GP - 01 - 7.4 - 0007 - QA Measures For Procurement of Purchased Parts 2.cleaned
GP - 01 - 7.4 - 0007 - QA Measures For Procurement of Purchased Parts 2.cleaned
GP-01-7.4-0007 | REV. 7
The aim of defined requirements is to ensure that new and change projects are carried out on schedule
and without any quality problems. Excelling in the automotive market while attaining growth requires
investment and continual improvements of quality and delivery along with rapid and flexible reactions to
change. Core principle of Vibracoustic is a Zero- D e f e c t strategy that protects customer satisfaction.
This strategy is only attainable with the active co-operation of our suppliers.
This procedure must be implemented and followed consequently for each project.
This Global Procedure is part of the framework contract with the supplier. Deviations from the defined
procedure must be agreed to in writing between VC and the supplier. The existing procedure
specification identifies the minimum requirements for the secure handling of new projects and series
production orders. In addition, the supplier must commit to employ suitable procedures and measures
which ensure that the work/product satisfies the requirements regarding quality, cost, and timely targets.
Department Date
Producer SCM 17.06.2022
Approval Process Owner SCM 17.06.2022
Approver Management System QM 31.08.2022
Approver Management Board
- 03.04.2023
(Global Procedures only)
TABLE OF CONTENTS
INTRODUCTION 1
1. PURPOSE 4
2. SCOPE 4
3. TERMS / DEFINITIONS / ABBREVIATIONS 4
3.1 Definitions 4
3.2 Abbreviations 6
4. PROCESS / METHOD / PROCEDURE 8
4.1 SQMS Supplier Quality Management System 8
4.2 QM-system 9
4.2.1 Product Safety Representative 9
4.2.2 Qualification of Special Processes – CQI 9
4.3 Contract Review 10
4.4 Control of documents 10
4.5 Customer Specific Requirements (CSR) 10
4.6 Control of materials and packaging provided by VC 10
4.7 Environmental protection 10
4.8 Responsible sourcing - Conflict Minerals and Cobalt Commitments 11
4.9 Audits 11
4.10 Staff 11
4.11 Equipment 11
4.12 Qualification of sub-contractors 11
4.13 Safety data sheets / Processing instructions 11
4.14 Software Quality Requirements 11
4.14.1 Software Development 11
4.14.2 Software Flashing 12
4.14.3 General Requirements 12
4.15 Advanced Product Quality Planning (APQP) 12
4.15.1 Control Plan 13
4.15.2 Process Flow Chart 13
4.15.3 Process-FMEA 13
4.16 Supplier Run@Rate 14
4.17 Production Part Approval Process (PPAP) 16
4.17.1 Requirements for series production release 16
4.17.2 Production Parts Approval 18
4.17.3 Tooling information 18
4.18 Series production 18
4.18.1 Test records 18
4.18.2 Early Production Containment (EPC) 19
4.18.3 Requalification Test 19
4.18.4 Zero defect – continuous improvement process 19
4.18.5 Traceability 19
4.18.6 Identification of containers, delivery notes, labelling and transport orders 19
4.18.7 Packaging 19
page 2 / 25 Uncontrolled Copy if Printed
GP-01-7.4-0007 | REV. 7
QUALITY ASSURANCE MEASURES FOR
PROCUREMENT OF PURCHASED PARTS
1. PURPOSE
In this procedure the procurement and quality assurance of purchased parts of production material
for all VC companies is specified. Thereby we want to ensure that
New products are launched on schedule and without any quality problems
Quality problems are identified, and robust solutions implemented prior to series production
Quality capability of processes are evidenced at series approval and during series production
2. SCOPE
This GP is valid for all procurement processes of production material for all VC companies with
partnership production of purchasing contracts and purchasing conditions. Exceptions to this procedure
must be agreed in writing. Standard products (e.g., catalogue goods, standard parts, standard colours,
lubricating materials, chemicals, etc.) and intercompany business are excluded.
3.1 Definitions
SQMS
The Supplier Quality Management System describes the business process of supplier selection,
evaluation, and development as well as actions for the protection of new projects and series parts.
