0% found this document useful (0 votes)
18 views5 pages

NT - DEscope - 11.12.2024

The project involves the 6-laning with access control of NH-48 in Karnataka, covering a distance from km 29.435 to km 74.168, including a bypass section. The total project cost is estimated at 844.11 crore, with Phase-1 costing 393.81 crore and Phase-2 costing 450.32 crore. The document outlines various construction components, costs, and de-scoped amounts for both phases.

Uploaded by

Charan Pendurthi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
18 views5 pages

NT - DEscope - 11.12.2024

The project involves the 6-laning with access control of NH-48 in Karnataka, covering a distance from km 29.435 to km 74.168, including a bypass section. The total project cost is estimated at 844.11 crore, with Phase-1 costing 393.81 crore and Phase-2 costing 450.32 crore. The document outlines various construction components, costs, and de-scoped amounts for both phases.

Uploaded by

Charan Pendurthi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

Name of Project: 6-Laning with access control from km 29.435 to km 74.

168 of Neelmangala -
Tumkur including Tumkur bypass section of NH-48 (Old NH-4) in the State of Karnataka on
EPC mode under Bharatmala Pariyojna.

S.No Description Value

1 Total project cost as per Contract Agreement 844.11

2 Phase -01 project cost as per CA 393.81

3 Phase -2 project cost as per CA 450.32

4 De scoped cost in Phase- I 49.56

5 De scoped cost in Phase-2 144.39

6 Total De scope 193.95

7 Revised Phase-01 project cost 344.25

8 Revised Phase-02 project cost 305.93

9 Revise
�INEe� •
a r 11 ct cost - 650.18
. , /-
004
::;.
;;11
:\j,JJ * *c:, \\I.
_J;;fBANOALORE'1l)
\cl)..\ n - ·-•-----

l"UMK\J
y
PIU-TU
6-L:rning with access control from km 29.435 lo km 74.168 uf Nr:t.hnangala - T u m k u r including Tumkur bypnss section of NH-48 (Old NH-4)
Project Name
in the State of Karnataka on EPC mode under Bharatmala Pariyojna
844.11 Cr. Phase-1
Revised Scope Descope
Weightage in
Type of Stage for % Weightage Total Amount Unit Rate
o/
10 to th e Stage for Payment Unit Scope
Works Payment to Particular in Rs in Rs
Contract Price Quantity Amount Quantity Amount Remarks

H = 844.11
A B C D E F G l=H/G
Cr.*B*E
A - Widening and Strengthening of existing Roadfrom chainage km 61+520 to km to

- Km63+300 and Km65+100 to 74+168 of Tumkur bypass


1. Earthwork up to top of the Sub-grade Kms
VJ
2 . Earthwork in Shoulders Kms
0... 3 . Sub-base course Kms
!

<!.' 4 . Non-Bituminous Base course 1.7 8 % Kms 2 9.6 5 5 2,6 5 ,94 ,5 30 8,9 6 , 8 0 7 29. 6 55 2 ,6 5 ,94 , 5 30

5. Bituminous Base course 10 .2 1% Kms 2 9.655 15 ,2 5 ,4 5 ,0 2 7 5 1,4 4 ,0 4 2 2 9.6 5 5 15 ,2 5 .4 5 ,0 2 7


6 . Wearing Course 4 .96 % Kms 3 0 .6 11 7, 4 1 .0 6 , 1 0 5 2 4 ,2 0 ,9 1 4 3 0 .6 1 1 7, 4 1,0 6 , 1 0 5
B.J - Reconstruction/ New - Realignment /bypass (flexible pavement) from chainage
12,95,36,276 12,95,36,276
- :-Km 61+520 to 74+ 168 of tumkur bypass
1 . Earthwork up to top of the Sub-grade 3 .77% Kms 5 .6 4 3 5 , 6 3 .2 6 ,616 99, 8 1 ,6 79 5 .64 3 5 ,63 .2 6,6 1 6
2 . Earthwork in Shcmklers -
Q,. J. Sub-base course 1.28% Kms 5.64:l ],91.24,15h 1\R9,001 5.643 1,91,2 4 . 1 56
I

o::i 4 . Non-Bituminous Base course 1 .26 % Kms 5 .64 3 1 ,88,2 5 ,34 1 33,36,052 5 .64 3 1, 8 8 ,2 5 ,34 1
5. Bituminous Base course 1 .62 % Kms 5 .6 4 3 2 ,4 2 .0 4 ,0 1 0 42,89,210 5 .6 4 3 2 ,4 2 ,0 4 ,0 l 0

