Qm-g75-Pl-0338 Rev A Procedure For Post Weld Heat Treatment
Qm-g75-Pl-0338 Rev A Procedure For Post Weld Heat Treatment
CRPO 117: MRJN TP-14 & 3 PDM│CRPO 118: MRJN 3 PDMs│CRPO 119: MRJN 4 PDMs
INFORMATION
NAME SIGNATURE
DATE
REVIEWED BY
Revision Log
INDEX
The Marjan Offshore Field is located in Arabian Gulf, approximately 85 km northeast of Tanajib
and approximately 260-km northeast of Dhahran. The field is located in medium-depth waters in
range of 29-m to 52-m.
CRPO 117: MRJN TP-14 & 3 PDMs, CRPO 118: MRJN 3 PDMs, CRPO 119: MRJN 4 PDMs IN
MARJAN is a part of the overall Marjan Field Development Program and it will provide ESP and
Future Gas Lift, Tie-In Platforms and Wellhead Facilities to increase Crude Oil Production.
A new offshore tie in platform to be installed under the project. It will be tied into MRJN GOSP-4
to deliver produced fluid to Gas Oil Separation Platform (GOSP) for separation of oil and gas.
Then the produced fluids will be transported onshore through export lines and interfiled pipelines.
The major project scope is detailed below:
CRPO 117: One TP (TP-14), Three PDMs (MRJN 740/749 (Gas Lift), MRJN 760/769 (initial free
flow), MRJN 780/789 (Gas Lift)), Modification at GOSP-4, Tie-in on TP-12, MRJN 26/28 Aux and
associated Cables & Pipelines.
CRPO 118: Three PDMs (MRJN 790/799 (Gas Lift), MRJN 560/569 (Free flow) & MRJN 530/539
(ESP)), Tie-in on TP-11, TP-13 and associated Cables & Pipelines
CRPO 119: Four ESP PDMs (MRJN 650/659, MRJN 830/839, MRJN 2000, 851/859), Gas Lift
(MRJN 800/809), Modification on TP-12 and associated Cables & Pipelines.
This procedure establishes the minimum Requirements for performance of Post Weld heat
Treatment in accordance with ASME Boiler and Pressure Vessel Code, Section VIII DIV1 and
Saudi Aramco Project Standards & Specifications.
The purpose of this document is to perform Post heat treatment of welds of Piping, and Pipeline
joints by using Electrical Resistance Method.
This Procedure is a “live” document and as such will be subject to periodic reviews / changes in
Line with identified and agreed amendments and improvements to the Project Quality
Management System during the project.
The order of precedence for drawings, specifications and standards for the facilities will be as
follows:
• Project Standards, which specifically include:
a) Company-provided Waivers.
b) Saudi Aramco Engineering Standards (SAES).
c) Saudi Aramco Material System Specifications (SAMSS)
d) Saudi Aramco Standard Drawings.
e) Saudi Aramco Engineering Procedures (SAEP).
f) Saudi Aramco General Instructions (GI's)
g) Scope of WORK, Preliminary design and all the Drawings and Documents. If the conflict
is between or within the documents in this Paragraph, the most stringent drawing,
specification, or standard shall control.
h) If at any time it is found that the standards and documents listed under Paragraphs
i) would permit a design that COMPANY/CONTRACTOR considers inferior to the
Preliminary Design required under Paragraph
j) COMPANY/CONTRACTOR shall have the right to maintain the design as required under
the Preliminary Design.
4.0 DEFINITIONS
The following items shall be used wherever mentioned in this document.
SAUDI ARABIAN OIL COMPANY (IK) AND
COMPANY
ARAMCO OVERSEAS COMPANY B.V.
SAPMT SAUDI ARAMCO PROJECT MANAGEMENT TEAM
SAPID SAUDI ARAMCO PROJECT INSEPCTION DEPARTMENT
CONTRACTOR LARSEN TOUBRO ARABIA LLC (IK) and
Larsen & Toubro Limited (OOK)
Larsen Toubro Arabia LLC (IK)
5.0 ABBREVIATIONS
The FACILITIES are designed to meet the applicable requirements of Saudi Aramco Standards,
International / industry standards, applicable Government and Regional Environmental
standards.
The cut-off date of COMPANY Standards and Specification will be 30th June 2022.