Initial Samples
Initial samples of finished product produced with the planned equipment, procedures, manufacturing
staff, materials, and semi-finished products exclusively for series production. They are used for Production
Part Approval Process.
FMEA
Failure Mode and Effects Analysis
This method is described in VDA volume 4, part 2 resp. and the AIAG reference manual. OEM specific
FMEA- requirements (i.e., Ford – FMEA) must be met by supplier.
Supplier
The term “supplier” refers to production facilities in this GP, not to trade organizations. Therefore,
an “Approval of Suppliers” always applies correspondingly to the audited production site only, not to
the general trade organization.
Sub-Contractor
The sub-contractor delivers to the supplier products or labour which have an effect to the products
of VC. The supplier guarantees the sub-contractors’ quality.
Sub- Customer
Supplier VC
Contractor
Within the PTR, the systematic analysis of the first production lot (first batch) should be analysed
systematically to guarantee the early and systematic process optimization and do not require the complete
planned series process.
Supplier Run@Rate (SRR)
Supplier Run@Rate serve as verification of processes and products. Parts must be manufactured with
operating supplies used for series production over an extended period of time (at least 300 parts or 1
shifts). With this milestone the production process will be technically evaluated (scrap, capacity) and the
necessary production documents checked. If manufacturing is not possible under series conditions, the
status must be communicated to VC and its effect on series production needs to be assessed.
Special Characteristics
Significant and critical characteristics are designated in the drawings using the following acronyms:
- Emphasis Characteristic = EC
Requirement for Ppk, Cpk value may be higher as per specific Customer Requirement.
3.2 Abbreviations
AIAG Automotive Industry Action Group
BU Business Unit
CM Commodity Management
DV Design Verification
GP Global Procedure
IR Inspection Report
PG Product Group
SW Software
VC Vibracoustic
Supplier Industrialization
4.2 QM-system
Certification of QMS according to ISO 9001 by accredited body is the minimum requirement for all VC
suppliers.
VC requests suppliers of productive parts and services to implement their QMS certified IATF 16949.
Those suppliers not yet certified to IATF 16949 must show plan to achieve this certification.
The requirements for error proofing and inspection of production parts must be fully implemented for all
VC products. The supplier must also incorporate any relevant VC / Customer Specific Requirements (may
be provided by VC upon request) into its QMS system that refers to the specific product or service.
The supplier must inform VC immediately if the certificate has been revoked, placed on suspension, or
expired without successful recertification.
After successful recertification, new certificates must be shared with VC electronically using VC
communication platform “LiveSource”
If requested by CSR, the suppliers must provide the PSCR certification using VC communication platform
“LiveSource”.
The CQI self-assessments must be performed at least annually. The cover sheet and action plans to
address gaps must be shared with VC electronically via VC communication platform “LiveSource”.
4. CQI standards
www.vda-qmc.de
The supplier is responsible to maintain and revise their system to the latest customer standards.
consider the country of manufacture and the customer. Customer Specific Standards and Requirements
must be considered for the specific process and product.
4.9 Audits
The supplier must audit its QM-System at regular intervals for effectiveness and compliance to the
requirements described in this procedure. VC is entitled to carry out – if necessary, with the customers,
audits at the supplier and at its sub-contractors – after appointments are made. The supplier must support
VC in carrying out the audit into the required procedures, data, and records for analysis of the Quality
Management System. VC will maintain the supplier’s confidentiality.
4.10 Staff
The supplier must demonstrate that all employees who work in the areas of planning, production and
inspection are qualified.
4.11 Equipment
The supplier must ensure that suitable test equipment for carrying out inspections defined in drawings
and its referenced documents are available and that the equipment is maintained in proper condition. The
suitability of inspection equipment, which is used for testing important characteristics, is to be verified
and records retained (AIAG MSA Manual or VDA Manual 5).
In case the supplier part includes safety related software, the software development must comply with
ISO 26262.
The target for the capability level must be agreed with the responsible SQATC/ PQE during nomination
phase. Recommended minimum is level 2 (managed) or higher as per Customer Specific requirements.
The correct transfer of the software between supplier and VC must be verified by check sum control.
The supplier must ensure that only the latest and approved SW is used in production.
