approach
(Section 3.3.2). (Section 3.4.3).
- Design information including the design, the
The Operator should develop a schedule for
design intent and design basis (Design Report
sequencing and implementing action plans, develop a
and DBR, Section 3.4.5).
budget, and obtain budget approval. Action plans
- Information on the construction of the tailings should then be implemented in accordance with the
facility, including as-built conditions (CRR, schedule, cognizant of the importance of effectively
Section 3.5.4), and deviations from the design managing change through this process (Section 2.3.2.1).
(DAR, Section 3.5.3).
- OMS activities (OMS manual, Section 2.4).
- Closure plan (Section 3.7.2).
— C
urrent and historical performance of the tailings
facility, including conformance with the design
intent, corporate policy on tailings management,
legal requirements and commitments to
communities (Section 2.3.4).
— E
PRP and results of any tests conducted
(Section 2.7).
— R
eports from a programme for reviewing tailings
safety (eg Independent Review) (Section 2.6).
In Detail — D
oes the Operator have an up-to-date risk
assessment (Section 3.2.4)? Does the Operator
Questions to consider in this gap analysis include:
understand the uncertainties associated with the
Questions related to governance of tailings risk assessment? Has the Operator identified
management credible failure modes and assessed the potential
— Does the Operator have a corporate policy on consequences of failure?
tailings management? Does this policy include a
— D
oes the Operator have an up-to-date risk
goal of eliminating fatalities and catastrophic
management plan and is it being implemented
failures (Section 2.2.3)?
(Section 3.2)? Does the risk management plan
— H
ave accountability and responsibility been reduce risk according to ALARP? Are additional
assigned for roles described in Section 2.2.2 and mitigations needed?
are persons in these roles appropriately
— D
oes the Operator have documentation on the
competent as per Section 2.2.4? Are there clear
design, the design intent, and the design basis for
lines of communication between key roles?
the tailings facility (eg a Design Report and DBR)?
— H
as a TMS been developed and implemented Is this documentation adequate and updated as
(Section 2.3)? Are processes in place to manage appropriate (Section 3.4.5)?
change (Section 2.3.2.1)?
— H
as an integrated tailings and water management
— H
as an OMS manual been developed and plan been developed and is it based on up-to-
implemented? Is it up to date, accessible, date data and operating rules (Section 3.2.3)?
understood and utilised by relevant personnel
— D
oes the Operator have a plan for construction
(Section 2.4)?
management, including quality management
— Is the Operator effectively managing information (Section 3.5.2)? Is construction being done in
related to tailings management (Section 2.5)? accordance with this plan?
— D
oes the Operator have a programme in place to — D
oes the Operator have an accurate, up-to-date
review tailings safety, including Independent record of the constructed tailings facility, including
Review (Section 2.6)? and accurate understanding of:
— D
oes the Operator have an EPRP? Is the plan - Current conditions (Section 3.5.4)?
tested and updated appropriately (Section 2.7)? - Deviations
from the design intent and design
Are communities and public sector agencies basis, including the rationale for such decisions
engaged (Section 2.2.5)? and assessment for implications to facility
performance (Section 3.5.3)?
Questions related to engineering practice
— D
oes the Operator have and use an up-to-date
— Is site characterisation information (including
closure plan towards which progress is being
tailings material characterisation) adequate and is
made?
this information up to date (Section 3.3.2)?
As part of the planning to implement a material change, — Medium- or longer-term decisions, such as:
the Operator should consider not only the need to - Responding to deficiencies in performance or
update relevant aspects of the design, but also other opportunities to continual improvement (eg
plans and processes. For example, implementing the responding to recommendations from
material change may necessitate changes to the OMS Independent Review) (Section 2.6).
manual.
- Material changes to improve performance (eg
The decision to implement the proposed material construction of a buttress).
change should be made at a level in the organisation - Adjusting the design or operating practices in
commensurate with the significance of the change (eg response to an updated validation of the design
RTFE, Accountable Executive or BoD, as appropriate). basis or updated predictions of the future
performance of the tailing facility.