17.70% 6. Wearing Course 0 .74 % Kms 5 .6 4 3 1 , 1 0 .5 6, 1 5 3 19, 5 9,2 6 9 5 .6 4 3 1 , 1 0 ,5 6 . 1 5 3

C. 1- Reconstruction/ New Service/ Slip Road with Flexible Pavement from chainage
1,04,60,01,697 82,82,66,574 21,77,35,124
:-Km 29+435 to 74+168 of tumkur bypass
0 1 . Earthwork up to top of the Sub-grade 8 .91% Kms 76 .6 78 13 ,3 L2 2 ,0 5 6 17, 3 6, 1 18 62 .0 5 2 1 0 ,77. 2 9,0 73 1 4 .6 2 6 2 . 5 3 ,92 .98 3
VJ 2 . Earthwork in Shoulders
t-------------------+----------+----+---------+-------------------------1---------+-----------i - Forest land at 3 0.5 60 to 31. 4 90 RHS and
3 . Sub-base course % Kms 4 ,4 3 ,5 6,5 1 6 to 6 1 + 5 2 0 BHS Over all De-scope.
1 - - - - - - - - - - - - - - - - - - - + - - - - - - + - - - - - + - - - - +15 -.1-8- - - - - _ _ ; _ - - + - -76- .67
- - 8- - - - - - -2 -2 ,6
+ 8-.0- 0-,-5 3- 9- + - - - - -2-9,57,
4 9+90 0
- - - 8-3-1- - + - - 6- 1.
- -6 8- 2- - + - - - - - - - 1-8-,2i4 .4 4 ,0 2 3 14 .996
0...
I

u 4 . Non-Bituminous Base course 19. 1 2 % Kms 76.67 8


1-------------------+------+-----+----+-----'-__;___;__-+-------------+------+-----------+--------+-------------i
2 8 , 5 6,67, 0 8 3 3 7,2 5, 5 4 2 6 1 .3 62 2 2 ,86.0 5 ,5 69 1 5.3 1 6 5 ,70 ,6 1,5 1 4 Note: The Work executed B/W 4 9.9 to 6 1.5 2
5. Bituminous Base course 1 6. 1 2 % Kms 76 .6 78 2 4 , 0 8,4 4 , 8 4 2 3 1,40 ,990 6 1 .0 1 2 1 9, 1 6.3 7, 1 4 8 1 5 .666 4 ,92 ,0 7,694 should be considered in scope.
t-------------------+------+-----+----+---__;___;___;__-+-------'-------+------+----------'---+--------+-------'---------i
6. Wearing Course 1 0 .68 % Kms 76.67 8 1 5 ,95.67, 17 8 2 0 , 8 1,0 0 3 5 6 .63 2 1 1 ,78 .5 0 ,76 0 2 0 .0 4 6 4 . 1 7, 1 6 .4 1 8

D. 1- Reconstruction and New culvert on existing road ,realignment ,bypass for


6,54,40,472 3,93,97,835 2,60,42,637
service road from chainage :-Km 29+435 to 74+ 168 of tumkur bypass

Forest land at 3 0 .5 6 0 to 3 1.4 90 RHS and


4 9+90 0 to 6 1 + 5 2 0 BHS Over all De-scope.
Culvert< 6 M 4. 3 8 % Nos 98 .0 0 6, 5 4 .4 0,4 72 6 ,6 7,760 5 9.0 0 0 3 ,93 .97,8 3 5 3 9.0 2 -6 0 ,4 2 ·63 7
Note: The Box culvert executed B/W 4 9.9 to
6 1 .5 2 should be considered in scope.