Larsen & Toubro Limited (OOK)
Larsen Toubro Arabia LLC (IK)
ASME B 31.4 ED 2016 Pipeline Transportation Systems for Liquids and Slurries
7.0 RESPONSIBILITIES
8.0 PROCEDURE
Contractor have plan to engage ITIS (Integrated Technologies for Industrial services co. ltd, KSA)
for performing Post Weld Heat Treatment activities required for Offshore Topside Hook-up and
accordingly issued Post Weld Heat Treatment & Preheating Procedure # ITIS/NDT/PWHT/01
Rev-05 dated 2nd Dec 2023 is attached and this will be implemented during work execution at
Offshore Topside Hook-up by Contractor.
Document No : ITIS/NDT/PWHT/01
Revision No : 05
Issue Date : 02-Dec-2023
TABLE OF CONTENTS
1.0 SCOPE 3
9.0 PREHEATING 14
10.0 INTERRUPTION 16
11.0 PRECAUTIONS 17
13.0 TABLE-01 19
1.0 SCOPE:
1.1. This procedure states explicitly in detail the minimum requirement for the external
localized preheat and Post Weld Heat Treatment (PWHT) of welds as well as other
associated areas in piping, vessels, structures etc. of carbon and alloy steel materials by
using the electrical resistance method.
1.2. This procedure covers description of the equipment, method of heating, location
and type of heating elements temperature measurement and thermocouple location.
1.3. Post Weld Heat Treatment (PWHT) shall be in accordance with ASME B31.3, ASME
Section VIII division 1 and as per client specifications.
2.0 REFERENCE DOCUMENTS:
Unless otherwise stated all codes and standards referenced in this procedure shall be
of the latest issue (including revisions – addenda and supplements) of the following
Documents:
4.1. Equipment
The equipment shall be proper condition & it should be bearing proper electrical power
input/output. Power distribution (supply) shall be of 380/440 Volts, with either single
phase secondary output or step down transformer secondary output (heat treatment unit)
Supplying low voltage circuits. The temperature control equipment shall be operated
manually or through regulators or it shall be (made) operated automatically with the Help
of modular controls. The chart type temperature recorder shall be used for recording
temperature. The frequency of calibration of temperature recorder shall be three months
& a proper valid sticker shall be displayed on the temp recorder.
4.2. Materials
All the connection materials required for the heat treatment shall be required as
per client specification.
Procedure ITIS/NDT/PWHT/01
Revision 04
Date 09-Aug-2016
POST WELD HEAT TREATMENT & PREHEATING PROCEDURE Page Page 5 of 26
5.1. The welds to be heat treated shall be prepared free of grease, lubricants dust and coatings
to avoid damage & short circuiting of accessories equipment’s.
5.2. Prior to the start of the PWHT, component shall be checked to ensure that all restrains
are removed and the component is free to expand and contract and suitable and sufficient
supports are used.
5.3. During heat treatment it shall be necessary to protect from oxidation the mechanical
surfaces line flange faces, threaded holes, threads by the application of coating such as
deoxaluminite or any other suitable coating material and shelf life of coatings shall be
monitored and maintained, and coatings shall not be applied if the shelf life or storage
condition has been exceeded.
5.4. PWHT shall follow all welding and repairs but shall be performed prior to any hydro test
or other load test.
5.5. Where practicable, open pipe ends of component shall be closed off to prevent the cooling
effects associated with draughts (chimney effects).
5.6. Heating elements shall be securely fixed in contact with the work piece by stainless steel
or Mild steel banding to suit the application. Under no circumstances shall galvanized wire
or other fixings likely to be detrimental to the pipe material to be utilized. Upon
completion of the Post Weld Heat Treatment, the thermocouple shall be removed and the
areas of attachment dressed by either grinding or filling before being non-destructively
examined using either dye Penetrate or magnetic particle inspection methods by Client
(if required) Client’s representative will sign and date the column inspection after Heat
Treatment.
5.7. Prior to the start of work the contractor or fabricator shall prepare a table listing each joint
or component requiring heat treatment, which shall be submitted to Saudi Aramco
Inspection for review. The table shall include the following information for each joint or
component: location, drawing number, diameter, wall thickness, material, heating rate,
and cooling rate, soak temperature, and soak time.
Procedure ITIS/NDT/PWHT/01
Revision 04
Date 09-Aug-2016
POST WELD HEAT TREATMENT & PREHEATING PROCEDURE Page Page 6 of 26
6.2.2 Longitudinal gaps between individual elements shall be limited to a maximum of 50mm
or’t’, whichever is the lesser for wall thickness above 10mm. For a wall thickness below 10mm
the gap shall be a maximum of 10mm. The heater pads above the weld center line shall be
rotated one quarter of a pad width with respect to the heaters below the weld centerline.