For serial production, the supplier needs to ensure and prove that the supplier’s tools chain used for
flashing fulfils the level of confidence in the use of tools requested by ISO26262.
Depending upon individual usage of the component there can be additional quality requirements from VC.
All requirements from specification or drawing needs to be respected.
A project time schedule must be created with consideration for the following items:
Responsible persons must be listed by name and contact data (phone, mobile, email)
All controls for product and process characteristics, test equipment, testing intervals, test volume, form
of the records and reaction plan must be defined for pre-series and series production.
The Control plan must reflect the entire process chain of contracted part-number, including outsourced
processes. The Control plan of the subcontractors must be provided to VC upon request.
All Control Plans must have a yearly re-qualification requirement, and the supplier must have the
information available for VC upon request.
Content of control plans must be adopted according to the regulations of IATF 16949 latest revision, or
AIAG.
A process flow chart must be compiled for the whole manufacturing process. The process flow chart must
be sent to VC as part of PPAP package. The process flow chart must reflect entire process chain of
contracted part-number, including outsourced processes.
Process flow chart must be submitted with every supplier final offer to VC. Draft may be accepted at this
time.
Remark: The process number sequence must be the same through all documents (Flow,
Control plan, FMEA)
4.15.3 Process-FMEA
The Failure Mode and Effects Analysis must be carried out before series production as a method of
proofing. To minimize potential cost and conduct appropriate corrective actions if needed, the FMEA
should be developed at the earliest possible time in the APQP process.
PFMEA must reflect entire process chain of contracted part number, including outsourced processes.
Method and formal structure must correspond to VDA 4, Part 2. OEM specific FMEA requirements (i.e.,
AIAG FMEA manual, Ford FMEA ranking system) must be assured by supplier.
A prerequisite for a production parts release (initial samples approval) is the supplier’s confirmation that
the required Process-FMEA has been carried out on the first sample test report. On request the FMEA must
be provided for review or presented at VC site.
page 13 / 25 Uncontrolled Copy if Printed
GP-01-7.4-0007 | REV. 7
QUALITY ASSURANCE MEASURES FOR
PROCUREMENT OF PURCHASED PARTS
Before series production the capability of important features must be proved during supplier Run@Rate.
The VC approved methods, processes and materials mentioned below must be used for this evaluation.
Supplier Run@Rate is performed in the following ways:
‘Zero defects strategy is only possible with controlled quality – efficient processes’
Process
Man Man
Material Material
Method Method
Environment Environment
50 5 5 … 5 5 5 5 … 5 5 …
Time
Minimum 50 parts or process- Minimum 125 parts or process- An appropriate period under
oriented extent oriented extent. The 125 parts normal series conditions in which
should ideally be done in 25 it is assured that all influencing
samples; 5 parts spread over the factors could become active.
lot Indicative value:
20 production days/lots
Pm, Pmk Pp , Ppk Cp, Cpk
Machine Performance
The study of machine performance determines the suitability of the manufacturing equipment for
production task.
Sample size: At least 50 parts from continuous production run in an uninterrupted sequence must be
measured.
Machine performance (Pm, Pmk): A machine performance of Pm, Pmk ≥ 1,67 for significant characteristics
is required (or higher as per specific Customer Requirement).
Note: [ISO 22514-3] uses the indices Pm & Pmk in place of Cm & Cmk, denoting Machine Performance.
Collect 5 parts, skip 5 parts, collect 5 parts, skip 5 parts, etc.... In cases of multiple cavities, we accept 125
samples for 1 feature if samples from all cavities are randomly selected. If capability is not OK, supplier
demonstration of capability per cavity is acceptable. All distributions must be normal (and process data
is statistically in control and stable).
Samples Records: Individual values must be recorded (test records) and may be viewed by VC upon
request.
Preliminary process performance (Ppk): To fulfil the demand for a “Zero Defect Objective” a Ppk>1.67 for
significant characteristics is required (or higher as per specific Customer Requirement).
Capability Records: The preliminary process capability study is part of the production parts inspection
procedure as per AIAG – PPAP and VDA 2 and must be submitted to VC as part of PPAP package.
