City of Madison - Microgrid Feasibility Study - Final Report
City of Madison - Microgrid Feasibility Study - Final Report
(a) does not make any warranty, express or implied, with respect to the use of any information,
apparatus, method, or process disclosed in this document, or represent that such use does not
infringe upon privately owned rights;
(b) does not assume any liability incurred with respect to or damages arising out of the use of
any information, apparatus, method, or process disclosed in this document.
Acknowledgements
We would like to thank City of Madison staff for their contributions to this report, and Arizona
State University and Command Consulting staff for providing feedback. We also thank Madison
Gas and Electric for data contributions.
Disclosure: “This material is based upon work supported by the U.S. Department of Energy’s
Office of Energy Efficiency and Renewable Energy (EERE) under the State Energy Program
Award Number DE-EE0008669.”
Full Legal Disclaimer: “This report was prepared as an account of work sponsored by an agency
of the United States Government. Neither the United States Government nor any agency
thereof, nor any of their employees, makes any warranty, express or implied, or assumes any
legal liability or responsibility for the accuracy, completeness or usefulness of any information,
apparatus, product or process disclosed, or represents that its use would not infringe privately
owned rights. Reference herein to any specific commercial product, process, or service by trade
name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its
endorsement, recommendation or favoring by the United States Government or any agency
thereof. The views and opinions of authors expressed herein do not necessarily state or reflect
those of the United States Government or any agency thereof.”
i
ACRONYMS
AVERT Avoided Emissions and Generation Tool
BESS battery energy storage systems
DER distributed energy resource
DOE Department of Energy
EIA Energy Information Administration
EPA Environmental Protection Agency
EV electric vehicle
HVAC heating, ventilation, and air conditioning
kW kilowatt
kWdc direct current kilowatt
kWh kilowatt-hour
MPGe miles per gallon gasoline equivalent
MWh megawatt-hour
NREL National Renewable Energy Lab
NPV net present value
NOX nitrous oxides
PSC Public Service Commission
PM2.5 particulate matter 2.5
SO2 sulfur dioxide
PV photovoltaics
V2G vehicle to grid
1
EXECUTIVE SUMMARY
This study details the work of Slipstream in partnership with the City of Madison to assess the
feasibility of establishing a microgrid at 1600 Emil St and 1501 W Badger Rd Streets, a site
housing Streets West and Engineering Operations. This site provides key functions during
emergencies including police and fire support functions, snow removal, road maintenance,
sewer maintenance, and mapping and situational awareness services.
In addition to hosting critical infrastructure, the site already has several distributed energy
resources which make it an ideal candidate for a microgrid. Namely, there are existing solar PV
arrays totaling 209 kW, with an additional 219 kW planned for installation in 2022. There are
also two back-up generators on site. Another key opportunity is the vehicle fleet; the site
currently has over 230 vehicles, a fleet which the city plans to convert to 100% electric vehicles
over the next five to 15 years.
The goals of the study were to evaluate integrating these components into a microgrid that
would be cost-effective, increase resilience, and contribute to the City of Madison’s emissions
reduction goals. The specific research questions addressed were:
1. What are potential battery energy storage systems (BESS) configurations to meet needs
at the site today?
2. As the vehicle fleet electrifies, how will those configurations perform?
3. What are the associated costs and benefits of each configuration?
The scenarios included for analysis were based on the expected timeline, charging needs, and
critical charging profile of the fleet. Fleet electrification was divided into two phases (Phase 1
and Phase 2) depending on the expected availability of commercial versions of existing fleet
vehicles. In addition, given the limited space available at the site for a BESS, the maximum
BESS which can be accommodated was used as an upper bound. These two factors were used
to develop four scenarios – fleet electrification phases 1 and 2 with no constraint on the battery
size, and the same phases with a BESS specified at the upper limit of 10 MWh.
RESULTS OVERVIEW
Table 1 shows summary results for the base case and the four scenarios. As the load increases
with no battery constraint, (moving from Phase 1 to Phase 2), the main difference in system
operation is that more solar is used on site, reducing exports. When the maximum battery size
is specified, the solar exports reduce further, and resiliency hours increase.
However, considering the emissions reduction and resiliency benefits puts these high upfront
costs in context. The systems with a large battery show the greatest emissions reduction due to
the ability of the BESS to use power from the grid at times when grid emissions intensity is
lowest. In the case of the Phase 2 BESS scenario, the large load amplifies the impacts of the
emissions reduction optimization to show the greatest benefit. By including the value of
2
emissions savings, the Phase 2 BESS scenario achieves a positive NPV despite having the
highest upfront costs.
Phase 1 Phase 2
Scenario Base case Phase 1 Phase 2
BESS BESS
Battery capacity (kW) 0 47 48 410 1,170
Battery size (kWh) 0 61 63 10,000 10,000
Generator energy
533 672 0 719 300
(kWh)
Solar exported (kWh) 327,213 269,206 233,409 127,189 124,654
Initial capital costs $0 $60,000 $61,600 $4,197,600 $4,786,500
Total cost $122,200 $208,600 $211,000 $7,503,000 $8,210,400
Total energy
$319,600 $274,400 $233,500 $388,900 $282,400
benefits
Valuing resiliency causes an increase in the NPV across scenarios, with the most significant
increase seen in the Phase 1 BESS scenario, where the 10 MWh battery provides the greatest
average resiliency. In the Phase 2 BESS scenario, the significant increase in critical load
causes a relative reduction in resiliency benefits.
Several recommendations and next steps were developed during the feasibility study,
summarized below.
RECOMMENDATIONS
Given that the site is currently operational with several major projects underway or in planning
stages, several recommendations address the existing infrastructure. First, the City should
develop a plan to electrically interconnect the three buildings at the site. This
interconnection is a key assumption of the analysis, as it enables the buildings to share loads
and resources, enhancing the benefits that each asset can provide. Second, as new solar PV
arrays are being installed, microgrid-ready inverters should be specified. Doing so will add
3
an incremental cost to the inverters but will enable them to integrate seamlessly with the BESS.
In addition, several of the existing inverters may also require upgrades or additional hardware to
be able to integrate with the planned microgrid controller. Finally, given the important role that
the BESS will play and the reality that space on site is limited, we recommend performing a
detailed site survey to establish a code-compliant BESS installation location.
Several other recommendations for general microgrid planning were developed during the
project. First, it is important to prioritize data collection and start early. The quality and
quantity of primary data collected directly impacts the relevance and robustness of the results
for the proposed microgrid. Key data to collect should cover the building energy loads (both
electric and natural gas), vehicle mileage and usage patterns, historical operating and
maintenance costs, and utility rates.
To achieve the city’s emissions reduction goals, nearly all natural gas end uses will need to be
converted to electric. This will add significant electric load, requiring larger batteries and PV
arrays to meet critical demand at each site where a microgrid is implemented. Thus, it is
important to develop a detailed plan for electrification of natural gas end uses to
understand the impact on any proposed microgrids.
