Air India LTD vs. GATI LTD., 2015 SCC OnLine Del 10220
Air India LTD vs. GATI LTD., 2015 SCC OnLine Del 10220
O.M.P. 1264/2013
Air India Ltd. .…. Petitioner
Mr. R.S. Suri, Senior Advocate with Mr. Manoj Arora, Mr. Siddharth
Shanker and Ms. Pallavi Tayal Chadda, Advocates.
Versus
Gati Ltd. .…. Respondent
Mr. P.V. Kapur, Senior Advocate with Mr. Vijay Nair, Mr. Ravi Gandhi,
Mr. Puneet Damodar and Mr. Ritesh Sharma, Advocates.
And
O.M.P. 1082/2014
Gati Ltd. .…. Petitioner
Mr. P.V. Kapur, Senior Advocate with Mr. Vijay Nair, Mr. Ravi Gandhi,
Mr. Puneet Damodar and Mr. Ritesh Sharma, Advocates
Versus
Air India Ltd. .…. Respondent
Mr. R.S. Suri, Senior Advocate with Mr. Manoj Arora, Mr. Siddharth
Shanker and Ms. Pallavi Tayal Chadda, Advocates.
O.M.P. 1264/2013 and O.M.P. 1082/2014
Decided on July 7, 2015
JUDGEMENT
1. These are two petitions under Section 34 of the Arbitration and
Conciliation Act, 1996 (‘Act’) challenging the unanimous Award dated
17th September 2013 of a three member Arbitral Tribunal (‘AT’) in the
disputes between the parties.
2. A wet lease freighter agreement (‘WLA’) was entered into between
GATI Ltd. (‘GATI’) and Indian Airlines Ltd. (‘IAL’) for lease of five
freighter Boeing 737-200 aircrafts. As a result of the merger of IAL with
Air India Ltd. (‘Air India’), all the rights, interest, duties, liabilities and
obligations of IAL and Air India have been vested in the National
Aviation Company of India Ltd. (‘NACIL’).
3. Air India owned old Boeing 737-200 aircrafts which were operated
by its passenger flight service called Alliance Air. Since the aircrafts
were not in good shape from the point of view of safety and security,
Air India decided to convert them into cargo freighters. Proposals were
invited by Air India from interested parties to block space in the said
SCC Online Web Edition, © 2025 EBC Publishing Pvt. Ltd.
Page 2 Friday, March 14, 2025
Printed For: Mr. Srinandan K .
SCC Online Web Edition: https://www.scconline.com
© 2025 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
cargo freighters which were to be operated under the ‘hub and spoke’
pattern. An offer was submitted by GATI on 9th April 2007, and its
acceptance resulted in the WLA being entered into between the parties
th
on 16 May 2007.
Relevant clauses of the WLA
4. In terms of the WLA, Air India agreed to lease five freighter
Boeing 737-200 aircrafts to GATI for a period of five years commencing
th th
from 15 July 2007 till 14 July 2012 on the terms and conditions
contained in the agreement. The aircrafts were to be provided with
cockpit crew and with complete maintenance, operations and full
insurance.
5. In terms of Clause 3.1 of the WLA, the leased aircrafts were to
offer payload of approximately 15 tons on each of them “on committed
basis for agreed freighter flights for the hours mentioned in Clause
5.1”. For the rest of the duration, Air India had discretion to use the
leased aircrafts. Air India was to ensure that the leased aircraft was in
compliance with the minimum ICAO requirements relating to their
airworthiness standards. Air India was to comply with the specific
requirements of the Directorate General of Civil Aviation (‘DGCA’) of
India; it was to obtain all Government clearances including clearances
of crew to operate the leased aircraft. In terms of Clause 3.4, the
operations and the maintenance of the aircraft were to be in accordance
with the rules and standards applicable in India and the approved
maintenance and flight manuals of Air India as per the
recommendations of the manufacturer of the aircraft. Under Clause 3.6,
it was provided that Air India assumed no responsibility for loss of
available payload due to any load restrictions or penalties imposed on
the sectors of operations that may arise based on the performance of
the aircraft.
