Percentage BoQ
Tender Inviting Authority: ASSISTANT ENGINEER ( PWD ) MAYNAGURI CONSTRUCTION SUB DIVISION, JALPAIGURI
Name of Work: "Construction of Cement Concrete Compound Pathway and Drainage works for Section Office –III, under Maynaguri
Construction Sub Division Jalpaiguri during the year 2022-2023
NIT NO. 03 of AE/MGCSD/PWD/JPG Circulated Vide Memo No. 114 dated 14.07.2022
PRICE SCHEDULE
Sl. Item Description Quantity Units Estimated TOTAL AMOUNT TOTAL AMOUNT
No. Rate In Words
1.00 Clearing compound premises of shurbs, INR Seven Thousand Seven
plants, jungles etc. by cutting and removing as Hundred & Eighteen Only
directed (Specific permission of Engineer-in-
Charge prior to execution will be necessary). 620.360 Sq.M 12.44 7718.00
(Payment to be made on area cleared).
2.00 Removal of rubbish,earth etc. from the INR Six Thousand Five Hundred &
working site and disposal of the same beyond Seventy Seven Only
the
compound, in conformity with the Municipal /
35.025 Cu.M 187.78 6577.00
Corporation Rules for such disposal, loading
into truck and cleaning the site in all respect
as per direction of Engineer in charge
3.00 Dismantling all types of masonry excepting INR One Thousand &Thirty Nine
cement concrete plain or reinforced, stacking Only
serviceable materials at site and removing 2.054 CuM 505.65 1039.00
rubbish as directed within a lead of 75 m
4.00 Earth work in excavation of foundation INR Two Thousand Nine Hundred &
trenches or drains, in all sorts of soil (including Seven Only
mixed soil but excluding laterite or sandstone)
including removing, spreading or stacking the
spoils within a lead of 75 m. as directed. The
item includes necessary trimming the sides of 21.550 % CuM 13491.82 2907.00
trenches, levelling, dressing and ramming the
bottom, bailing out water as required
complete.
5.00 Earth work in filling in foundation trenches or INR Six Hundred & Thirty Only
plinth with good earth, in layers not exceeding
150 mm. including watering and ramming etc.
layer by layer complete. (Payment to be made
on the basis of measurement of finished 7.183 % CuM 8771.32 630.00
quantity of work)
a) With earth obtained from excavation of
foundation.
6.00 125 mm. thick brick work with 1st class bricks INR Seven Thousand Five Hundred
in cement mortar (1:4) in 10.080 Sq.M 753.80 7598.00 & Ninety Eight Only
7.00 Brick work with 1st class bricks in cement INR Forty Thousand Two Hundred &
mortar (1:4) 6.975 Cu.M 57771.80 40258.00 Fifty Eight Only
7.10 (b) In superstructure, ground floor INR Nine Hundred & Forty Only
0.156 Cu.M 6024.05 940.00
8.00 (A) Filling in foundation or plinth by silver INR Nine Thousand One Hundred &
sand in layers not exceeding 150 mm as Eighty Two Only
directed and consolidating the same by
thorough saturation with water, ramming
complete including the cost of supply of sand. 15.578 %Cu.M 58943.43 9182.00
(payment to be made on measurement of
finished quantity)
9.00 Supplying and laying Polythene Sheet INR Three Thousand Seven
(150gm / sq.m.) over damp proof course or Hundred & Four Only
below flooring or roof terracing or in 136.420 SqM 27.15 3704.00
foundation or in foundation trenches.
10.00 Ordinary Cement concrete (mix 1:2:4) with INR Seventy Two Thousand Nine
graded stone chips (20 mm nominal size) Hundred & Twenty Four Only
excluding shuttering and reinforcement,if any,
in ground floor as per relevant IS codes. 12.197 Cu.M 5978.82 72924.00
a) Pakur Variety
11.00 Ordinary Cement concrete (mix 1:1.5:3) with INR Eleven Thousand Seven
graded stone chips (20 mm nominal size) Hundred & Thirty Four Only
excluding shuttering and reinforcement if any,
1.789 Cu.M 6558.71 11734.00
in ground floor as per relevant IS codes.