CONCLUSION
A microgrid at the Badger Rd and Emil St site can help meet several City of Madison goals:
increase use of renewable energy, improve resiliency, reduce pollution and carbon emissions,
and reduce energy costs. The results in this study highlight the various ways that the benefits of
a BESS can be evaluated to justify the significant upfront cost, especially as electrification of the
vehicle fleet increases the electric load that the microgrid must be able to meet.
Key barriers to implementation include the high cost of a BESS sufficiently sized to meet the
needs of the site, and the fact that the total solar PV capacity on site is limited. Load
management strategies, including smart charging and V2G, could be used to carefully manage
the critical load and increase resiliency despite the limited PV capacity.
When considering the total cost of the system, it is critical to include resiliency and emissions
benefits. With a BESS, the microgrid provides significant resiliency benefits when planning for a
major outage on an annual basis. The BESS also provides environmental and health benefits by
enabling the facility to use less power from the grid during times when grid emissions factors are
4
highest. Accounting for the value of these benefits significantly increases the NPV of the
proposed microgrid.
Based on these takeaways, we recommend that the City of Madison pursue a microgrid at the
site with a BESS. Given that the fleet will be electrified over time, we recommend installing a
small modular BESS, with the option to expand over time. This will enable the site to
immediately take advantage of the benefits of a microgrid, while enabling staff to study the real-
world performance and to make informed decisions about future expansions.
5
1 INTRODUCTION
As climate change normalizes extreme weather events, grid and community resiliency are put to
the test. To respond to this growing need, the City of Madison is actively planning its resiliency
efforts and increasing the resilience of critical city infrastructure, implementing renewable
energy projects, and pursuing aggressive emissions reduction targets. With funding from the
Wisconsin Public Service Commission (PSC) and in partnership with Slipstream, the City of
Madison assessed the feasibility of establishing a microgrid at a site which provides key
functions during emergencies including snow removal, road maintenance, sewer maintenance,
police and fire support functions, and mapping and situational awareness services. This site
also hosts over 200 vehicles, a fleet which the city plans to convert to 100% electric vehicles
over the next five to 15 years.
The goals of the study were to evaluate integrating existing and planned distributed energy
resources (DER) at the site into a microgrid that would cost-effectively provide for electric
vehicle (EV) charging while increasing resilience for the city of Madison by providing back-up
power at the site. Existing assets include several solar photovoltaic (PV) arrays and a natural
gas generator. Additional PV arrays and a battery energy storage system (BESS) are planned
for the near future.
The analysis considered the ability of the microgrid to provide continuous backup power for
critical loads at the site while cost-effectively enabling EV charging. The specific research
questions were:
1. What are potential BESS configurations to meet needs at the site today?
2. As the vehicle fleet electrifies, how will those configurations perform?
3. What are the associated costs and benefits of each configuration?
The report starts by providing project background and details on the City of Madison and the
site. We then describe the methodology and results of the microgrid planning. The results
highlight the tradeoffs between different system configurations to inform future microgrid
planning, but a more in-depth analysis would be needed if the city decided to proceed with a
microgrid installation. We provide a checklist of microgrid considerations for the site, as well as
general recommendations for other sites that they city may consider converting to microgrids in
the future.
1.1 BACKGROUND
The City of Madison is the second-largest city in Wisconsin, home to 255,000 people. The city
has a goal for city operations to be emissions neutral by 2030. As part of that goal, Madison has
been installing solar PV arrays at several of its buildings.1 Most of Madison, including the
proposed microgrid site, is served by Madison Gas and Electric (MGE) an investor-owned utility.
6
The microgrid study focused on three adjacent city-owned facilities that already have solar PV
and back-up generators on-site, shown in Figure 1.
Figure 1. Site layout for Streets West and Engineering Operations showing proposed changes.
The facilities house Madison’s streets division and engineering operations and are city
headquarters for several critical government functions: emergency support services, snow
removal, road maintenance, and sewer maintenance. The facilities currently have 209 kilowatts
(kW) of solar PV installed, with an additional 200 kW of additions planned through 2023, which
would maximize the roof capacity at the site. Most of the inverters are compatible with SunSpec
Modbus and could likely be integrated with any future microgrid. The site also has a newer 300-
kW natural gas generator and an older 100-kW diesel generator, which is near end-of-life.
The site houses over 230 vehicles and gas-operated machines, including both heavy- and light-
duty vehicles. The City of Madison plans to electrify as much of its fleet as possible over the
next 10 years. This study analyzed how the expanded EV fleet with managed charging would
impact the performance and configuration needs of the microgrid, both while grid connected and
during outages.
2 METHODOLOGY
We conducted the feasibility study with a set of four analysis stages and ongoing stakeholder
engagement. We started by identifying tools to evaluate microgrid system configurations, costs,
7
and benefits. We evaluated seven tools and their ability to optimize assets and dispatch to meet
the critical functions of the microgrid. We then collected energy, cost, technology, and site data
to use as inputs in the analysis. Finally, we ran several initial scenarios through the selected
analysis tool and compared the high-level results to identify a set of alternatives for the site. The
final step was to summarize the associated costs and benefits for the final scenarios.
Figure 2 illustrates the four phases of analysis. The following section provides additional detail
on the tool selection process and the data inputs utilized for the analysis.
• What are the key functions vehicle fleet should be able to provide during outages or
emergency events, and which vehicle types are critical to this?
• What near-term plans does the facility have for adding, upgrading, or modifying DERs?
• How does this site fit into larger city goals for renewable energy? Are there specific
emissions or renewables targets the site needs to meet?
In addition to the staff stakeholder group, we also engaged the local utility in discussions.
Involvement of the utility was essential to understand any size restrictions, applicable financial
rates and benefits, and the utility’s interest in co-ownership models.
2Krah, “Behind-the-Meter Solar + Storage Modeling Tool Comparison”; Tozzi and Jo, “A Comparative
Analysis of Renewable Energy Simulation Tools.”
8
when evaluating each tool. The features that were evaluated and the desired criteria are shown
in Table 2. Features are listed roughly in order of importance to the analysis.
Table 2. Microgrid analysis tool critical features and criteria for each site.
Next, we reviewed the literature about these tools and consulted documentation and user
forums to determine whether each tool met these requirements. We qualitatively analyzed each
tool to determine if the requirement was fully met, partially met, or not met, represented through
filled, half-filled, and unfilled Harvey balls, respectively (Table 3). In some cases, we could not
determine if a requirement was met, or we ended our evaluation after identifying that a tool did
not meet the more critical requirements. In these cases, the associated cell in the matrix is left
blank.
Table 3. Critical feature matrix for the eight microgrid analysis tools considered.