6. Under Clause 4.1, it was stated that the aircrafts were scheduled
to be inducted as per Clause 5.6 which set out a table of the dates of
such schedule. The five aircrafts were numbered as A1 to A5. The
scheduled date of the operation of the aircraft with reference to the in-
date and out-date for conversion at the vendor's location were as
under:
Aircraft Aircraft Aircraft out Aircraft
proposed in Date from Schedule date
date at Vendors Vendors for Operation
Location for Location after
Conversion Conversion
A1 25th Mar'2007 30 Jun'2007 15 Jul'2007
A2 15 May'2007 15 Aug'2007 01 Sep'2007
SCC Online Web Edition, © 2025 EBC Publishing Pvt. Ltd.
Page 3 Friday, March 14, 2025
Printed For: Mr. Srinandan K .
SCC Online Web Edition: https://www.scconline.com
© 2025 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
lease, the fact was that specific identified aircrafts were to be provided
to GATI. He reiterated that the minutes of the BOD meeting dated 11th
July 2007 itself recorded that the first aircraft was meant to be given to
INDIAPOST. There was no denial of this fact in the SOD filed by Air
India before the AT.
24. The Court has been shown the minutes of the meeting held
between the parties on 5th September 2007. Part-1 of the said meeting
nd
states “The 2 Aircraft to GATI is arriving on 16.09.2007 duly
converted and it would take 15 days for completing the formalities and
painting”. Admittedly, there was no aircraft delivered to GATI prior to
September 2007. It is not possible to read the minutes of the meeting
dated 5th September 2007 as an admission by GATI that it
acknowledged that the first aircraft has already been given to
INDIAPOST by Air India. On the other hand, as rightly noted by AT, the
rd th
minutes of the 93 meeting of the BOD held on 11 July 2007 notes
that five aircrafts were already at Miami for conversion and it had been
decided to convert a sixth aircraft on the same basis as well. The
minutes clearly recorded “The first converted aircraft to be given to DOP
for operations in NE stations as per the schedule and GATI operation to
commence from 01.09.2007.” The above minutes therefore
acknowledge that despite the agreement with GATI, the BOD had
unilaterally decided to postpone the commencement of the operations
to 1st September 2007 without the knowledge of GATI. When read with
these minutes the reference to the ‘second freighter’ in the minutes
th
dated 5 September 2007 could only refer to the second freighter
aircraft which was then given to GATI as the first aircraft under the
WLA.
25. The Court is unable to agree with the submissions of Mr. Suri
that the AT has misread and misinterpreted the WLA. The
correspondence between the parties shows that there was no
agreement between the parties to rephrase the WLA as a charter
agreement. The conclusion of the AT that the aircraft VT-EHH was
definitely the subject matter of WLA and that its allotment to
INDIAPOST was in breach of the WLA appear to be a perfectly possible
conclusion on the reading of the entire evidence. Clearly the minutes of
th
the BOD meeting of 11 July 2007 reveals that IAL was fully aware of
the consequences of the breach it was committing of the WLA in
diverting the first freighter aircraft to INDIAPOST. The Court therefore
finds no error having been committed by the AT in deciding the Issue
No. 1 in favour of GATI.
Issue No. 2
SCC Online Web Edition, © 2025 EBC Publishing Pvt. Ltd.
Page 8 Friday, March 14, 2025
Printed For: Mr. Srinandan K .
SCC Online Web Edition: https://www.scconline.com
© 2025 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
26. Two questions were addressed under Issue No. 2. The first was
whether there was a delayed and deficient delivery of aircrafts [2(a)]
and whether the dates mentioned in Clause 5.8 of the agreement were
promised dates or tentative dates [2(b)]. As far as the first freighter
th
aircraft was concerned since it was delivered only on 17 October 2007,
th
instead of 15 July 2007, clearly there was a delay of more than three
th
months. Likewise, the second aircraft was offered on 27 December
2007 after a delay of more than four months. The third, which was
initially offered on 7th May 2008, and then withdrawn, reoffered on 11th
July 2008, was with a delay of seven months and the fourth aircraft was
th
offered on 27 July 2008 with a delay of more than eight months. As
regards the fifth freighter, the finding of the AT was that there was no
documentary evidence to support the plea that it was at all offered to
GATI but not taken delivery of. The AT accordingly concluded that the
fifth freighter was in fact never offered. Both the issues were
accordingly answered in favour of GATI by the AT.