Minor Bridges 9.1 8 % Rrnt 2 77.0 0 2 ,5 5,7 1 ,4 68 92 ,3 16 2 4 2 .6 0 0 2 ,2 3 ,95 ,8 0 6 34 .4 31 ,75 ,66 2


A. 2.1-New minor Bridges (Length>6m & <60m forservice road from chainage km
15,40,13,778 15,40, 13,779
29+435 to 74+168 including Tumkur bypass
11)
[/)
cd
. . c
0....
l. Foundation 9.7 8 % Rmt 4 1 .3 0 2 , 72. 4 2 , 8 0 6 6 ,59,6 3 2 4 1 .3 0 0 2 ,72 .4 2 ,80 6
2 . Sub-structure 2 0 .3 7% Rrnt 4 1 .3 0 5 ,67,4 1 ,918 1 3 ,7 3 , 8 96 4 1.3 0 0 5 ,67,4 1,9 1 8
3 . Super Structure 12 .97% Rrnt 4 1.30 3,61. 2 8, 75 2 8 ,74 ,7 8 8 4 1 .3 0 0 3 ,6 1 .2 8 ,75 2
4 . Approaches 5 .8 6% Nos 1 0 .0 0 1 ,6 3 ,2 3 ,3 99 16 ,3 2 ,3 4 0 1 0 .0 0 0 1 ,63 ,2 3 ,3 99
3.30% 6. Other Ancillary works 6 .3 1% Rmt 5 .0 0 I, 75 ,76 ,90 3 35 ,15 ,38 1 5 .0 0 0 1, 75 ,76 ,90 3
B.2- Nrw nndrrrn"" " I nvf'rrnss s for main carriageway from chaina11e Km 61+520
9,KIJ, 15, 42 3,42,74,857

-
to 74+168 of Tumkur bypass
I. l·oundution - - - - - - + - - - - - - - + - - -1.2)% - - - 1 4 _ , _ 7 . 7•1.00
- + - - - - - + - R111L (_,,_?.4_?_. + - - - - - 4 _ 6_;_,_0 3 _1 _ _ 24_._oo_ _ - + -_ _ _ l_l.c., l_l,;_, 2_14 _ _ _ 5_0_ _ - - +_ _ _ _ 2_.;_3,15, 0 2 9
-+- -+-
VJ
2. Sub-slrudure
t - - - - - - - - - - - - - - - - - + - - - - - + - - - - - + - - - - - - + - 4.4
- - - 1%
1 Rmt 74 00 2 2 , _4,;_
", -_ _R :l_:l :-l + - _ _ _ 1._66_._00_5- l - _ _ 2_4_.o_o _ _ _ _ _ _ _ ,_Y....;_, _4_. I_II_X4 - - _ _ _ _o _____
8 __ 83 .0
3 a. Casting of Girders _ _ _ _ _ _ _ _ _ _ 3. 0 3% _ _ _ _ _ _ _ _ _ 8.
.,___Nos _00 8_4,_4_ 0_,2_5 6_ _ _ _ l_U_,55__,u_3_2 _ _ _ _ _ _ _ _ _ _ _ _ _ _ -_____ R_ _ _ _ _ _ _ 4 4 0 55
s__._ _,_l _ --1 64+ 535 RHS and 6 4+ 8 2 5 RHS 2 11us VUPs at
I
3b. -------......,,,.SE
1-- Super Structure ,/;_. ,,---:::-,..... 8 .8 5 %
-....:....:....:..:....:....::.__+__:..=.:.::_+- Rrnt 74 .0 0
_ __:_.:...:....::...+---= ..5:..=
2 .,:..4:..6:. :. 2 ,:.=
2 .3:.:3
__ 3 :,.:3.:3:..:,.:1.:3:..:8
---=-. - -.;. .:.::..:__:__ _ f - -_ _ _ 7:.:.:.::..:2.:.:..:.:..+ - - - -=:..:_ _ _ _ f---=---1:...::... :..:6:.:.,:5:..:6.:.,:9:..:1_4, ROB Ch.64+ 6 5 0 rider span de scoped.
2 4 .0 0 0 9 , 9 5 , :; J 9 5 o 6

