Important Values and Calculations
PERT Standard Deviation Variance Float or Slack Planned Value or Work Perf. Measurement Baseline (PMB) Budget at Completion (BAC) Earned Value Actual Cost (Incurred) Cost Variance (CV) Schedule Variance (SV) Cost Performance Index (CPI) Burn Rate Sched. Performance Index (SPI) Estimate At Completion (EAC) (P + (4*M) + O ) / 6 P=Pessimistic, M=Most Likely, O=Optimistic (P - O) / 6 [(P - O) / 6 ]^2 LS-ES (Late Start - Early Start) and LF-EF (Late Finish - Early Finish) PV PV PV EV AC EV - AC (Earned Value - Actual Cost) EV - PV (Earned Value - Planned Value) EV / AC (Earned Value / Actual Cost) 1 / CPI EV / PV (Earned Value / Planned Value) BAC / CPI, AC + ETC -- Initial Estimates are flawed AC + BAC - EV -- Future variance are Atypical AC + (BAC - EV) / CPI -- Future Variance would be typical EAC - AC (Estimate at Completion - Actual Cost) EV/ BAC (Earned Value / Budget at Completion) BAC - EAC (Budget at Completion - Estimate At Completion) TCPI index of less then 1.0 is good because it indicates the efficiency to complete is less than planned. How efficient must the project team be to complete the remaining work with the remaining money? ( BAC - EV ) / ( BAC - AC ) The option with the larger NPV is better FV / ((1 + r)^t) [FV = Future Value, r = interest rate, t = term in years] Bigger is better (IRR) Bigger is better ((BCR or Benefit / Cost) revenue or payback VS. cost) Or PV or Revenue / PV of Cost A shorter payback period is better (Net Investment / Avg. Annual cash flow) PV = Budgeted Cost of Work Scheduled EV = Budgeted Cost of Work Performed AC = Actual Cost of Work Performed -25% - +75% (-50 to +100% PMBOK) -10% - +25% -5% - +10% [N(N -1)] / 2 Probability * Impact [(Ceiling Price - Target Price) / Buyer's Share Ratio] + Target Cost 1 = 68.27% 2 = 95.45% 3 = 99.73% 6 = 99.99985% Net Earnings Before Taxes (NEBT) / Total Sales OR Net Earnings After Taxes (NEAT) / Total Sales NEBT / Total Assets OR NEAT / Total Assets NEBT / Total Investment OR NEAT / Total Investment Current Assets - Current Liabilities Cash Flow * Discount Factor Savings = Target Cost Actual Cost Bonus = Savings * Percentage Contract Cost = Bonus + Fees Total Cost = Actual Cost + Contract Cost
PROCESS 4.1 Develop Project Charter
INPUTS
.1 Project statement of work .2 Business case .3 Contract .4 Enterprise Environmental factors .5 Organizational process assets
TOOLS & TECHNIQUES
OUTPUTS
PROCESS 4.2 Develop Project Management Plan
INPUTS
.1 Project charter .2 Outputs from planning processes .3 Enterprise Environmental Factors .4 Organizational process assets
TOOLS & TECHNIQUES
OUTPUTS
.1 Project Management Plan
PROCESS 4.3 Direct and Manage Project Execution
INPUTS
.1 Project management plan .2 Approved change requests .3 Enterprise environmental factors .4 Organizational process assets
TOOLS & TECHNIQUES
OUTPUTS
.1 Deliverables .2 Work performance information .3 Change requests .4 Project management plan updates .5 Project document updates
PROCESS 4.4 Monitor and Control Project Work PROCESS 4.5 Perform Integrated Change Control
INPUTS
.1 Project management plan .2 Performance reports .3 Enterprise environmental factors .4 Organizational process assets
TOOLS & TECHNIQUES
OUTPUTS
.1 Change requests .2 Project management plan updates .3 Project document updates
PROCESS 4.6 Close Project or Phase
INPUTS
.1 Project management plan .2 Accepted deliverables .3 Organizational process assets
TOOLS & TECHNIQUES
OUTPUTS
.1 Final product, service, or result transition .2 Organizational process assets updates
.1 Expert judgment
.1 Project charter
.1 Expert judgment
4. Project Integration Management
.1 Expert judgment .2 Project management information system
.1 Expert judgment
.1 Expert Judgement
INPUTS
.1 Project management plan .2 Work performance information .3 Change requests .4 Enterprise environmental factors .5 Organizational process assets
TOOLS & TECHNIQUES