27. Mr. Suri submitted that the AT erroneously interpreted Clause
5.8 of the WLA which only provided for tentative dates. The delay
attributable to the agencies in Miami, USA in converting the aircrafts
could not be fastened on Air India. This aspect had been dealt with in a
supplement to Note-3 which was submitted to the AT by Air India. The
air operator licence which had been filed during the arbitral proceedings
proved that Air India converted six aircrafts and not five. Both the
Clauses 4.1 and 5.8, according to Mr. Suri, clearly provided that any
delay on the part of the agencies entrusted with the conversion of the
aircrafts, would not make Air India liable. Apart from not proving that it
suffered any loss of business, GATI did not lead any evidence to show
that it had any problems with the postponement of the commencement
th
of the operations w.e.f. 18 October 2007. This only showed that GATI
had prior knowledge that it was to start operations from October 2007
and not from 15th July 2007 as proposed in the WLA.
28. Mr. Kapur, in reply, pointed out that once the WLA itself had
settled the schedule for induction of the aircraft, it was obvious that
any delay would adversely affect the business of GATI. He submitted
that the interpretation placed by the AT on Clauses 4.1 and 5.8 that
they cannot offer protection against unreasonable delay was a plausible
interpretation. He pointed out that detailed reasons have been given by
the AT in the impugned Award for its conclusions. He further submitted
that what Air India was inviting the Court to do was to re-appreciate
the evidence. At no point of time the Air India proved before the AT
that it had a fifth aircraft ready to be offered to GATI. It was submitted
that if the findings of the AT were plausible, this Court should not
SCC Online Web Edition, © 2025 EBC Publishing Pvt. Ltd.
Page 9 Friday, March 14, 2025
Printed For: Mr. Srinandan K .
SCC Online Web Edition: https://www.scconline.com
© 2025 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
enhancing the payload. However, it has been confirmed by him that the
same cannot be increased”. The note concluded “Therefore, the
available payload could be 12.5 tonnes only”.
th
43. The minutes of the meeting dated 15 July 2008 also recorded
that the DGM(Finance) has suggested that the agreement itself to be
amended to ensure ‘correct billing and settlement’ on the issue of
‘payload capacity’ The correspondence between the parties which has
been discussed by the AT showed that the case of Air India was that
the full load would become available only when the ‘hub and spoke
operations’ with the fourth freighter would commence.
44. The AT also discussed the evidence of six of the witnesses of Air
India who were posted at various airports. They deposed instances
“directly within their knowledge where 15 MT payload or payload more
than 12.5 MT was tendered on behalf of the Claimant, but it was
refused to be accepted for carriage by the freighter operating with the
Claimant by the Respondent”.
45. Nothing has been shown to the Court to persuade it to hold that
the above conclusion of the AT on the reading of the depositions of the
aforementioned witnesses i.e. CWs 3 to 8 was erroneous. The AT also
appears to have been persuaded by the fact that cargo in excess of 12
to 12.5 MT was carried by Air India by next available commercial flight
without charging GATI for it, thereby admitting to its failure. The AT
has also discussed the evidence of Mr. Anil Shakdher (RW-2) as regards
the availability of payload after accounting for the fuel requirement. In
particular it has even set out the entire evidence in this regard. In para
7.3.33 it has dwelled on the expression ‘approximate’ and concluded
that the expression ‘approximately 15MT’ may at the most permit a
variation between the range of 14 to 16 and not a reduction to 12.5 MT
which would be really a variation of 37.5% over 15 MT.
