.
1",
/"
IN THE HIGH COURT OF TANZANIA
AT DAR ES SALAAM
CIVIL CASE NO. 311 OF 1999
MWENGE GAS AND LUB OIL LTD PLAINTIFF
VERSUS
UNIVERSITY OF DAR ES SALAAM DEFENDANT
RULING
A.Shangwa,J.
On 17/8/1999 , DR. Lamwai for the plaintiff
MWENGE GAS AND LUB OILS LTD filed a suit against
the defendant the UNIVERSITY OF DAR ES SALAAM
claiming for damages for breach of the Lease
Agreement which was entered into between the
parties on 1/3/1995.
On 6/3/2002, Dr. Lamwai prayed for leave to
amend the plaint so as to introduce a claim for
damages for eviction and for the properties which
were confiscated and to exclude the name of the 2nd
defendant who was wrongly impleaded. Leave to
amend the plaint was accordingly granted by
Bubeshi, J (Rtd) and the amended plaint was
presented for filing on 28/4/2005.
On 5/5/2005, learned counsel for the defendant
Mr. Kalolo, Advocate filed a written statement of
Defence to the amended plaint in which he raised a
preliminary objection stating that the action is barred
by limitation, and that the amendment introduces a
new cause of action contrary to law.
On 13/12/2005, I ordered that the defendant's
preliminary objection should be argued by way of
written submissions and it was accordingly so
argued. These submissions were drawn and filed by
3
M/S M.A. Ismail & Co; Advocates for the defendant
and by the Managing Director of the plaintiff
company Mr. Wakhill Godfrey Muro.
Learned counsel for the defendant submitted
that the amended plaint introduces a new cause of
action to wit breach of contract and wrongful
execution of a High Court Decree in Civil Case 326 of
1997 on the 18/8/1999, whereupon the plaintiff
claims Tshs 40 Million as lost cash plus other sums as
specific damages.
Furthermore, counsel for the defendant
submitted that the amendment has unreasonably
been delayed as the suit was first instituted in 1999.
Some three books by learned authors were referred
to me in which the principle to be taken into
consideration in allowing the amendment of
pleadings were laid down.
First, I was referred to Rao & Chittaley in their
commentaries on the Indian Civil Procedure
Code( 16th Edn) Vol. 2 at page 2248 where it is
written that "a party is aI/owed to make such amendments
as may be necessary for determining the real question in
controversy or to avoid a multiplicity of suits, provided that
there has been no undue delay, that no new or inconsistent
cause of action is introduced, that no vested right, interest
on accrued legal right is affected and the amendment can be
aI/owed without injustice to the other side'~
Secondly, I was referred to C.K. Takwan in his
treatise titled Civil Procedure, 5th Edn at page 152
where some of the principles which have to be taken
into consideration in dealing with applications for
5
amendment of pleadings are mentioned. One of these
principles is that "no amendment should be aI/owed which
amounts to or results in defeating a legal right to the
opposite party on account of lapse of time'~
Thirdly, I was referred to Mogha's Law of
Pleadings, 14th Edn at page 145 where it is provided
inter - alia that "an amendment, the effect of which is to
change the cause of action on which the original suit was
based .. may not ordinarily be al/owed'~
It was further submitted by learned counsel for
the defendant that the plaintiff's claim which
enhances the original figure of shs 50 Million to over
shs 500 Million in form of specific damages which
were never part of the original claim are time barred
for having been introduced more than six years from
when the cause of action arose.
6
In reply, the plaintiff company's Managing
Director Mr. Wakhill G. Muro submitted that the
amendment made by the plaintiff did not in any way
introduce a new cause of action as alleged by the
defendant, and that limitation cannot be raised as a
defence against the hearing of his suit. He contended
that the amended plaint repeats the right to reliefs
claimed against the defendant in respect of the same
acts as detailed in the original plaint.
He cited the case of Edward Masanja Ng'ahwani Vs
Attorney General and Another Civil Appeal No. 61 of 2001
(unreported) in which the Court of Appeal of Tanzania
stated that an amendment duly made with or without
leave takes effect not from the date when the
amendment is made but from the date of the original
document which it amends.
7
It appears to me that this preliminary objection
by counsel for the defendant has been raised
belatedly. In my view, the objection that the action is
barred by limitation, and that the amendment
introduces a new cause of action contrary to law,
ought to have been raised when Dr. Lamwai who
was representing the plaintiff by then prayed for
leave to amend the plaint so as to introduce a claim
for damages for eviction and for the properties which
were confiscated by the defendant. At that time, one
of the defendant's counsel Mr. Kalolo was present
and did not object to Dr. Lamwai's prayer. As a result,
the Court Bubeshi, J (Rtd) allowed the plaintiff to
amend his plaint as prayed. I think Mr. Kalolo was
supposed to tell the Court before allowing the
plaintiff to amend the plaint that the amendment
sought to be made introduces a new cause of action
and that introducing such an action would render the
original suit time barred.
Now, as this Court has already allowed the
plaintiff to amend the plaint, the good principles for
allowing amendments to the pleadings that are found
in the books by learned authors which have been
referred to me by Mr. Kalolo cannot be of any
assistance to this Court. Those principles are useful
in cases where the court has not yet allowed the
party to the suit to amend the pleadings and not
thereafter. They relate to situations as to when an
amendment to pleadings should not be allowed by
the Court.
At any rate, I am of the view that no new cause
of action has been introduced by the plaintiff in its
amended plaint. The cause of action in the amended
plaint remains the same as the claim in the original plaint. In
the original plaint filed in 1999/ the plaintiff was pleading for
damages for breach of contract i.e. LeaseAgreement. In the
amended plaint filed in 2005/ the plaintiff is claiming for the
samething. What the plaintiff has simply done in the
amended plaint is to boost the total claim for specific
damages to be assessedby the Court from Tshs 190 to over
Tshs 500 Million.
Another question to be considered by this Court is
whether or not the plaintiff's action of increasing the total
amount of specific damages from Tshs 190 Million to over
Tshs 500 Million following the breach of the Lease
Agreement renders the plaintiff's suit time barred.
My answer to this question is No. As the cause of
action in the original plaint namely breach of the
tenancy / Lease Agreement remains unchanged in
the amended plaint the question that the action is
time barred should not arise. For these reasons, I
hereby overrule the defendant's preliminary
objection and order that the suit should come for
pre- trial conference on 31/5/2006.
~
A. Shangwa,J.
24/5/2006.
Delivered in open Court this 24th day of May, 2006.
~
A. Shangwa,
24/5/2006.