ACTIVITY TABLE
ACTIVITY TABLE
1 1 Standard Two-Storey School Building 284 days Mon 24/03/25 Fri 15/05/26
2 1.1 Pre-Construction Stage 48 days Mon 24/03/25 Thu 05/06/25
3 1.1.1 Planning and Approval 48 days Mon 24/03/25 Thu 05/06/25
4 1.1.1.1 Initial Site Inspection and Surveying 3 days Mon 24/03/25 Wed 26/03/25 5
5 1.1.1.2 Project Design Finalization 13 days Thu 27/03/25 Wed 16/04/25 4 6,7,8
6 1.1.1.3 Procurement of Materials 7 days Mon 21/04/25 Tue 29/04/25 5 14
7 1.1.1.4 Permits and Clearance 25 days Mon 21/04/25 Tue 27/05/25 5 9
8 1.1.1.5 Safety and Health Planning 5 days Mon 21/04/25 Fri 25/04/25 5 9SS,11
9 1.1.1.6 Site Mobilization 7 days Wed 28/05/25 Thu 05/06/25 7,8SS,11
10 1.1.2 Site Preparation 42 days Mon 24/03/25 Wed 28/05/25
11 1.1.2.1 Site Clearing 7 days Mon 28/04/25 Wed 07/05/25 8 12,13,9
12 1.1.2.2 Construction of Fence and Access Roads 7 days Thu 08/05/25 Mon 19/05/25 11 18
13 1.1.2.3 Construction of Temporary Facilities and Utilities 14 days Thu 08/05/25 Wed 28/05/25 11
14 1.1.2.4 Material Handling and Initial Delivery of Materials 7 days Wed 30/04/25 Fri 09/05/25 6 18
15 1.1.2.5 Pre-Construction Meeting 2 days Mon 24/03/25 Tue 25/03/25 18
16 1.2 Construction Stage 234 days Tue 20/05/25 Thu 23/04/26
17 1.2.1 Substructure Work 61 days Tue 20/05/25 Tue 12/08/25 49
18 1.2.1.1 Excavation and Earthworks 10 days Tue 20/05/25 Mon 02/06/25 12,14,15 19
19 1.2.1.2 Soil Compaction 8 days Tue 03/06/25 Thu 12/06/25 18 20
20 1.2.1.3 Foundation Layout 5 days Fri 13/06/25 Thu 19/06/25 19 21
21 1.2.1.4 Formwork and Rebar Installation 5 days Fri 20/06/25 Thu 26/06/25 20 22
22 1.2.1.5 Concrete Pouring and Curing 28 days Fri 27/06/25 Tue 05/08/25 21 23,25SS
23 1.2.1.6 Backfiling 5 days Wed 06/08/25 Tue 12/08/25 22
24 1.2.2 Superstructure 180 days Fri 27/06/25 Thu 12/03/26 49
25 1.2.2.1 Construction of Column (Ground Floor to Roof) 28 days Fri 27/06/25 Tue 05/08/25 22SS 26
26 1.2.2.2 Construction of Beams (Foot Tie 56 days Wed 06/08/25 Thu 23/10/25 25 27SS
Beams,Beams,Girder)
27 1.2.2.3 Slab Formwork and Pouring (Ground and Second 56 days Wed 06/08/25 Thu 23/10/25 26SS 28
Floor)
28 1.2.2.4 Concrete Stair Works 14 days Fri 24/10/25 Wed 12/11/25 27 29
29 1.2.2.5 Masonry Wall Construction 40 days Thu 13/11/25 Tue 13/01/26 28 34,43,30
30 1.2.2.6 Roof Truss Fabrication and Installation 7 days Wed 14/01/26 Thu 22/01/26 29 31
31 1.2.2.7 Roof Sheeting and Insulation 5 days Fri 23/01/26 Thu 29/01/26 30 35,44,32
32 1.2.2.8 Interior Wall Plastering 30 days Fri 30/01/26 Thu 12/03/26 31 38,39,37,42
33 1.2.3 Building Envelope 42 days Wed 14/01/26 Thu 12/03/26
34 1.2.3.1 Doors and Windows Installation 5 days Wed 14/01/26 Tue 20/01/26 29 35
35 1.2.3.2 Exterior Wall Finishes (Paint, Plaster) 30 days Fri 30/01/26 Thu 12/03/26 34,31
36 1.2.4 Interior Finishes 14 days Fri 13/03/26 Mon 06/04/26
37 1.2.4.1 Floor Finishes (Tiles) 10 days Fri 13/03/26 Fri 27/03/26 32 40
38 1.2.4.2 Ceiling Installation 5 days Fri 13/03/26 Fri 20/03/26 32
39 1.2.4.3 Interior Wall Finishes (Painting,Tiling) 5 days Fri 13/03/26 Fri 20/03/26 32
40 1.2.4.4 Carpentry Works Installation (Blackboards, cabinets) 4 days Mon 30/03/26 Mon 06/04/26 37 46
Page 1
ID WBS Task Name Duration Start Finish Predecessors Successors
Page 2