OUTPUTS
.1 Project Management Plan
.1 Expert judgment
PROCESS 5.1 Collect Requirements PROCESS
INPUTS
.1 Project Charter .2 Stakeholder register
TOOLS & TECHNIQUES
.1 Interviews .2 Focus groups .3 Facilitated workshops .4 Group creativity techniques .5 Group decision making techniques .6 Questionnaires and surveys .7 Observations .8 Prototypes
OUTPUTS
.1 Requirements documentation .2 Requirements management plan .3 Requirements traceability matrix
PROCESS
INPUTS
.1 Project management plan .2 Requirements documentation .3 Requirements traceability matrix .4 Validated deliverables
TOOLS & TECHNIQUES
OUTPUTS
.1 Accepted deliverables .2 Change requests .3 Project document updates
Estimate To Complete Percentage Complete Variance At Completion To Complete Performance Index (TCPI)
5.4 Verify Scope
.1 Inspection
INPUTS
.1 Project charter .2 Requirements documentation .3 Organizational process assets
TOOLS & TECHNIQUES .1 Expert judgment .2 Product Analysis .3 Alternatives Identification .4 Facilitated workshops TOOLS & TECHNIQUES
OUTPUTS
.1 Project scope statement .2 Project document updates
PROCESS
INPUTS
.1 Project management plan .2 Work performance information .3 Requirements documentation .4 Requirements traceability matrix .5 Organizational process assets
TOOLS & TECHNIQUES
OUTPUTS
.1 Work performance measurements .2 Organizational process assets .3 Change requests .4 Project management plan updates .5 Project document updates
5. Project Scope Management
Net Present Value (NPV) Present Value (PV) Internal Rate of Return (IRR) Benefit Cost Ratio (BCR) Payback Period BCWS BCWP ACWP Order of Magnitude Estimate Budget Estimate Definitive Estimate Communication Channels Expected Monetary Value (EMV) Point of Total Assumption (PTA) Sigma
5.2 Define Scope
5.5 Control Scope
.1 Variance analysis
PROCESS
INPUTS
.1 Project scope statement .2 Requirements documentation .3 Organizational process assets
OUTPUTS
.1 WBS .2 WBS dictionary .3 Scope baseline .4 Project document updates
5.3 Create WBS
.1 Decomposition
PROCESS
INPUTS
.1 Scope baseline .2 Enterprise environmental factors .3 Organizational process assets
TOOLS & TECHNIQUES .1 Decomposition .2 Rolling wave planning .3 Templates .4 Expert judgment TOOLS & TECHNIQUES
.1 Precedence diagramming method (PDM) .2 Dependency determination .3 Applying leads and lags .4 Schedule network templates
OUTPUTS
.1 Activity list .2 Activity attributes .3 Milestone list
PROCESS 6.6 Control Schedule
INPUTS
.1 Project management plan .2 Project Schedule .3 Work performance information .4 Organizational process assets
TOOLS & TECHNIQUES
.1 Performance reviews .2 Variance analysis .3 Project management software .4 Resource leveling .5 What-if scenario analysis .6 Adjusting leads and lags .7 Schedule compression .8 Scheduling tool
OUTPUTS
.1 Work performance measurement .2 Organizational process assets updates .3 Change requests .4 Project management plan updates .5 Project document updates
6.1 Define Activities
Return on Sales (ROS) Return on Assets (ROA) Return on Investment (ROI) Working Capital Discounted Cash Flow Contract related formulas
PROCESS 6.2 Sequence Activities PROCESS
INPUTS
.1 Activity list .2 Activity attributes .3 Milestone list .4 Project scope statement .5 Organizational process assets
OUTPUTS
.1 Project schedule network diagrams .2 Project document updates
INPUTS
.1 Activity list 2. Activity attributes .3 Resource calendars .4 Enterprise environmental factors .5 Organizational process assets
TOOLS & TECHNIQUES
.1 Expert judgment .2 Alternatives analysis .3 Published estimating data .4 Bottom-up estimating .5 Project management software
OUTPUTS
.1 Activity resource requirements .2 Resource breakdown structure .3 Project document updates
6. Project Time Management
6.3 Estimate Activity Resources PROCESS 6.4 Estimate Activity Durations PROCESS 6.5 Develop Schedule
INPUTS
