, ~ Tl~E~INE~i ii
PROJECT TITLE: V1TER B+G+3P+22+R RESIDENTIAL BUILDING W/ RETAIL @ GROUND
                                                                                                                                           I                            DAILY SITE REPORT                                                        Day: Friday
THE EMPLOYER:                                    THE DEVELOPMENT MANAGER:                                                                      Accidents:                           Humidity / Rains                      Temp at 8 am =   °C
                                                                                                                                                                                                                                                 Date:
                                                                                                                                               Cumulative Man-hours w/o Accidents   Wind /Sandstorms
  Object 1
  Real EstateDevelopment l.L.C.
                                                     Object 1
                                                     RealEstateOe·1elopment LL.C.
                                                                                                                                                                                                                          Temp at 1 pm =   °C
                                                                                                                                                                                                                                                02-05-2025
                                               Major Achievements / Activities of the Day                                                            Manpower at Site                                           Engineer's Comments
* Shutter and steel fixing for Verticals Upper Roof Slab
                                                                                                                                                  Manpower (as applicable)
                                                                                                                                                                                    - Contractor is responsible for any deviation between the DSR and the
* Preparation for Plaster Elevation 3,1,4                                                                                                      Project Manager        1
* plaster works for elevation 1,3,4
                                                                                                                                               Construction Manager
                                                                                                                                                                                    actual site condition observed in the future.
* Plaster works 11th &14th floor                                                                                                                                      1
* Plaster preparation works 15th floor
                                                                                                                                               Planning Engineer
                                                                                                                                                                                    - Dimensions, coordinates, layouts, levels and details to be as per IFC
* Screed work in progress 11th & 12th floor
* Waterproof work in progress in 12th Floor
                                                                                                                                               QA/QC Engineers        1             Drawing.
* Block work , 19th , 20th floor floor
* floor and wall tile 9th & 10th floor                                                                                                         Safety Engineer        1             - Enhance safety measures& general housekeeping, risk assessment and
* false ceiling in progress
* Chiller pipe trench in progress/ entrance, drive way area                                                                                    Project Engineers      2             HSE Plan
* Manhole work for entrance drive way area
* Curing for-casted items.                                                                                                                     Foreman                4             to be followed.
MEP:
                                                                                                                                               Surveyor               1             -Contractor to follow authorities’ requirements and rules.
1) 17th & 18th floor first fix.
2) light wiring at 11th , 12th and 14th floor                                                                                                  Draftsmen                            -Old concrete and rust on steel to be treated properly and brushed prior to
3) Plumbing work on 11th 12th and 13th floor
4) Podium 2 riser duct insulation                                                                                                              Storekeeper            1             concrete
                                               Work in Progress / Planned for the Next Day                                                     Site Secretary /DC     1             - De-shuttering to be as per Approved design.
                                                                                                                                               Office Boys            1             - All Materials to be stored properly.                                  o
* Casting Vertical and CW for Upper Roof and Machine Room
                                                                                                                                               Drivers                1             - Curing process to be as per standards.
                                                                                                                                                                                    Date:                                      Signature:
* Shutter and steel fixing for Verticals Upper Roof Slab
* Preparation for Plaster Elevation 3,1,4
* plaster works for elevation 1,3,4                                                                                                                 Sub-Total-1       15            - MAR 02/05/2025
                                                                                                                                                                                               Approval must be Obtained for      All materials before use.
* Plaster works 11th &14th floor
* Plaster preparation works 15th floor
                                                                                                                                                                                    - MVR  Plant     and must
                                                                                                                                                                                               Approval    Machinery
                                                                                                                                                                                                                be obtained forQty      Working
                                                                                                                                                                                                                                 All materials       Breakdown/
                                                                                                                                                                                                                                                before  use.
* Screed work in progress 11th & 12th floor
* Waterproof work in progress in 12th Floor                                                                                                                                         - All shop (asdrawing
                                                                                                                                                                                                     applicable)
                                                                                                                                                                                                            must be approved before startHours       Idle
                                                                                                                                                                                                                                             related activity.
* Block work , 19th , 20th floor floor
* floor and wall tile 9th & 10th floor                                                                                                         Charge hand                   3      -Roller
                                                                                                                                                                                      BlockCompactor
                                                                                                                                                                                               work Method of Statement to be0 followed.
* false ceiling in progress
* Chiller pipe trench in progress/ entrance, drive way area                                                                                    Watchman                      2      -Plate  Compactor
                                                                                                                                                                                      Plaster   work Method of Statement to be   1 followed.
* Manhole work for entrance drive way area
* Curing for casted items.                                                                                                                     Operator                      4      -Vibrator   + Shaft Method of Statement to 2be followed.
                                                                                                                                                                                      Spray Plaster
MEP:
1) 17th & 18th floor first fix                                                                                                                 Plumber                       1      -Drill
                                                                                                                                                                                      BlockMachine
                                                                                                                                                                                               work Completion RFI to be submitted
                                                                                                                                                                                                                                 6        prior plaster preparation.
2) Plumbing work on 11th 12th and 13th floor
3) Podium 2 riser duct insulation                                                                                                              Masons                        35     -Grinder
                                                                                                                                                                                      MEP Clearance to be Submitted Prior 5starting any activity.
4) 19th floor riser drainage piping
5) 8th Floor telephone room trunking                                                                                                           Carpenters                    35     -Hilti/Jack  hammer
                                                                                                                                                                                      All Required      NOC's to be available at5site.
                                                                                    Areas of Concern                                           Steel Fixers                  37     -Block   / Stone to
                                                                                                                                                                                      Contractor      Grinding Machines
                                                                                                                                                                                                        make sure                1
                                                                                                                                                                                                                   all finished activity are approved prior to start the
                                                                                                                                               Electricians                  3       Jig Saw
                                                                                                                                                                                    next   activity.                             4
                                                                                                                                               Chainmen/Rigger               6      -Air Blower to follow to the quality control
                                                                                                                                                                                      Contractor                                 1 procedure.
                                                                                                                                               Helpers                       40      Air Compressor                              1
                                                                                                                                               Others                        40      Pick Ups                                    1
                                                                                                                                                                                    Shovel
                                                                                                                                                     Sub-Total-2             191    Excavators/Bobcat/forklift                  2
                                                                                                                                                       Sub-Contractors              Tower Cranes/Mobile crane                   2
                                                                                                                                               Site laboratory                      Roller Machine                              0
                                                                                                                                               Third Party Inspection               Dumpers
                                                                                                                                               Anti-termite Treatment               Bar Bending Machines                        2
                                                                                                                                               MEP Works               118          Bar Shearing Machine/Cutting                2
                                                           Major Materials Received on Site                                                    Aluminum                             Welding Machine
                                                                                                                                               Joinery                              Car
                                                                                                                                               Marble Works                         Bus                                         1
                                                                                                                                               Tiling Works                  19     Cutting Set
                                                                                                                                               Painting                      8      Concrete Mixer
                                                                                                                                               Lifts                                Table Saw                                   1
                                                                                                                                               Miscellaneous                 30     Bench Saw
                                                                                                                                                                                    Tipper/Traila                               1
                                                                                                                                                     Sub-Total-3             179    Electrical hand saw                         4
                                                                                                                                                                                    Digital Thermometers
Prepared by:                                 Projects Manager:                                                                                                                      Surveying Equipment                         2
                                                                                                           Form No.: CVT/DSR/R01/01/2024          Total Manpower             415
Eng.Mansour Ali                           IEng.Samer Rayes                                             I