The process of considering potential material changes,
and of implementing approved material changes should Decision-making for medium- and longer-term
be properly documented. The DAR (Section 3.5.4) is decisions would typically be addressed through the
intended to contain a record of all the deviations from process to manage change (Section 2.3.2.1) as these
the design across the lifecycle, including both material would be considered material changes (Section 3.6.3).
and non-material changes. The records contained in These types of decisions are also addressed in
the DAR also provide a basis for assessing the potential Section 3.4.3 in the context of the discussion of the
cumulative effects of proposed changes or deviations. If precautionary-based approach and application of the
any material changes are proposed that are outside the observational method (Sections 3.4.3.4 and 3.4.3.5),
scope of the DAR, these should also be properly and the discussion of the performance-based
documented. approach (Section 3.4.3.6).
— D
efer or transfer risks to the Closure phase without The advantage of this approach, including pre-defining
fully considering the potential implications. the risk controls to be implemented, is that it facilitates
prompt action if the performance is outside the
A rigorous approach to decisions provides a structured,
specified range, since the Operator, with input from the
consistent mechanism for decision-making, helping to
EOR, has already identified the action to be taken. It also
ensure that decisions are taken by persons with the
empowers junior staff with the authority to act in the
appropriate authority and competencies, and are based
event that the RTFE and EOR cannot be contacted in a
on relevant information.
timely manner.
A decision-making framework is based on the intersection
between credible failure modes, performance indicators
and criteria, and the risk management plan. A decision-
making framework should identify:
— C
redible failure modes potentially subject
to immediate or short-term decisions (ie
implementation of mitigation).
— P
erformance indicators and criteria able to
measure and assess performance relevant to
those credible failure modes.
— S
urveillance measures aligned with the
performance criteria.
— P
re-defined risk management measures (risk controls)
to be taken if the performance criteria associated with
the credible failure modes are not met.
Figure 17: Integrated Mine Closure Framework across each lifecycle phase
Final Relinquishment
Project Design Construction Operations & Progressive Closure Closure Post-Closure
Conception
Stakeholder Engagement
Project Conception:
— Perform relevant baseline studies and data
gathering, including biodiversity baselines,
relevant to the tailings facility.
In Detail
— Engagement with communities and Indigenous
Progressive closure of tailings facilities needs to be
Peoples to understand post-mine land capability
integrated into the broader site closure plan. For
of tailings facilities, potential uses and impact on
guidance on mine closure planning and execution,
closure design.
ICMM’s Integrated Mine Closure Good Practice Guide
(2025) highlights the crucial steps for managing mine — Develop post-mining land use objectives for the
waste (including tailings), which need to be tailings facility.
considered throughout the mine’s life.
— Development of closure plans for the tailings
The items summarised below should be considered facility, based on a range of mine plan scenarios
specifically for the context of closing tailings facilities. and predictive modelling.
— Identification of activities required to attain long- — Ensure a QA/QC plan detects, manages and
term physical and chemical stability and achieve evaluates deviations from original designs,
the post-closure land use (eg chemical and geotechnical (such as differential settlement)
physical characterisation and associated and geochemical deviances. Integrate associated
management activities). actions into updated mine plans. Track waste
material source and destination required to enable
— Identify and address the potential modes of failure
progressive and final closure of the tailings facility.
that could occur post-closure, such as increasing
the capacity of emergency spillways to account — Update risk management plans, OMS activities
for overtopping events. and closure plans during any progressive closure
opportunities.
— Thoroughly characterise the geochemistry of the
tailings, underlying geology and tailings
Operations:
embankment and foundation construction
— Progressive closure of areas where tailings
materials (see GARD guide for appropriate
deposition is complete including water
protocols for geochemical characterisation3).
management, resloping, cover placement,
— Evaluate, plan and schedule specific material revegetation, monitoring and maintenance.
source and destination requirements to enable
— Evaluate and document the performance of
integration of progressive and final closure into
progressively closed areas and continuously
mine plans.
integrate improvement opportunities into
— Plan for closure and post-closure site water progressive and final closure plans.
management requirements, such as using
— Track and document any material changes
adaptive water management approaches and
between design and execution and evaluate their
climate-specific cover systems.
impact on progressive and final closure plans for
— Consider and plan for post-closure ongoing the tailings facility. Integrate outcomes into
monitoring of seepage to confirm that volumes subsequent mine plan iterations.
and quality meet and will continue to meet
— Update risk management plans, OMS activities
discharge criteria.
and closure plans during any progressive closure
— Identify the salvage and storage of soils to enable opportunities.
progressive and final closure of the tailings facility
and integrate into mine plans.