.1 Activity list .2 Activity attributes .3 Activity resource requirements .4 Resource calendars .5 Project scope statement .6 Enterprise environmental factors .7 Organizational process assets
TOOLS & TECHNIQUES .1 Expert judgment .2 Analogous estimating .3 Parametric estimating .4 Three-point estimates .5 Reserve analysis TOOLS & TECHNIQUES
.1 Schedule network analysis .2 Critical path method .3 Critical chain method .4 Resource leveling .5 What-if scenario analysis .6 Applying leads and lags .7 Schedule compression .8 Scheduling tool
OUTPUTS
.1 Activity duration estimates .2 Project document updates
INPUTS
.1 Activity list .2 Activity attributes .3 Project schedule network diagrams .4 Activity resource requirements .5 Resource calendars .6 Activity duration estimates .7 Project scope statement .8 Enterprise environmental factors .9 Organizational process assets
OUTPUTS
.1 Project schedule .2 Schedule baseline .3 Schedule data .4 Project document updates
PROCESS
INPUTS
.1 Scope baseline .2 Project schedule .3 Human resource plan .4 Risk register .5 Enterprise environmental factors .6 Organizational process assets
TOOLS & TECHNIQUES
.1 Expert judgment .2 Analogous estimating .3 Parametric estimating .4 bottom-up estimating .5 Three-point estimates .6 Reserve analysis .7 Cost of quality .8 Project management estimating software .9 Vendor bid analysis
OUTPUTS
.1 Activity cost estimates .2 Basis of estimates .3 Project document updates
PROCESS
INPUTS
.1 Project management plan .2 Project funding requirements .3 Work performance information .4 Organizational process assets
TOOLS & TECHNIQUES
.1 Earned value management .2 Forecasting .3 To-complete performance index (TCPI) .4 Variance analysis .5 Project management software
OUTPUTS
.1 Work performance measurements .2 Budget forecasts .3 Organizational process assets updates .4 Change requests .5 Project management plan updates .6 Project document updates
7.1 Estimate Costs
7.3 Control Costs
7. Project Cost Management
PROCESS 7.2 Determine Budget
INPUTS
.1 Activity cost estimates .2 Basis of estimates .3 Scope baseline .4 Project schedule .5 Resource calendars .6 Contracts .7 Organizational process assets
TOOLS & TECHNIQUES .1 Cost aggregation .2 Reserve analysis .3 Expert judgment .4 Historical relationships .5 Funding limit reconciliation TOOLS & TECHNIQUES
.1 Cost-benefit analysis .2 Cost of quality .3 Control charts .4 Benchmarking .5 Design of experiments .6 Statistical sampling .7 Flowcharting .8 Proprietary quality management methodologies .9 Additional quality planning tools
OUTPUTS
.1 Cost performance baseline .2 Project funding requirements .3 Project document updates
PROCESS
INPUTS
.1 Scope baseline .2 Stakeholder register .3 Cost performance baseline .4 Schedule baseline .5 Risk register .6 Enterprise environmental factors .7 Organizational process assets
OUTPUTS
.1 Quality management plan .2 Quality metrics .3 Quality checklists .4 Process improvement plan .5 Project document updates
PROCESS 8.2 Perform Quality Assurance
INPUTS
.1 Project management plan .2 Quality metrics .3 Work performance information .4 Quality control measurements
TOOLS & TECHNIQUES .1 Plan Quality and Perform Quality Control tools and techniques .2 Quality audits .3 Process Analysis
OUTPUTS
.1 Organizational process asset updates .2 Change requests .3 Project management plan updates .4 Project document updates
PROCESS 8.3 Perform Quality Control
INPUTS
.1 Project management plan .2 Quality metrics .3 Quality Checklists .4 Work performance measurements .5 Approved change requests .6 Deliverables .7 Organizational process assets
TOOLS & TECHNIQUES
.1 Cause and effect diagrams .2 Control charts .3 Flowcharting .4 Histogram .5 Pareto chart .6 Run chart .7 Scatter diagram .8 Statistical sampling .9 Inspection .10 Approved change requests review
OUTPUTS
.1 Quality control measurements .2 Validated changes .3 Validated deliverables .4 Organizational process assets updates .5 Change requests .6 Project management plan updates .7 Project document updates
