K-RIDE – C2B
YESHWANTPUR STATION CONSTRUCTION SEQUENCE
Construction Scope
• Size: Length of Building 205 M , Width 34.25 M , Height 33.1 M above ground 12.5 M
  below ground .
• Adjacent Details: Along the building One side is Indian Railway Running line & Other side
  is Private high raise G+14 building .
• Floor Details: Station consisting of two Basement floors, one Ground floor, one
  concourse floor , two numbers platform floor, one PD floor and Terrace floor.
• Key Features: With 3 different tracks at elevated level in One Station with skew
  Alignment in plan.
• Foundation : Based on Tender Schematic Drawing, Open Raft Foundation @ 12m below
  Ground level shown. It may vary as per actual Design
• Access Road: Due to one side running Indian Railway & other side High rise building, we
  have restricted two numbers feeding point only, further at one point, other contractor
  piling work is also going on.
PROPOSED YPR STATION SECTION
     TERRACE SLAB
       PD FLOOR
    UPPER PLATFORM
   LOWER PLATFORM
   CONCOURSE SLAB
   GROUND LVL SLAB
   BASEMENT LVL-02
   BASEMENT LVL-02
STATION GROUND LEVEL LAYOUT PLAN (Separate PDF file attached with this document)
YPR STATION - D-WALL PLAN
TOP-
TOP-DOWN METHOD – CONSTRUCTION OF TOTAL BUILDING IN 3 PARTS
   PART -1 – LENGTH 60 M       PART -2 – LENGTH 60 M          PART -3 – REMAING LENGTH 80 M
     TOP-
     TOP-DOWN METHOD – STAGE-
                       STAGE-1 – GUIDE WALL & RETAINING WALL CONSTRUCTION BY D-
                                                                             D-WALL METHOD
     AS PRPOSED BY Assy. STUP Consultants.
GROUND LVL
                                                                       1. INSTALL GUIDE WALL (APPROX. 1.2M DEEP,
                                                                          150MM THICK) FOR RETAINIG WALL
                                                                          CONSTRUCTION
                                                      12.4M APPROX..
BASEMENT-O1                                                            2. CAST RETAINING WALL IN PANEL SIZE AS PER
                                                                          GFC DRAWING UP TP TOP OF GUIDE WALL
                                                                          LEVEL USING D-WALL METHOD.
BASEMENT-O2                                                            3. BEFORE CASTING, COUPLER SHALL BE LEFT AT
                                                                          BASEMENT LVL-01 AND BASEMENT LVL-02 AS
                                                                          APPLICABLE.
                                                                       4. WATER STOPPER SHALL ALSO LEFT IN POSITION
                                                      7.5M
                                                                          TO ACHIEVE PROPER WATER TIGHT JOINTS
                                                                          BETWEEN ADJACENT RETAINIG WALL PANNELS
             TOP-
             TOP-DOWN METHOD STAGE-
                             STAGE-2 - BARRETTE CONSTRUCTION AS PRPOSED BY Assy. STUP Consultants.
                                                                             1. ALL BARRETTE SHALL BE MARKED AT
GROUND LVL                                                                      SITE AS PER GFC DRAWING.
                                                                             2. SOIL GRABBING UP TO REQUIRED
                                                                                DEPTH FOR BARRETEES AS PER GFC
                                                            12.4M APPROX..
BASEMENT-O1                                                                     DRAWING.
                                                                             3. INSTALL REINFORCEMENT CAGE FOR
                                                                                BARRETTE (APPROX SIZE: 2500X1200)
                                                                                AT BARRETTE LOCATIONS.
BASEMENT-O2                                                                  4. NECESSARY COUPLERS TO BE
                                                                                PROVIDED IN BARRETTE FOR
                                                                                CONNCTING RESPECTIVE LEVEL
                                    7.5 M
                                                            7.5M
                                                                                FLOOR SLAB/RAFT SLAB
                                                                             5. POUR CONCRETE IN BARRETE.
             TOP-
             TOP-DOWN METHOD - STAGE-
                               STAGE-3 -GROUND LEVEL SLAB CONSTRUCTION AS PRPOSED BY
             Assy.STUP Consultants.
                                                                       1. LEVELING WITH PCC & REQUIRED FORMWORK
GROUND LVL                                                                TO BE PLACED FOR CASTING OF GROUND LEVEL
                                                                          SLAB.
                                                                       2. TEMPORARY OPENINGS TO BE KEPT IN A
                                                      12.4M APPROX..
BASEMENT-O1                                                               STRATIGICAL LOCATION FOR MUCK AND
                                                                          CONCRETING IN NEXT STAGES.