3. Source: http://www.gardguide.com/index.php?title=Main_Page
— Pre-mining land use and the historical, current Several of these factors may be beyond the direct
and potential future use of surrounding lands. influence of the Operator, therefore ongoing
engagement and consultation are important.
— Permanent alterations to the landscape as a
result of mining and tailings storage activities. Further detail can be found in the ICMM
Integrated Mine Closure: Good Practice Guide
— Land capability of the tailings storage facility
(2025), Section 5.
to define feasible land uses.
3.7.3 Development of Success Criteria — Specific: Criteria should relate directly to the
overarching closure objectives of the site or can be
Success criteria, also known as closure criteria, are
specific to closure activities which apply to the
measurable parameters that indicate when closure
tailings facility.
activities have been successful. Success criteria may be
developed specifically for the tailings facility, and should — Measurable: Criteria must be able to be measured to
be integrated within the site-wide closure plan. Success demonstrate that it has been met to stakeholders or
criteria should be Specific, Measurable, Achievable, the regulator. Numerical criteria are common as they
Relevant and Timely (SMART) indicators. SMART are easily measured, but narrative criteria may also
principles for closure are: be required. For example, as-built drawings or field
inspections.
For tailings facilities, success criteria development — Performance of stormwater runoff conveyance
should be aligned with the closure objective of structures (eg occurrence and volume (litres/year) of
developing a final landform that supports the identified direct discharge (overflows) or field inspection
post-closure land use. For many tailings facilities reports),
effective closure can be demonstrated through using
— Effluent water chemistry (eg monitoring results and
SMART success criteria to show that a landform is safe,
inspection reports).
stable, non-polluting, and able to sustain the identified
post-closure land use. Tool 10, ‘Considerations in developing closure activities
for domain specific issues’ from the ICMM Integrated
Examples of success criteria include:
Mine Closure Good Practice Guide (2025), provides
— Soil stability and erosion rates for rehabilitated considerations on the physical and chemical stability
areas (eg tonnes/hectare/year, field observations), of tailings at closure. It is a valuable reference for
developing success criteria across these areas.
— R
isk assessment should be updated for closure, and — Community engagement continues.
the risk management plan updated accordingly.
— E
PRP is updated to reflect closure conditions,
— O
MS manual should be updated for closure and including a potential change in the role of the
implemented to meet the requirements for the Operator and third parties in responding to an
Closure and Post-Closure phases. emergency as the Operator’s on-site resources
change.
— C
onstruction activities are carried out as per the
closure plan, with adherence to design specifications Figure 18 illustrates the key activities of the Closure
and quality management requirements. phase of the lifecycle.
Closure
Implement closure in
accordance with closure plan
and final closure design.
Conduct operation,
maintenance and surveillance
activities in accordance with:
– Performance objectives
– Risk management plan
– DBR
– Closure plan
Evaluate performance of
tailings facility and tailings
management governance:
– Address deficiencies
– Implement measures for
continual improvement
Review/update:
– DBR
Temporary Suspension
– Tailings management system
– OMS manual
– EPRP
– Site characterisation models
Project Design Construction Operations Post-Closure
Conception – Risk assessment
Potential material
changes go to
either Project
Conception or
Design, depending
on complexity
Material Changes
Note: The red boxes and lines indicate activities/relationships expected to occur for all tailings facilities.
The yellow boxes and lines indicate activities/relationships that may occur.
Post-Closure
Conduct operation,
maintenance and surveillance
activities in accordance with:
– Performance objectives
– Risk management plan
– DBR
– Closure plan
Evaluate performance of
tailings facility and tailings
management governance:
– Address deficiencies
– Implement measures for
continual improvement
Temporary Suspension Review/update:
– DBR
– Tailings management system
– OMS manual
– EPRP
Project Design Construction Operations Closure – Site characterisation models
Conception – Risk assessment
Potential material
changes go to
either Project
Conception or
Design, depending
on complexity
Material Changes
Note: The red boxes and lines indicate activities/relationships expected to occur for all tailings facilities.
The yellow boxes and lines indicate activities/relationships that may occur.
Accountability: The answerability of an individual for Breach analysis: A study that assumes a failure of
their own performance and that of any personnel they the tailings facility and estimates its impact. Breach
direct, and for the completion of specified deliverables analyses should be based on credible failure modes
or tasks in accordance with defined expectations. An where loss of containment is possible. The results
accountable person may delegate responsibility for should determine the physical area impacted by a
completion of the deliverable or task, but not the potential failure, flow arrival times, depth and velocities,
accountability. duration of flooding, and depth of material deposition.