Pakur Variety
12.00 Reinforcement for reinforced concrete work in INR Thirteen Thousand Nine
all sorts of structures Hundred & Eighty Five Only
including distribution bars, stirrups, binders etc
initial straightening and removal of loose rust
(if necessary), cutting to requisite length,
hooking and bending to correct shape, placing 0.211 MT 66372.55 13985.00
in proper position and binding with 16 gauge
black annealed wire at every intersection,
complete as per drawing and direction.
13.00 Hire and labour charges for shuttering with INR Eighteen Thousand Seven
centering and necessary staging upto 4 m Hundred & Four Only
using approved stout props and thick hard
wood planks of approved thickness with
required bracing for concrete slabs, beams 50.410 SqM 371.03 18704.00
and columns, lintels curved or straight
including fitting, fixing and striking out after
completion of works (upto roof of ground floor)
14.00 (a) Supplying, fitting galvanised 3 ply 12 INR Two Thousand Three Hundred
gauge / 4 points line of & Eighty Only
barbed wire in fencing (holes already made in
the body of the post)
or fixed by staples tightening and fixing the
wires in taut condition
with straining bolts including the cost of cutting 76.000 %Mtr 3131.16 2380.00
and of lapping
joints in the wire as necessary but excluding
the cost of galvanised
staples,straining bolt and binding wire where
necessary
15.00 Supplying galvanised straining bolts (with eye INR One Thousand Five Hundred &
at one end with Fifty Seven Only
double nuts and washers) fitted and fixed 32.000 Each 48.64 1557.00
complete. (i) 10 mm. dia.
a) 150 mm.
11.00 Cutting of Trees including Cutting of Trunks, INR Three Thousand One Hundred
Branches & Thirty Six Only
and Removal of Stumps,
Cutting of trees, including cutting of trunks,
branches and removal of stumps & roots,
refilling, compaction of backfilling and stacking
of serviceable material by manual means with 2.000 Each 1567.84 3136.00
all lifts as per Technical
Specifications Clause 201 for Rural Roads of
MORD. A. Lead upto 100 m
iv) Girth above 1800 mm to 2700 mm
12.00 a) 25 mm thick Tiles as per IS: 1237-2012 for INR Seventy Four Thousand Seven
footpath,ramp,staircase of public building(over Hundred & Ninety One Only
25 mm thick (Avg) Cement mortar (1:3) &
Cement Slurry @ 4.4 kg/Sq.m at back side of
Block. Cement for Mortar & Slurry to be 95.340 SqM 784.47 74791.00
supplied by Department).
(ii) Coloured Decorative
13.00 Plaster (to wall, floor, ceiling etc.) with sand INR Fifteen Thousand Four Hundred
and cement mortar including rounding off or & Forty Two Only
chamfering corners as directed and raking out
joints including throating, nosing and drip
course, scaffolding/staging where necessary
(Ground floor).[Excluding cost of chipping over 98.580 SqM 156.65 15442.00
concrete surface]
(ii) With 1:6 cement mortar
(b) 15 mm thick plaster
14.00 Neat cement punning about 1.5mm thick in INR Two Thousand Eight Hundred &
wall, dado, window sill, floor etc. 76.850 SqM 37.00 2843.00 Forty Three Only
NOTE:Cement 0.152 cu.m per100 sq.m.
15.00 Applying decorative cement based paint of INR Four Thousand Seven Hundred
approved quality after preparing the surface & Seventy Two Only
including scraping the same thoroughly
(plastered or concrete surface) as per 86.100 SqM 55.43 4772.00
manufacturer's specification.
In Ground floor: (iii) Two coats.
16.00 Priming one coat on steel or other metal INR Five Hundred & Twenty One
surface with synthetic oil bound primer of Only
approved quality including smoothening 15.870 Sq.M 32.80 521.00
surfaces by sand papering etc.
17.00 Painting with best quality synthetic enamel INR One Thousand Four Hundred &
paint of approved make and brand including Eighteen Only
smoothening surface by sand papering etc.
including using of approved putty etc. on the
surface if necessary b) On steel or other metal 15.870 Sq.M 89.36 1418.00
surfaceWith super gloss (hi-gloss)iv) Two
coats (with any shade except white).
304760.00 INR Three Lakh Four Thousand
Seven Hundred & Sixty Only
Total Amount
Assistant Engineer, (P.W.D.)
Maynaguri Construction Sub-Division
Jalpaiguri