DER-
Critical features REopt HOMER DER-CAM SAM ESyst MDT
VET
Back-up generator ◐ ◐ ● ● ◯ ◯ ◯
Resiliency ● ● ● ◐ ◯ ◯ ●
Existing PV ● ● ● ● ◐ ◐ ◐
Custom load profile ● ● ● ◐ ● ● ◐
Load growth ◐ ◯ ● - ● - -
BESS modeling ● ◐ ● ◐ ● ● -
Hourly results ● ● ● ◯ ● ◯ -
Optimization ◐ ● ● ● ◐ ◯ ●
License ● ● ◯ ◐ ● ◐ ◐
Based on our analysis, we decided to proceed with REopt due to its ability to meet each of the
priority features and the open-source license and API (application programming interface,
allowing the use of a scripting language to programmatically run scenarios). Figure 3 illustrates
9
the key inputs and outputs from REopt.3 The user inputs the technology of interest, any
resiliency or environmental goals, energy cost data, and a custom load profile. The tool then
finds the least-cost option that satisfies the goals and provides system size, system financial,
and resiliency outputs. The least-cost option is based on net present value (NPV) which is
calculated over a 25-year lifetime.
To model resiliency, the tool requires the user to input the length and timing of an outage the
optimal system should be able to withstand (e.g., June 19 from 1 to 5 pm). The tool then finds
the least-cost option system that can withstand an outage at that time while still providing the
load required. After the tool finds the least-cost option for that specific constraint, it evaluates
resiliency (or length of outage the system could sustain) at each hour of the year.
The coincident peak demand for the main site was 173 kW in 2021. With the library included,
the peak demand would have been 184 kW.
10
Table 4. Summary of load and solar attributes by building.
We confirmed that all installed and planned inverters are compatible with SunSpec Modbus,
either natively, with a firmware upgrade, or with an external hardware upgrade. This will be a
minimum requirement for integration with any future microgrid controller, enabling the controller
11
to utilize the voltage regulation, power factor management, and export limiting capabilities of
each inverter.4 However, all the existing inverters are grid-tied, meaning they require a stable
grid connection to produce power. While a BESS could likely provide a stable enough signal to
support operation of these inverters, it may be necessary to include multi-mode inverters (either
through expansion or replacement) which would be capable of coordinating with a microgrid
controller to establish a grid signal during outages.
Due to the total planned capacity, the site will not be eligible for net metering (MGE’s limit is 100
kW) but will be able to sell excess solar generation to the grid at wholesale rates.
We used this timeline and the inventory of current vehicles and mileage records to split
electrification into two phases: Phase 1 vehicles are ones that will be electrified in the near-term
(5 to 10 years) and Phase 2 vehicles are ones that will be electrified in the long-term (10+
years). Phase 1 included all passenger vehicles, pickup trucks, and a small set of miscellaneous
equipment (117 vehicles total), while Phase 2 included all heavy-duty vehicles and the rest of
the miscellaneous equipment (an additional 105 vehicles). Eight electric vehicles are already
housed at the site. The inventory (along with expected kWh needed to power each vehicle type)
is in Table 6. “Refuse truck” includes seven Vactor trucks in addition to traditional refuse trucks.
The MPGe ratings by vehicle type are from AFLEET.5 For the miscellaneous equipment, we
simply used a conversion from gallons of gasoline to kWh, as information about the efficiency of
most equipment types was not readily available. While this is a conservative estimate (as
electrified versions of each type of equipment are likely to be more fuel efficient), fuel use for
this equipment is less than 5% of the annual total for the fleet, and thus is not likely to
significantly affect the analysis. The total vehicle counts and expected energy consumption by
phase is summarized in Table 7. Note that the totals shown in Table 7 do not exactly match the
sum of the values in Table 6, as they are instead derived from the simulation results described
in the following section.
12
Table 6. Fleet electrification phases, vehicle quantities, and energy consumption – by vehicle type.
Vehicle type MPGe Quantity Annual mileage (per Annual kWh (total)
vehicle)
Phase 1
Pickup 57.3 29 9,015 153,758
Pickup (large) 37.8 29 15,000 387,817
SUV 69.5 6 7,247 21,084
Sedan 106.2 15 4,583 21,815
Van 29.1 13 13,500 203,242
Misc. truck 16.0 16 12,000 404,400
Misc. equipment - 9 - 7,229
Phase 2
Dump truck 13.7 18 96,300 236,884
Refuse truck 4.8 14 322,000 2,260,708
Misc. equipment - 73 - 428,047
Table 7. Fleet electrification phases, vehicle quantities, and energy consumption – total.
Load profile EVs Additional kWh Total kWh Load growth vs baseline
Base building load 8 556,000 556,000 -
Phase 1 117 1,231,000 1,787,000 323%
Phase 2 105 3,104,000 4,891,000 985%
TOTAL 230 4,891,000 - -
For charging strategies, we assumed a minimum power charging strategy (where vehicles
charge slowly for the duration of time while they are off shift) for most vehicles, with an
immediate charging strategy for 10% of vehicles to cover those which must be always close to a
full charge to accommodate city operational needs. Once the fleet types and charging strategies
were selected, we ran the code (included with the publication) using the vehicle quantities and
average efficiencies and scaling the annual vehicle mileage of the model fleets to match the
actual fleet. Figure 4 shows the resulting hourly charging profile for the two phases.
13
Phase 1 Phase 2
1000
900
800
Demand (kW) 700
600
500
400
300
200
100
0
0 2 4 6 8 10 12 14 16 18 20 22
Hour
Figure 4. Electric vehicle average hourly load profiles: Phase 1 and 2 electrification.
There remains uncertainty around the final load profile, as the fleet electrification schedule is still
being developed, and in some cases fully electric replacements are not yet available for
vehicles in the fleet. These assumptions are considered a best guess and have been provided
to City staff to serve as a baseline for updating the load profiles as the electrification schedule is
updated.
Ultimately, we applied Clean Coalition’s VOR123 methodology of define Tier 1, Tier 2, and Tier
3 critical loads.6 While this methodology was developed for categorizing facility loads, our
stakeholder discussions led to the conclusion that there was no clear way to determine which of
the vehicles should be considered critical in an annual model given the varied nature of
emergencies the City needs to anticipate and the diversity of vehicles, and their functions,
located at the site.
Instead, stakeholders decided to divide the entire EV charging load into three tiers. Given the
robustness of the VOR123 methodology for facility loads, we determined that the same criteria
and general guidelines could be applied to a vehicle fleet in the absence of available data and
studies on this specific topic. As plans for completing the microgrid go forward, the city will need
14
to embark on a detailed study of how different vehicles are used in different types of
emergencies to be able to properly size and operate the microgrid.
Under the VOR123 methodology, 10% of all load is considered critical or life sustaining (Tier 1),
15% is considered priority (Tier 2), and the remaining 75% is considered discretionary (Tier 3).
Given the nature of the facility and the current requirement to provide 100% backup power to
the facility loads during outages, we assume that all Tier 1 and 2 vehicle functions must also be
available during outages.