8. Project Quality Management
8.1 Plan Quality
PROCESS 9.1 Develop Human Resource Plan
INPUTS
.1 Activity resource requirements .2 Enterprise environmental factors .3 Organizational process assets
TOOLS & TECHNIQUES .1 Organization charts and position descriptions .2 Networking .3 Organizational theory
OUTPUTS
PROCESS 9.2 Acquire Project Team PROCESS 9.3 Develop Project Team PROCESS 9.4 Manage Project Team
INPUTS
.1 Project management plan .2 Enterprise environmental factors .3 Organizational process assets
TOOLS & TECHNIQUES .1 Pre-assignment .2 Negotiation .3 Acquisition .4 Virtual teams TOOLS & TECHNIQUES
.1 Interpersonal skills .2 Training .3 Team-building activities .4 Ground rules .5 Co-location .6 Recognition and rewards
OUTPUTS
.1 Project staff assignments .2 Resource calendars .3 Project management plan updates
.1 Human resource plan
9. Project Human Resources Management
INPUTS
.1 Project staff assignments .2 Project management plan .3 Resource calendars
OUTPUTS
.1 Team performance assessments .2 Enterprise environmental factors updates
INPUTS
.1 Project staff assignments .2 Project management plan .3 Team performance assessments .4 Performance reports .5 Organizational process assets
TOOLS & TECHNIQUES
.1 Observation and conversation .2 Project performance appraisals .3 Conflict management .4 Issue log .5 Interpersonal skills
OUTPUTS
.1 Enterprise environmental factors updates .2 Organizational process assets updates .3 Change requests .4 Project management plan updates
PROCESS 10.1 Identify Stakeholders
INPUTS
.1 Project charter .2 Procurement documents .3 Enterprise environmental factors .4 Organizational process assets
TOOLS & TECHNIQUES
OUTPUTS
.1 Stakeholder register .2 Stakeholder management strategy
PROCESS 10.2 Plan Communications
INPUTS
.1 Stakeholder register .2 Stakeholder management strategy .3 Enterprise environmental factors .4 Organizational process assets
TOOLS & TECHNIQUES
.1 Communication requirements analysis .2 Communication technology .3 Communication models .4 Communication methods
OUTPUTS
.1 Communication management plan .2 Project document updates
PROCESS 10.3 Distribute Information PROCESS 10.4 Manage Stakeholder Expectations
INPUTS
.1 Project management plan .2 Performance reports .3 Organizational process assets
TOOLS & TECHNIQUES .1 Communication methods .2 Information distribution tools TOOLS & TECHNIQUES .1 Communication methods .2 Interpersonal skills .3 Management skills
OUTPUTS
.1 Organizational process assets updates
PROCESS 10.5 Report Performance
INPUTS
.1 Project management plan .2 Work performance information .3 Work performance measurements .4 Budget forecasts .5 Organizational process assets
TOOLS & TECHNIQUES .1 Variance analysis .2 Forecasting methods .3 Communication methods .4 Reporting systems
OUTPUTS
.1 Performance reports .2 Organizational process assets updates .3 Change requests
.1 Stakeholder analysis .2 Expert judgment
10. Project Communications Management
INPUTS
.1 Stakeholder register .2 Stakeholder management strategy .3 Project management plan .4 Issue log .5 Change log .6 Organizational process assets
OUTPUTS
.1 Organizational process assets updates .2 Change requests .3 Project management plan updates .4 Project document updates
PROCESS 11.1 Plan Risk Management PROCESS
INPUTS
.1 Project scope statement .2 Cost management plan .3 Schedule management plan .4 Communications management plan .5 Enterprise environmental factors .6 Organizational process assets
TOOLS & TECHNIQUES
OUTPUTS
PROCESS 11.6 Monitor and Control Risks
INPUTS
.1 Risk register .2 Project management plan .3 Work performance integration .4 Performance reports
TOOLS & TECHNIQUES
.1 Risk reassessment .2 Risk audits .3 Variance and trend analysis .4 Technical performance measurement .5 Reserve analysis .6 Status meetings
OUTPUTS