/ 1--d\.
= - +
4a. Casting of RE walls 0 .8 2 5% Sqm 4 0 69.8 2 2 .98 ,0 8 9 5 6 4.6 k&Oft ,V oo 11 ,4 9,0 47 2 0 3 4.9 11 ,4 9,0 47
4 b. RE wall //// \ ' 8 .8 2 5 % Sqm 4 0 69.8 2 ,4 5 ,8 2 , 5 93_ rt.fJ.. 2,0){-: 1, 2 2,9 1,3 0 5 2 0 34 .9 1, 2 2 ,9 1,30 5

l C>. I
,s. *tJ
PR TcrtlAECTOA
--
iUM'f,.U
Nat,onal H1gtw,ays Authority Of lndla
Revised Scope Descope
Weightage in
Type of Stage for % Weightage Total Amount Unit Rate
% to the Stage for Payment Unit Scope
Works Payment to Particular in Rs in Rs
Contract Price Quantity Amount Quantity Amount Remarks

H = 844.11
A B C D E F G l=H/G
Cr.*B*E
5. Approaches and Other Ancillary works 8.34% Nos 6.00 2,32,31,595 38,71,933 2.000 77,43,865 4 1,54,87, 730
I I II 111111 I I I I I I I i
I
A.2- New Major Bridges - service roads from chainage km 29+435 to 74+168 of
49.55,22.198 49 ,55,22, J95
Tumkur bypass
J. Foundation 9.86% Rmt 1900.00 7,73, 19,970 40,695 1,900 7,73, 19,968
2. Sub-structure 7.01% Rmt 1900.00 5,49,70.891 28,932 1,900 5,49. 70,895
9 3a. Casting of Girders/Segments 5.36% Nos 136.00 4,20,46,396 3,09, 165 136 4,20,46,396
"'
cd
3b. Super Structure 35.39% Rmt 1900.00 27, 75,06,216 1,46,056 1,900 27,75,06,210
4. Wearing coat including expansion joint 2.94% Rmt 1900.00 2,30,54.839 12,134 1,900 2,30.54,847
I.. <l.'
5. Miscellaneous items like hand rails,crash
2.46% Rmt 1900.00 1,92,90,783 10,153 1,900 1,92.90, 776
0
barrier,road markings etc.
6. Wing walls/ return walls upto top 0.10% Nos 16.00 7,84,178 49,011 16 7,84,178
8. Approches 0.07% Nos 12.00 5,48.925 45,744 12 5,48,925
9.29%
CQ C.2- New Elevated Section /Flyovers/Grade Sepearators from chaiange km 61+520 to
0 28.86,55.992 28,86,55,967
km 74+168 of Tumkur bypass
I. Foundation 5.77% Rmt 430.00 4,52,47,082 1,05,226 410.0 4,52.47,081
2. Sub-structure 4.17% Rmt 430.00 3,27,00,231 76,047 430.0 3,27,00,232
9 3a. Casting of Girders 9.42% Nos 56.00 7,38.69,586 13, 19,100 56.0 7,38,69,585
"'
11)

3b. Super Structure 9.42% Rmt 430.00 7,38.69,586 1,71,790 430.0 7,38.69,584
4. Wearing coat including expesion joint 1.73% Rmt 430.00 1,35,66,283 31,549 430.0 1,35,66,281
u
5. Miscellaneous items 0.71% Rmt 430.00 55.67,665 12,948 430.0 55,67,666
7a. Casting of RE walls 0.358% Sqm 4974 28.07,358 564 4,974.2 28,07,339
7b. Retaining/ Reinforced earth walls 2.502% Sqm 4974 1,96,20, 138 3,944 4,974.2 1,96,20, 135
2.73% Nos 2.00 2, 14,08,065 1,07,04,032 2.0 2, 14,08,065