During phase 1 of vehicle electrification, this need could be met with a mix of the EVs and
ICEVs which would be operational at that point. Thus, we assume that 10% of electric charging
needs would be critical, with the remaining 15% served by ICEVs. For phase 2, all the Tier 1
and 2 needs must be met with EVs, as no ICEVs will remain in the fleet at this time – thus 25%
of charging demand would be critical at this point. On average, each vehicle in the fleet travels
44 miles per day. With critical charging limited to 25%, every vehicle would be able to travel 11
miles per day, or 25% of vehicles could travel 44 miles per day.
Note, this does not directly translate to the fleet only being able to operate at 15% or 25%
capacity, as each vehicle in the fleet would have a battery capacity able to sustain more than
one shift of normal operations given current mileage patterns. Nevertheless, as the demand for
operating vehicles may increase during an emergency, it will be important to monitor the state of
charge of each vehicle to prioritize how each is operated and charged, especially during
extended power outages.
Using Madison’s fleet inventory and annual mileage records, combined with average fuel
economy ratings from the Department of Energy’s Alternative Fuels Data Center 7, we
calculated that the fleet of vehicles at the site uses over 240,000 gallons of gasoline and diesel
fuel per year. Using an average fuel price over the last 12 months of $3.72 per gallon,8 this
amounts to over $900,000 in annual fuel expenditure. In contrast, our analysis indicates that if
fully electrified, the fleet would use roughly 4,125,000 kWh per year. Even at the peak electric
rate ($0.104 per kWh, see Section 2.3.5), this represents a cost of just under $430,000 per year,
for a savings of greater than 50% annually.
15
A recent report from Argonne National Labs indicates that on average, electric vehicles (EV)
have annual maintenance costs roughly 40% lower than internal combustion engine vehicles
(ICEV).9
Routine outages are more common and are shorter in length and major outages occur less
frequency but are often 1 to 5 days in length. While the data tells us that outages occur year-
round, the Department of Energy reports that in Wisconsin, June is month with the highest
frequency of outages.12 Based on this data, we utilize outages in June as the constraint in each
of the scenarios and tested varying outage lengths.
9 Burnham et al., “Comprehensive Total Cost of Ownership Quantification for Vehicles with Different Size
Classes and Powertrains.”
10 MGE, “2021Corporate Responsibility and Sustainability Report.”
11 US EIA, “Electric Power Monthly - U.S. Energy Information Administration (EIA).”
12 US DOE, “State of Wisconsin Energy Sector Risk Profile.”
13 Anderson, Hotchkiss, and Murphy, “Valuing Resilience in Electricity Systems.”
14 Rickerson, Zitelman, and Jones, “Valuing Resilience for Microgrids: Challenges, Innovative
16
include willingness-to-pay surveys and tools to help facilities develop bottom-up monetary
estimates for lost time spent on critical functions.
There are limited studies that quantify the more human benefits from microgrids. The best
reference for these values is a study from Lawrence Berkeley National Lab that includes
estimates from willingness-to-pay studies for the residential and commercial sector.15 Table 9
illustrates the study’s findings on the value of resiliency across outage lengths and sectors.
For our purposes, we utilize the residential values as the commercial values assume lost
productivity from commercial or industrial processes. The main limitation is that the values do
not extend past outage lengths of 16 hours.
Table 10. BESS system costs – upfront, operations and maintenance and replacement.
Table 11 lists the utility and wholesale rates utilized in the analysis (the table shows a simplified
summary as the actual rate schedules include three different peak periods). Under MGE’s rate
structure, the most cost-effective option at the site is the time-of-day rate, which the site is using
currently. The peak demand for the site is currently less than 200 kW, but as the fleet electrifies
the demand will increase above 200 kW, meaning that the rate will change from CG-4 to CG-2,
with higher demand charges and lower energy charges. As the limit for net metering is 100 kW
15 Sullivan, Schellenberg, and Blundell, “Updated Value of Service Reliability Estimates for Electric Utility
Customers in the United States.”
16 Ray, “Lazard’s Levelized Cost of Energy Analysis—Version 15.0”; Feldman and Margolis, “Fall 2021
17
and the planned capacity is nearly 500 kW, we utilized wholesale rates for sale of excess solar.
We also include the fixed demand charge to account for potential peak demand savings.
We assume a 2.5 percent escalation rate for operations and maintenance costs, a 2.3 percent
increase in electricity rates, and utilize a 3 percent discount rate.
To estimate the monetary impact of the emissions savings, we apply cost per ton estimates to
each. Table 12 lists the cost per ton for each of the major pollutants.19 The air quality pollutants
have significant costs per ton as the reduction in emissions has the potential to prevent
premature death, which is valued at roughly $9 million. The cost for each is assumed to
increased gradually over the analysis lifetime.
Social Cost of Carbon, Methane,”; Heo, Adams, and Gao, “The Estimating Air Pollution Social Impact
Using Regression (EASIUR) Model.”
18
2.3.7 BESS constraints
The site has limited space for a battery energy storage system – two 40-foot storage containers
are likely the largest which could be installed, which would support a 10 megawatt-hour (MWh)
system.20 For the analysis we allowed the BESS to be charged from the from the grid as
needed, to ensure sufficient energy availability for covering outages.
REopt constrains the BESS to a minimum state of charge of 20%, as discharging the battery
below 20% on a regular basis would reduce the lifespan.21
Lithium-ion batteries are available in a wide range of power to energy ratios,22 though in practice
the choices would be limited as these are dependent variables. However, to allow REopt the
flexibility to optimize both variables, we only applied a constraint to the energy variable.
Table 13. Natural gas generator parameters converted from diesel equivalents.
The other critical parameter for generator modeling is the minimum load. The generator was
constrained to run with a minimum load of 50%, as extended operation at lower loads can
decrease the life of the generator and cause maintenance issues, unplanned shutdowns, and
increased emissions.25
20 Fu, Remo, and Margolis, “2018 U.S. Utility-Scale Photovoltaics-Plus-Energy Storage System Costs
Benchmark.”
21 Anderson et al., “REopt Lite User Manual.”
22 Dechent et al., “ENPOLITE.”
23 US EIA, “British Thermal Units (Btu).”
24 US EPA, “AP-42.”
25 Jabeck, “The Impact of Generator Set Underloading.”
19
2.4 SCENARIO SELECTION
As an existing facility with existing distributed energy resources and a planned electric vehicle
fleet, several assumptions are already included in the base case, limiting the scenario selection
process. First, the three electric services which exist on the site will be merged into a single
service, allowing all buildings to share loads and resources. Second, the existing 300 kW
natural gas-burning generator will remain and is sufficiently sized to support the full building load
today (prior to additional fleet electrification). Third, the maximum solar capacity on site has
been calculated as 483 kW, all of which will be installed prior to any microgrid implementation
work.
With these constraints in mind, we analyzed four scenarios to understand the range of
possibilities for the facility as the fleet is electrified, compared to the base case with only the
existing facility load. As the fleet electrifies, a larger portion of the load will become critical to
operations during outages. Scenarios are modeled first with an upper limit on storage capacity,
then with a fixed capacity of 10 MWh, to understand the range of options between these two
extremes. Table 14 lists the inputs that vary between the scenarios. Note that the outage
coverage constraint is removed in Scenarios 3 and 4 as there is no solution possible within the
given constraints that would guarantee coverage of any power outage, due to the significant
increase in load.