The breach analysis is based on scenarios which are
Accountable Executive: One or more executive(s) who
not connected to probability of occurrence. It is
is/are directly answerable to the CEO on matters related
primarily used to inform emergency preparedness and
to this Standard, communicates with the Board of
response planning and for determining the potential
Directors, and who is accountable for the safety of
consequences of failure. [based on the definition
tailings facilities and for minimising the social and provided in the Standard]
environmental consequences of a potential tailings
facility failure. The Accountable Executive(s) may Catastrophic failure: A tailings facility failure that results
delegate responsibilities but not accountability. in material disruption to social, environmental and local
[based on the definition provided in the Standard] economic systems. Such failures are a function of the
interaction between hazard exposure, vulnerability, and
As low as reasonably practicable (ALARP): ALARP the capacity of people and systems to respond.
requires that all reasonable measures be taken with Catastrophic events typically involve numerous adverse
respect to ‘tolerable’ or acceptable risks to reduce them impacts, at different scales and over different
even further until the cost and other impacts of timeframes, including loss of life, damage to physical
additional risk reduction are grossly disproportionate to infrastructure or natural assets, and disruption to lives,
the benefit. [based on the definition provided in the livelihoods and social order. Operators may be affected
Standard] by damage to assets, disruption to operations, financial
Authority: The power to make decisions, assign loss or negative impact to reputation. Catastrophic
responsibilities, or delegate some or all authority, as failures exceed the capacity of affected people to cope
appropriate. The ability to act on behalf of the Operator. using their own resources, triggering the need for
outside assistance in emergency response, restoration
Board of Directors (BoD): The ultimate governing body and recovery efforts. [based on the definition provided
of the Operator typically elected by the shareholders of in the Standard]
the Operator. The BoD is the entity with the final
Community: A social group possessing shared beliefs
decision-making authority for the Operator and holds
and values, stable membership and the expectation of
the authority to, among other things, set the Operator’s
continued interaction. It may be defined geographically,
policies, objectives and overall direction as well as
by political or resource boundaries, or socially as a
oversee the firm’s executives. As the term is used here,
community of individuals with common interests.
it encompasses any individual or entity with control over
the Operator, including, for example, the owner or Construction versus Design Intent Verification (CDIV):
owners. Where the State serves as the Operator, the Intended to ensure the design intent is implemented
BoD shall be understood to mean the government and still being met if the site conditions vary from the
official with ultimate responsibility for the final decisions design assumptions. The CDIV identifies any
of the Operator. [based on the definition provided in the discrepancies between the field conditions and the
Standard] design assumptions, such that the design can be
During the Closure or Post-Closure phases, tailings Procedure: A documented description of how a
facilities could return to the Operations phase. In task is to be carried out.
addition, tailings could be removed for reprocessing to
Observational method: A continuous, managed,
recover additional commodities of value, or to be used integrated, process of design, construction control,
for other purposes (eg construction material). monitoring and review that enables previously defined
In some jurisdictions, during the Post-Closure phase, modifications to be incorporated during or after
responsibility for a tailings facility may transfer from the construction as appropriate. All of these aspects must
Operator to jurisdictional control. It is recommended for be demonstrably robust. The key element of the
Operators to work with stakeholders to ensure that observational method is the proactive assessment at
appropriate monitoring and maintenance will continue the design stage of every possible unfavourable
to occur during the Post-Closure phase and that situation that might be disclosed by the monitoring
dedicated oversite and financial mechanisms are in programme and the development of an action plan or
mitigative measure to reduce risk in case the
place for required activities.