II. Lined Drain 55.44% Kms 128.47 65,65.68,341 51, I0, 754 104.248 53,27.85,880 24.22 12.37,82,461 Forest area and 49.9 to 61.52 descoped
III. Road signs,safety devices, Road Furnitures 0.35% Kms 93.62 41,45,002 44,273 79.320 35, 11,723 14.30 6,33,102 Forest area, 49 to 61.52 and Tumkur bypass
IV. Road marking & Studs 1.88% Kms 93.62 2,22.64,583 2,37,809 79.320 1,88.62,970 14.30 34,00,662 reallignment descoped.
.::,::
I.. V. Crash Barrier 11.24% Kms 11.25 13,31.13, 783 1.18,28.131 11.254 13,31.13, 783
0
9 VI. Project facilities
I.. 14.03% "'
11)
G,
.c
cd a) Bus Bays 0.54% Nos 31.00 63,95, 146 2,06,295 22.0 45,38,491 9.00 18,56,655 From 49.9 to 61.52
0...
d) Truck Parking 9.26% Nos 2.00 10,96,64,914 5,48,32,457 LU 10,96,64,914
e) Junction Improvements 9.93% Nos 57.00 11,75,99,633 20,63,151 40.0 8,25,26,058 17.00 3,50, 73,575
X. Street Lighting 0.81% Kms 13.03 95.92,719 7,36,203 13.0 95,92,719
XVH. Other miscellaneous works 10.57% Nos 5.00 12,51,79,065 2,50,35,813 5.0 12,51, 79,065

I. EHT line %
JI. EHT crossings Nos 7.00 7.00
Ill. HT/LT line Kms 51.93 51.93
- 2.33%
0
O
"'J
IV. HT/LT crossings
100.00%
Nos 16.00
19,66,77,630 19,66, 77,630
16.00
'..;: 19,66, 77.630
;;;i
cd V. Water pipeline Kms 28.40 28.40
VI. Water pipeline crossings Nos 12.00 12.00
VII.Sewage lines

Amount Proposed for Descope for reduction of Width in Tumkur Bypass (8. 75-7.5) 3,52,64,580
Adjusted against work executed in the descoped stretches (10%) Cl. 8.3.3 -1,59,79,498
49,56,25,465
3,44,24, 78,238 Revised Contract price Phase-0 I

OJECT DIRECTOR
National Highways Authority Of lndla
PIU-TUMAKURU
PROJECT NAME
: 6-Laning with access control from km 29.435 to km 74.168 of Neelmangala - T u m k u r including Tumkur bypass section ofNH-48 (Old NH-
4) in the State of Karnataka on EPC mode under Bharatmala Pariyojna
844.ll Cr. Phase-2
Weightage in I,. -
C
% Revised Scope Descope
Type of % to the Weightage Total Amount Unit Rate
e
Qi

= Stage for Payment Unit Scope


Qi
Works Contract bJ) ....
to in Rs in Rs Amount Remarks
,,S Quantity Amount Quantity
Price J
fJ Q.
Particular
H = 844.11
A B u D E F G I = H/G
Cr.*B*E
A - Widening and Strengthening of existing Roadfrom chainage km 61+520 to km
74+ 168 of Tumkur bypass
N
9u 1. Earthwork up to top of the Sub-grade 0.00% Kms 0.000

-..
,,
I .
"'
.c
Q.
2. Earthwork in Shoulders
3. Sub-base course
0.00%
0.00%
Kms
Kms
0.000
0.000
<
...
-; 4. Non-Bituminous Base course 0.00% Kms 0.000
5. Bituminous Base course 0.00% Kms 0.000
0
I . 6. Wearing Course 0.00% Kms 0.000
·;Q .
u B.1 - Reconstruction / New - Realignment /bypass (flexible pavement ) from chainage
I . 2,02, 78,49,347 1,38,05,44,521 64, 73,04,826
:-Km 29+435 to 61+520
=
"
O
'
C : N
9u 1. Earthwork up to top of the Sub-grade Kms
8.96% 63.52 18,83,24,317 29,64,703 43.245 12,82,09, 773 20.277 6,01, 14,544
.sC:
0A)
"' 2. Earthwork in Shoulders Kms
u .c
"
C Q . 3. Sub-base course 23.72% Kms 63.52 49,85,55,001 78,48,522 43.245 33,94, 12,480 20.277 15,91,42,522 From Km.48+600 to Km.61+200 de scoped
'i 24.90¾ CQ 4. Non-Bituminous Base course 20.51% Kms 63.52 43, 10,86, 133 67,86,391 43.245 29,34,80, 184 20.277 13, 76,05,949
5. Bituminous Base course 29.63% Kms 63.52 62.27,73,385 98,04.035 43.245 42,39,79,417 20.277 19,87,93,967
..
I .
u
-; 6. Wearing Course 13.66% Kms 63.52 28.71,10,511 45.19,849 43.245 19,54,62,668 20.277 9,16,47,843
0A) C. 1- Reconstruction/ New Service/ Slip Road with Flexible Pavement from chainage
:c=
C:

·=
:-Km 29+435 to 74+168 of tumkur bypass
N
ij 0 I. Earthwork up to top of the Sub-grade Kms
u
I
0.00% 0.000
"' "' 2. Earthwork in Shoulders Kms
..;;i::
.c
I .
0 Q. 3. Sub-base course 0.00% Kms 0.000
"O
'
0
= u 4. Non-Bituminous Base course
5. Bituminous Base course
0.00%
0.00%
Kms
Kms
0.000
0.000
c
:i
6. Wearing Course 0.00% Kms 0.000
I
u
"' D. 1- Reconstruction and New culvert on existing road ,realignment ,bypass for 4,10,43,897
=N 7,41,94,737 3,31,50,840
fo service road from chainage :-Km 29+435 to 74+ 168 of tumkur bypass

A. 1-Windening and repairs of minor Bridges (Length>6m & <60m) for Service from 20,76,394
43,64,049 22,87,655
chainage km 29+435 to 74+168 including Tumkur bypass
From 48 to 61.2 descoped,
"'
u Minor Bridges 0.50% Rmt 72.30 43,64,049 60,360 37.90 22.87.655 34.40 20,76,394 Ch.50+243 RHS. 51+046 RHS and 53+436
"
"'' N BHS.
9u
Q .
"' A. 2.J-New minor Bridges (Length>6m & <60m forservice road from chainage km
..
I .
.c 2,68,82,540 2,74,37,317 98,57,552
Q. 29+435 to 74+168 including Tumkur bypass
< I . Foundation 1/o t 1 ,4 3,30,489 11.75 1,93,197
"'
"' 74, 18,883 2,32,932 46,81,932 11.75 27,36,950

=
0.85% Rmt 20.10
Q .
I .
u ..,.
c:,
1.64% 1,43, 14,080 4,49,422 20.10 90,33,375 11.75 52.80,704
"
O
,I
I"')
C : 1/c ' 4, l.02.33,694 2 10.18,278
.;.:"'.;. 15,71,058 1,57,1 31,57,826 4 6,28,423
u
Irr 1/o
0A)
"
O B.2- New underpasses/ overpasses for main carriageway from chainage Km 29+435 23,61,23,913
'i: 84,14,75,870 60,53,51,957
CQ to 61+520
N
55.80,941
I .
0 0
I I . Foundation 2.16% Rmt 277.00 1.88,52,690 68.060 195.00 1.32.71,750 82.00
.5 "' 2,07,99,340 I YUP at 30+500 due to forest land and I
2. Sub-structure 8.05% 7,02,61,1 195.00 4,94.61,844 82.00
.c
i=.. 3. Su er Structure 18.66% 16,28,66,297 195.00 11, ' 0 82.00 4,82,13,128 LYUP at 57+600 due to Railway cables and I
CQ 4. RE wall 44.91% 39.19. 78,854 26.99_51,718 B1R4 12,20,27, 136 YUP 55+ 160 which is under 48 to 58 descoped
stretch
22.63% 30.00

ECT DIRECTOR
National Highways Authorltv o, lrirl i 1

r-- .. .., i
Weightage in i.. - % Revised Scope Descope
Type o f % to the cE
E Weightage Total Amount Unit Rate
Stage for Payment Unit Scope
Works Contract QJ)
to in Rs in Rs Remarks
Q.
Quantity Amount Quantity Amount
Price Particular

B.2- New ROB/RUB from chainage km 29+435 to km 74+168 36, 73,55,321 36, 73,55,321