Process capability (Cp, Cpk): An ongoing process capability of Cp, Cpk ≥ 1.33 for significant characteristics
is required (or higher as per specific Customer Requirement).
Some customers might request higher preliminary and long-term process capabilities. Information about
deviating capability requirements to the above-mentioned standard requirements will be communicated
during the project.
If process capability cannot be reached a reaction plan must be agreed upon with VC Supplier Quality.
1 Step PPAP requires the Standard PPAP elements as mentioned into 4.16.1. The supplier produces the
defined PPAP documents and delivers them to VC together with the PPAP samples. The series release
(PPAP Approval) is given after receiving correct and complete PPAP reports and approving the
dimensional and functional characteristics.
2 Step PPAP requires a supplier Run@Rate audit on site performed by VC staff or an external agent.
The series release (PPAP approval) is given after the supplier receives the approval of successful
Run@Rate audit using ‘FO-01-7.0-0103 Run@Rate Suppliers on site’ and after receiving correct and
complete PPAP reports and approving the dimensional and functional characteristics.
Supplier is notified if a 1-Step or 2-Step PPAP is required including necessary documents prior to or with
the PPAP purchasing order.
For critical or safety critical purchased parts (cc = critical characteristics) the 2 step PPAP
is mandatory.
Submission Provided by
FMEA Supplier
Control Plan
Supplier
Early Production Containment Plan
Initial process studies for CC, SC, and EC characteristics: Cp, Cpk / Pp, Ppk. (Recorded in FO-
Supplier
01-7.3-0216)
Master samples (min. one sample/cavity, min. 2 pcs stored at
Supplier
supplier location for entire project life)
PPAP samples (1 per cavity, min. 6 samples; marked; with single measurements results) Supplier
300 pcs for PTR delivered. Delivery marked with PSW cover sheet Supplier
Run@Rate audit (Supplier)
Supplier
(Full audit including capacity analysis using FO-01-7.0-0103)
IMDS Supplier
Approval of sub-suppliers - PSW/EMPB
(FO-01-7.4-0335_ Sub-Supplier-Tree) Supplier
Others
e.g.: Documented approach for warranty analysis (for functional components), Software Supplier
specific deliverables, Appearance approval report, Archiving plan for safety parts, etc.)
Notes:
Part submission Warrant: In cases where the customer requires his own forms for supplier PPAP, the
required forms must be used.
Dimensional Results: Measurement results must be assigned to the individual parts
PPAP documentation must be sent to VC through VC communication platform “LiveSource”. The delivery
of PPAP samples must be clearly labelled as PPAP samples, separated from the series delivery.
No series parts may be supplied to VC before approval. Permission regarding deviations (enclosure
Nr.7) will be granted should series deliveries be needed for reasons of timing (see Item 4.17.11).
The Production Parts Approval Process (PPAP) must be carried out by the supplier in the following
cases:
new project / sampling (repeated sampling)
amendments to product design / material
changes in production process
transfers to other production locations
transfer of lines in the same production site
use of new tools and cavities
use of different machine
use of new suppliers
interruption in production for longer than 12 months
additional IATF and Customer specific requirements to be considered
end of production (or according to specific requirements of VC customers, legal requirements). Test
records of safety parts (A-Parts) must be kept for a period of 15 years after end of production. Test
records must be available for review at any time by VC.
An annual requalification is required. The requalification includes functional testing required on the
drawing, a full dimensional layout, capability analysis and material certification consistent with records
submitted at PPAP. Recent test / capability data and layout results are acceptable.
As per 4.14.1, yearly requalification must be mentioned into the control plan.
To minimize quality risk and to avoid waste (scrap, rework, test expenditure, etc.), the supplier evaluates
process and product on a regular basis and introduces measures for continual improvement.
The quality objective for all suppliers is „Zero Defect”. Each supplier is expected to develop necessary
actions in order to achieve this „Zero Defect” target.
VC conducts supplier performance evaluation on regular basis. Results from the evaluation will be used
as a basis for escalation or development activities.