unfavourable situation is observed. This element forms
Maintenance: Includes preventative, predictive and the basis of a performance-based risk management
corrective activities carried out to provide continued approach. The objective is to achieve greater overall
proper operation of all infrastructure (eg civil, safety. See Peck, R.B. (1969), ‘Advantages and
mechanical, electrical, instrumentation, etc), or to adjust Limitations of the observational method in Applied Soil
infrastructure to ensure operation in conformance with Mechanics’, Geotechnique 19(2), pp.171–187. [based on
performance objectives. the definition provided in the Standard]
Operator: An entity that singly, or jointly with other Responsible Tailings Facility Engineer (RTFE): An
entities, exercises ultimate control of a tailings facility. engineer appointed by the Operator to be responsible
This may include a corporation, partnership, owner, for the tailings facility. The RTFE must be available at all
affiliate, subsidiary, joint venture or other entity, including times during the Construction, Operations and Closure
any State agency, that controls a tailings facility. [based phases of the lifecycle. The RTFE has clearly defined,
on the definition provided in the Standard] delegated responsibility for management of the tailings
facility and has appropriate qualifications and
Performance: There are three key terms related to experience compatible with the level of complexity of
performance, defined as follows: the tailings facility. The RTFE is responsible for the
erformance objectives are overall goals, arising from
P scope of work and budget requirements for the tailings
the Operator’s policy and commitment, which are facility, including risk management. The RTFE may
quantified where practicable. They may be defined at delegate specific tasks and responsibilities for aspects
various levels of detail such as this tailings facility will of tailings management to qualified personnel but not
not experience a catastrophic failure versus accountability. [based on the definition provided in the
deformation of the embankment will be minimised. Standard]
Performance indicators are detailed performance Risk: A potential negative impact, detrimental to
requirements that arise from the performance operations, a facility, the environment, public health, or
objectives and that need to be established and met safety, that may arise from some present process or
in order to achieve those objectives. Performance future event. When evaluating risk, both the potential
indicators must be measurable and quantifiable. severity and consequence of the impact and its
probability of occurrence are considered.
Performance criteria are established based on
expected or predicted performance and are used to Risk controls: Measures put in place to either:
evaluate performance indicators and define limits of — P
revent or reduce the likelihood of the occurrence of
performance outside which risk management action an unwanted event; or
needs to be taken.
— M
inimise or mitigate the negative consequences if
Personnel: Includes employees, contractors and the unwanted event does occur.
consultants (eg designer, Engineer-of-Record) and
Risks need to be managed via controls, and risk
includes those with direct responsibilities for tailings
controls should have designated owners and defined
management as well as those with indirect
accountabilities. Some risk controls are designated as
responsibilities whose roles may be related in some
critical controls.
manner to tailings management (eg heavy equipment
operators working on or adjacent to tailings facilities). Stakeholders: Persons or groups who are directly or
indirectly affected by a project, as well as those who may
Quality: The degree to which a set of inherent
have interests in a project and/or the ability to influence
characteristics fulfils requirement.
its outcome, positively or negatively. Stakeholders may
Quality assurance (QA): All those planned and include workers, trade unions, project-affected people or
systematic activities implemented to provide communities and their formal and informal
Disclaimer
This publication contains general guidance only and should not be relied upon as
a substitute for appropriate technical expertise. Although reasonable precautions
have been taken to verify the information contained in this publication as of the date
of publication, it is being distributed without warranty of any kind, either express
or implied. This document has been prepared with the input of various International
Council on Mining and Metals (‘ICMM’) members and other parties. However, the
responsibility for its adoption and application rests solely with each individual member
company. At no stage does ICMM or any individual company accept responsibility
for the failures or liabilities of any other member company, and expressly disclaims the
same. Each ICMM member company is responsible for determining and implementing
management practices at its facility, and ICMM expressly disclaims any responsibility
related to determination or implementation of any management practice.
Each ICMM member company is responsible for determining and implementing
management practices at its facility, and ICMM expressly disclaims any responsibility
related to determination or implementation of any management practice. Moreover,
although ICMM and its members are committed to an aspirational goal of zero fatalities
at any mine site or facility, mining is an inherently hazardous industry, and this goal
unfortunately has yet to be achieved.
In no event shall ICMM (including its officers, directors, and affiliates, as well
as its contributors, reviewers, or editors to this publication) be liable for damages
or losses of any kind, however arising, from the use of or reliance on this document,
or implementation of any plan, policy, guidance, or decision, or the like, based on this
general guidance. ICMM, its officers, and its directors expressly disclaim any liability
of any nature whatsoever, whether under equity, common law, tort, contract, estoppel,
negligence, strict liability, or any other theory, for any direct, incidental, special, punitive,
consequential, or indirect damages arising from or related to the use of or reliance
on this document.
The responsibility for the interpretation and use of this publication lies with the user
(who should not assume that it is error-free or that it will be suitable for the user’s purpose)
and ICMM. ICMM’s officers and directors assume no responsibility whatsoever for errors
or omissions in this publication or in other source materials that are referenced by this
publication, and expressly disclaim the same.