46. The Court is not persuaded to hold that the above detailed
discussion of the evidence by the AT and its analysis suffers from any
material irregularity much less any patent illegality. On the evidence
before it, it was for the AT to take a call on what was the inference to
be drawn as any reasonable person would in the facts and
circumstances of the case. None of the findings of the AT is improbable
or contrary to the evidence on record. The award in respect of the
aforementioned three issues cannot said to be erroneous warranting
any interference by this Court.
Issue No. 4
47. Issue No. 4 was whether the Nagpur airport was not ready for
operations as a hub and spoke center and whether the Claimants were
not ready to implement the hub and spoke operations from Nagpur [4
(a) and 4(b)]. The AT concluded after extensively dealing with the
SCC Online Web Edition, © 2025 EBC Publishing Pvt. Ltd.
Page 13 Friday, March 14, 2025
Printed For: Mr. Srinandan K .
SCC Online Web Edition: https://www.scconline.com
© 2025 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
th
evidence that there were at least three letters namely letters dated 8
August, 19th August and 8th October 2008, whereby GATI indicated its
readiness and willingness to commence hub and spoke operations but
Air India did not respond, much less give any fixed date for such
commencement.
48. Further, the internal reports dated 19th May, 11th August, 2nd
th
September and 8 September 2008 of Air India clearly showed the
acceptance of readiness on the part of Air India to commence hub and
spoke operations at Nagpur. In para 7.4.29, the AT recorded the
contention of Mr. Suri that hub and spoke operations were to start only
after four freighters were to be inducted. In the petition under Section
34 of the Act, there is no averment that the above contention recorded
in para 7.4.29 was not made by Mr. Suri. He, however, urged that the
AT failed to look at the matter from the operational and technical
aspects of the industry's norms and practices. According to him, the
internal reports and discussions between the officers of Air India have
been misunderstood by the AT as revealing an absence of readiness to
commence the hub and spoke operations at Nagpur.
49. On the other hand, Mr. Suri again took the Court through the
entire correspondence to show that the Respondent was never prepared
to avail of the fourth freighter even after it was offered by Air India. He
submitted that at no point of time, did GATI inform the Air India that it
was unable to start operations at Nagpur because the hub and spoke
operations had not commenced. Even on 6th August 2008, GATI
informed Air India that they would operate only three freighters from
th
Nagpur as a hub and spoke pattern from 9 September 2008 and the
fourth would be a standby. Mr. Suri accordingly submitted that no
evidence had been produced by GATI to show that the Nagpur airport
was not ready for the hub and spoke operations.
50. The Court does not propose to re-appreciate the entire evidence
on this aspect. This has been exhaustively discussed by the AT in paras
7.4.1 to 7.4.30. The inferences drawn by the AT from three letters
whereby GATI had expressed its readiness to commence the hub and
spoke operations has not been countered by Air India. The inferences
drawn by the AT from the internal reports and communications have
not been shown to be erroneous.
51. The contents of the said internal notes do reveal that the
infrastructure at Nagpur was not ready for the hub and spoke
operations during the dates of these notes i.e. between May and
September 2008. The Court is not expected to re-appreciate the
evidence and to interfere with the impugned Award only because a
different view is possible. In any event, this Court is not persuaded to
SCC Online Web Edition, © 2025 EBC Publishing Pvt. Ltd.
Page 14 Friday, March 14, 2025
Printed For: Mr. Srinandan K .
SCC Online Web Edition: https://www.scconline.com
© 2025 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
56. The Court has already upheld the findings of the AT on the
failures of the Air India to fulfill its obligations under the WLA. The AT
has discussed Section 39 of the Indian Contract Act, 1872. It gives the
right to the promisee to put an end to the contract if the promisor, in
this case Air India, “has refused to perform, or disabled itself from
performing, its promise in its entirety.” In these circumstances the
conclusion of the AT that Section 39 permits GATI to terminate the
contract without having to comply with the requirement of Clause 12.1,
which was not attracted to a case of repudiatory breach of contract is a
perfectly plausible conclusion and cannot be faulted with.
57. The Court notes that as regards the actual claim for damages
what has been awarded by the AT is not the entire amount claimed. As
regards the amount wrongly charged on account of deficient payload
capacity, as against the claim of Rs. 1741.97 lakhs, the AT has awarded
only 50% as a corollary to the conclusion that the promised payload
capacity was not made available.