20
3 RESULTS
Table 15 illustrates the performance outputs for the base case and the four alternative
scenarios. As the load increases with no battery constraint, (moving from Phase 1 to Phase 2),
the main difference in system operation is that more solar is used on site, reducing exports.
When the maximum battery size is specified, the solar exports reduce further, and resiliency
hours increase. However, the high capital cost of the battery causes the net present value
(NPV) to be negative. The NPV accounts for the costs and benefits of grid and solar energy
only; factors such as health impacts, carbon emissions, and avoided outage costs are not
included in these values. As the City of Madison reviews these results and plans for the future of
the microgrid at the site, these factors, along with BESS financing options, will need to be
considered.
The following sections will explore the financial and resilience impacts, additional system
benefits, and two sensitivities.
21
augmentation, oversizing, or modular implementation are also possible and may result in
reduced total costs.26
All energy and demand savings are provided by the optimized dispatch of the BESS. Export
credits are a function of how much excess solar generation is sold back to the grid.
As the size and capacity of the battery increase, the energy savings also increase, as the
battery can shift the times during which energy from the grid is used. Yet, this comes at the cost
of increased demand charges – the high battery capacity (over 400 kW) results in significant
demand charges when the battery must recharge from the grid.
26Shin and Hur, “Optimal Energy Storage Sizing with Battery Augmentation for Renewable-Plus-Storage
Power Plants”; EPRI, “Energy Storage, DER, and Microgrid Project Valuation: EPRI DER-VET Analysis in
Action.”
22
100%
Figure 6 illustrates how resilience varies over the course of the year. The figure uses data from
the Phase 2 BESS system, but the pattern is similar for all systems. Outage survivability is
greatest during the spring and summer due to increased solar availability and lowest during the
winter.
180
Average survivable outage (hours)
160
140
120
100
80
60
40
20
0
January April July October
23
societal benefits of reduced carbon and criteria pollutant emissions. This section will highlight
those benefits and show how the inclusion of the benefits impact NPV.
The lifetime savings for resiliency depend directly on the frequency of emergency events and
outages. As these outages are irregular in nature, there is no way to know how often the
outages will occur during the lifetime of the system. However, research does show that outages
are expected to increase in frequency as extreme weather events increase and as the grid
faces generation shortages.27
Table 17 lists the resiliency monetary value for different outage frequencies across the system
lifetime.
Utilizing the monetary values for an outage occurring every year, Table 18 shows the NPV for
each system when the value of resiliency is included. Valuing resiliency causes an increase in
the NPV across scenarios, with the most significant increase seen in the Phase 2 BESS
scenario, where the combination of the 10 MWh battery and the higher critical load provides the
greatest resiliency value..
27Robert Walton, “MISO Prepares for ‘worst-Case Scenarios,’ Heads into Summer with Insufficient Firm
Generation”; Rickerson, Zitelman, and Jones, “Valuing Resilience for Microgrids: Challenges, Innovative
Approaches, and State Needs.”
24
Table 18. Resiliency monetary value impact on net present value.
Phase 1 Phase 2
Base case Phase 1 Phase 2
BESS BESS
Total cost $122,200 $208,600 $211,000 $7,503,000 $8,210,400
Energy benefits $319,600 $274,400 $233,500 $388,900 $282,400
NPV without resiliency $197,400 $65,800 $22,500 -$7,114,100 -$7,928,000
Table 19 illustrates the emissions reductions in tons and the resulting monetary benefits.
Because the solar PV on the site is included in the base case, the emissions reductions are not
reflected in the results. The systems with a large battery show the greatest emissions reduction
due to the ability of the BESS to selectively use power from the grid. As climate and health
impacts are included in the objective, the system is optimized to use power from the grid at
times when grid emissions intensity is lowest. The Phase 2 BESS scenario shows the greatest
savings overall, as the larger load amplifies the impacts of the emissions reduction optimization.
Phase 1 Phase 2
Phase 1 Phase 2
BESS BESS
NOx savings (tons) 0.5 0.5 4.0 11.4
SO2 savings (tons) 1.4 1.4 14.2 34.1
PM2.5 savings (tons) 0.0 0.0 0.3 0.8
Health benefit $72,200 $73,500 $728,400 $1,796,700
Table 20 illustrates how adding the monetary value of the reduced air quality health impacts and
reduced carbon emissions impacts NPV. By including the value of emissions savings, the
Phase 2 BESS scenario achieves a positive NPV
25
Table 20. Carbon and criteria pollutant monetary value impact on net present value.
Phase 1 Phase 2
Base case Phase 1 Phase 2
BESS BESS
Total cost $122,200 $208,600 $211,000 $7,503,000 $8,210,400
Energy benefit $319,600 $274,400 $233,500 $388,900 $282,400
Resiliency benefit $2,248,900 $2,746,700 $916,200 $2,746,700 $6,633,300
NPV with resiliency $2,446,300 $2,812,500 $938,700 -$4,367,400 -$1,294,700
Figure 7. The site (red outline) showing the Library Service Center (blue outline) 500 feet east.
A sensitivity with the Library Service Center was run using the full building load during normal
operations, with only 10% of power supplied during critical operations (assuming only 10% of
26
the facility load would be considered critical, per the discussion of the VOR123 methodology in
Section 2.3.3.2). This adds 53 kW of solar PV capacity and 100,000 kWh per year of load.
Selected results of the analysis with the Library Service Center included are shown in Table 21.
The most significant result is for the Phase 1 BESS scenario, where the addition of 53 kW of
solar capacity allows for a significant increase in resiliency hours, resulting in a corresponding
increase in resiliency benefit. Because the library adds minimal additional load, and even less
critical load, the resiliency benefits outweigh the added energy and capital costs (the library
requires a minimal increase in the battery capacity).
Table 21. Results summary with the Library Service Center included.
By integrating the Library Service Center, the additional solar capacity can be used to increase
the NPV and resiliency, while the Service Center itself receives the benefit of backup power.
During an outage the library would not need to operate at full capacity, but continuous power for
the HVAC system would be beneficial as humidity-sensitive library materials are housed in the
building.
However, integration would likely be challenging to accomplish due to the distance and the likely
need for horizontal drilling to provide an electrical connection. In addition, Library Services
currently benefits from MGE’s net metering rate – once integrated with the larger array at the
main site, the total would be over the net metering limit, meaning that solar would be reimbursed
at the lower wholesale rate, resulting in a net increase in the operating costs for Library
Services.
27
Given these findings, a review of the available solar capacity at the main site is recommended,
as an increase in solar capacity of approximately 11% results in a 32% increase in resiliency
hours, and 41% increase in overall NPV in the Phase 1 BESS scenario.