6.3 Pipe / Flange Welds
6.3.1 Pipe/flange welds shall be heat treated in accordance with the general principles of butt
welds between pipe members of unequal thickness, i.e. the provision of independent control
circuits on each side of the weld.
6.3.2 It may be necessary to fit an additional band of heating elements to the outside diameter
of the flange to compensate for heat losses.
6.4 Pipe to Branch Welds
6.4.1 The heating system to be applied to the main pipe member shall comprise of a full
circumferential band extending for a minimum distance each side of the branch of 3 x t1 and /
or otherwise as required by the governing standard (t1 = thickness of main pipe).
6.4.2 The heating system applied to the branch shall comprise of an independent
circumferential band extending for a minimum distance of 3 x t2 along the branch pipe, and /
or otherwise as required by the governing standard. (t2 = thickness of branch).
6.4.3 Gaps shall be limited in so far as practicable with respect to pipe attitude and dimensions
as detailed under items 6.2.1 and 6.2.2, as shall instructions for independent control of heater
circuits.
6.5 General
6.5.1 There shall be a maximum of three heating elements per circuit and controlled from any
one thermocouple.
6.5.2 Elements shall be securely fixed in contact with the work-piece by soft iron wire, stainless
steel, or mild steel banding to suit the application. Under no circumstances shall galvanized
wire or other fixings likely to be detrimental to the pipe material be utilised.
6.5.3 Where elements are manufactured with cold tails, care should be taken to avoid trapping
the cold tail and power supply cable between the work-piece and the insulation. Element tails
Procedure ITIS/NDT/PWHT/01
Revision 04
Date 09-Aug-2016
POST WELD HEAT TREATMENT & PREHEATING PROCEDURE Page Page 8 of 26
should be adequately supported to avoid undue strain at the element/tail junction and at the
hot/cold tail junction.
6.5.4 Prior to the start of post weld heat treatment the components shall be checked to ensure
that all restraints have been removed and that the pipe is free to expand and contract.
6.5.5 Prior to post weld heat treatment the Contractor shall ensure that the components are
properly supported to prevent sagging and distortion.
6.5.6 Where practicable, pipe ends shall be closed off to prevent the cooling effects associated
with drafts (chimney effects).
6.5.7 During heat treatment the component or work shall be protected from all types of
inclement weather conditions.
6.5.8 All machined surfaces that may reach soak temperature, such as flanges, faces, fitted bolt
holes, threads etc. and should be protected from oxidation during heat treatment by coating
these surfaces with suitable oxide inhibiting paint.
6.5.9 Where valves or other specialist items are affected by the heat treatment of associated
welds, the Contractor shall ensure that recommendations of the manufacturers are followed
with regards to the removal and/or positioning of internals.
6.6 Complex Geometries
Where weld joint geometry is more complex than a butt weld as defined in items 6.1 to 6.5,
Special procedures shall be raised for approval.
The procedure for PWHT has to be followed for the various steel grades as mentioned below.
The soak time shall be defined by that on the Saudi Aramco CSD approved WPS.
4
Procedure ITIS/NDT/PWHT/01
Revision 04
Date 09-Aug-2016
POST WELD HEAT TREATMENT & PREHEATING PROCEDURE Page Page 9 of 26
Heat treatment shall be carried out by electrical resistance elements, in the form of modular
Ceramic heating pads fitted around the weld. The heater pads are operated from heat transfer
Units requiring 380/440 volts, 3 Phase primary electric supply. The heater pads shall be
standard size as per the Table-1.
7.0 BASIC REQUIREMENTS TO CARRYOUT PWHT AND THE METHODOLOGY:
Procedure ITIS/NDT/PWHT/01
Revision 04
Date 09-Aug-2016
POST WELD HEAT TREATMENT & PREHEATING PROCEDURE Page Page 10 of 26
7.1.Thermocouples Description:
a. The thermocouples shall be type ‘K’ i.e. nickel-chromium / nickel - aluminum type
in accordance With BS 1041. Part - 4. The thermocouples should have initial
calibration check.
b. All the thermocouple wires should have valid certificate of conformance with a
tolerance of +/- 0.75% between the temperatures ranges 4000 C to 8000 C.
c. The general ‘K’ type thermocouple wire shall have dimension 1/0.71 mm of Ni-
Cr/Ni-A1. The positive & negative charges should be marked properly.