.1 Risk register updates .2 Organizational process assets updates .3 Change requests .4 Project management plan updates .5 Project document updates
.1 Planning meetings and analysis
.1 Risk management plan
INPUTS
.1 Risk management plan .2 Activity cost estimates .3 Activity duration estimates .4 Scope baseline .5 Stakeholder register .6 Cost management plan .7 Schedule management plan .8 Quality management plan .9 Project documents .10 Enterprise environmental factors .11 Organizational process assets
TOOLS & TECHNIQUES
.1 Documentation reviews .2 Information gathering techniques .3 Checklist analysis .4 Assumptions analysis .5 Diagramming techniques .6 SWOT analysis .7 Expert judgment
OUTPUTS
11.2 Identify Risks
.1 Risk register
PROCESS
INPUTS
.1 Risk register .2 Risk management plan .3 Project scope statement .4 Organizational process assets
TOOLS & TECHNIQUES
.1 Risk probability and impact assessment .2 Probability and impact matrix .3 Risk data quality assessment .4 Risk categorization .5 Risk urgency assessment .6 Expert judgment
OUTPUTS
11. Project Risk Management
11.3 Perform Qualitative Risk Analysis PROCESS 11.4 Perform Quantitative Risk Analysis PROCESS 11.5 Plan Risk Responses
.1 Risk register updates
INPUTS
.1 Risk register .2 Risk management plan .3 Cost management plan .4 Schedule management plan .5 Organizational process assets
TOOLS & TECHNIQUES .1 Data gathering and representation techniques .2 Quantitative risk analysis and modeling techniques .e Expert judgment TOOLS & TECHNIQUES
.1 Strategies for negative risks or threats .2 Strategies for positive risks or opportunities .3 Contingent response strategies .4 Expert judgment
OUTPUTS
.1 Risk register updates
INPUTS
.1 Risk register .2 Risk management plan
OUTPUTS
.1 Risk register updates .2 Risk-related contract decisions .3 Project management plan .4 Project document updates
PROCESS
INPUTS
.1 Scope baseline .2 Requirements documentation .3 Teaming agreements .4 Risk register .5 Risk-related contract decisions .6 Activity resource requirements .7 Project schedule .8 Activity cost estimates .9 Cost performance baseline .10 Enterprise environmental factors .11 Organizational process assets
TOOLS & TECHNIQUES
OUTPUTS
.1 Procurement management plan .2 Procurement statements of work .3 Make-or-buy decisions .4 Procurement documents .5 Source selection criteria .6 Change requests
PROCESS 12.2 Conduct Procurements
INPUTS
.1 Project management plan .2 Procurement documents .3 Source selection criteria .4 Qualified seller list .5 Seller proposals .6 Project documents .7 Make-or-buy decisions .8 Teaming agreements .9 Organizational process assets
TOOLS & TECHNIQUES
.1 Bidder conferences .2 Proposal evaluation techniques .3 Independent estimates .4 Expert judgment .5 Advertising .6 Internet search .7 Procurement negotiations
OUTPUTS
.1 Selected sellers .2 Procurement contract award .3 Resource calendars .4 Change requests .5 Project management plan updates .6 Project document updates
PROCESS 12.3 Administer Procurements
INPUTS
.1 Procurement documents .2 Project management plan .3 Contract .4 Performance reports .5 Approved change requests .6 Work performance information
TOOLS & TECHNIQUES
.1 Contract change control system .2 Procurement performance reviews .3 Inspections and audits .4 Performance reporting .5 Payment systems .6 Claims administration .7 Records management system
OUTPUTS
.1 Procurement documentation .2 Organizational process assets updates .3 Change requests .4 Project management plan updates
PROCESS 12.4 Close Procurements
INPUTS
.1 Project management plan .2 Procurement documentation
TOOLS & TECHNIQUES .1 Procurement audits .2 Negotiated settlements .3 Records management system
OUTPUTS
.1 Closed procurements .2 Organizational process assets updates
12. Project Procurement Management
12.1 Plan Procurements
.1 Make-or-buy analysis .2 Expert judgment .3 Contract types
PMBOK At-a-Glance By Nunzio M. Fortugno April, 2010