4.18.5 Traceability
Suitable identification systems must be applied. The test results of a part must be traceable. The batch
nr. and production date must be noted on the delivery note. Supplier must be able to trace back the
following information for the produced parts:
VC Part number
Drawing index
Production Date / Production Batch
Production Line / Machine
Material Batch
During production, the following must be secured:
FIFO (First-in First-out)
Identification of part status (Finished/unfinished, checked/not checked; OK/NOK)
Detailed requirements for Delivery notes and transport orders are also described in VC General
Procedure (GP-01-7.4-0009).
4.18.7 Packaging
Packaging of products must be agreed by VC and documented as part of the PPAP records. This should
comply with the overall Logistics requirement for suppliers.
page 19 / 25 Uncontrolled Copy if Printed
GP-01-7.4-0007 | REV. 7
QUALITY ASSURANCE MEASURES FOR
PROCUREMENT OF PURCHASED PARTS
VC does not conduct receiving inspection of characteristics that the supplier is contracted for. Only product
identification, shipping documents, and transport damage is reviewed. In any cases, Supplier liability of
defective goods remains according to VC general terms and condition of purchase.
Should faulty parts be found at delivery and/or in production process, it may result in the return of the
entire delivery. As soon as the supplier is notified, the supplier is obligated to ensure no further defective
parts are delivered, by establishing containment activities. Stocks of finished parts must be inspected or
replaced with certified material and corrective actions initiated.
The supplier is required to inform VC immediately when faulty products have been released for delivery.
VC reserves the right, in case of a line stop to directly arrange inspection and rework, and to charge any
expenses incurred by VC to the supplier if the supplier fails to respond to VC within 1 hour. For each
complaint, the supplier will receive a notification. The 8D methodology is required utilizing VC’s
communication platform “LiveSource” for documenting the corrective actions. A Problem-Solving-Process
sheet (FO-01-8.5-0160-PSP-Supplier available on “LiveSource”) must be used and submitted to VC for
repetitive complaints and complaints from VC customer. For any other complaints PSP must be used on
VC request.
The containment action must be submitted to VC within 24 hours. The permanent corrective action must
be completed within 10 working days after the initial notice. Extra time is possible when a defect sample
part is necessary for carrying out the root cause analysis but is not available.
The risk analysis (FMEA) must be reviewed as part of the corrective action. Additional analysis and
documentation may be requested by VC based on the severity of the non-conformity.
VC reserves the right to charge verifiable complaint related cost incurred, back to the supplier. Refer
to LI-01-7.4-0016 (available under www.vibracoustic.com/downloads).
VC may grant deviation to certain process / product requirements when the deviation does not violate
VC’s customer requirements, affect durability, nor any governmental / regulatory requirements. Supplier
request the deviation using the form mentioned in enclosure Nr.7. Any deviation will be limited in scope,
duration and/or quantity and the appropriate deviation form shall be fully signed and approved. Product
shipped under a deviation must be keep separate and clearly identified in delivery. Every rework process
of parts must be released by permission of deviation.
4.18.12 Subcontractor
For series deliveries it is only allowed to consider subcontractors, whose parts have been used for PPAP
to VC. The Subcontractor must submit a PPAP to the supplier and the supplier must evaluate and
release it before submitting the whole PPAP to VC. A change is only allowed after submission of new
sample parts to VC (see 4.16. PPAP). For the new sampling it is only allowed to use approved
subcontractors.
For a subcontractor change during serial production VC must be informed in advance (see 4.16. PPAP).
The order to the subcontractor is only allowed after written agreement by VC. A delivery to VC is only
allowed after full approval of PPAP by VC. In the case of a supplier change for safety critical purchased
parts an intensified PPAP is mandatory.
Safety critical characteristics comprise in case of deviations a risk for life and limb.
Safety critical characteristics must be 100% insurable. Sampling inspections are not sufficient. For the
safety critical characteristics which can be tested via destruction only, (e.g., the compression test for
metal parts) one adequate sample control per load is sufficient. However, test method and sample rate
must secure 100% conformity of critical characteristic. It must be ensured, that the purchase parts will
be delivered via traceable batches without exceptions.
The quantity and frequency of testing defined in the control plan must be agreed with VC in separate
process before PPAP submission. A member of the engineering as well as quality department of the
supplier should participate in this agreement.