Other issues
58. The other amount awarded is Rs. 429.58 lakhs being
overcharged on account of unilateral increase in the ATF prices. This
has been discussed threadbare under Issue No. 12 in the Award with
reference to the correspondence between the parties and the minutes
of the meetings. If there was any change which was contemplated, it
had to be incorporated in the agreement. The minutes of the meeting
shows that there was no such amendment to the agreement to permit
any unilateral increase in the ATF rates. On the question of excess
amount recovered by encashing the BG, the AT has allowed the claim of
Rs. 59,64,535. This also is based on the evidence produced before the
AT.
Damages
59. However, the Court finds that in para 7.14.8 the AT found
substance in the criticism of Air India and concluded “The least which
the Claimant could have done was to file before the Tribunal its annual
accounts indicating the trends of profits wherefrom some reasonable
inference as to the likely loss suffered by the Claimant could have been
drawn”. Nevertheless, the Tribunal appears to have gone by the
principle that “the Claimant cannot be left high and dry”. While
observing in para 7.14.10 that “we would not like to speculate”, the AT
has proceeded to make an assessment of “just and reasonable profits”
and awarded a sum of Rs. 497 lakhs by way of damages.
60. This was not a case where Air India had wrongfully terminated
the contract. This was a case where GATI had terminated the contract
on account of repudiatory breaches by Air India. Therefore, the decision
relied upon by the AT viz., A.T. Brij Paul Singh v. State of Gujarat
(1984) 4 SCC 59 was not strictly applicable. On the other hand, Air
SCC Online Web Edition, © 2025 EBC Publishing Pvt. Ltd.
Page 16 Friday, March 14, 2025
Printed For: Mr. Srinandan K .
SCC Online Web Edition: https://www.scconline.com
© 2025 EBC Publishing Pvt. Ltd., Lucknow.
-----------------------------------------------------------------------------------------------------------------------------------------------------------
India was justified in its plea that it was incumbent upon GATI to
provide at least some basis as to the likely loss it may have suffered by
producing its annual accounts or any other evidence. This clearly GATI
failed to do. Consequently, the Court finds no basis for the AT to award
GATI Rs. 497 lakhs by way of damages. The award to that extent is
hereby set aside.
Costs
61. However, as regards awarding the cost of arbitration the Court is
unable to find any error having been committed by the AT and
therefore, it is not considered necessary to interfere with the Award in
that regard.
62. As regards counter claims of Air India, which was essentially by
way of damages and would have resulted only if GATI was found to be
in breach of the agreement, since the Court has upheld the findings of
the AT that it was Air India who committed breach of several
obligations and thereby repudiated the contract its rejection of the
counter claims of Air India is accordingly upheld.
63. O.M.P. No. 1082 of 2014 by GATI is a petition under Section 9 of
the Act, seeking directions to Air India to deposit the awarded amount
or create a charge on an immoveable property or provide a bank
guarantee. The Court is not at this stage inclined to grant such relief.
The remedy under Section 36 of the Act would, in any event, be
available to GATI at the appropriate stage.
Conclusion
64. O.M.P. No. 1264 of 2013 by Air India is disposed of by setting
aside the award of Rs. 497 lakhs in favour of GATI and upholding the
impugned Award dated 17th September 2013 in all other respects.
O.M.P. No. 1082 of 2014 is dismissed. There shall be no order as to
costs.
———
Disclaimer: While every effort is made to avoid any mistake or omission, this casenote/ headnote/ judgment/ act/ rule/
regulation/ circular/ notification is being circulated on the condition and understanding that the publisher would not be
liable in any manner by reason of any mistake or omission or for any action taken or omitted to be taken or advice
rendered or accepted on the basis of this casenote/ headnote/ judgment/ act/ rule/ regulation/ circular/ notification. All
disputes will be subject exclusively to jurisdiction of courts, tribunals and forums at Lucknow only. The authenticity of
this text must be verified from the original source.