7.2. Compensating Cable:
The cable recommended shall be twin type wire PVC coated copper/constant connection
to thermocouple, with proper plug & socket. Copper constant compensating cable shall
be used for connecting thermocouple wires & the temperature recorder. Connect the
copper lead (+ve) to nickel-chromium conductor (non magnetic yellow) and the
constantan lead (-ve) to the nickel – Aluminum conductor (magnetic red).
7.3. Color Coding of the Cables:
Color of the J or K cables used, shall be BS 1041. Part – 4 or Either ANSI or IEC as quoted
below:
ALLOY COMPOSITION MAXIMUM T/C
GRADE IEC 584-3 COLOR ASTM/ANSI E-320
TYPE (+VE) BS1843 DIN-43714
(-VE) LEAD TEMPERATURE CODING COLOR CODING
LEAD RANGE
IRON CONSTANTAN
J Fe Copper-Nickel -210 to 1200°C
(Magnetic) Cu-Ni +black/ -white +white/ -red
Jacket: black Jacket: black
+brown/ -blue
Nickel- Nickel- Jacket: Red
K Chromium Aluminum Ni- -270 to 1372°C
Ni-Cr Al (Magnetic) +green/ -white +red/ -green +yellow/ -red
Jacket: green Jacket: green Jacket: yellow
+White/ -blue
Jacket: Red
Procedure ITIS/NDT/PWHT/01
Revision 04
Date 09-Aug-2016
POST WELD HEAT TREATMENT & PREHEATING PROCEDURE Page Page 11 of 26
• If multiple heating zones are used being not monitored by a primary TC, then
additional requirements of TC should be done.
2. For localized PWHT of vessels it should be monitored using a minimum of four sets
of thermocouples, with each set having one TC on the inside & outside surfaces. The
positioning of each set shall be done on the weld center line at 900 spacing around
the vessel circumference. We may require additional TC if multiple heating zones
are used & when it is not monitored by a primary set of TC.
As per client’s requirement or as per code additional thermocouples shall be fixed
to confirm hot zone or gradient limitation.
3. Thermocouple extension cable should be necessarily of iron-constantan
compensating cable with connection through plug & socket as Copper lead (+ ve) to
nickel chromium (Non Magnetic) Constantan lead (-ve) to nickel aluminum
(Magnetic).
Procedure ITIS/NDT/PWHT/01
Revision 04
Date 09-Aug-2016
POST WELD HEAT TREATMENT & PREHEATING PROCEDURE Page Page 12 of 26
• Wall thickness
• Gradient requirement
• Site conditions
In all cases the minimum requirement shall be two (2) layers for densities (80Kg / m3
& 96Kg /m3).
d. Insulation shall be fixed using black annealed iron wire taking care, not damaging or
cutting into the insulation.
e. By following proper PWHT cycles, the item or the particular joint shall be completed
& the cooling rate should be controlled under insulation.
7.6. Temperature Recorders & Calibration:
a. Temperature Recorders shall be potentiometric, self-compensating type, calibrated in
degrees with respect to a Nickel Chromium/Nickel Aluminum thermocouple, Type
K.
b. Temperature recorders shall be calibrated every Three months or after major repair.
The calibration certificate should be kept & a sticker should be attached on the
instrument. Instruments used for calibration purpose shall be having certification
Procedure ITIS/NDT/PWHT/01
Revision 04
Date 09-Aug-2016
POST WELD HEAT TREATMENT & PREHEATING PROCEDURE Page Page 13 of 26
h. There is no contingency plan for the equipment, therefore any failure must be brought
to the attention of the Saudi Aramco inspector.
Specification of cable: 2 x 13/0.2 mm Cu/Con compensating cable type V, with color code
as per BS1843.
c. If multiple heating zones are used being not monitored by a primary T/C, then
additional requirements of T/C should be done.
After the completion of Post Weld Heating remove the thermocouples & ground smoothly the
area, to achieve sound metal. As per the specification / instruction of the inspector the areas
are to be examined by MT or PT after grinding.
9.0 PREHEATING:
9.1 Preheat shall be in accordance with the ASME B31.3 and SAES-W-011. For materials not
covered by the Code or this Standard, the preheat and shall be as specified in the approved
welding procedure.