                                                                       3. PLACE THE REINFORCEMENT FOR THE GROUND
                                                                          LEVEL SLAB WITH NECESSARY CONNECTION
BASEMENT-O2                                                               WITH RETAINING WALL REINFORCEMENTS
                                                                       4. CAST THE GROUND LEVEL SLAB INTEGRATING
                                                                          WITH CAST-IN-SITU RETAINING WALL
                                      7.5M
                                                         7.5M
        TOP-
        TOP-DOWN METHOD - STAGE-
                          STAGE-4 –REMOVAL OF EARTH BELOW GL SLAB & FIRST LEVEL BASEMENT
        SLAB CONSTRUCTION
                                                                          1. AFTER 14 DAYS OF CASTING OF GROUND
                                                                             LEVEL SLAB, EXCAVATION CAN BE CARRIED
GROUND LVL                                                                   OUT FOR BASEMENT LEVEL SLAB-01.
                                                                          2. PCC & REQUIRED FORMWORK TO BE PLACED
                                                                             FOR CASTING OF BASEMENT LEVEL SLAB 01
                                                         12.4M APPROX..
                                                                          3. TEMPORARY OPENINGS TO BE KEPT IN A
BASEMENT-O1
                                                                             STRATEGIC LOCATION FOR MUCK AND
                                                                             CONCRETING IN NEXT STAGES.
                                                                          4. PLACE THE REINFORCEMENT FOR THE
BASEMENT-O2                                                                  BASEMENT LEVEL SLAB-01 WITH NECESSARY
                                                                             CONNECTION WITH RETAINING WALL
                                                                             REINFORCEMENTS
                                                           7.5M
                                                                          5. CAST THE BASEMENT LEVEL SLAB-01
                                  7.5M
                                                                             INTEGRATING WITH RETAINING WALL
       TOP-
       TOP-DOWN METHOD - STAGE-
                         STAGE-5 –REMOVAL OF EARTH BELOW FIRST BASEMENT & RAFT SLAB
       CONSTRUCTION
GROUND LVL
                                                                                  12.4M APPROX..
BASEMENT-O1
BASEMENT-O2
                                       7.5M
                                                                                  7.5M
             1. REPEATE PREVIOUS STAGE-4 METHODS FOR REMOVAL OF SOIL BELOW FIRST BASEMENT
                FLOOR & RAFT SLAB CONSTRUCTION.
METHOD OF MUCK REMOVAL UP TO -5M & -12.5m LEVEL
TYPICAL COUPLER ARRANGEMENT DETAILS
Continued……
  TOP-
  TOP-DOWN METHOD–
           METHOD– Tower Crane
NOTE:
1. TOWER CRANE RADIUS – 60M
2. TOP TRUSS PROTRUDED AROUND @ 15M INTO IR
   AREA. BUT, LIFTED LOAD SHOULD BE WELL WITH IN
   KRIDE AREA
TOP-
TOP-DOWN METHOD–
         METHOD– Tower Crane -Section
              TOP-
              TOP-DOWN METHOD - STAGE-
                                STAGE-5 –SIMULTANEOUSLY CONSTRUCTION WORK TOWARDS
              UP SIDE & DOWNSIDE
Basement 01                                                                                          First floor slab
                After casting of basement level 01 slab, during the Raft casting, parallelly first
                                       floor also can be constructed.
WHY WE ARE GOING WITH TOP-DOWN METHOD CONSTRUCTION
• 1. Space constraints & Obstructions for Anchorage system
A) As per design, minimum Anchorage length required is ranging from 14m to 20m. Same is not
available towards Apartment side.
WHY WE GOING WITH TOP-DOWN METHOD CONSTRUCTION
• 2. Difficult for Installation & Removing “Strut & Waller” system
• A) Huge Structural Materials required for Strut and Waller arrangement.
• B) There is no Crane access for Installing & removing Struts.
• C) Manual shifting time will not match for this project.
                                                                     With conventional soldier pile with Strut and Waller
Note: Both Excavation & Retaining wall (by D-wall method) payment will explore to get from client for which
necessary scheme/GFC drawing shall be prepared accordingly.
CONCLUSION OF TOP-
              TOP-DOWN METHOD
• As per site condition, one side Indian Railways running line and other side private High-
  rise Apartment, due to which, there is no access along length of the building.
• As per design, minimum Anchorage length required is ranging from 14m to 20m. Same
  is not available due to Obstruction of High-rise building Basement floors (2 numbers)
• Towards Railway side, Space in between proposed Station building and Railway boundary
  is very less, we cannot provide shoring arrangement.
• In Safety point of view, shoring arrangement with secant pile/soldier pile not suitable for
  protection & safety of existing Railway Boundary during construction period of 7 to 8
  months.
• In Construction of Bottom-up method, time cycle is more and not matching with KD
  requirements.
• Installation & Material Cost of “Secant pile/soldier pile along with Waller beam with
  Strut/Anchoring can be saved.
• Casting of Basement level-01 & Ground level slab Staging work can be avoided and cost
  saved.
• Similar type Top-Down construction project is going on at Chennai.
• Ground level casted slab will act as a Strut and Waller support in Top-Down method.
• As per concern of Designer, the Tender Schematic drawing “Raft foundation along with
  Retaining wall” will not cater design requirements.
• After thorough review of site along with DDC designer input, it is better to go for
  construction of Retaining wall (by D-wall Method) and two basements with Top-Down
  Method.
         Hence we are preferring Top-Down method for YPR Station construction.
                                   Thank You