0% found this document useful (0 votes)
18 views1 page

Sockets Installation

The inspection report for the industrial socket installation at the MEP Works for A31 project outlines the compliance of installed sockets with approved drawings and specifications. It includes checks on the condition, connection, and rating of the sockets, as well as the correct number of outlets. The report is prepared by a subcontractor and requires signatures from both the inspector and the client.

Uploaded by

raghuveer0609
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
18 views1 page

Sockets Installation

The inspection report for the industrial socket installation at the MEP Works for A31 project outlines the compliance of installed sockets with approved drawings and specifications. It includes checks on the condition, connection, and rating of the sockets, as well as the correct number of outlets. The report is prepared by a subcontractor and requires signatures from both the inspector and the client.

Uploaded by

raghuveer0609
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

INSPECTION REPORT FOR INDUSTRIAL SOCKET INSTALL

CLIENT : JONY
RECORD NO. :
PROJECT : MEP WORKS FOR A31
UNIT :
PROJECT NO. : AO0421JD02
PAGE : ___ OF ___ DATE:_____________

PLANT DRAWING NO.: __________________

LOCATION : ___________________________

ACCEPTABLE
ITEM INSPECTION ITEM REMARKS
YES NO
The Industrial Sockets installed as per the approved
1 drawing

Specifications of Sockets materials comply with the drawing


2
& Contract specification. IMR is clear.
Industrial sockets outlet undamaged and correct
3 connection

4 Number of Industrial socket outlets / Circuits is correct

5 All Industrial sockets outlets rating correct and IP rating.

All Circuits installed and identified according to approved


6
drawings and specifications.
Note:

PREPARED BY : __________________ _______________


SUBCONTRACTOR DATE

INSPECTED BY : ______________ _________ WITNESS BY : ______________ __________