Because the solar capacity cannot be increased, the only way to achieve emissions reduction is
to increase the battery size and capacity. The optimization then operates the battery to
selectively use energy from the grid; when grid emissions are highest, the battery exports solar
to reduce total emissions. When grid emissions are lowest, the microgrid imports energy to
serve load and charge the battery. While this causes energy costs to increase, it is more than
offset by the emissions benefit. In addition to the emissions benefits, this strategy also results in
reduced need for the generator and increased resiliency due to the larger battery.
Table 22. Results summary for Phase 1 scenario with emissions reduction targets.
Emissions reduction
None 10% 20% 30% 40%
target
Battery kW 47 297 594 1,407 3,317
Battery kWh 61 430 1,407 3,146 7,409
Generator kWh 672 445 0 0 0
Solar export (kWh) 269,206 264,100 303,512 372,201 461,465
Initial capital cost $60,000 $396,600 $1,005,800 $2,310,900 $5,445,100
Total cost $208,600 $699,100 $1,659,300 $3,633,900 $8,395,600
Total energy benefit $274,500 $207,500 $69,800 -$122,100 -$500,600
These results indicate that increasing the battery size will contribute to both emissions reduction
goals and resiliency benefits. The reduced reliance on generators means that with a sufficiently
28
sized BESS, it may be possible to eliminate the existing natural gas generator, reducing
operating costs, as well as any capital cost that would be associated with integrating the
generator into the microgrid.
4 MICROGRID CHECKLIST
Through this feasibility study, we identified best practices for evaluating microgrids for the City
of Madison. The following section summarizes these considerations, starting with specific next
steps for the site at Badger Rd and Emil St, followed by more general recommendations.
Specify microgrid-ready inverters for all new PV arrays. While the existing inverters all have
SunSpec Modbus capability which would enable them to interface with a microgrid controller,
they are grid-tied inverters which require a grid signal to generate power. Specifying multi-mode
inverters (which can operate in grid-tied or grid-forming fashion) will ensure that there is
sufficient power available to establish a stable signal during islanded operation to support the
balance of the inverters. While the BESS inverter will by default be multi-mode, specifying
several additional PV inverters as multi-mode in addition can help support the BESS inverter
and may lower the total cost.
Consult with vendors to prepare for microgrid integration of existing DER components.
While all the PV inverters on site are SunSpec Modbus capable, some may require firmware
upgrades or additional hardware to enable integration, and communication cabling may need to
be installed. The generator, generator controller, and all associated automatic transfer switches
will also require evaluation to determine how they could integrate with a future microgrid
controller. The generator currently utilizes an open-transfer switch. In a microgrid configuration,
the BESS would utilize a closed-transfer switch to prevent momentary outages during transition
to island. Then as the BESS charge drops, the generator would need to come on-line in parallel
with the BESS; to accomplish this, the existing generator ATS would likely need to be replaced
or upgraded.
Perform a site survey to establish acceptable BESS installation location. The National Fire
Protection agency (NFPA) provides guidelines for allowable locations of a BESS, along with
29
required enclosures and fire suppression systems.28 Given the limited space and high traffic of
the site today, identifying a suitable location for a BESS, and confirming the total allowable
capacity, will be a critical step before undertaking further microgrid planning.
Consider BESS replacement strategy in the bidding process. The battery cells used in a
BESS today naturally degrade over time, a fact which must be accounted for in the design of the
system. To ensure that the BESS provides all the expected benefits for the site, there are three
typical strategies which the city could consider at installation; replacement, augmentation, and
oversizing.29 The first option is a full replacement roughly 10 years into the project lifetime. With
an augmentation strategy, new cells would be added periodically to offset the degradation of
older cells, and older cells would be removed as their capacity degrades below acceptable
limits. The last option is to oversize the system at the onset, so that as the system degrades, it
still hits the minimum capacity needs.
For this site, due to the expected vehicle electrification timeline, a modular augmentation
strategy will likely be the most cost-effective; at installation, the BESS should be sized according
to the expected near-term EV charging load, with periodic modular expansions corresponding to
the expansion of the EV fleet. To accommodate this expected growth, the location where the
battery is to be housed should be designed from the outset to be large enough for the final
expected battery size.
For the vehicle fleet, consider implementing a telematics system to record interval data by
vehicle type. With a record of the times at which vehicles depart and return to their assigned
28 National Fire Protection Association, “NFPA 855: Standard for the Installation of Stationary Energy
Storage Systems.”
29 Shin and Hur, “Optimal Energy Storage Sizing with Battery Augmentation for Renewable-Plus-Storage
Power Plants”; EPRI, “Energy Storage, DER, and Microgrid Project Valuation: EPRI DER-VET Analysis in
Action.”
30
facility, along with daily mileage, a more accurate model of the charging load profile could be
developed to enhance the BESS sizing optimization.
We also found that there are several intricacies to the required inputs of the tools, including:
Financial data points, rebates at the utility, state, and federal level, current utility rate, and
potential utility rates. For these reasons, it is important to budget ample time to collect data,
review and organize the data, and determine additional inputs.
Consider alternatives for natural gas-burning end uses including generators, space
heating, and water heating. In 2020, natural gas usage represented 40% of the utility cost and
81% of the total energy used by the Badger Rd and Emil St site. The majority of this was used
for space heating, with some additional use for water heating, the natural gas generator, and the
brine heaters. To achieve the city’s emissions reduction goals, nearly all natural gas end uses at
this site and other city facilities will need to be converted to electric. This will add significant
electric load, requiring larger batteries and PV arrays to meet critical demand at each site where
a microgrid is implemented. However, additional electric uses, especially when implemented
through a load control system, can also enhance the ability of a microgrid to reduce emissions
and increase energy benefits.
Consider vehicle-to-grid as a potential solution for powering critical loads from the
energy stored in non-critical EVs during outages and emergencies. In addition to smart
charging, vehicle to grid (V2G) could be a solution to enable the battery capacity of fleet
vehicles to be used in a similar fashion to a standalone BESS. While the infrastructure to
implement V2G can be costly, and operation can reduce battery lifespan, there are cases where
the benefits outweigh these costs. If V2G can be used to supplement a smaller standalone
BESS during outages, the upfront capital cost can be reduced without sacrificing resiliency
benefits.
Sites with existing generators should consider lifetime of generator. At sites with existing
diesel generators, it is generally not cost effective to replace a generator with battery storage
when just looking at resiliency and energy benefits. The diesel generators provide needed
resiliency and the upfront costs for batteries is too high for the energy benefits to outweigh the
cost. Additionally, if the diesel generator is only running occasionally, the environmental impact
can be small.
31
For these sites, the most financially feasible option for a microgrid installation is likely at the end
of the generator’s lifetime. At that point, the BESS and its associated benefits can better
compete with the generator and provide additional emissions benefits. The site should start by
installing solar to lower its emissions and then upgrade to a full microgrid at the end of the diesel
generator’s lifetime or when emissions reduction at the specific site is deemed critical to
meeting city-wide goals.