The supplier must assure customer specific requirements related to Safety Critical features are followed.
The fulfilment of the safety critical parts features must be documented completely (e.g., by a supplier
certificate for each batch sent with the delivery). In case of no special agreement, the supplier must be
able to send the documentation by request on the same day.
In case the supplier delivers functional components or products (e.g., bearing, damper, electrical
components . . .) to VC, the supplier must establish process for field part analysis, root cause investigation
and continuous improvement. The process must follow related OEM and IATF requirements.
This Supplier scorecard presents criteria that will be used by Vibracoustic to rate the supplier performance.
The performance criteria are defined into the FO-01-7.4-0354 Supplier Sample Score Card and available
into our “VC Communication platform LiveSource”. Supplier shall access their performance data through
this platform. The supplier ‘s performance is taken into consideration for future sourcing decision as well
as for identifying area to focus continuous improvement activities. Supplier scorecard will be published
monthly into LiveSource.
The maximum quality score is 100 and the score is deducted with each incident.
The number of deducted points is defined for each incident based on incident severity.
Supplier will be notified about escalation level and invited to an initial meeting in writing, using FO-01-
7.4-0064. Supplier coaching event will be started in “VC Communication platform LiveSource”. During
initial meeting the target agreements and the exit criteria will be agreed.
Escalation activities Level 1
Supplier presents the Action Plan (using FO-01-7.4-0061) covering following three areas:
Part specific improvements (based on Quality complaints during the last 3 months)
Systematic improvements (quality complaints in last 12 months, APQP & LL process)
General improvements
The progress of activities must be reported to VC on regular basis
The supplier executive management is required to take direct ownership on escalation activities.
Furthermore, the supplier is required to the define escalation team and escalation leader.
In general, the supplier shall stay on escalation L1 for max.3 months, if de-escalation can not
be reached foreseeably despite all initiated activities the upwards escalation shell be started
If de-escalation criteria are sustainably reached and after agreement with VC cross functional
team VC escalation leader ends the escalation.
…
Note: not a comprehensive list, the activities will be set based on actual situation and related risk.
Additional activities for Escalation Level 2
A face-to-face meeting/online meeting must be realized on weekly base where supplier is
requested to present progress of escalation activities
Optional: Firewall at supplier and/or VC
Optional: Quality Control by independent source
Optional: Problem solving support with respect to technical and quality system improvements
Optional: Supplier status is set to NBH
Optional: Notification of supplier´s IATF 16949/ISO 9001 certification body on actual VC
escalation
All support costs during Q-support shall be charged to the supplier
5. Counterparts in VC
Program
Activity / Task GCM PQE SQA Plant SDE / STA
Buyer
Supplier APQP ✓
ECR Request ✓
6. APPENDIX / ENCLOSURE
Type of
No. Title/Description Enclosure
Document
1 List Definition of Special Characteristics LI-01-7.3-0049
2 OPI Early Production Containment OPI-01-7.4-0015
3 List Minimum requirements-M04 components with threads LI-01-7.4-0082
4 List Supplier Quality Cost Recovery Table LI-01-7.4-0016
5 Form Problem Solving Process Supplier FO-01-8.5-0160
6 Form Run@Rate suppliers (full audit) FO-01-7.0-0103
7 Form Permission-for-Deviation FO-01-8.3-0002
8 Form Supplier Process design review FO-01-7.0-0217
9 Form Supplier Process readiness FO-01-7.0-0237
10 Form EPC Form FO-01-7.4-0149
11 Form Shipment Marking Triangle FO-01-7.4-0146
12 Form Supplier Special Characteristics FO-01-7.3-0216
13 Form Supplier Change Request FO-01-7.4-0300
14 Form Sub-Supplier-Tree FO-01-7.4-0335
15 Form Supplier Sample Score Card FO-01-7.4-0354
16 Form Supplier Improvement Activity FO-01-7.4-0061
17 Form Supplier Escalation Matrix FO-01-7.4-0208
8. DOCUMENTATION
Vibracoustic will keep this procedure on file. In case of a revision the latest edition will be kept for at
least 3 years after revision.