0% found this document useful (0 votes)
6 views

ACTIVITY TABLE

The document outlines the project schedule for constructing a standard two-storey school building, detailing tasks, durations, start and finish dates, and dependencies. The project spans 284 days from March 24, 2025, to May 15, 2026, divided into pre-construction, construction, and post-construction stages. Key tasks include planning, site preparation, substructure and superstructure work, and final inspections.

Uploaded by

Roi Patolot
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
6 views

ACTIVITY TABLE

The document outlines the project schedule for constructing a standard two-storey school building, detailing tasks, durations, start and finish dates, and dependencies. The project spans 284 days from March 24, 2025, to May 15, 2026, divided into pre-construction, construction, and post-construction stages. Key tasks include planning, site preparation, substructure and superstructure work, and final inspections.

Uploaded by

Roi Patolot
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

ID WBS Task Name Duration Start Finish Predecessors Successors

1 1 Standard Two-Storey School Building 284 days Mon 24/03/25 Fri 15/05/26
2 1.1 Pre-Construction Stage 48 days Mon 24/03/25 Thu 05/06/25
3 1.1.1 Planning and Approval 48 days Mon 24/03/25 Thu 05/06/25
4 1.1.1.1 Initial Site Inspection and Surveying 3 days Mon 24/03/25 Wed 26/03/25 5
5 1.1.1.2 Project Design Finalization 13 days Thu 27/03/25 Wed 16/04/25 4 6,7,8
6 1.1.1.3 Procurement of Materials 7 days Mon 21/04/25 Tue 29/04/25 5 14
7 1.1.1.4 Permits and Clearance 25 days Mon 21/04/25 Tue 27/05/25 5 9
8 1.1.1.5 Safety and Health Planning 5 days Mon 21/04/25 Fri 25/04/25 5 9SS,11
9 1.1.1.6 Site Mobilization 7 days Wed 28/05/25 Thu 05/06/25 7,8SS,11
10 1.1.2 Site Preparation 42 days Mon 24/03/25 Wed 28/05/25
11 1.1.2.1 Site Clearing 7 days Mon 28/04/25 Wed 07/05/25 8 12,13,9
12 1.1.2.2 Construction of Fence and Access Roads 7 days Thu 08/05/25 Mon 19/05/25 11 18
13 1.1.2.3 Construction of Temporary Facilities and Utilities 14 days Thu 08/05/25 Wed 28/05/25 11
14 1.1.2.4 Material Handling and Initial Delivery of Materials 7 days Wed 30/04/25 Fri 09/05/25 6 18
15 1.1.2.5 Pre-Construction Meeting 2 days Mon 24/03/25 Tue 25/03/25 18
16 1.2 Construction Stage 234 days Tue 20/05/25 Thu 23/04/26
17 1.2.1 Substructure Work 61 days Tue 20/05/25 Tue 12/08/25 49
18 1.2.1.1 Excavation and Earthworks 10 days Tue 20/05/25 Mon 02/06/25 12,14,15 19
19 1.2.1.2 Soil Compaction 8 days Tue 03/06/25 Thu 12/06/25 18 20
20 1.2.1.3 Foundation Layout 5 days Fri 13/06/25 Thu 19/06/25 19 21
21 1.2.1.4 Formwork and Rebar Installation 5 days Fri 20/06/25 Thu 26/06/25 20 22
22 1.2.1.5 Concrete Pouring and Curing 28 days Fri 27/06/25 Tue 05/08/25 21 23,25SS
23 1.2.1.6 Backfiling 5 days Wed 06/08/25 Tue 12/08/25 22
24 1.2.2 Superstructure 180 days Fri 27/06/25 Thu 12/03/26 49
25 1.2.2.1 Construction of Column (Ground Floor to Roof) 28 days Fri 27/06/25 Tue 05/08/25 22SS 26
26 1.2.2.2 Construction of Beams (Foot Tie 56 days Wed 06/08/25 Thu 23/10/25 25 27SS
Beams,Beams,Girder)
27 1.2.2.3 Slab Formwork and Pouring (Ground and Second 56 days Wed 06/08/25 Thu 23/10/25 26SS 28
Floor)
28 1.2.2.4 Concrete Stair Works 14 days Fri 24/10/25 Wed 12/11/25 27 29
29 1.2.2.5 Masonry Wall Construction 40 days Thu 13/11/25 Tue 13/01/26 28 34,43,30
30 1.2.2.6 Roof Truss Fabrication and Installation 7 days Wed 14/01/26 Thu 22/01/26 29 31
31 1.2.2.7 Roof Sheeting and Insulation 5 days Fri 23/01/26 Thu 29/01/26 30 35,44,32
32 1.2.2.8 Interior Wall Plastering 30 days Fri 30/01/26 Thu 12/03/26 31 38,39,37,42
33 1.2.3 Building Envelope 42 days Wed 14/01/26 Thu 12/03/26
34 1.2.3.1 Doors and Windows Installation 5 days Wed 14/01/26 Tue 20/01/26 29 35
35 1.2.3.2 Exterior Wall Finishes (Paint, Plaster) 30 days Fri 30/01/26 Thu 12/03/26 34,31
36 1.2.4 Interior Finishes 14 days Fri 13/03/26 Mon 06/04/26
37 1.2.4.1 Floor Finishes (Tiles) 10 days Fri 13/03/26 Fri 27/03/26 32 40
38 1.2.4.2 Ceiling Installation 5 days Fri 13/03/26 Fri 20/03/26 32
39 1.2.4.3 Interior Wall Finishes (Painting,Tiling) 5 days Fri 13/03/26 Fri 20/03/26 32
40 1.2.4.4 Carpentry Works Installation (Blackboards, cabinets) 4 days Mon 30/03/26 Mon 06/04/26 37 46
Page 1
ID WBS Task Name Duration Start Finish Predecessors Successors