Adding a BESS to a site with an existing generator may be cost-effective for sites where a large
solar PV array is existing or planned. The load shifting and demand limiting benefits of a BESS
can be fully utilized at such sites, especially where excess solar generation may otherwise need
to be exported to the grid at the lower wholesale rate.
Utilize microgrid ready design during renovations and construction. The upfront capital
costs associated with establishing a microgrid are often a deterrent. One solution is to install the
microgrid components piece by piece based on their own value proposition, while ensuring they
are microgrid ready. For example, solar PV arrays can be installed first, with inverters confirmed
to be microgrid compatible. NREL provides suggestions on RFP language to include to ensure
solar panels and inverters are microgrid-ready.30 Language should be included that inverters
should comply with applicable provisions in the IEEE Series of Interconnection Standards
(specifically IEEE 1547-2018) and that the inverters should be multi-mode DC to AC inverters
with islanding functionality.
Consider energy efficiency and demand management to decrease solar and storage
capacity needs. When sizing a solar plus storage system, the baseline load is the single most
important factor. If there are ways to decrease total energy use through energy efficiency and
demand management, this can allow for a smaller and less costly system. As part of an
evaluation of the microgrid installation, consider if there are ways to improve efficiency in the
building, such as lighting improvements or HVAC system upgrades, or ways to manage demand
through plug load or lighting controls.
For sites intended to provide resiliency benefits, it will be important to consider what measures
can be installed that can shed or shift load to reduce the amount of energy needed during an
outage.
When sizing DER components, determine the critical loads at the facility. The amount of
load that must be sustained during an outage is a critical factor in the size of storage required
for a microgrid. Consultation with stakeholders familiar with the building and its critical loads is
also key to the success of a microgrid.
32
It may also be useful to utilize the Clean Coalition’s VOR123 methodology.31 The methodology
suggests that most buildings can split their load into three tiers. Tier 1 represents roughly 10
percent of load and are critical items that require power always. Tier 2 represents roughly 15
percent of total load and are all other priority loads, and Tier 3 represents the last 75 percent
and all discretionary loads. To utilize this methodology, split all the major spaces in the building
into Tier 1, Tier 2 and Tier 3. From there, data such as square footage, occupancy, or
submetering can be used to estimate energy needs for each tier.
• Utilize national estimates from LBNL. This is one of the most cited values of resiliency but is
limited as it only includes values for outage durations up to 16 hours32
• Estimate the value using NREL’s Customer Damage Function Calculator. This tool allows
the user to input any damaged equipment costs, lost data costs, food or product spoilage
costs, or any other interruption costs33
• Estimate human health benefits for a community resiliency center. Other studies have
considered their population and estimated how many people would need electricity
dependent medical care or heating and cooling centers to estimate health impacts and
associated avoided costs34
31 Lewis and Mullendore, “Valuing Resilience in Solar+Storage Microgrids: A New Critical Load Tiering
Approach.”
32 Sullivan, Schellenberg, and Blundell, “Updated Value of Service Reliability Estimates for Electric Utility
33
5 CONCLUSION
A microgrid at the Badger Rd and Emil St site can help meet several City of Madison goals:
increase use of renewable energy, improve resiliency, reduce pollution and carbon emissions,
and reduce energy costs. The microgrid can help provide these benefits and generate net
financial savings over the lifetime of the system. While a complete implementation is costly,
there are several lower cost incremental upgrades that the city can implement to enable an
eventual microgrid.
The results in this study highlight the various ways that the benefits of a BESS can be evaluated
to justify the significant upfront cost, especially as electrification of the vehicle fleet increases the
electric load that the microgrid must be able to meet. Important findings include:
Battery sizes and costs increase as the load and emissions reduction goals increase.
There are two primary factors that impact battery size – the critical load profile and the site’s
emissions reduction target. As the electric vehicle fleet expands, the size of the battery
increases, which decreases net present value (before emissions and resiliency are accounted
for). Similarly, as the emissions reduction target increases, the size of the battery increases. To
address this, the City of Madison will need to decide how to value the other benefits that the
BESS provides.
The planned PV capacity is not sufficient to support the full critical load after all vehicles
are electrified. As modeled, even the largest feasible BESS (10 MWh) could only guarantee
backup power for outages of two days or less. There are several ways to address this, the
simplest of which would be increasing the solar generating capacity on site. Other strategies
such as smart charging and V2G could be used to carefully manage the critical load and
increase resiliency.
Including resiliency and emissions benefits significantly increases the net present value
compared to having no BESS on-site. The BESS scenarios provide significant resiliency
benefits when planning for a major outage on an annual basis. The BESS also provides
environmental and health benefits by enabling the facility to selectively utilize power from the
grid depending on when the emissions factor is lowest, reducing reliance on fossil fuels and the
resulting carbon and criteria pollutant emissions. Across all scenarios, the monetary value of
resilience and reduced emissions results in a greatly increased NPV. In the case of the future,
fully electrified site (Phase 2) valuing resiliency and emissions changes the NPV from negative
$0.7M to positive $1.6M.
Based on these takeaways, we recommend that the City of Madison pursue a microgrid at the
site with a BESS. Given that the fleet will be electrified over time, we recommend installing a
small modular BESS, with the option to expand over time. This will enable the site to
immediately take advantage of the benefits of a microgrid, while enabling staff to study the real-
world performance and to make informed decisions about future expansions.
As the fleet electrifies, several tasks should be completed to determine the ideal BESS size:
34
• Perform a detailed study of usage patterns of vehicles on site to develop a more
accurate load profile
• Model expected usage of vehicles during varying types of emergencies to develop a
more accurate critical load profile
• Research smart charging solutions that integrate with microgrid controllers to
understand options for managing critical charging loads during power outages.
35
6 REFERENCES
Anderson, Kate, Dan Olis, Bill Becker, Linda Parkhill, Nick Laws, Xiangkun Li, Sakshi Mishra, et
al. “REopt Lite User Manual,” March 2, 2021. https://doi.org/10.2172/1770888.
Anderson, Katherine H., Elizabeth L. Hotchkiss, and Caitlin Murphy. “Valuing Resilience in
Electricity Systems.” National Renewable Energy Lab. (NREL), Golden, CO (United
States), September 27, 2019. https://www.osti.gov/biblio/1569203.
Argonne National Lab. “AFLEET Tool.” Alternative Fuel Life-Cycle Environmental and Economic
Transportation (AFLEET) Tool, April 9, 2021. https://greet.es.anl.gov/afleet_tool.
Booth, Samuel. “Microgrid-Ready Solar PV - Planning for Resiliency.” National Renewable
Energy Lab. (NREL), Golden, CO (United States), September 2017.
https://www.osti.gov/servlets/purl/1401958.
Borlaug, Brennan, Matteo Muratori, Madeline Gilleran, David Woody, William Muston, Thomas
Canada, Andrew Ingram, Hal Gresham, and Charlie McQueen. “Heavy-Duty Truck
Electrification and the Impacts of Depot Charging on Electricity Distribution Systems.”