Procedure ITIS/NDT/PWHT/01
Revision 04
Date 09-Aug-2016
POST WELD HEAT TREATMENT & PREHEATING PROCEDURE Page Page 15 of 26
9.2 The minimum preheat shall not be less than the greater of the following:
a) 10°C
b) The required or recommended preheat listed in ASME B31.3.
c) The preheat listed in Standard Drawing for carbon steel materials (all ASME P-No. 1
materials, including API grades up to and including X60).
d) For steels with specified minimum yield strengths above 60 ksi, (including API grades X65
or greater) or for materials not listed as an ASME P-Number, the preheat shall be
determined by Consulting Services Department and shall be as specified in the approved
welding procedure. Special applications may require special weld ability tests to evaluate
the preheat temperature.
9.3 If a weld joint is wet or has surface moisture or condensation, it shall be dried by heating
for a distance of 100 mm from the weld joint and shall be warm to the hand before welding
unless a greater preheat temperature is required.
9.4 Temperature--indicating crayons, thermocouples, or calibrated contact pyrometers shall be
used to measure preheat and interpass temperatures. Temperature-indicating crayons shall
not be used for any weld joint that is to be coated or that will have a heat-shrink sleeve
installed on it.
9.5 The preheat temperature shall be established over a minimum distance of 75 mm on each
side of weld.
9.6 If the wall thickness exceeds 25 mm and preheating is to be done from the same side as
the welding, then the heat source shall be removed for 1 minute to allow for temperature
equalization prior to measuring the temperature
9.7 Minimum numbers of equally spaced recording thermocouple (T/C), which are required
for preheat shall be as follows:
9.7.1 For pipes having diameter of 12 Inch (305mm) or less: 1T/C on each side of the
weld.
9.7.2 For pipes having diameter above 305mm (12 inch) - 2T/C on each side of the
weld.
9.8 If multiple heating zones are used being not monitored by a primary T/C, then additional
requirements of T/C should be done.
Procedure ITIS/NDT/PWHT/01
Revision 04
Date 09-Aug-2016
POST WELD HEAT TREATMENT & PREHEATING PROCEDURE Page Page 16 of 26
After the completion of Preheating remove the thermocouples & ground smoothly the
area, to achieve sound metal. As per the specification / instruction of the inspector the
areas are to be examined by MT or PT after grinding.
9.11 Preheat Temperatures:
Notes:
Base metal Minimum preheat Nominal wall Rate of heating rate of cooling
temperature thickness
P. No
2220C/Hour/1 2220C/Hour/1
P.NO-04 ALL
1490C inch thickness inch thickness
2220C/Hour/1 2220C/Hour/1
P-5A,5B ,5C ALL
1770C inch thickness inch thickness
2. Maximum heating and cooling rates shall not exceed that required by ASME Section
VIII UCS-56 (d) (2) and (5) and SAES W -011 Par 13.4
10. INTERRUPTION
10.1 An interruption to the heat treatment process is defined as failure by one or more
thermocouples to maintain the specified heating, cooling rates, temperature differentials or to
achieve the soak temperature. This may be the result of power loss, equipment failure or
operator error.
10.2 Once the out of specification thermocouple trace(s) has (have) been identified, the heat
treatment cycle shall placed into hold whilst investigation takes place to determine if the fault
can be found and remedial work carried out safely with a minimum of delay.
Procedure ITIS/NDT/PWHT/01
Revision 04
Date 09-Aug-2016
POST WELD HEAT TREATMENT & PREHEATING PROCEDURE Page Page 17 of 26
10.3 Once the remedial work has been carried out, and provided it is safe to do so, the heat
treatment may be restarted. A check shall be made of the temperatures of all controlling
thermocouples at the time of re-starting. The temperature of any thermocouple that is below
the set point shall be raised at a rate no greater than that specified by the code or specific
procedure until the overall temperature differential is within acceptable limits.
10.4 If the interruption occurs during the soak period, then the temperature of any
thermocouple which falls below the minimum specified soak temperature shall be re-
established at a rate no greater than that specified by the code or specific procedure. The
holding time shall be extended to ensure that all thermocouples have recorded temperatures
within the soak range for the minimum soak time.
10.5 In the event that the heat treatment chart indicates that any specified overall temperature
differentials are increasing, and will exceed the value given in the code or specification
document, then the heating or cooling rates shall be reduced or the process put on hold, and
Action taken as per paragraph 10.2 herein. Where differentials exceed the specified value a
note shall be made on the heat treatment chart and the Contractor advised. If the differentials
cannot be corrected the Contractor is to be consulted as to whether or not the heat treatment is
to continue.