Except where explicitly stated otherwise, the views expressed do not necessarily represent
the decisions or the stated policy of ICMM, its officers, or its directors, and this document
does not constitute a position statement or other mandatory commitment that members
of ICMM are obliged to adopt.
ICMM, its officers, and its directors are not responsible for, and make no representation(s)
about, the content or reliability of linked websites, and linking should not be taken
as endorsement of any kind. We have no control over the availability of linked pages
and accept no responsibility for them.
The designations employed and the presentation of the material in this publication
do not imply the expression of any opinion whatsoever on the part of ICMM, its officers,
or its directors concerning the legal status of any country, territory, city or area or
of its authorities, or concerning delimitation of any frontiers or boundaries. In addition,
the mention of specific entities, individuals, source materials, trade names, or commercial
processes in this publication does not constitute endorsement by ICMM, its officers,
or its directors.
This guidance is not intended to extend the scope of the Global Industry Standard on
Tailings Management nor provide a definitive interpretation of any of the requirements
within the Global Industry Standard on Tailings Management.
ICMM
53-64 Chancery Lane
London, WC2A 1QS
United Kingdom
+
44 [0] 20 7467 5070
[email protected]
icmm.com Updated February 2025
Integration of risk management principles into tailings facility design enhances safety and performance by reducing uncertainty and refining risk estimates through improved site characterization and relevant modeling. This enables the engineering design to focus on reducing or eliminating specific risks, informing decisions that address both likelihood and consequences of failure events . The development of a comprehensive risk management plan helps manage residual risks by incorporating risk assessments, surveillance, and independent reviews throughout the facility's lifecycle . Risk-informed decision-making ensures that performance objectives are realistically set and updated, reflecting the ALARP (As Low As Reasonably Practicable) principle to balance risk reduction efforts with feasibility . This approach supports robust designs that enhance the structural integrity of facilities, mitigating credible failure modes and responding dynamically to changing conditions and data ."}
Emergency Preparedness and Response Planning (EPRP) is crucial in managing risks associated with tailings facilities by ensuring operators are prepared to prevent, mitigate, or reduce impacts from potential emergencies, including catastrophic failures . The EPRP integrates sitewide emergency planning, identifying credible failure scenarios and preparing detailed response measures such as identifying roles, responsibilities, and resources needed during emergencies . It facilitates coordination with off-site emergency responders, local communities, and public sector agencies, ensuring all relevant parties are informed and involved in developing effective emergency response strategies . Regular testing and reviewing of the EPRP are mandatory to ensure its adequacy and alignment with updates in risk assessments, technological advancements, and legal requirements . This comprehensive approach helps in maintaining a shared state of readiness for emergency scenarios, ultimately enhancing the resilience of tailings facilities against failure ."}
During the development of a closure plan for tailings facilities, it is important to begin planning from the Project Conception phase, integrating closure and post-closure considerations into all design and operational activities. The plan should outline a vision, principles, and objectives, becoming more detailed during the Design phase and refined throughout Operations, with regular updates and adaptations to meet regulatory, environmental, and stakeholder expectations . Progressive closure activities should be incorporated, allowing for phased reclamation to enhance the probability of achieving closure objectives and managing financial risks . Key elements include evaluating landform design to ensure long-term physical and chemical stability, managing water and seepage, selecting appropriate technologies, and engaging with stakeholders to align with post-closure land use objectives . The closure plan should incorporate detailed baseline studies, stakeholder engagement for post-mining land use planning, and development of SMART criteria to measure closure success . Additionally, integration of sitewide water management and other mine waste management practices is critical for ensuring safe and effective closure .
The Tailings Management System (TMS) serves as a comprehensive framework for managing and safely operating tailings facilities throughout their lifecycle. It is designed to integrate people, resources, processes, and practices to help operators achieve performance objectives, manage risks, and ensure safe tailings management . The TMS is based on the Plan-Do-Check-Act cycle, which includes establishing policies, planning, risk assessments, performance evaluations, and continual improvement . It ensures alignment and integration with other relevant systems like environmental and social management systems . Operation, Maintenance, and Surveillance (OMS) activities are critical for the day-to-day implementation of the TMS and engineering practices for safe tailings management. OMS involves the operational, maintenance, and surveillance aspects, which are essential to understand and manage risks, ensure performance objectives are being met, and maintain effective control of tailings management . The OMS manual outlines specific roles, responsibilities, communication lines, and procedures, ensuring integration with overall tailings management and risk management plans . The OMS is applicable across all phases of the tailings facility lifecycle, from operations through to post-closure .