Nature Energy 6, no. 6 (June 2021): 673–82. https://doi.org/10.1038/s41560-021-00855-
0.
Burnham, Andrew, David Gohlke, Luke Rush, Thomas Stephens, Yan Zhou, Mark A. Delucchi,
Alicia Birky, et al. “Comprehensive Total Cost of Ownership Quantification for Vehicles
with Different Size Classes and Powertrains.” Argonne National Lab. (ANL), Argonne, IL
(United States), April 1, 2021. https://doi.org/10.2172/1780970.
“Customer Damage Function Calculator.” Accessed June 12, 2022. https://cdfc.nrel.gov.
Dechent, Philipp, Alexander Epp, Dominik Jöst, Yuliya Preger, Peter M. Attia, Weihan Li, and
Dirk Uwe Sauer. “ENPOLITE: Comparing Lithium-Ion Cells across Energy, Power,
Lifetime, and Temperature.” ACS Energy Letters 6, no. 6 (June 11, 2021): 2351–55.
https://doi.org/10.1021/acsenergylett.1c00743.
EPRI. “Energy Storage, DER, and Microgrid Project Valuation: EPRI DER-VET Analysis in
Action.” October 2021. https://www.der-vet.com/files/EPRI_DER-VET_Overview.pdf.
Feldman, David, and Robert Margolis. “Fall 2021 Solar Industry Update,” 2021, 64.
Fu, Ran, Timothy Remo, and Robert Margolis. “2018 U.S. Utility-Scale Photovoltaics-Plus-
Energy Storage System Costs Benchmark.” Renewable Energy, 2018, 32.
https://www.nrel.gov/docs/fy19osti/71714.pdf.
Heo, Jinhyok, Peter J. Adams, and H. Gao. “The Estimating Air Pollution Social Impact Using
Regression (EASIUR) Model.” The Center for Air, Climate, & Energy Solutions (CACES),
June 2015. https://www.caces.us/easiur.
Interagency Working Group on Social Cost of Greenhouse Gases. “Technical Support
Document: Social Cost of Carbon, Methane,” 2021, 48.
Jabeck, Brian. “The Impact of Generator Set Underloading.” Caterpillar, October 2013.
https://www.cat.com/en_US/by-industry/electric-power/Articles/White-papers/the-impact-
of-generator-set-underloading.html.
Krah, Kathleen. “Behind-the-Meter Solar + Storage Modeling Tool Comparison.” National
Renewable Energy Lab. (NREL), Golden, CO (United States), April 12, 2019.
https://www.osti.gov/biblio/1507688-behind-meter-solar-storage-modeling-tool-
comparison.
Lewis, Craig. “A Revolutionary Way to Easily Value Resilience for Any Facility.” Clean Coalition
(blog), April 29, 2021. https://clean-coalition.org/news/a-revolutionary-way-to-easily-
value-resilience-for-any-facility/.
Lewis, Craig, and Seth Mullendore. “Valuing Resilience in Solar+Storage Microgrids: A New
Critical Load Tiering Approach.” Clean Energy Group, August 11, 2020.
https://www.cleanegroup.org/wp-content/uploads/RPP-webinar-8-11-20-slides.pdf.
36
MGE. “2021Corporate Responsibility and Sustainability Report.” Madison Gas and Electric,
2022. https://www.mge.com/responsibility-and-sustainability/2021-corporate-
report/sustainability-report.
National Fire Protection Association. “NFPA 855: Standard for the Installation of Stationary
Energy Storage Systems,” 2020. https://www.nfpa.org/codes-and-standards/all-codes-
and-standards/list-of-codes-and-standards/detail?code=855.
Ray, Douglas. “Lazard’s Levelized Cost of Energy Analysis—Version 15.0,” 2021, 21.
Rickerson, Wilson, Kiera Zitelman, and Kelsey Jones. “Valuing Resilience for Microgrids:
Challenges, Innovative Approaches, and State Needs,” February 2022, 36.
https://www.naseo.org/data/sites/1/documents/publications/NARUC_Resilience_for_Micr
ogrids_INTERACTIVE_021122.pdf.
Robert Walton. “MISO Prepares for ‘worst-Case Scenarios,’ Heads into Summer with
Insufficient Firm Generation.” Utility Dive, April 29, 2022.
https://www.utilitydive.com/news/miso-prepares-for-worst-case-scenarios-heads-into-
summer-with-insufficie/622932/?:%20Utility%20Dive:%20Daily%20Dive%2004-30-2022.
Rolon, Abigial, Alexendria Calven, and Nazik Aytjanova. “Solar and Energy Storage for
Resiliency,” 2018.
https://sfenvironment.org/sites/default/files/fliers/files/sfe_en_solar_resilient_cost_benefit
_analysis.pdf.
Shin, Hunyoung, and Jin Hur. “Optimal Energy Storage Sizing with Battery Augmentation for
Renewable-Plus-Storage Power Plants.” IEEE Access 8 (2020): 187730–43.
https://doi.org/10.1109/ACCESS.2020.3031197.
Sullivan, Michael, Josh Schellenberg, and Marshall Blundell. “Updated Value of Service
Reliability Estimates for Electric Utility Customers in the United States,” January 1, 2015.
https://doi.org/10.2172/1172643.
Tozzi, Peter, and Jin Ho Jo. “A Comparative Analysis of Renewable Energy Simulation Tools:
Performance Simulation Model vs. System Optimization.” Renewable and Sustainable
Energy Reviews 80 (December 2017): 390–98.
https://doi.org/10.1016/j.rser.2017.05.153.
US DOE. “Average Fuel Economy by Major Vehicle Category.” Alternative Fuels Data Center,
February 2020. https://afdc.energy.gov/data/10310.
———. “State of Wisconsin Energy Sector Risk Profile.” Department of Energy (DOE), Office of
Cybersecurity, Energy Security, and Emergency Response (CESER), March 2021.
US EIA. “British Thermal Units (Btu).” U.S. Energy Information Agency, May 13, 2021.
https://www.eia.gov/energyexplained/units-and-calculators/british-thermal-units.php.
———. “Electric Power Monthly - U.S. Energy Information Administration (EIA),” 2022.
https://www.eia.gov/electricity/monthly/epm_table_grapher.php.
———. “Midwest (PADD 2) Gasoline and Diesel Retail Prices.” U.S. Energy Information
Agency, June 13, 2022. https://www.eia.gov/dnav/pet/pet_pri_gnd_dcus_r20_m.htm.
US EPA. “AVoided Emissions and GeneRation Tool (AVERT).” Collections and Lists. U.S.
Environmental Protection Agency, March 31, 2022. https://www.epa.gov/avert.
US EPA, OAR. “Volume I: Stationary Point and Area Sources.” Other Policies and Guidance.
Compilation of Air Pollutant Emissions Factors. US EPA, January 1995.
https://www.epa.gov/air-emissions-factors-and-quantification/ap-42-compilation-air-
emissions-factors.
37