10.6 If remedial work cannot be carried out in time to effectively restore the heat treatment
cycle, the process shall be aborted and the Contractor advised. The heat treatment shall be re-
started at another time.
10.7 In the event of an interruption to the cooling cycle, which cannot be rectified, that results
in the maximum cooling rate being exceeded, the heat treatment shall be completed, and the
matter brought to the attention of the Contractor. If a concession is not granted, then the heat
treatment will be repeated by agreement with the Contractor.
10.8 A note of the interruption, and the time at which it occurred shall be made on the heat
treatment chart and brought to the attention of the Contractor.
10.9 If the interruption results in a heat treatment cycle that does not comply with the
specification or code requirements, a non-conformance report shall be raised.
Procedure ITIS/NDT/PWHT/01
Revision 04
Date 09-Aug-2016
POST WELD HEAT TREATMENT & PREHEATING PROCEDURE Page Page 18 of 26
The heat treatment cycle chart shall be treated as the proof & record for any heat treatment
completion. Technicians will fill out the record sheets of Heat Treatment prior to start of any
PWHT and client shall authorize specifications complying with governing code.
On completion, the record of the Heat Treatment along with client, as minimum the following
information will be provided:
1. Client Identity
2. Contract /Job Identity
3. Specification Details
4. Spool number, diameter and weld numbers
5. Material specification
6. Thermocouple locations
7. Heating and Cooling Rate
8. Soaking (holding) time
9. Technician name
10. Location map of particular vessels
11. Date and Chart speed
Chart will be submitted to the Records shall be maintained for a maximum of three months with
all Charts & documents.
Procedure ITIS/NDT/PWHT/01
Revision 04
Date 09-Aug-2016
POST WELD HEAT TREATMENT & PREHEATING PROCEDURE Page Page 19 of 26
13. TABLE 1
Typical Application
For Ceramic Heating Elements
Wx L Volts KW
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
ITEM RE-INSP
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A
No. DATE
B
Thermocouple Requirements - Specified in Procedure
If localized PWHT is used, the following
minimum number of equally spaced recording
thermocouples (T/C) shall be used:
SAES-W-011,
B1 a) Pipe diameter of 305 mm or less: 1 T/C.
Para. 13.13
b) Pipe diameter above 305 mm up to and
including 610 mm: 2 T/C.
c) Pipe diameter above 610 mm: 4 T/C.
Additional TCs are required if multiple heat
SAES-W-011,
B2 control zones are used, in which a control zone
Para. 13.13
is not monitored by any of the primary T/Cs.
Thermocouples and a calibrated temperature
SAES-W-011,
B3 chart recorder shall be used to provide an
Para. 13.14
accurate and legible record of all PWHTs.
All charts shall be marked with the date and
SAES-W-011,
B4 sufficient information to uniquely identify the
Para. 13.14
joint/component being heat treated.
Multipoint chart recorders clearly
differentiate/identify each channel /point by use SAES-W-011,
B5
of different colored inks or automatic # Para. 13.14
stamping.
Temperature recorders shall be calibrated every
SAES-W-011,
B6 three months & a current calibration sticker shall
Para. 13.15
be maintained on the recorder.
Calibration frequency may be extended to 12*
months with PID approval if documented SAES-W-011,
B7 calibration checks for recorder demonstrate Para. 13.15 &
acceptable accuracy for a suitable period. *Sch Sch Q, M&TE
Q M&TE limit.
Only Type K (Chromel-Alumel) or Type J (iron-
Constantan) TCs are permitted. All extension,
compensating, and jumper cables in the SAES-W-011,
B8
measurement or control circuits shall be the Para. 13.16.1
specified TC wire or matching extension wire,
i.e., KX or JX, as appropriate.
Procedure ITIS/NDT/PWHT/01
Revision 04
Date 09-Aug-2016
POST WELD HEAT TREATMENT & PREHEATING PROCEDURE Page Page 25 of 26
REFERENCE DOCUMENTS
1. SAES-W-011, Welding Requirements for On-Plot Piping, (1 January 2018)
2. ASME B31.3, Process Piping (2013 Edition)
Contractor / Third-Party Saudi Aramco
Construction Representative* PMT Representative
Procedure ITIS/NDT/PWHT/01
Revision 04
Date 09-Aug-2016
POST WELD HEAT TREATMENT & PREHEATING PROCEDURE Page Page 26 of 26