1. Foundation 2.93% R.mt 228.00 1,57,54,553 69,099 228.00 1,57,54,553.45


2. Sub-structure 4.19% R.mt 228.00 2,25,29,549 98,814 228.00 2,25,29,549.13
N 3. Super Structure (incl. bearing) 41.86% R.mt 228.00 22.50.80,412 9.87, 195 228.00 22,50,80,412.10
4. Wearin coat includin ex esion joint 0.87% R.mt 228.00 46,77,973 20,517 228.00 46.77,973.21
-= 5. Miscellaneous items like hand rails,crash ROB 3 nos de-scupt: Km.SO 1285, 55 1940 &
Q,,.
1.08% R.mt 228.00 58,07, 139 25,470 228.00 58,07, 139.16
.0.
t..
barrier,road markin sect. 64+650

=
6. Retaining/ Reinforced earth walls 8.57% R.mt 12000.00 4,60,80, 725 3,840 12000.00 4,60.80, 724.60

=
8. Approaches and Other Ancillary Works
;;;;) '$. (wearing coat, expansion joints, hand rails, crash

=
0
a:: t-
8.82% R.mt 6.00 4, 74,24,970 79,04, 162 6.00 4,74.24,969.77
barriers, road signs & markings. stone pitching,
0 protection works etc.)
a::
C.2- New Elevated Section /Flyovers/Grade Sepearators from chaiange km 61+520 to
J7,02,88,979 9,04,08,553 7,98,80,425
km 74+168 ofTumkur bypass
N 1. Foundation 1.96% R.mt 80.00 1,05,38,882 1,31,736 40.00 52,69,441 40 52,69,441.09
.., 2. Sub-stmcture 2.75% R.mt 80.00 1,47,86,697 1,84,834 40.00 73,93,348 40 73,93,348.47
-= 3. Super Structure 6.11% R.mt 80.00 3,28.53,3 2 4, 10,667 40.00 ] ,6L1,26,676 40 1,64,26,676.04

= I 4. Wearing coat including cxpcsion joint


5. Miscellaneous items
0.72%
0.19%
Rmt
R.mt
R0.00
80.00
38,71,426
10,21,626
48,393
12,770
40.00
40.00
19,35,713
5.10,813
40
40
19,35,713.05
5,10,813.17
1 No Plyover at Km.52+680.

7. Retaining/ Reinforced earth walls 9.79% 15000.00 5,26,40,641 3,509 9000.00 3, 15,84,385 6000 2, I 0,56,256.42
8. Approaches and Other Ancillary works 10.15% 4.00 5,45,76,354 1,36,44,089 2.72.88,177 2 2,72.88,177.06

I. Toll Plaza 27.49% Nos 1.00 27.24,21,815 27,24.21,815 1.00 27,24.21,815 0


III. Road signs,safety devices, Road Furnitures
0.31% Kms 63.52 30,72,054 48,362 43.25 20,91,431 18.917 9,14,851
etc
IV. Road marking & Studs 1.70% Kms 63.52 1.68,46,747 2.65.211 43.25 1,14.69,138 18.917 50. 16,923
..;i::
V. Crash Barrier 11.51% Kms 28.40 I 1,40,62,390 40.16,281 17.42 6.99,71,653 10.978 4,40,90,736
t.. N
0 Vl. Project facilities
:i: ;,

-=
t..
r-: "' a) Bus Bays 0.00% Nos 0.00 From Km.48+600 to Km.61+200 de scoped
.. -=
=- d) Truck Parking 0.00% Nos 0.00
0
Vii. Rain Water Harvestin 0.35% Nos 1.00 34,68,448 34,68,448 1.00 34.68,448
Viii. Retainin Wall 4 . 1/o ,77,53,936 5,81,20,917 8.22 47,77,53,936
X. Street Lighting 1.21% 42.81 1,19,90,920 2,80,096 37.22 1,04,25, 182 5.59 15,65,738
Xii. ATMS 6.28% 63.52 6.22,33,867 9,79.719 63.52 6.22.33,867 0

I. EHT line
II. EHT crossings

= = III. HT/LT line


f
N
'$.
;, I

"' 0.00%
Q
0 -=
Q,,.
VI. Water pipeline crossings
Vil.Sewage lines

Amount for Utility@ 0.00% Rs. =

Total Cost or Project in Rs. = 4,50,32, 96,884 3,06,87,83,711 1,44,38, 77,390 Total De-scope amount
Say 450.33 3,05,94,19,494 Revised Contract price Phase-02

You might also like