The design principles of tailings facilities impact their long-term safety and performance by incorporating risk-informed decision-making, performance-based approaches, and closure considerations from the outset. These principles ensure the facility is designed to anticipate and mitigate credible failure modes, such as seepage and deformation, by incorporating advanced modelling and simulation techniques to predict and manage risks throughout its lifecycle . Emphasizing structured assessments and updates based on ongoing data collection and analysis supports continual adaptation to site-specific conditions and evolving environmental factors, further enhancing stability and safety . Adherence to a robust safety culture within the mining industry ensures that tailings management incorporates comprehensive risk assessments and updates to reflect changes over time, thereby minimizing potential human errors and environmental impacts .
Surveillance in tailings management is crucial for reducing risks and ensuring safety through regular inspection and monitoring activities, which include the collection and timely reporting of both qualitative and quantitative data. This data enables decision-making to verify if performance objectives, risk management plans, and design intentions are met . Surveillance activities, including site observation, inspections, and instrument monitoring, help identify trends and potential issues, allowing for corrective actions before significant risks develop . An effective surveillance program involves a multidisciplinary team and adapts to the lifecycle phases of the tailings facility, addressing changes in site conditions . Surveillance results are critical inputs for risk assessments, which underpin risk-informed decision-making, focusing on reducing risks related to catastrophic failures . Ultimately, surveillance supports the safe and responsible management of tailings facilities by enabling prompt and informed responses to identified risks .
The tailings facility lifecycle consists of six phases: Project Conception, Design, Construction, Operations, Closure, and Post-Closure . During these phases, tailings management involves continuous adjustments and updates. Potential reuse or processing of tailings is considered particularly in the Closure and Post-Closure phases. For instance, tailings can be removed for reprocessing to recover additional commodities or used for other purposes such as construction material . Furthermore, the Operations phase may explore alternative deposition approaches to achieve closure objectives, influencing potential future uses of tailings . Integrating tailings management with ore processing and mine planning throughout the lifecycle supports decision-making regarding tailings reuse or processing .
Transparency and information sharing are crucial in stakeholder engagement and risk management for tailings facilities as they foster trust, accountability, and effective communication between operators and stakeholders, including communities and regulatory bodies. Involving stakeholders in surveillance activities, such as downstream water quality monitoring, builds trust and allows operators to incorporate community insights and concerns into risk management efforts, enhancing the overall management strategy . Furthermore, sharing detailed and up-to-date information helps ensure that decisions regarding tailings management are based on a comprehensive understanding of risks and potential consequences, thereby improving risk evaluation and mitigation measures . Transparently communicating these risks and management strategies to all stakeholders, including legal obligations and safety protocols, enhances confidence in the facility's safety and operational integrity, contributing to more informed and collaborative stakeholder interactions . Regularly updated risk assessments and clear communication lines ensure stakeholders are informed of potential changes and developments, sustaining engagement and trust .
Governance establishes accountability, competency, and structured decision-making, which are critical for safe tailings management. It includes developing a Tailings Management System (TMS) that encompasses planning, execution, and oversight according to corporate policies . Ensuring accountability across all levels through designated roles (e.g., Accountable Executive), and maintaining good communication with stakeholders help manage risk effectively . The governance framework necessitates integration with other site-level management systems, such as environmental and social management systems, ensuring holistic management practices throughout a facility's lifecycle . Effective governance is a precondition for all tailings management activities, supporting aspects such as emergency preparedness, transparency, and continual improvement in safety protocols .
Accountability is crucial in the governance of tailings facilities as it ensures that operators, defined broadly as owners and operators, are answerable for the safety and integrity of tailings management systems . It involves establishing clear roles, responsibilities, and communication channels within an organization to manage tailings effectively. Accountability cannot be delegated and must be supported by corporate commitment to safety, providing necessary resources to achieve safe management . This includes ensuring competent personnel, engaging communities, and sharing information with external parties like regulators . An Accountable Executive must have the authority proportional to their responsibilities in maintaining tailings safety standards and minimizing risks . Effective governance through accountability integrates with other elements such as risk management, communication, and training to provide a comprehensive safety framework .