41 1.2.5 Rough-in Phase 47 days Wed 14/01/26 Fri 20/03/26 49


42 1.2.5.1 Electrical Conduit Layout 5 days Fri 13/03/26 Fri 20/03/26 32
43 1.2.5.2 Plumbing rough-in and Plumbing Fixtures Installation 5 days Wed 14/01/26 Tue 20/01/26 29 46
44 1.2.5.3 Mechanical Systems Installation 5 days Fri 30/01/26 Thu 05/02/26 31 47
45 1.2.6 Fixtures Phase 44 days Fri 06/02/26 Tue 14/04/26 49
46 1.2.6.1 Electrical and Plumbing Fixtures Installation 5 days Tue 07/04/26 Tue 14/04/26 40,43 52
47 1.2.6.2 Fire Protection Installation 5 days Fri 06/02/26 Thu 12/02/26 44 52
48 1.2.7 Quality Control 7 days Wed 15/04/26 Thu 23/04/26
49 1.2.7.1 Structural, Electrical and Plumbing Inspection 7 days Wed 15/04/26 Thu 23/04/26 17,24,41,45
50 1.3 Post-Construction Stage 22 days Wed 15/04/26 Fri 15/05/26
51 1.3.1 Testing of Systems 5 days Wed 15/04/26 Tue 21/04/26
52 1.3.1.1 Final Testing of MEPF Systems 5 days Wed 15/04/26 Tue 21/04/26 46,47 54
53 1.3.2 Deficiency Management and Correction 10 days Wed 22/04/26 Wed 06/05/26
54 1.3.2.1 Punchlisting and Deficiency Work 5 days Wed 22/04/26 Tue 28/04/26 52 55
55 1.3.2.2 Rectifications and Repairs 5 days Wed 29/04/26 Wed 06/05/26 54 57
56 1.3.3 Final Inspection and Turn-over 7 days Thu 07/05/26 Fri 15/05/26
57 1.3.3.1 Final Cleaning and Site Demobilization 5 days Thu 07/05/26 Wed 13/05/26 55 58
58 1.3.3.2 Final Inspection and Approval 2 days Thu 14/05/26 Fri 15/05/26 57 59FF
59 1.3.3.3 Handover to Owner 0 days Fri 15/05/26 Fri 15/05/26 58FF

Page 2

You might also like